Project Milestone Schedule Update May 25 2017.pdf

PDF 237 KB Posted

Attached to
Construction Manager as Constructor (CMc), New - Greenville, SC Federal Courthouse Building
Solicitation number
GS--04-P-16-BV-C-7005
Issued by

About this file

Project Milestone Schedule Update May 25 2017.pdf

View the file

Other files

File Type Posted
0003_Solicitation_Amendment_GS-04-P-16-BV-C-7005_0003.pdf PDF
0002_Solicitation_Amendment_GS-04-P-16-BV-C-7005R.pdf PDF
0001_Solicitation_Amendment_GS-04-P-16-BV-C-7005_0001R.pdf PDF
GSA 013600COBieFY15UpdateOct.12014_SolicitationNo.GS-04-P-16-BV-C-7005.docx.pdf PDF
Technology Policy for PBS-Owned Buildings Monitoring _ Control Systems.pdf PDF
GSA 014100 Structural Testing Laboratory Services FY15 Update Oct. 1, 2014_Solicitation No. GS-04-P-16-BV-C-7005.pdf PDF
GSA 013300 Submittal Procedures FY15 Update Oct. 1, 2014_Solicitation No. GS-04-P-16-BV-C-7005.pdf PDF
06032016 FitForPurposeintheChangingClimate Greenville SC.pdf PDF
TheSolicitation_GreenvilleSC.pdf PDF
GSA 016000 Product Requirements FY15 Update Oct. 1, 2014.pdf PDF
GSA 015930SecurityRegulationsFY15UpdateOct.12014.docx.pdf PDF
Updated Meeting Schedule Matrix_Design Restart_R02_082216.pdf PDF
GSA 013100 Project Management _ Coordination FY15 Update Oct. 1, 2014_Solicitation No. GS-04-P-16-BV-C-7005.pdf PDF
SITESv2_Scorecard.pdf PDF
NBSAP_Clarification2_2014 Jun -4762.pdf PDF
Greenville SC AE SOW CONTRACT MODIFICATION_6-17-16_FINAL_R04.pdf PDF
USAO Design Guide 10-13-15.pdf PDF
CMc_Pricing_Sheet_Attachment_A_REV_01.pdf PDF
CMcSOW_Greenville_SC_CTHS_Attachment_B.pdf PDF
GSA__Form527-15b_(1).pdf PDF
GSA 012900 Payment Procedures FY15 Update Oct. 1, 2014_Solicitation No. GS-04-P-16-BV-C-7005.pdf PDF
GSA 017000ExecutionRequirementsFY15UpdateOct.12014.docx.pdf PDF
SITESv2_RatingSystem —
Courts Mailroom Construction Guidelines.pdf PDF
SF_1442_GS-04-P-16-BV-C-7005__Greenville_SC_CMc_Solicitation.pdf PDF
GSA 014025QualityControlTestingforAirBarriersFY15UpdateOct.12014_SolicitationNo.GS-04-P-16-BV-C-7005.docx.pdf PDF
GSA 015639TreePlantProtectionFY15UpdateOct.12014.docx.pdf PDF
GSA 012100 Allowances FY15 Update Oct. 1, 2014_Solicitation No. GS-04-P-16-BV-C-7005 —
GSA 014200ReferencesFY15UpdateOct.12014_SolicitationNo.GS-04-P-16-BV-C-7005.doc.pdf PDF
US Courts Design Guide 2007.pdf PDF
2017-04-18-finishes.pdf PDF
The_Agreement_Greenvill_SC_CMc_May_15_2017_(1).pdf PDF
Greenville, SC Courthouse Project Phase II ESA report - PHE May 27, 2010.pdf PDF
GSA 017410 Construction Indoor Air Quality FY15 Update Oct. 1, 2014.pdf PDF
2014 Final, Pub 64 Revised.pdf PDF
CMc301_Reps_and_Certs_Attachment_C.docx DOCX document
GSA 017810ProjectRecordDocumentsFY15UpdateOct.12014.docx.pdf PDF
GSA 018111SustainableDesignRequirementsFY15UpdateOct.12014.docx.pdf PDF
GSA 017350 Fire Prevention Precautions for Hot Work FY15 Update Oct. 1, 2014.pdf PDF
NBSAP_Clarification1_2013 July Final-VOIDs.pdf PDF
GSA 017419ConstructionNonhazardousWasteManagementDisposalFY15UpdateOct.12014.docx.pdf PDF
PBS_P_3490.2_Document_Security_for_Sensitive_But_Unclassified_Building_Information_-_(Signed_on_Sept._2__2014).pdf PDF
GSA 017822 Operation _ Maintenance Documentation FY15 Update Oct. 1, 2014.pdf PDF
GSA 014000 Quality Assurance _ Control FY15 Update Oct. 1, 2014_Solicitation No. GS-04-P-16-BV-C-7005.pdf PDF
Layout_of_Water_Main_DOC120616-12062016151956_(1).pdf PDF
SpringSt1_Irvine_2017_Water Main Relocation_Greenville SC CTHS Project.pdf PDF
GSARegion4BuildingAutomationSystemRequirementsv6.pdf PDF
NBSAP_Final_Feb 2013.pdf PDF
GSA 013000 Electronic Project Management FY15 Update Oct. 1, 2014_Solicitation No. GS-04-P-BV-C-7005.pdf PDF
GSA 013200 Construction Progress Documentation FY15 Update Oct. 1, 2014_Solicitation No. GS-04-P-16-BV-C-7005.pdf PDF
Show 40 more

