Greenville, SC Courthouse Project Greenville, South Carolina Solicitation No. GS-04-P-16-BV-C-7005

FY15 Update Oct. 1, 2014 Allowances 012100 - 1

SECTION 012100 - ALLOWANCES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. The Government is providing the references included in this sub-section for information purposes only and is not intended to provide a comprehensive, all-inclusive list of any and all potentially relevant portions of the Contract Documents. Drawings and general provisions of the Contract, including Federal Acquisition Regulations (FAR) and General Services Administration Acquisition Regulations (GSAR) contract clauses, and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements governing allowances.

1. Certain items may be described in the Contract Documents as allowance items. The purpose of allowance items is to defer selection of actual products and systems to a later date when direction will be provided to the Contractor. The Contracting Officer will issue Modifications to incorporate allowance items in the Work after actual products and systems have been determined.

B. Types of allowance items may include the following :

1. Lump-sum allowance items.

2. Unit-price allowance items.

3. Quantity allowance items.

1.3 SELECTION AND PURCHASE

A. At the earliest practical date after award of the Contract, advise the Contracting Officer of the date when final selection and purchase of each product or system described by an allowance item must be completed to avoid delaying the Work. Allowances must be included in all schedule submissions

1.4 ACTION SUBMITTALS

A. Submit proposals for products or systems described by allowance items in the form specified for Change Orders.

1.5 INFORMATIONAL SUBMITTALS

A. Submit copies of invoices or delivery slips to show actual quantities of materials delivered to the site for use in fulfillment of each unit-price and quantity allowance item.

B. Coordinate and process submittals for allowance items in same manner as for other portions of the Work.

Greenville, SC Courthouse Project Greenville, South Carolina Solicitation No. GS-04-P-16-BV-C-7005

FY15 Update Oct. 1, 2014 Allowances 012100 - 2

1.6 COORDINATION

A. Coordinate allowance items with other portions of the Work. Furnish templates as required to coordinate installation.

B. Modifications based on an allowance item shall include cost to Contractor of specific products and systems selected by the Contracting Officer under allowance and shall include taxes, freight, delivery to Project site, Contractor's costs for receiving and handling at Project site, labor, installation, overhead, and profit.

1. If requested by the Contracting Officer, purchase additional quantities under unit-price or quantity allowances and prepare unused material for storage by Contracting Officer.

Deliver unused material to Contracting Officer's storage space as directed.

1.7 ADJUSTMENT OF ALLOWANCE ITEMS

A. Modifications to an allowance item shall comply with the changes clauses and any other contract modifications procedures found in the Contract Documents.

B. Contracting Officer reserves the right to establish the quantity of work-in-place by independent quantity survey, measure, or count.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine products covered by an allowance item promptly on delivery for damage or defects.

Return damaged or defective products to manufacturer for replacement.

3.2 PREPARATION

A. Coordinate materials and their installation for each allowance item with related materials and installations to ensure that each allowance item is completely integrated and interfaced with related work.

3.3 SCHEDULE OF ALLOWANCE ITEMS

A. Allowance Item No. 01: Unit-Price Allowance for Partnering sessions.

END OF SECTION 012100

PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. The Government is providing the references included in this sub-section for information purposes only and is not intended to provide a comprehensive, all-inclusive list of any and all potentially relevant portions of the Contract Documents. Drawin...
1.2 SUMMARY
A. Section includes administrative and procedural requirements governing allowances.
1. Certain items may be described in the Contract Documents as allowance items. The purpose of allowance items is to defer selection of actual products and systems to a later date when direction will be provided to the Contractor. The Contracting Of...
B. Types of allowance items may include the following :
1. Lump-sum allowance items.
2. Unit-price allowance items.
3. Quantity allowance items.
1.3 SELECTION AND PURCHASE
A. At the earliest practical date after award of the Contract, advise the Contracting Officer of the date when final selection and purchase of each product or system described by an allowance item must be completed to avoid delaying the Work. Allowan...
1.4 ACTION SUBMITTALS
A. Submit proposals for products or systems described by allowance items in the form specified for Change Orders.
1.5 INFORMATIONAL SUBMITTALS
A. Submit copies of invoices or delivery slips to show actual quantities of materials delivered to the site for use in fulfillment of each unit-price and quantity allowance item.
B. Coordinate and process submittals for allowance items in same manner as for other portions of the Work.
1.6 COORDINATION
A. Coordinate allowance items with other portions of the Work. Furnish templates as required to coordinate installation.
B. Modifications based on an allowance item shall include cost to Contractor of specific products and systems selected by the Contracting Officer under allowance and shall include taxes, freight, delivery to Project site, Contractor's costs for receiv...
1. If requested by the Contracting Officer, purchase additional quantities under unit-price or quantity allowances and prepare unused material for storage by Contracting Officer. Deliver unused material to Contracting Officer's storage space as direc...
1.7 ADJUSTMENT OF ALLOWANCE ITEMS
A. Modifications to an allowance item shall comply with the changes clauses and any other contract modifications procedures found in the Contract Documents.
B. Contracting Officer reserves the right to establish the quantity of work-in-place by independent quantity survey, measure, or count.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine products covered by an allowance item promptly on delivery for damage or defects. Return damaged or defective products to manufacturer for replacement.
3.2 PREPARATION
A. Coordinate materials and their installation for each allowance item with related materials and installations to ensure that each allowance item is completely integrated and interfaced with related work.
3.3 SCHEDULE OF ALLOWANCE ITEMS
A. Allowance Item No. 01: Unit-Price Allowance for Partnering sessions.
END OF SECTION 012100

