CMc_Pricing_Sheet_Attachment_A_REV_01.pdf
PDF 71 KB Posted
- Attached to
- Construction Manager as Constructor (CMc), New - Greenville, SC Federal Courthouse Building
- Solicitation number
- GS--04-P-16-BV-C-7005
About this file
CMc_Pricing_Sheet_Attachment_A_REV_01.pdf
View the file
Other files
Show 40 more
Latest 50 of 79 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Standard Form (SF) 1442, Page 1 of 2
CONSTRUCTION MANAGER AS CONSTRUCTOR CONTRACT
Attachment No. “A” Pricing Schedule May 15, 2017
RFP Solicitation GS-04-P-16-BV-C-7005
Greenville, SC Courthouse Project, Greenville, SC
CMc Design Phase Services (Base Contract inclusive of Profit, Overhead, Fringes)
A. Total Firm Fixed Fee for Design Phase Services $_______________________________
B. Design Phase Markups for additional CMc Services Not Included in this scope -
Overhead _______________% Profit___________________% Commission_____________%
Construction Phase Work (Option)
(1) Target Estimated Cost of Work (ECW) $_______________________________
CMc Construction Phase Services Option I
(2) CMc Contingency Allowance (1 x 3%) $_______________________________
(3) Fee (Commission, Overhead, and Profit) $_______________________________
(4) Option I Guaranteed Maximum Price (GMP) (1 + 2 + 3) $_______________________________
(5) Target Estimated Cost of Work (ECW) $_______________________________
CMc Construction Option II: (Site Demolition)
(6) CMc Contingency Allowance (5 x 3%) $_______________________________
(7) Fee (Commission, Overhead, and Profit) $_______________________________
(8) Option II Guaranteed Maximum Price (GMP) (5 + 6 + 7) $_______________________________
(9) Target Estimated Cost of Work (ECW) $_______________________________
CMc Construction Option III: (Water Main Relocation)
(10) CMc Contingency Allowance (9 x 3%) $_______________________________
(11) Fee (Commission, Overhead, and Profit) $_______________________________
(12)Option III Guaranteed Maximum Price (GMP)(9 +10 +11) $_______________________________
Standard Form (SF) 1442, Page 1 of 2
CONSTRUCTION MANAGER AS CONSTRUCTOR CONTRACT
(13) Unit Pricing per Partnering Session $________________________
(14)Total Evaluated Price (A + 4 + 8 +12+13) $________________________
Construction Phase Markups For changes in construction services to be negotiated, if any, not included in this scope.
Overhead % Profit %
Commission % Extended Overhead (per calendar day)____________
Offerors are hereby advised that failure to offer on all items in the solicitation (i.e. , base, options) will render the offer non responsive and therefore will be rejected.