Latest 50 of 79 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Start: 19-Nov-2013 Finish: 01-Apr-2021

PM Milestone Schedule

Gantt Chart View

Task Name Status Responsible % Compl…

Remain Duration

Early Start Early Finish Actual Start Actual Finish

PM Milestone Schedule Laura Sha… 25.7 % 1,427.… 02-Mar-2017 01-Apr-2021 19-Nov-2013

PM Schedule - (Greenville CH) 25.7 % 1,427.… 02-Mar-2017 01-Apr-2021 19-Nov-2013

Planning 0.0 % 1,379.… 01-Apr-2021 01-Apr-2021 17-Dec-2015

Customer Request 100.0 % 0.0d 17-Dec-2015 17-Dec-2015 17-Dec-2015 17-Dec-2015

FY 2016 Capital Program Approval 100.0 % 0.0d 17-Dec-2015 17-Dec-2015 17-Dec-2015 17-Dec-2015

Speed Date Meeting (DC) Ismael Sant… 100.0 % 0.0d 23-Feb-2016 23-Feb-2016 23-Feb-2016 23-Feb-2016

Site Visit Meeting with Customer (Courts)(Atlanta) Ismael Sant… 100.0 % 0.0d 31-Mar-2016 31-Mar-2016 31-Mar-2016 31-Mar-2016

Central Office Kick Off Meeting Les Shepherd 100.0 % 0.0d 20-Apr-2016 20-Apr-2016 20-Apr-2016 20-Apr-2016

Change Benchmark (Program) 100.0 % 0.0d 23-Feb-2016 23-Feb-2016 23-Feb-2016 23-Feb-2016

Requirements Finalized (Updated Anycourt Approved) Laura Shadix 100.0 % 0.0d 15-Mar-2016 15-Mar-2016 15-Mar-2016 15-Mar-2016

Signed OA Derick Nix 0.0 % 0.0d 01-Apr-2021 01-Apr-2021

Authority/Funding 100.0… 718.5d 19-Nov-2013 19-Aug-2016 19-Nov-2013 19-Aug-2016

Prospectus Approval 100.0 % 0.0d 18-May-2016 18-May-2016 18-May-2016 18-May-2016

Funds in Place Laura Shadix 100.0 % 0.0d 17-Dec-2015 17-Dec-2015 17-Dec-2015 17-Dec-2015

SBA Approval / Waiver for Full & Open Competition (CMa) Swindale Rh… 100.0 % 0.0d 06-Jul-2016 06-Jul-2016 06-Jul-2016 06-Jul-2016

SBA Approval/ Waiver for Full & Open Competition (CMc) Swindale Rh… 100.0 % 0.0d 19-Aug-2016 19-Aug-2016 19-Aug-2016 19-Aug-2016

Site Acquisition Complete 100.0 % 0.0d 19-Nov-2013 19-Nov-2013 19-Nov-2013 19-Nov-2013

Design 44.5 % 320.3d 02-Mar-2017 05-Jun-2018 18-Mar-2016

Complete SOW AE Contract Modification Laura Shadix 100.0 % 0.0d 18-Mar-2016 17-Jun-2016 18-Mar-2016 17-Jun-2016

PM Submits PR (Design Phase A/E Contract Modification) Ismael Sant… 100.0 % 0.0d 27-May-2016 27-May-2016 27-May-2016 27-May-2016

Contracting Accepts PR Swindale Rh… 100.0 % 0.0d 06-Jun-2016 06-Jun-2016 06-Jun-2016 06-Jun-2016

Design Firm Selected/Price Proposal Requested Swindale Rh… 100.0 % 0.0d 20-Jun-2016 20-Jun-2016 20-Jun-2016 20-Jun-2016

RFP Issued to HBRA Swindale Rh… 100.0 % 0.0d 20-Jun-2016 20-Jun-2016 20-Jun-2016 20-Jun-2016

Receive A/E Fee Proposal Swindale Rh… 100.0 % 0.0d 08-Jul-2016 08-Jul-2016 08-Jul-2016 08-Jul-2016

Design Award Swindale Rh… 100.0 % 0.0d 31-Aug-2016 31-Aug-2016 31-Aug-2016 31-Aug-2016

Design Start Swindale Rh… 100.0 % 0.0d 31-Aug-2016 31-Aug-2016 31-Aug-2016 31-Aug-2016

A/E Updates Final Concept Programming/Housing Plan Documents Craig Brandt 100.0 % 0.0d 31-Aug-2016 20-Sep-2016 31-Aug-2016 20-Sep-2016

GSA/ Courts/ USMS Review & Approval of Revised Housing Plan/Program Laura Shadix 100.0 % 0.0d 21-Sep-2016 21-Sep-2016 21-Sep-2016 21-Sep-2016

Project Kickoff/ Design Restart Meeting (Greenville) Laura Shadix 100.0 % 0.0d 26-Sep-2016 26-Sep-2016 26-Sep-2016 26-Sep-2016

