GSA 017350 Fire Prevention Precautions for Hot Work FY15 Update Oct. 1, 2014.pdf

PDF 27 KB Posted

Attached to
Construction Manager as Constructor (CMc), New - Greenville, SC Federal Courthouse Building
Solicitation number
GS--04-P-16-BV-C-7005
Issued by

About this file

GSA 017350 Fire Prevention Precautions for Hot Work

View the file

Other files

File Type Posted
0003_Solicitation_Amendment_GS-04-P-16-BV-C-7005_0003.pdf PDF
0002_Solicitation_Amendment_GS-04-P-16-BV-C-7005R.pdf PDF
0001_Solicitation_Amendment_GS-04-P-16-BV-C-7005_0001R.pdf PDF
GSA 013600COBieFY15UpdateOct.12014_SolicitationNo.GS-04-P-16-BV-C-7005.docx.pdf PDF
Technology Policy for PBS-Owned Buildings Monitoring _ Control Systems.pdf PDF
GSA 014100 Structural Testing Laboratory Services FY15 Update Oct. 1, 2014_Solicitation No. GS-04-P-16-BV-C-7005.pdf PDF
GSA 013300 Submittal Procedures FY15 Update Oct. 1, 2014_Solicitation No. GS-04-P-16-BV-C-7005.pdf PDF
06032016 FitForPurposeintheChangingClimate Greenville SC.pdf PDF
TheSolicitation_GreenvilleSC.pdf PDF
GSA 016000 Product Requirements FY15 Update Oct. 1, 2014.pdf PDF
GSA 015930SecurityRegulationsFY15UpdateOct.12014.docx.pdf PDF
Updated Meeting Schedule Matrix_Design Restart_R02_082216.pdf PDF
GSA 013100 Project Management _ Coordination FY15 Update Oct. 1, 2014_Solicitation No. GS-04-P-16-BV-C-7005.pdf PDF
SITESv2_Scorecard.pdf PDF
NBSAP_Clarification2_2014 Jun -4762.pdf PDF
Greenville SC AE SOW CONTRACT MODIFICATION_6-17-16_FINAL_R04.pdf PDF
Project Milestone Schedule Update May 25 2017.pdf PDF
USAO Design Guide 10-13-15.pdf PDF
CMc_Pricing_Sheet_Attachment_A_REV_01.pdf PDF
CMcSOW_Greenville_SC_CTHS_Attachment_B.pdf PDF
GSA__Form527-15b_(1).pdf PDF
GSA 012900 Payment Procedures FY15 Update Oct. 1, 2014_Solicitation No. GS-04-P-16-BV-C-7005.pdf PDF
GSA 017000ExecutionRequirementsFY15UpdateOct.12014.docx.pdf PDF
SITESv2_RatingSystem —
Courts Mailroom Construction Guidelines.pdf PDF
SF_1442_GS-04-P-16-BV-C-7005__Greenville_SC_CMc_Solicitation.pdf PDF
GSA 014025QualityControlTestingforAirBarriersFY15UpdateOct.12014_SolicitationNo.GS-04-P-16-BV-C-7005.docx.pdf PDF
GSA 015639TreePlantProtectionFY15UpdateOct.12014.docx.pdf PDF
GSA 012100 Allowances FY15 Update Oct. 1, 2014_Solicitation No. GS-04-P-16-BV-C-7005 —
GSA 014200ReferencesFY15UpdateOct.12014_SolicitationNo.GS-04-P-16-BV-C-7005.doc.pdf PDF
US Courts Design Guide 2007.pdf PDF
2017-04-18-finishes.pdf PDF
The_Agreement_Greenvill_SC_CMc_May_15_2017_(1).pdf PDF
Greenville, SC Courthouse Project Phase II ESA report - PHE May 27, 2010.pdf PDF
GSA 017410 Construction Indoor Air Quality FY15 Update Oct. 1, 2014.pdf PDF
2014 Final, Pub 64 Revised.pdf PDF
CMc301_Reps_and_Certs_Attachment_C.docx DOCX document
GSA 017810ProjectRecordDocumentsFY15UpdateOct.12014.docx.pdf PDF
GSA 018111SustainableDesignRequirementsFY15UpdateOct.12014.docx.pdf PDF
NBSAP_Clarification1_2013 July Final-VOIDs.pdf PDF
GSA 017419ConstructionNonhazardousWasteManagementDisposalFY15UpdateOct.12014.docx.pdf PDF
PBS_P_3490.2_Document_Security_for_Sensitive_But_Unclassified_Building_Information_-_(Signed_on_Sept._2__2014).pdf PDF
GSA 017822 Operation _ Maintenance Documentation FY15 Update Oct. 1, 2014.pdf PDF
GSA 014000 Quality Assurance _ Control FY15 Update Oct. 1, 2014_Solicitation No. GS-04-P-16-BV-C-7005.pdf PDF
Layout_of_Water_Main_DOC120616-12062016151956_(1).pdf PDF
SpringSt1_Irvine_2017_Water Main Relocation_Greenville SC CTHS Project.pdf PDF
GSARegion4BuildingAutomationSystemRequirementsv6.pdf PDF
NBSAP_Final_Feb 2013.pdf PDF
GSA 013000 Electronic Project Management FY15 Update Oct. 1, 2014_Solicitation No. GS-04-P-BV-C-7005.pdf PDF
GSA 013200 Construction Progress Documentation FY15 Update Oct. 1, 2014_Solicitation No. GS-04-P-16-BV-C-7005.pdf PDF
Show 40 more

Latest 50 of 79 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Greenville, SC Courthouse Project Greenville, South Carolina Solicitation No. GS-04-P-16-BV-C-7005

FY15 Update Oct. 1, 2014 Fire Prevention Precautions for Hot Work 017350 - 1

SECTION 017350 - FIRE PREVENTION PRECAUTIONS FOR HOT WORK

PART 1 - GENERAL

1.1 SUMMARY

A. This section applies to safeguards to be observed in performing hot work, including welding, soldering, brazing and other operations where open flames or implements utilizing heat are used.

B. Hot Work Permit: Comply with NFPA 51B. Do not conduct operations involving the use of open-flame, electrical arc equipment, or flammable substances until a permit for welding, cutting, and burning has been issued by the Government.

1. GSA will identify and delineate the responsibilities of the Government permit authorizing individual before or during the Preconstruction Meeting.

C. Hot work permit duration shall be one work shift for a specific location unless otherwise agreed to by the Government and Contractor.

1.2 SAFETY PRECAUTIONS

A. Prior to operations, the site shall be visited and suitable locations established for the portable equipment storage during non-working hours. The Contractor and the Government shall coordinate and designate such locations. The Contractor shall ensure that operations involving the use of open-flame, electrical arc equipment or flammable substances are not conducted until a permit for welding, cutting, and burning has been completed, signed and issued by the GSA Building Manager.

B. The GSA Building Manager must approve the location of asphalt kettles for roofing work.

C. Prior to commencing operations, a positive determination shall be made that it is impractical to conduct the hot work in a shop area or outside of the building. Coordinate suitable locations for hot equipment operations agreeable to the Contracting Officer’s Representative.

1.3 NOTIFICATON

A. The Contractor shall notify GSA’s Building Manager at least 24 hours in advance of the area of operations for each day and of all subsequent changes that occur.

B. The Contractor shall notify the GSA Building Manager of all locations where hot work has been performed not less than 30 minutes before the work or no more than 90 minutes after work is completed or stopped for the day.

PART 2 - PRODUCTS (Not Applicable)

PART 3 - EXECUTION

FY15 Update Oct. 1, 2014 Fire Prevention Precautions for Hot Work 017350 - 2

3.1 INSPECTION

A. Before starting operations, the Contractor shall furnish trained personnel to provide fire watches for locations where hot work is to be performed. One fire watcher may observe no more than two (2) locations if in a relatively small contiguous area if approved by the Contracting Officer's Representative and in compliance with applicable fire codes. Contractor shall furnish suitable type, fully-charged, operable portable fire extinguisher to each fire watcher.

1. The Contractor shall provide fire watchers who know how to operate the fire extinguisher, how to initiate a fire alarm and how to summon the fire department.

B. Before starting operations, take suitable precautions to minimize the hazard of a fire communicating to the opposite side of walls, floors, ceilings and roofs from the operations.

3.2 SAFETY MEASURES

A. Hot work shall not be done in or near rooms or areas where flammable liquids or explosive vapors are present or thought to be present. A combustible gas indicator (explosimeter) test shall be conducted to assure that each area is safe. The Contractor is responsible for arranging and paying for each test.

B. Insofar as possible, the Contractor shall remove and keep the area free from all combustibles, including rubbish, paper and waste within a radius of 25 feet (7.62 m) from hot operations.

1. If combustible material cannot be removed, the Contractor shall furnish fireproof blankets to cover such materials. At the direction of the Building Manager or Contracting Officer's Representative, floors, walls, and ceilings of combustible material shall be wetted thoroughly with water before, during, and after operations sufficiently to afford adequate protection.

2. Where possible, the Contractor shall furnish and use baffles of metal or gypsum board to prevent the spraying of sparks, hot slag and other hot particles into surrounding combustible material.

C. The Contractor shall prevent the spread of sparks and particles of hot metal through open windows, doors, and holes and cracks in floors, walls, ceilings and roofs.

D. Cylinders of gas used in hot work shall be placed a safe distance from the work. The Contractor shall provide hoses and equipment free of deterioration, malfunction and leaks. Suitable supports shall be provided to prevent accidental overturning of cylinders. All cylinder control valves shall be shut off while in use with the gas pressure regulator set at 15 psi (103 kPa) or less.

