This document contains questions from industry relating to a solicitation for C-130 contract depot maintenance and mid-cycle paint services. The solicitation will be a five-year IDIQ contract awarded to one contractor located within the CONUS region. The contract will include firm fixed price and other contract types for travel, fuel, and over and above work. Services required are C-130H and J PDM, UDLM, and mid-cycle paint for aircraft that cannot be handled organically by USAF depots due to capacity constraints. The document provides clarification such as pricing being based on quantity bands by fiscal year, over and above tasks including material costs, and assumptions for technical evaluations being non-binding.

View the file

Other files

File Type Posted
RFP_Atch_2_C130_UDLM_PDM_Pricing_Model_dtd_8Jan2020.xlsx XLSX spreadsheet
RFP_Atch_1_C130_PWS_UDLM_PDM_07Jan2020.pdf PDF
Amendment_ FA850420R0001_ 0001_dtd_16Jan20.pdf PDF
RFP_Atch_2_C130_UDLM_PDM_Pricing_Model_dtd_8Jan2020.pdf PDF
Revision 01 - Industry Questions with USG Responses to UDLM PDM RFP - 14 Jan 2020.pdf PDF
RFP_Atch_4_C130_UDLM_PDM_DD_254_dtd_22Oct19.pdf PDF
RFP_Atch_11_C130_UDLM_PDM_Consent_Form_dtd_21Oct19.pdf PDF
C130_PWS_UDLM_PDM_App_F_C130HJ_ Work Control Document_Master Operations Coversheet_dtd_21Oct19.pdf PDF
RFP_Atch_9_C130_UDLM_PDM_Past_Performance_Questionnaire_dtd_5Nov19.pdf PDF
C130_PWS_UDLM_PDM_App_C_C130_FY19_CDMWA_dtd_21Oct19.pdf PDF
RFP_Atch_18_C130_UDLM_PDM_GFP_List_dtd_22Oct19.pdf PDF
C130_PWS_UDLM_PDM_App_F_C130HJ _ Work Cards_WCD _Master Operations_dtd_19Mar19.xlsx XLSX spreadsheet
RFP_Atch_8_C130_UDLM_PDM_Section_M_dtd_4 Nov 19.pdf PDF
C130_PWS_UDLM_PDM_App_H_Examples_dtd_ 2019 09 12.pdf PDF
RFP_Atch_7_C130_UDLM_PDM_Section_L_dtd_4Nov 19.pdf PDF
C130_PWS_UDLM_PDM_App_E_USG_IS_Access_Matrix_dtd_7Nov19.pdf PDF
C130_PWS_UDLM_PDM_App_A_C130HJ_Work_Spec_FY20_dtd_12Sep19.pdf PDF
C130_PWS_UDLM_PDM_App_B_C130HJ_Catalog_M_Task_FFP_List_dtd_31Oct19.pdf PDF
RFP_Atch_6_C130_UDLM_PDM_TO_Library_Access_Procedures_dtd_21OCT19.pdf PDF
RFP_Atch_13_C130_UDL_PDM_Relevancy_Table_dtd_5Nov19.pdf PDF
RFP_Atch_3_C130_UDLM_PDM_CDRLS_dtd_31Oct19.pdf PDF
RFP_Atch_10_C130_UDLM_PDM_Client_Authorization_Letter_dtd_21Oct19.pdf PDF
RFP_Atch_17_C130_UDLM_PDM_Safety_dtd_12Feb29.pdf PDF
FA850420R0001 dtd 27 Nov 19.pdf PDF
RFP_Atch_12_C130_UDLM_PDM_Transmittal_Letter_dtd_21Oct19.pdf PDF
RFP_Atch_1_C130_PWS_UDLM_PDM_dtd_5Nov19.pdf PDF
C130_PWS_UDLM_PDM_App_D_C130J_Aircraft_Mid-Cycle_Paint_Work_Specs_dtd_21Oct19.pdf PDF
RFP_Atch_14_C130_UDLM_PDM_Electronic_Format_for_All_Proposal_Volumes_dtd_21Oct19.pdf PDF
RFP_Atch_2_C130_UDLM_PDM_Pricing_Model_dtd_31Oct19.xlsx XLSX spreadsheet
RFP_Atch_15_C130_UDML_PDM_PPI_for_Offerors_undated.pdf PDF
C130_PWS_UDLM_PDM_App_G_Acronym_List_dtd_21Oct19.pdf PDF
RFP_Atch_5_C130_UDLM_PDM_Packaging_Form_158_dtd_19Apr19.pdf PDF
RFP_Atch_16_C130_UDLM_PDM_PPI_Tool_undated.docx DOCX document
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Unclassified DRS Proprietary//Competition Sensitive