Meeting with the City of Greenville (GSA/ Courts/ HBRA) Laura Shadix 100.0 % 0.0d 26-Sep-2016 26-Sep-2016 26-Sep-2016 26-Sep-2016

USDC Space Plan Review Comments Due John Brady 100.0 % 0.0d 21-Oct-2016 21-Oct-2016 21-Oct-2016 21-Oct-2016

2012 2013

25.7 %

25.7 %

100.0 %

100.0 %

Summary

Deleted Summary

Milestone

Deleted Milestone

Task

Critical Task

Deleted Task

Assignment

Deleted Assignment

Start On

Start No Earlier

Start No Later

Finish On

Finish No Earlier

Finish No Later

Start Float

Finish Float

Link

Critical Link

Inactive Link

Printed On 25-May-2017 4:33 PM

PM Milestone Schedule

Gantt Chart View

2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038

0.0 %

100.0 %

100.0 %

100.0 %

100.0 %

100.0 %

100.0 %

100.0 %

0.0 %

100.0 %

100.0 %

100.0 %

100.0 %

44.5 %

No Assignments100.0 %

100.0 %

100.0 %

100.0 %

100.0 %

100.0 %

100.0 %

100.0 %

No Assignments100.0 %

No Assignments100.0 %

100.0 %

No Assignments100.0 %

100.0 %

Summary

Deleted Summary

Milestone

Deleted Milestone

Task

Critical Task

Deleted Task

Assignment

Deleted Assignment

Start On

Start No Earlier

Start No Later

Finish On

Finish No Earlier

Finish No Later

Start Float

Finish Float

Link

Critical Link

PM Milestone Schedule

Gantt Chart View

Task Name Status Responsible % Compl…

Remain Duration

Early Start Early Finish Actual Start Actual Finish

A/E Completes Revisions/ Final Submitted Program Craig Brandt 100.0 % 0.0d 25-Oct-2016 26-Oct-2016 25-Oct-2016 26-Oct-2016

SITES/LEED Meeting (Greenville) Laura Shadix 100.0 % 0.0d 02-Nov-2016 02-Nov-2016 02-Nov-2016 02-Nov-2016

A/E Updates Final Concept Plans & Narratives (Pricing Set) Craig Brandt 100.0 % -0.0d 31-Oct-2016 17-Nov-2016 31-Oct-2016 17-Nov-2016

A/E Updates Final Concept Cost Estimate Craig Brandt 100.0 % 0.0d 18-Nov-2016 12-Dec-2016 18-Nov-2016 12-Dec-2016

Design Review Meeting (Greenville) Laura Shadix 100.0 % 0.0d 19-Dec-2016 19-Dec-2016 19-Dec-2016 19-Dec-2016

Building Stacking and Floorplans Finalized Craig Brandt 100.0 % 0.0d 21-Mar-2017 21-Mar-2017 21-Mar-2017 21-Mar-2017

Final Concept Cost Estimate Reconcilation Meeting (Greenville) Craig Brandt 100.0 % 0.0d 20-Dec-2016 20-Dec-2016 20-Dec-2016 20-Dec-2016

A/E Updates Final Concept Plans (95% Final Concept Drawings) Craig Brandt 100.0 % 0.0d 20-Jan-2017 20-Jan-2017 20-Jan-2017 20-Jan-2017

Printing and Distribution 95% Final Concept Drawings Craig Brandt 100.0 % 0.0d 23-Jan-2017 24-Jan-2017 23-Jan-2017 24-Jan-2017

GSA/ Courts / USMS Review of Revised Concept Drawings (95% FCH Submission) Laura Shadix 100.0 % 0.0d 24-Jan-2017 10-Feb-2017 24-Jan-2017 10-Feb-2017

Jacobs Independent Third Party Estimate FCH Submission Laura Shadix 100.0 % 0.0d 24-Jan-2017 10-Feb-2017 24-Jan-2017 10-Feb-2017

SDM Review & Reconciliation of 95% FCH Submission Jay Jaqua 100.0 % 0.0d 24-Jan-2017 10-Feb-2017 24-Jan-2017 10-Feb-2017

Update Final Concept Cost Estimate Craig Brandt 100.0 % 0.0d 24-Jan-2017 10-Feb-2017 24-Jan-2017 10-Feb-2017

Final Review Comments Due to HBRA Laura Shadix 100.0 % 0.0d 13-Feb-2017 13-Feb-2017 13-Feb-2017 13-Feb-2017

Design Review Meeting (Greenville) Laura Shadix 100.0 % 0.0d 15-Feb-2017 15-Feb-2017 15-Feb-2017 15-Feb-2017

Final Concept Cost Estimate Review and Reconciliation (Jacobs/ Aiken) Laura Shadix 100.0 % 0.0d 13-Feb-2017 22-Feb-2017 13-Feb-2017 22-Feb-2017

Integrated Design Review (IDR) Phase of Final Concepts Concluded Laura Shadix 100.0 % 0.0d 22-Feb-2017 22-Feb-2017 22-Feb-2017 22-Feb-2017

HBRA to start Model for Commissioner's Presentation Craig Brandt 100.0 % 0.0d 06-Feb-2017 30-Mar-2017 06-Feb-2017 30-Mar-2017

Update Draft Pro Forma OAs Derick Nix 100.0 % 0.0d 12-Aug-2016 12-Aug-2016 12-Aug-2016 12-Aug-2016