Other files

File Type Posted
0003_Solicitation_Amendment_GS-04-P-16-BV-C-7005_0003.pdf PDF
0002_Solicitation_Amendment_GS-04-P-16-BV-C-7005R.pdf PDF
0001_Solicitation_Amendment_GS-04-P-16-BV-C-7005_0001R.pdf PDF
GSA 013600COBieFY15UpdateOct.12014_SolicitationNo.GS-04-P-16-BV-C-7005.docx.pdf PDF
Technology Policy for PBS-Owned Buildings Monitoring _ Control Systems.pdf PDF
GSA 014100 Structural Testing Laboratory Services FY15 Update Oct. 1, 2014_Solicitation No. GS-04-P-16-BV-C-7005.pdf PDF
GSA 013300 Submittal Procedures FY15 Update Oct. 1, 2014_Solicitation No. GS-04-P-16-BV-C-7005.pdf PDF
06032016 FitForPurposeintheChangingClimate Greenville SC.pdf PDF
TheSolicitation_GreenvilleSC.pdf PDF
GSA 016000 Product Requirements FY15 Update Oct. 1, 2014.pdf PDF
GSA 015930SecurityRegulationsFY15UpdateOct.12014.docx.pdf PDF
Updated Meeting Schedule Matrix_Design Restart_R02_082216.pdf PDF
GSA 013100 Project Management _ Coordination FY15 Update Oct. 1, 2014_Solicitation No. GS-04-P-16-BV-C-7005.pdf PDF
SITESv2_Scorecard.pdf PDF
NBSAP_Clarification2_2014 Jun -4762.pdf PDF
Greenville SC AE SOW CONTRACT MODIFICATION_6-17-16_FINAL_R04.pdf PDF
Project Milestone Schedule Update May 25 2017.pdf PDF
USAO Design Guide 10-13-15.pdf PDF
CMc_Pricing_Sheet_Attachment_A_REV_01.pdf PDF
CMcSOW_Greenville_SC_CTHS_Attachment_B.pdf PDF
GSA__Form527-15b_(1).pdf PDF
GSA 012900 Payment Procedures FY15 Update Oct. 1, 2014_Solicitation No. GS-04-P-16-BV-C-7005.pdf PDF
GSA 017000ExecutionRequirementsFY15UpdateOct.12014.docx.pdf PDF
SITESv2_RatingSystem —
Courts Mailroom Construction Guidelines.pdf PDF
SF_1442_GS-04-P-16-BV-C-7005__Greenville_SC_CMc_Solicitation.pdf PDF
GSA 014025QualityControlTestingforAirBarriersFY15UpdateOct.12014_SolicitationNo.GS-04-P-16-BV-C-7005.docx.pdf PDF
GSA 015639TreePlantProtectionFY15UpdateOct.12014.docx.pdf PDF
GSA 014200ReferencesFY15UpdateOct.12014_SolicitationNo.GS-04-P-16-BV-C-7005.doc.pdf PDF
US Courts Design Guide 2007.pdf PDF
2017-04-18-finishes.pdf PDF
The_Agreement_Greenvill_SC_CMc_May_15_2017_(1).pdf PDF
Greenville, SC Courthouse Project Phase II ESA report - PHE May 27, 2010.pdf PDF
GSA 017410 Construction Indoor Air Quality FY15 Update Oct. 1, 2014.pdf PDF
2014 Final, Pub 64 Revised.pdf PDF
CMc301_Reps_and_Certs_Attachment_C.docx DOCX document
GSA 017810ProjectRecordDocumentsFY15UpdateOct.12014.docx.pdf PDF
GSA 018111SustainableDesignRequirementsFY15UpdateOct.12014.docx.pdf PDF
GSA 017350 Fire Prevention Precautions for Hot Work FY15 Update Oct. 1, 2014.pdf PDF
NBSAP_Clarification1_2013 July Final-VOIDs.pdf PDF
GSA 017419ConstructionNonhazardousWasteManagementDisposalFY15UpdateOct.12014.docx.pdf PDF
PBS_P_3490.2_Document_Security_for_Sensitive_But_Unclassified_Building_Information_-_(Signed_on_Sept._2__2014).pdf PDF
GSA 017822 Operation _ Maintenance Documentation FY15 Update Oct. 1, 2014.pdf PDF
GSA 014000 Quality Assurance _ Control FY15 Update Oct. 1, 2014_Solicitation No. GS-04-P-16-BV-C-7005.pdf PDF
Layout_of_Water_Main_DOC120616-12062016151956_(1).pdf PDF
SpringSt1_Irvine_2017_Water Main Relocation_Greenville SC CTHS Project.pdf PDF
GSARegion4BuildingAutomationSystemRequirementsv6.pdf PDF
NBSAP_Final_Feb 2013.pdf PDF
GSA 013000 Electronic Project Management FY15 Update Oct. 1, 2014_Solicitation No. GS-04-P-BV-C-7005.pdf PDF
GSA 013200 Construction Progress Documentation FY15 Update Oct. 1, 2014_Solicitation No. GS-04-P-16-BV-C-7005.pdf PDF
Show 40 more

Latest 50 of 79 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .