GSA 018111SustainableDesignRequirementsFY15UpdateOct.12014.docx.pdf
PDF 21 KB Posted
- Attached to
- Construction Manager as Constructor (CMc), New - Greenville, SC Federal Courthouse Building
- Solicitation number
- GS--04-P-16-BV-C-7005
About this file
GSA 018111SustainableDesignRequirementsFY15UpdateOct
View the file
Other files
Show 40 more
Latest 50 of 79 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Greenville, SC Courthouse Project Greenville, South Carolina Solicitation No. GS-04-P-16-BV-C-7005
FY15 Update Oct. 1, 2014 Sustainable Design Requirements 018111 -- 1
SECTION 018111 -- SUSTAINABLE DESIGN REQUIREMENTS
PART 1 – GENERAL
1. SUMMARY
A. This Section describes general requirements and procedures to comply with the Guiding Principles for Federal Leadership in High Performance and Sustainable Buildings, Executive Orders 13423 and 13514, the Energy Policy Act of 2005 (EPAct 2005), and the Energy Independence and Security Act of 2007 (EISA 2007).
B. Contractor shall be required to coordinate with subsequent technical sections herein as to the sustainability requirements.
1.1 OBJECTIVES
A. Aside from the LEED® credits for use of recycled materials, the GSA is required to buy recovered materials as designated by the U.S. Environmental Protection Agency (EPA) through the comprehensive procurement guidelines (CPG). Information can be obtained about the EPA list of designated products and accompanying recycled–content recommendations on the internet at www.epa.gov/cpg. Additional requirements for use of biobased, rapidly renewable content, and recycled content materials are as per P100 2010 page 94.
B. gBuild -Green Building Upgrade Information Lifecycle Database is GSA’s system for tracking and reporting high-performance green building (HPGB) related data. gBUILD allows project teams to collaborate in a centralized secure environment that reduces and streamlines data calls for program-wide reporting. Internal GSA users and external users will be provided usernames and passwords.
1.2 RELATED DOCUMENTS
The Government is providing the references included in this sub-section for information purposes only and is not intended to provide a comprehensive, all-inclusive list of any and all potentially relevant portions of the Contract Documents.
A. Section 017410 Construction Indoor Air Quality Management
B. Section 017419 Construction Nonhazardous Waste & Management Disposal
C. Section 018109 Testing for Indoor Air Quality
D. Section 019113 Commissioning http://www.epa.gov/cpg
Greenville, SC Courthouse Project Greenville, South Carolina Solicitation No. GS-04-P-16-BV-C-7005
FY15 Update Oct. 1, 2014 Sustainable Design Requirements 018111 -- 2
1.3 SUBMITTALS
A. Shall meet LEED documentation requirements. In the event that the Contractor's submittal cannot comply with both standards, then the more stringent standard shall apply.
B. Commissioning: See Section 019113 Commissioning for submittal requirements.
C. Sustainable Design Progress Reports: Concurrent with each Application for Payment, submit reports for the following:
1. Construction Waste Management: Waste reduction progress reports and logs complying with the requirements of Section 017419 Construction Nonhazardous Waste & Management Disposal.
2. Construction IAQ Management: See section 017410 Construction Indoor Air Quality Management for Construction IAQ management progress report requirements.
1.4 QUALITY CONTROL
A. Preconstruction Meeting: After award of Contract and prior to the commencement of the Work, schedule and conduct meeting with Owner, Architect, and all Subcontractors to discuss sustainability requirements, expected submittals, the Construction Waste Management Plan, and the required Construction Indoor Air Quality (IAQ) Management Plan. The purpose of this meeting is to develop a mutual understanding of the project’s sustainable design requirements and coordination of the Contractor’s management of these requirements with the Contracting Officer and the Construction Quality Manager.
B. Construction Job Conferences: The status of compliance with the sustainable design requirements of these specifications will be an agenda item at all regular job meetings conducted during the course of work at the site.
PART 2 - PRODUCTS
Products and processes that minimize environmental impact to the extent currently possible have been included in the Construction Documents. These products include but are not limited to paint, gypsum wall board, carpet, acoustic ceiling tile and concrete. The Contractor is responsible for maintaining and supporting these objectives in developing means and methods for performing the work of this Contract and in proposing product substitutions and/or changes to specified processes.
END OF SECTION 018111