Receive Signed Draft Pro Forma OAs Derick Nix 0.0 % 1.0d 02-Mar-2017 03-Mar-2017 02-Mar-2017

Readiness Checklist sent to OCA Laura Shadix 100.0 % 0.0d 30-Mar-2017 30-Mar-2017 30-Mar-2017 30-Mar-2017

Receive Final Reconciled FCH Estimate Report (CMa) Laura Shadix 100.0 % 0.0d 28-Feb-2017 28-Feb-2017 28-Feb-2017 28-Feb-2017

Issue Commissioner's Electronic Presentation Package to OCA & Courts Laura Shadix 100.0 % 0.0d 21-Mar-2017 21-Mar-2017 21-Mar-2017 21-Mar-2017

Concept Design Approval (Commissioner's Presentation) Marty Bowers 100.0 % 0.0d 03-Apr-2017 03-Apr-2017 03-Apr-2017 03-Apr-2017

Submit Final Concept Package - FOR RECORD Craig Brandt 100.0 % 0.0d 04-Apr-2017 04-Apr-2017 04-Apr-2017 04-Apr-2017

Design Development Phase (3.3.4) 15.8 % 77.0d 05-Apr-2017 09-Aug-2017 04-Apr-2017

Exercise of Design Development Phase Option Swindale Rh… 100.0 % 0.0d 04-Apr-2017 04-Apr-2017 04-Apr-2017 04-Apr-2017

DD review meeting No. 1 - Interior Finish Discussions/ IDR (Greenville) Craig Brandt 100.0 % 0.0d 18-Apr-2017 19-Apr-2017 18-Apr-2017 19-Apr-2017

Preliminary DD Submittal (Section 3.3.4.2.2) Craig Brandt 100.0 % 0.0d 18-Apr-2017 16-May-2017 18-Apr-2017 16-May-2017

Preliminary DD Space Plan Submittal Review Laura Shadix 0.0 % 15.0d 17-May-2017 07-Jun-2017 17-May-2017

Physical Courtroom Mockup (Greenville) Laura Shadix 100.0 % 0.0d 12-May-2017 12-May-2017 12-May-2017 12-May-2017

2012 2013

Summary

Deleted Summary

Milestone

Deleted Milestone

Task

Critical Task

Deleted Task

Assignment

Deleted Assignment

Start On

Start No Earlier

Start No Later

Finish On

Finish No Earlier

Finish No Later

Start Float

Finish Float

Link

Critical Link

PM Milestone Schedule

Gantt Chart View

2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038

No Assignments100.0 %

No Assignments100.0 %

No Assignments100.0 %

No Assignments100.0 %

No Assignments100.0 %

100.0 %

No Assignments100.0 %

100.0 %

No Assignments100.0 %

No Assignments100.0 %

No Assignments100.0 %

No Assignments100.0 %

No Assignments100.0 %

No Assignments100.0 %

No Assignments100.0 %

No Assignments100.0 %

100.0 %

No Assignments100.0 %

No Assignments100.0 %

No Assignments0.0 %

No Assignments100.0 %

No Assignments100.0 %

No Assignments100.0 %

100.0 %

No Assignments100.0 %

15.8 %

No Assignments100.0 %

No Assignments100.0 %

No Assignments100.0 %

No Assignments0.0 %

No Assignments100.0 %

Summary

Deleted Summary

Milestone

Deleted Milestone

Task

Critical Task

Deleted Task

Assignment

Deleted Assignment

Start On

Start No Earlier

Start No Later

Finish On

Finish No Earlier

Finish No Later

Start Float

Finish Float

Link

Critical Link

PM Milestone Schedule

Gantt Chart View

Task Name Status Responsible % Compl…

Remain Duration

Early Start Early Finish Actual Start Actual Finish

Second Site Visit / Evaluation Physical Courtroom Mockup (Date to be finalized by P… Laura Shadix 100.0 % 0.0d 24-May-2017 24-May-2017 24-May-2017 24-May-2017

35% DD Development Craig Brandt 0.0 % 63.0d 05-Apr-2017 30-Jun-2017 05-Apr-2017

35% DD Submittal Craig Brandt 0.0 % 0.0d 03-Jul-2017 03-Jul-2017

35% DD Submission Review Laura Shadix 0.0 % 15.0d 05-Jul-2017 25-Jul-2017

35% DD Cost Estimate Submission Philip Blair 0.0 % 15.0d 05-Jul-2017 25-Jul-2017

35% DD Submittal Review/Develop Independent Cost Estimate Laura Shadix 0.0 % 15.0d 05-Jul-2017 25-Jul-2017

DD Onboard Review (Greenville) Laura Shadix 0.0 % 3.0d 26-Jul-2017 28-Jul-2017

VE Workshop (Location & Dates TBD) Laura Shadix 0.0 % 1.5d 31-Jul-2017 01-Aug-2017