# RFP Document Section # RFP Wording Question for Government Government Response

1 Section L, Section M

The formal release dated 5 November deleted the requirement for a cross reference matrix in volume one. Does the Government desire or expect a CRM to be submitted as part of the Offerors submittal.

A Cross Reference Matrix is not required.

2 UDLM/PDM

Pricing Model

Attachment 2 For the qty band pricing, is it the Government's intent that bands will be utilized consecutively. For example, if the Government exercises 4 H1's in FY21, the first three aircraft would utilize the qty 1-3 band pricing and the 4th aircraft would utilize the 4-6 band pricing.

The USG intends the pricing bands to be used consecutively based off the initial order but starting in the appropriate quantity band of the initial order. If 4 of the same type aircraft are on the initial order, all 4 of those aircraft will all be priced in the 4‐6 pricing band. Any subsequent order of the same type aircraft will continue consecutively on the pricing band. See Attached example.

3 PWS Section L Paragraph B.1.

Offerors shall ensure that all clauses and provisions that require “fill-in” information are appropriately completed, including the proposed prices associated with the contract line items in the Schedule of the RFP.

When completing the model contract, what aircraft variant should the contractor assume when entering the unit price?

Referenced paragraph will be changed to add the following language: ". . . (by completing "RFP_Atch_2_C130_UDLM_PDM_Pricing Model_dtd_31Oct19). . . " Please note that the RFP_Atch_2_C130_UDLM_PDM_Pricing Model_dtd_31Oct19 will be incorporated into final contract. Please note that the prices will not need to be filled in on the model contract, but only in attachment 2.

The clauses will need to be filled in as applicable.

4 Paragraph II, C, 1.3.3, Page

Section M, Evaluation Basis for Award

1.3.3. The associated goals expressed in terms of percentages of the total planned subcontracted dollars is provided. Adequate rationale is provided if limited or no subcontracting possibilities exist for these socio-economic entities. Offerors are cautioned against only acknowledging a goal is not met, if applicable.

Adequate rationale includes specific reasons why a goal is unmet and any actions being taken to increase any unmet goals.

In order to allow common calculation basis of small business content, will the government provide a defined basic program scale or scope. (qty of PDM, qty of UDLM, qty of Paint)

The subcontract percentages are not dependent on quantities. The RFP provided the 2019 DoD subcontracting goals as a reference, however each offeror is to develop their own plan to utilize small business.

5 RFP, PWS There are many references to "fiscal year" within the RFP & PWS. When (month/year) should the Offeror begin the fiscal year for pricing purposes?

DoD Fiscal year is 1 Oct‐ 30 Sept

6 Section L 2.1.1 Assumptions: For technical evaluation purposes only, assume the following when responding to this subfactor: The plan shall describe the approach for eight C-130H(83+) PDM aircraft, four C-130J-30 PDM/D-Check aircraft, and six mid-cycle paint. When responding to this subfactor, assume the first PDM/D-Check aircraft will be inducted on 1 March 2021 and subsequent PDM/D-Check aircraft will be inducted in even/equal intervals across the rest of FY21. When responding to this subfactor, assume the first Mid-Cycle Paint aircraft will be inducted on 1 February 2021 and subsequent Mid-Cycle Paint aircraft will be inducted in even/equal intervals across the remaining FY21 period. 2.2.1.1 Eight C-130H(83+) PDM aircraft, four C-130J-30 PDM/D-Check aircraft, and six Mid- Cycle Paint. When responding to this subfactor, assume the first PDM/D-Check aircraft will be inducted on 1 March 2021 and subsequent PDM aircraft will be inducted in even/equal intervals across the rest of FY21. When responding to this subfactor, assume the first Mid-Cycle Paint aircraft will be inducted on 1 February 2021 and subsequent Mid-Cycle Paint aircraft will be inducted in even/equal intervals across the rest of FY21.

Assuming the fiscal year is 1 October through 30 September, Section L paragraphs 2.1.1 and

2.2.1.1 requires Offerors to describe and address available facilities and/or demonstrate the ability to obtain facilities to support 12 PDMs (eight C-130H (83+) PDM aircraft and four C- 130J-30 PDM/D-Check aircraft) within a seven-month period. With the first aircraft inducted on 1 March 2021 and the remaining aircraft to be spread evenly over FY21, this seven- month period drives Offerors to demonstrate much higher hangar requirements for FY21 than what will be required to support annual maximum PDM quantities in FY-22-25. Would USAF consider changing the requirement in Section L from"... even/equal intervals across the rest of FY21" to" ... even/equal intervals across a 12-month period of performance"? This would align with the basic period of performance for FY21 stated on page 3 in Section B of the RFP.

The first year is a 12 month period, 3 month ramp up timeframe, and 9 month induction period. Delivery of aircraft back to the USG after completion of the PDM can be after the 12 month period in which it was inducted.

For example, an aircraft may be inducted on 30 Sep (last day of the FY) and returned to the USG in the next FY after PDM is completed. There is no "period of performance" on task orders but instead required deliveries. The requirement in Section L re: assumption, will not be changed. The assumption was placed in Section L for technical evaluation purposes only and is not a firm requirement.

Contractor Questions UDLM/PDM RFP Questions/Ansers dated 31 Dec 2019

DRS Proprietary/Competition Sensitive

DRS Proprietary//Competition Sensitive

# RFP Document Section # RFP Wording Question for Government Government Response

7 PWS 4.5.2. AFTO Form 103 workload tasks shall be either a FFP Catalog M task (see Appendix B) or a negotiated task prior to PDM induction. The FFP Catalog M tasks will be used for PDM and UDLM support. If a task on FFP Catalog M list is part of the basic PDM Work Spec, it will be completed as part of the PDM CLIN X001. Any work outside the PDM work spec, but within the PWS, shall be considered Over and Above (O&A). No O&A task shall be completed until authorized by PCO or their delegates.

PWS paragraph 4.5.2 has two sentences that may conflict. The sentence recently added states: "If a task on FFP Catalog M list is part of the basic PDM Work Spec, it will be completed as part of the PDM CLIN X001". Does this mean that Offerors should include the prices for the Catalog M tasks in their proposed price for PDM work under CLIN x001? For instance, aircraft in-processing/out-processing must be done for every PDM. Should Offerors price these tasks individually under CLIN x005 and price these tasks again in their proposed PDM prices under CLIN x001?

Yes, any task shown on the C130 PWS UDLM PDM App B C130HJ Catalog M Task FFP List that are part of a normal PDM process should be priced under PDM CLIN x001. All tasks shown on the C130 PWS UDLM PDM App B C130HJ Catalog M Task FFP List are to be priced as stand alone tasks.

8 Section L 1.1.1. CLINs x001 (C130 PDM): Offerors shall propose a fixed unit price for each quantity range, based on the estimated Maximum Quantity for each Fiscal Year (FY).