E. When hot work operations are completed or ended for the day, each location of the day’s work shall be inspected by the Contractor 60 minutes after completion of operations to detect for hidden or smoldering fires and to ensure that proper housekeeping is maintained. Contractor shall cleanup the area of work at the end of each shift or workday. Contractor shall provide a continuous fire watch at least 24 hours after the burning work has been completed

F. Where sprinkler protection exists, the sprinkler system shall be maintained without interruption while operations are being performed. If operations are performed close to automatic sprinkler heads, gypsum board sheets or damp cloth guards may be used to shield the individual heads temporarily. The heads shall be inspected by the Contractor immediately after hot work operations cease, to ensure all materials have been removed from the heads and that the heads have not been damaged.

FY15 Update Oct. 1, 2014 Fire Prevention Precautions for Hot Work 017350 - 3

G. Suitable type, fully-charged, operable portable fire extinguisher shall be available at all times during hot work operations.

H. If any of the above safeguards are not employed or are violated, the Government may verbally stop the Work followed by written notice until compliance is obtained. Such stoppage shall not relieve the Contractor form performing his work within the Contract period for the Contract price.

END OF SECTION 017350

PART 1 - GENERAL
1.1 SUMMARY
A. This section applies to safeguards to be observed in performing hot work, including welding, soldering, brazing and other operations where open flames or implements utilizing heat are used.
B. Hot Work Permit: Comply with NFPA 51B. Do not conduct operations involving the use of open-flame, electrical arc equipment, or flammable substances until a permit for welding, cutting, and burning has been issued by the Government.
1. GSA will identify and delineate the responsibilities of the Government permit authorizing individual before or during the Preconstruction Meeting.

C. Hot work permit duration shall be one work shift for a specific location unless otherwise agreed to by the Government and Contractor.

1.2 SAFETY PRECAUTIONS
A. Prior to operations, the site shall be visited and suitable locations established for the portable equipment storage during non-working hours. The Contractor and the Government shall coordinate and designate such locations. The Contractor shall ...
B. The GSA Building Manager must approve the location of asphalt kettles for roofing work.
C. Prior to commencing operations, a positive determination shall be made that it is impractical to conduct the hot work in a shop area or outside of the building. Coordinate suitable locations for hot equipment operations agreeable to the Contractin...
1.3 NOTIFICATON
A. The Contractor shall notify GSA’s Building Manager at least 24 hours in advance of the area of operations for each day and of all subsequent changes that occur.
B. The Contractor shall notify the GSA Building Manager of all locations where hot work has been performed not less than 30 minutes before the work or no more than 90 minutes after work is completed or stopped for the day.
PART 2 - PRODUCTS (Not Applicable)
PART 3 - EXECUTION
3.1 INSPECTION
A. Before starting operations, the Contractor shall furnish trained personnel to provide fire watches for locations where hot work is to be performed. One fire watcher may observe no more than two (2) locations if in a relatively small contiguous are...
1. The Contractor shall provide fire watchers who know how to operate the fire extinguisher, how to initiate a fire alarm and how to summon the fire department.

B. Before starting operations, take suitable precautions to minimize the hazard of a fire communicating to the opposite side of walls, floors, ceilings and roofs from the operations.

3.2 SAFETY MEASURES
A. Hot work shall not be done in or near rooms or areas where flammable liquids or explosive vapors are present or thought to be present. A combustible gas indicator (explosimeter) test shall be conducted to assure that each area is safe. The Contra...
B. Insofar as possible, the Contractor shall remove and keep the area free from all combustibles, including rubbish, paper and waste within a radius of 25 feet (7.62 m) from hot operations.
1. If combustible material cannot be removed, the Contractor shall furnish fireproof blankets to cover such materials. At the direction of the Building Manager or Contracting Officer's Representative, floors, walls, and ceilings of combustible materi...
2. Where possible, the Contractor shall furnish and use baffles of metal or gypsum board to prevent the spraying of sparks, hot slag and other hot particles into surrounding combustible material.
C. The Contractor shall prevent the spread of sparks and particles of hot metal through open windows, doors, and holes and cracks in floors, walls, ceilings and roofs.
D. Cylinders of gas used in hot work shall be placed a safe distance from the work. The Contractor shall provide hoses and equipment free of deterioration, malfunction and leaks. Suitable supports shall be provided to prevent accidental overturning ...
E. When hot work operations are completed or ended for the day, each location of the day’s work shall be inspected by the Contractor 60 minutes after completion of operations to detect for hidden or smoldering fires and to ensure that proper housekeep...
F. Where sprinkler protection exists, the sprinkler system shall be maintained without interruption while operations are being performed. If operations are performed close to automatic sprinkler heads, gypsum board sheets or damp cloth guards may be ...
G. Suitable type, fully-charged, operable portable fire extinguisher shall be available at all times during hot work operations.
H. If any of the above safeguards are not employed or are violated, the Government may verbally stop the Work followed by written notice until compliance is obtained. Such stoppage shall not relieve the Contractor form performing his work within the ...