VE Preliminary Report Due Laura Shadix 0.0 % 1.0d 01-Aug-2017 02-Aug-2017

Review VE Preliminary Report Laura Shadix 0.0 % 3.0d 02-Aug-2017 07-Aug-2017

Final VE Report Due Laura Shadix 0.0 % 2.0d 07-Aug-2017 09-Aug-2017

Construction Document Phase 0.0 % 214.0d 09-Aug-2017 05-Jun-2018

Exercise of CD Phase Option Swindale Rh… 0.0 % 1.1d 09-Aug-2017 10-Aug-2017

BIM Coordination Meeting Laura Shadix 0.0 % 1.0d 10-Aug-2017 11-Aug-2017

Envelope Integrity Coordination Meeting (date TBD) Laura Shadix 0.0 % 1.0d 10-Aug-2017 11-Aug-2017

In-Progress (65%) CD Development Craig Brandt 0.0 % 62.8d 10-Aug-2017 07-Nov-2017

In Progress (65%) USMS Coordination Meeting (DC) (Date to be coordinated with U… Craig Brandt 0.0 % 1.0d 24-Aug-2017 25-Aug-2017

In-Progress CD's 65% Construction Documents Submittal Craig Brandt 0.0 % 0.0d 07-Nov-2017 07-Nov-2017

In-Progress 65% CD Submittal Review Laura Shadix 0.0 % 20.0d 07-Nov-2017 05-Dec-2017

In-Progress (65%) Cost Estimate Submittal Philip Blair 0.0 % 0.0d 05-Dec-2017 05-Dec-2017

In-Progress (65%) Submittal Review / Development of IGE Laura Shadix 0.0 % 20.0d 07-Nov-2017 05-Dec-2017

In-Progress (65%) Design/Cost Review Meetings (Greenville) Laura Shadix 0.0 % 4.5d 05-Dec-2017 11-Dec-2017

CD Commissioning & Controls Integration Meeting Laura Shadix 0.0 % 1.0d 08-Dec-2017 11-Dec-2017

Pre-Final (90%) CD Development Craig Brandt 0.0 % 80.0d 07-Nov-2017 27-Feb-2018

Pre-Final 90% Construction Document Submittal Craig Brandt 0.0 % 0.0d 27-Feb-2018 27-Feb-2018

Pre-Final 90% Construction Document Submittal Review Laura Shadix 0.0 % 20.0d 27-Feb-2018 27-Mar-2018

Pre-Final (90%) CD Cost Estimate Submittal Philip Blair 0.0 % 0.0d 27-Mar-2018 27-Mar-2018

Pre-Final (90%) CD Submittal Review/ Development of IGE Laura Shadix 0.0 % 20.0d 27-Feb-2018 27-Mar-2018

Pre-Final (90%) CD Design/Cost Review Meetings (Greenville) Laura Shadix 0.0 % 4.5d 27-Mar-2018 02-Apr-2018

For Construction Set (100%) CD Development Craig Brandt 0.0 % 20.0d 27-Mar-2018 24-Apr-2018

For Construction Set (100%) CD Submittal w/ 100% Cost Estimate Craig Brandt 0.0 % 0.0d 24-Apr-2018 24-Apr-2018

2012 2013

Summary

Deleted Summary

Milestone

Deleted Milestone

Task

Critical Task

Deleted Task

Assignment

Deleted Assignment

Start On

Start No Earlier

Start No Later

Finish On

Finish No Earlier

Finish No Later

Start Float

Finish Float

Link

Critical Link

PM Milestone Schedule

Gantt Chart View

2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038

No Assignments100.0 %

No Assignments0.0 %

0.0 %

No Assignments0.0 %

No Assignments0.0 %

No Assignments0.0 %

No Assignments0.0 %

No Assignments0.0 %

No Assignments0.0 %

No Assignments0.0 %

No Assignments0.0 %

0.0 %

No Assignments0.0 %

No Assignments0.0 %

No Assignments0.0 %

No Assignments0.0 %

No Assignments0.0 %

0.0 %

No Assignments0.0 %

0.0 %

No Assignments0.0 %

No Assignments0.0 %

No Assignments0.0 %

No Assignments0.0 %

0.0 %

No Assignments0.0 %

0.0 %

No Assignments0.0 %

No Assignments0.0 %

No Assignments0.0 %

0.0 %

Summary

Deleted Summary

Milestone

Deleted Milestone

Task

Critical Task

Deleted Task

Assignment

Deleted Assignment

Start On

Start No Earlier

Start No Later

Finish On

Finish No Earlier

Finish No Later

Start Float

Finish Float

Link

Critical Link

PM Milestone Schedule

Gantt Chart View

Task Name Status Responsible % Compl…

Remain Duration

Early Start Early Finish Actual Start Actual Finish

For Construction Set (100%) CD Compliance Check (CM) Laura Shadix 0.0 % 20.0d 24-Apr-2018 22-May-2018

Final design corrections Craig Brandt 0.0 % 10.0d 22-May-2018 05-Jun-2018

Design Complete Craig Brandt 0.0 % 0.0d 05-Jun-2018 05-Jun-2018

Art In Architecture Laura Sha… 15.0 % 974.0d 19-May-2017 27-Jan-2021 06-Sep-2016

AiA Meetings Requiring Customer Presence 1 - Initial Art Panel Meeting (Greenville) Nicole Avila 100.0 % 0.0d 06-Sep-2016 06-Sep-2016 06-Sep-2016 06-Sep-2016

Post FedBizOps Announcement Swindale Rh… 100.0 % 0.0d 23-Sep-2016 23-Sep-2016 23-Sep-2016 23-Sep-2016