1.1.2. CLINs x003 (C130 PDM Paint): Offerors shall propose a

fixed unit price for each quantity range, based on the estimated Max Quantity for each FY.

1.1.3. CLINs x004 (C130J Mid-Cycle Paint): Offerors shall

proposed a fixed unit price for each quantity range, based on the estimated Maximum Quantity for each FY.

Instructions contained in Section L paragraph E.1.1.1 thru 1.1.3 states that fixed unit prices for CLINs X001, X003, X004 should be based on" ... the estimated Maximum Quantity for each Fiscal Year." This appears to contradict the purpose of establishing price ranges. Should the unit prices for these CLINs be based on maximum quantities for each FY, or should they be based on the quantities specified in each price range?

The Instructions in Section L, paragraph E.1.1.1 thru 1.1.3 will be changed to include "…the estimated Maximum Quantity in each pricing band for each Fiscal Year.

9 Appendix A 3.2.2.2.4.1.1 - CP - Report any disbonds outside of the allowable limits (IAW TO 1C-130A-36, Inspection CW-48) to engineering

AC130U

AC130W

C130H 73-74 C130H 78-82 C130H 83+

HC130(H)N 88-93

HC130N/P 64-69

LC130H

MC130H

MC130P

WC130H

Assigned MDS(s) 1B3I - AFT Nacelle Boron Repair Inspection and Thermography Scan Assigned Tasks

Appendix A section 3.2.2.2.4 requires a Thermography Inspections to existing Boron repairs in accordance with TO 1C-130A-36, Inspection CW-48. TO 1C-130A-36 Page 15-30-00.

Table 2-13 states "Contact WR-AFLCMC for Authorized Equipment". Please identify the equipment required to accomplish this task.

The equipment required to perform TO 1C‐130A‐36, Inspection CW‐48 is listed within the specific inspection instructions, see inspection paragraph 7.2.19, CW‐48, Boron Repair Patches (57‐10‐20). Required NDI equipment is listed under sub‐paragraph 7.2.19.5.1. The “Thermographic imaging equipment” and “recording medium” mentioned in the list does not specify a certain model or type. For reference, the Robins AFB NDI group uses the following thermographic imaging equipment and media:

FLIR SC660, 640 x 480 IR resolution, non‐radiometric video recording to on‐board memory card, built‐in digital camera, flip‐out 5.6” LCD display. This is used with a tripod to mount the camera looking up at the wing surface.

IAW the note in paragraph 7.2.19.5.1, C‐130 engineering must approve new equipment prior to implementation.

This can be accomplished after contract award via TAR in AIRCAT IAW PWS paragraph 4.31.

10 PWS 4.16.7. The prices for O&A firm fixed price items listed in Appendix B do not include any payment for contactor furnished direct parts and materials.

PWS 4.16.7 states that "O&A FFP items in Appendix B do not include any payment for contractor furnished direct parts and materials". Does this mean that contractors should not include any material or subcontracts in the pricing of the O&A FFP Appendix B (Catalog M) line items?

This will be changed to read, "The prices for O&A firm fixed price items listed in Appendix B shall include any costs for contractor furnished parts and materials (XB3/XF3 coded parts) The contractor is not required and should not provide break out of subcontractor costs for an FFP line item.

11 Reference FAR 52.211-12 "Liquidated Damages - Construction (SEP 2000)". Please remove this clause as it does not apply to the work anticipated under a resulting contract.

Clause will be removed

12 Reference the RFP, Section I, Page 53. At the bottom of the page DFARS 252.204-7004 titled "BASIC AGREEMENT APPLICABILITY (FEB 2019)" is listed. The clause number is duplicative to the clause listed next above and on the same page titled "Level I Antiterrorism Awareness Training for Contractors (FEB 2019)". The Antiterrorism clause is the clause associated with this DFARS number. Please clarify.

PCO will remove basic agreement

DRS Proprietary/Competition Sensitive