Receive Expressions of Interest Nicole Avila 100.0 % 0.0d 23-Sep-2016 25-Oct-2016 23-Sep-2016 25-Oct-2016

Establish the Competitive Field of Artist Candidates (2 months minimum) Nicole Avila 100.0 % 0.0d 07-Sep-2016 02-Nov-2016 07-Sep-2016 02-Nov-2016

AiA Meetings Requiring Customer Presence 2 - Artist Selection Meeting (Greenville) Nicole Avila 100.0 % 0.0d 18-Nov-2016 18-Nov-2016 18-Nov-2016 18-Nov-2016

Draft Report Nicole Avila 100.0 % 0.0d 21-Nov-2016 10-Feb-2017 21-Nov-2016 10-Feb-2017

Review and Approval of Report (RC Concurrence/ Chief Architect Approves) Nicole Avila 100.0 % 0.0d 13-Feb-2017 02-Mar-2017 13-Feb-2017 02-Mar-2017

Issue Project Agreement/Scope of Services to Selected Artist Swindale Rh… 100.0 % 0.0d 06-Mar-2017 06-Mar-2017 06-Mar-2017 06-Mar-2017

AiA Artist Contract Award Swindale Rh… 0.0 % 0.0d 19-May-2017 19-May-2017

AiA Meetings Requiring Customer Presence 3 - Artist Site Visit (Greenville) Nicole Avila 0.0 % 0.0d 16-Jun-2017 16-Jun-2017

Artist Preliminary Concept Design Audrey Entorf 0.0 % 40.0d 19-Jun-2017 11-Aug-2017

GSA Review Nicole Avila 0.0 % 20.0d 14-Aug-2017 08-Sep-2017

Artist Develops Final Concept Design Audrey Entorf 0.0 % 40.0d 11-Sep-2017 03-Nov-2017

AiA Meetings Requiring Customer Presence 4 - Artist Concept Presentation (Greenville) Nicole Avila 0.0 % 0.0d 10-Nov-2017 10-Nov-2017

Panel Review and Approval Final Concept (RC Concurrence/ Chief Architect Approval) Nicole Avila 0.0 % 20.0d 13-Nov-2017 08-Dec-2017

Artist prepares Design Development Documents Audrey Entorf 0.0 % 1.0d 05-Mar-2018 05-Mar-2018

GSA Review of Design Development Docs and Approval to begin Fabrication Audrey Entorf 0.0 % 1.0d 03-Apr-2018 03-Apr-2018

Fabrication and Installation Laura Shadix 0.0 % 650.0d 05-Jun-2018 01-Dec-2020

Plaque Installed Laura Shadix 0.0 % 1.0d 30-Nov-2020 01-Dec-2020

Project Documentation/ Photographs/ Maintenance Instructions Laura Shadix 0.0 % 1.0d 26-Jan-2021 27-Jan-2021

Finish Art In Architecture Laura Shadix 0.0 % 0.0d 27-Jan-2021 27-Jan-2021

CMa Procurement Laura Sha… 100.0… 0.0d 01-Sep-2016 06-Jan-2017 01-Sep-2016 06-Jan-2017

Finalize CMa Scope & IGE Laura Shadix 100.0 % 0.0d 01-Sep-2016 01-Sep-2016 01-Sep-2016 01-Sep-2016

PM Submits PR Laura Shadix 100.0 % 0.0d 01-Sep-2016 01-Sep-2016 01-Sep-2016 01-Sep-2016

Contracting Accepts PR Swindale Rh… 100.0 % 0.0d 07-Sep-2016 07-Sep-2016 07-Sep-2016 07-Sep-2016

Finalize CMa Aquisition Plan (ASP) Swindale Rh… 100.0 % 0.0d 08-Sep-2016 29-Sep-2016 08-Sep-2016 29-Sep-2016

Develop CMa Technical Evaluation Plan (TEP) (FAR Part 8) Laura Shadix 100.0 % 0.0d 08-Sep-2016 04-Oct-2016 08-Sep-2016 04-Oct-2016

2012 2013

Summary

Deleted Summary

Milestone

Deleted Milestone

Task

Critical Task

Deleted Task

Assignment

Deleted Assignment

Start On

Start No Earlier

Start No Later

Finish On

Finish No Earlier

Finish No Later

Start Float

Finish Float

Link

Critical Link

PM Milestone Schedule

Gantt Chart View

2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038

No Assignments0.0 %

No Assignments0.0 %

0.0 %

15.0 %

100.0 %

No Assignments100.0 %

No Assignments100.0 %

No Assignments100.0 %

100.0 %

No Assignments100.0 %

No Assignments100.0 %

No Assignments100.0 %

0.0 %

0.0 %

No Assignments0.0 %

No Assignments0.0 %

No Assignments0.0 %

0.0 %

No Assignments0.0 %

No Assignments0.0 %

No Assignments0.0 %

No Assignments0.0 %

No Assignments0.0 %

No Assignments0.0 %

0.0 %

100.0 %

100.0 %

No Assignments100.0 %

100.0 %

No Assignments100.0 %

No Assignments100.0 %

Summary

Deleted Summary

Milestone

Deleted Milestone

Task

Critical Task

Deleted Task

Assignment

Deleted Assignment

Start On

Start No Earlier

Start No Later

Finish On

Finish No Earlier

Finish No Later

Start Float

Finish Float

Link

Critical Link

PM Milestone Schedule

Gantt Chart View

Task Name Status Responsible % Compl…

Remain Duration

Early Start Early Finish Actual Start Actual Finish

Review and Approval of ASP & TEP Swindale Rh… 100.0 % 0.0d 05-Oct-2016 07-Oct-2016 05-Oct-2016 07-Oct-2016

Issue RFQ (GSA Schedule) Swindale Rh… 100.0 % 0.0d 11-Oct-2016 11-Oct-2016 11-Oct-2016 11-Oct-2016

Receive Cost and Technical Proposals Swindale Rh… 100.0 % 0.0d 11-Oct-2016 07-Nov-2016 11-Oct-2016 07-Nov-2016

Tech. Review and Evaluation of Proposals/ Develop Shortlist Laura Shadix 100.0 % 0.0d 09-Nov-2016 17-Nov-2016 09-Nov-2016 17-Nov-2016

Finalize Tech. Evaluation Report Laura Shadix 100.0 % 0.0d 30-Nov-2016 13-Dec-2016 30-Nov-2016 13-Dec-2016

Review & Approval of Tech. Evaluation Report (CRB/ Acquisition) Swindale Rh… 100.0 % 0.0d 14-Dec-2016 28-Dec-2016 14-Dec-2016 28-Dec-2016

CMa Contract Award Swindale Rh… 100.0 % 0.0d 06-Jan-2017 06-Jan-2017 06-Jan-2017 06-Jan-2017

Construction 72.2 % 299.5d 25-May-2017 23-Feb-2021 06-Jan-2017

CMa Award Swindale Rh… 100.0 % 0.0d 06-Jan-2017 06-Jan-2017 06-Jan-2017 06-Jan-2017

CXa Award Swindale Rh… 100.0 % 0.0d 06-Jan-2017 06-Jan-2017 06-Jan-2017 06-Jan-2017

Develop CMc Acquistion Plan Swindale Rh… 100.0 % 0.0d 17-Feb-2017 17-Feb-2017 17-Feb-2017 17-Feb-2017

Review & Approval of CMc Acquistion Plan (CRB/ Acquisition) Swindale Rh… 100.0 % 0.0d 27-Feb-2017 15-Mar-2017 27-Feb-2017 15-Mar-2017

CMc Acquisition Plan Finalized Swindale Rh… 100.0 % 0.0d 15-Mar-2017 15-Mar-2017 15-Mar-2017 15-Mar-2017

Develop & Finalize Source Selection Plan (SSP) Swindale Rh… 100.0 % 0.0d 01-Mar-2017 10-Apr-2017 01-Mar-2017 10-Apr-2017

Review & Approval of SSP (CRB/Acquisition/Legal) Swindale Rh… 100.0 % 0.0d 11-Apr-2017 24-Apr-2017 11-Apr-2017 24-Apr-2017

CMc Scope Issued to ODC for review Bill Cushist 100.0 % 0.0d 17-Apr-2017 17-Apr-2017 17-Apr-2017 17-Apr-2017

Review of CMc Scope (ODC) Marty Bowers 100.0 % 0.0d 18-Apr-2017 02-May-2017 18-Apr-2017 02-May-2017

Develop CMc IGE Laura Shadix 100.0 % 0.0d 18-May-2017 18-May-2017 18-May-2017 18-May-2017

PM Submits CMc PR (SoW, IGE) Laura Shadix 100.0 % 0.0d 18-May-2017 18-May-2017 18-May-2017 18-May-2017

Contracting Accepts CMc PR Swindale Rh… 100.0 % 0.0d 25-May-2017 25-May-2017 25-May-2017 25-May-2017

Draft FedBizOpps Announcement (Presolicitation Notice) Swindale Rh… 100.0 % 0.0d 28-Mar-2017 28-Mar-2017 28-Mar-2017 28-Mar-2017

Review & Approval of FedBizOpps Announcement (Presolicitation Notice) Laura Shadix 100.0 % 0.0d 29-Mar-2017 28-Apr-2017 29-Mar-2017 28-Apr-2017

Issue PreSolicitation Notice Swindale Rh… 100.0 % 0.0d 01-May-2017 01-May-2017 01-May-2017 01-May-2017

Construction RFP Issued Swindale Rh… 0.0 % 0.0d 26-May-2017 26-May-2017

Preproposal Conference (Greenville) Swindale Rh… 0.0 % 1.0d 25-May-2017 25-May-2017

Receipt of Offeror Questions Swindale Rh… 0.0 % 0.0d 07-Jun-2017 07-Jun-2017

Government Response Laura Shadix 0.0 % 0.0d 14-Jun-2017 14-Jun-2017

CMc Proposals Received Swindale Rh… 0.0 % 0.0d 30-Jun-2017 30-Jun-2017

Initiate Past Performance Evaluation Swindale Rh… 0.0 % 0.0d 03-Jul-2017 03-Jul-2017

Source Selection Evaluation (Develop Shortlist)(Atlanta) Laura Shadix 0.0 % 3.0d 05-Jul-2017 07-Jul-2017

Publish Shortlisted Firms in FedBizOpps Swindale Rh… 0.0 % 2.0d 10-Jul-2017 11-Jul-2017

2012 2013

Summary

Deleted Summary

Milestone

Deleted Milestone

Task

Critical Task

Deleted Task

Assignment

Deleted Assignment

Start On

Start No Earlier

Start No Later

Finish On

Finish No Earlier

Finish No Later

Start Float

Finish Float

Link

Critical Link

PM Milestone Schedule

Gantt Chart View

2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038

No Assignments100.0 %

100.0 %

No Assignments100.0 %

No Assignments100.0 %

No Assignments100.0 %

No Assignments100.0 %

100.0 %

72.2 %

100.0 %

100.0 %

No Assignments100.0 %

No Assignments100.0 %

100.0 %

No Assignments100.0 %

No Assignments100.0 %

100.0 %

No Assignments100.0 %

No Assignments100.0 %

100.0 %

100.0 %

No Assignments100.0 %

No Assignments100.0 %

100.0 %

0.0 %

No Assignments0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

No Assignments0.0 %

No Assignments0.0 %

Summary

Deleted Summary

Milestone

Deleted Milestone

Task

Critical Task

Deleted Task

Assignment

Deleted Assignment

Start On

Start No Earlier

Start No Later

Finish On

Finish No Earlier

Finish No Later

Start Float

Finish Float

Link

Critical Link

PM Milestone Schedule

Gantt Chart View

Task Name Status Responsible % Compl…

Remain Duration

Early Start Early Finish Actual Start Actual Finish

CMc Firms Interviewed (Atlanta) Swindale Rh… 0.0 % 0.0d 21-Jul-2017 21-Jul-2017

Request Final Proposal Revisions (FPR) Swindale Rh… 0.0 % 0.0d 26-Jul-2017 26-Jul-2017

Receive Final Proposal Revisions (FPR) Swindale Rh… 0.0 % 0.0d 09-Aug-2017 09-Aug-2017

SSEB Technical and Price Evaluations - Final Proposal Revisions (Atlanta) Laura Shadix 0.0 % 2.0d 10-Aug-2017 11-Aug-2017

Draft Source Selection Evaluation Board (SSEB) Report Laura Shadix 0.0 % 20.0d 14-Aug-2017 08-Sep-2017

Review and Approval of SSEB Report Laura Shadix 0.0 % 5.0d 11-Sep-2017 15-Sep-2017

CMc Firm Selected Swindale Rh… 0.0 % 0.0d 15-Sep-2017 15-Sep-2017

CMc Acquistion/Legal Reviews Started Swindale Rh… 0.0 % 0.0d 15-Sep-2017 15-Sep-2017

CMc Acquistion/Legal Reviews Completed Swindale Rh… 0.0 % 0.0d 22-Sep-2017 22-Sep-2017

CMc Award Swindale Rh… 0.0 % 0.0d 13-Oct-2017 13-Oct-2017

Debriefing of Offerors (Atlanta) Swindale Rh… 0.0 % 0.0d 24-Oct-2017 24-Oct-2017

Construction NTP Swindale Rh… 0.0 % 0.0d 05-Jun-2018 05-Jun-2018

Construction Peer Review 35% (Date to be coordinated with Project Delivery Team) Laura Shadix 0.0 % 0.0d 09-Apr-2019 09-Apr-2019

Construction Peer Review 65% (Date to be coordinated with Project Delivery Team) Laura Shadix 0.0 % 0.0d 14-Jan-2020 14-Jan-2020

Construction Peer Review 90% (Date to be coordinated with Project Delivery Team) Laura Shadix 0.0 % 0.0d 30-Jun-2020 30-Jun-2020

Substantial Completion Laura Shadix 0.0 % 0.0d 01-Dec-2020 01-Dec-2020

Construction Complete Laura Shadix 0.0 % 0.0d 23-Feb-2021 23-Feb-2021

Tenant 0.0 % 60.0d 06-Oct-2020 29-Dec-2020

Pre-Occupancy Tenant Access Laura Shadix 0.0 % 0.0d 06-Oct-2020 06-Oct-2020

Occupancy Laura Shadix 0.0 % 0.0d 29-Dec-2020 29-Dec-2020

Rent Start Laura Shadix 0.0 % 0.0d 01-Dec-2020 01-Dec-2020

Close out 0.0 % 0.0d 23-Feb-2021 23-Feb-2021

Project Close Out Laura Shadix 0.0 % 0.0d 23-Feb-2021 23-Feb-2021

2012 2013

Summary

Deleted Summary

Milestone

Deleted Milestone

Task

Critical Task

Deleted Task

Assignment

Deleted Assignment

Start On

Start No Earlier

Start No Later

Finish On

Finish No Earlier

Finish No Later

Start Float

Finish Float

Link

Critical Link

PM Milestone Schedule

Gantt Chart View

2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038

0.0 %

0.0 %

0.0 %

No Assignments0.0 %

No Assignments0.0 %

No Assignments0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

Summary

Deleted Summary

Milestone

Deleted Milestone

Task

Critical Task

Deleted Task

Assignment

Deleted Assignment

Start On

Start No Earlier

Start No Later

Finish On

Finish No Earlier

Finish No Later

Start Float

Finish Float

Link

Critical Link

File details come from the government source that posted it. Updated .