RFI__5_Answer.pdf

PDF 58 KB Posted

Attached to
Mechanical Electrical IDIQ Federal contract opportunity
Solicitation number
FA8501-18-R-0003
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Robins Air Force Base

About this file

This document contains a request for information response and details of a federal contract opportunity. The request for information response clarifies that specification section 09 29 00 for gypsum board installation applies to the ceiling work on the project per the drawings. The federal contract opportunity is a mechanical-electrical indefinite-delivery indefinite-quantity construction contract to provide mechanical and electrical maintenance support at Robins Air Force Base, Georgia. Work will include a range of HVAC, controls, utility distribution, boiler, lighting, fire suppression and alarm system repairs, renovations, upgrades and new construction. The contractor will furnish all materials, equipment, labor and general conditions for each task order.

RFI #5 Answers

View the file

Other files for this federal contract opportunity

Other files attached to Mechanical Electrical IDIQ, newest first.
File Type Posted
RFI__6_Answers.pdf PDF
Atch__33_-_Addendum__2_Mech_Elec.pdf PDF
Atch__35_-_09_29_00_-_Gypsum_Board.pdf PDF
Atch__34_-_Revised_Project_Table_of_Contents_22_Mar_18.pdf PDF
Atch__8_-_AF_Form_3052.xlsx XLSX spreadsheet
Atch__10_-_AF_Form_3065.xlsx XLSX spreadsheet
Atch__9_-_AF_Form_3064.xlsx XLSX spreadsheet
FA8501-18-R-0003-0002.pdf PDF
Atch__14_-_Schedule_of_Values.xlsx XLSX spreadsheet
RFI__4_Answers.pdf PDF
RFI__3_Answers.pdf PDF
Atch__31_-_Addendum__1_Mech-Elec.pdf PDF
Atch__30_-_VPP_DART-TCIR_Chart.xlsx XLSX spreadsheet
Atch__32_-_CIP_Concrete_Specifications.pdf PDF
RFI__2_Answers.pdf PDF
FA8501-18-R-0003-0001.pdf PDF
Site_Visit_Slides_&_Sign_In_Sheet.pdf PDF
RFI__1_Answers.pdf PDF
Atch__29_-_UHHZ090516_Combined_Drawings.pdf PDF
Atch__4_-_Robins_AFB_Division_1_Specs_and_Forms_REVISED_24_April_2017.pdf PDF
Atch__28_-_UHHZ090516_Combined_Specifications.pdf PDF
Atch__15_-_BLANK_SAMPLE_Dig_Permit_Form_v3.0.pdf PDF
Atch__17_-_BLANK_SAMPLE_DD_Form_1354_Transfer_and_Acceptance_of_DoD_Real_Property.pdf PDF
Atch__2_-_App_C_UHHZ_170241.pdf PDF
Atch__1_-_Mech-Elec_SOW.pdf PDF
Atch__10_-_BLANK_SAMPLE_AF_Form_3065.pdf PDF
Atch__14_-_BLANK_SAMPLE_Schedule_of_Values_Template_UNLOCKED.pdf PDF
Atch__20_-_Best_Practices_for_Landscape_Guidelines_Robins_AFB_3-15-2011.pdf PDF
Atch__12_-_01560_Environmental_Requirements_2018.pdf PDF
Atch__9_-_BLANK_SAMPLE_AF_Form_3064.pdf PDF
Atch__23_-_AFI_31-204_RAFB_Sup_1_Motor_Vehicle_Traffic_Supervision.pdf PDF
Atch__30_-_VPP_DART-TCIR_Chart.xlsx XLSX spreadsheet
Atch__8_-_BLANK_SAMPLE_AF_Form_3052.pdf PDF
Atch__13_-_Wage_Determination.pdf PDF
Atch__5_-_UHHZ170241_BIDDING_SCHEDULE_(TEP).pdf PDF
Atch__11_-_BLANK_SAMPLE_AF_Form_3000_with_digital_signatures.pdf PDF
Atch__26_-_UFC_4_010_05_Sensitive_Compartmented_Information_Facilities_Planning,_Design,_and_Construction.pdf PDF
Atch__18_-_Technical_Spec_for_ICD705_version1.2_April_23_2012.pdf PDF
Atch__19_-_AFSC_Energy_Metering_Requirements_24_June_2016.pdf PDF
Atch__7_-_Robins_AFB_Asbestos_Management_Plan_-_January_2015.pdf PDF
FA8501-18-R-0003.pdf PDF
Atch__16_-_BLANK_SAMPLE_Master_Utility_Outage.pdf PDF
Atch__24_-_Air_Force_Manual_32_1084_Civil_Engineering_Facility_Requirements.pdf PDF
Atch__22_-_BLANK_SAMPLE_AF_Form_66_SUBMITTAL_REGISTER.pdf PDF
Atch__3_-_PROCEDURAL_GUIDE_FOR_DESIGNERS_INCLUDING_AE_FIRMS_29_May_15.pdf PDF
Atch__21_-_Form20SP.STANDARDSensitiveEquipmentPropertyRequest.Revised15July2016.pdf PDF
Atch__27_-_BFS-RAFB_16_FEB_17.pdf PDF
Atch__25_-_AF_Form_2586_Flightline_Driving_Request.pdf PDF
Atch__6_-_Robins_AFB_Architectural_Compatiblity_Standards_18_Aug_2015.pdf PDF
Show all 49

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Request for Information # 5

FA8501-18-R-0003

1. Drawings A103 and A104, reflected ceiling, clearly show new ceiling soffits of GWB. The demolition and replacement appear to show complete ceiling replacement for both ACT and GWB ceiling, up to the lanes. However, you did not include a spec for GWB and framing, and the Statement of Work does not explicitly mention replacement of the hard ceiling. So we have contractors that are only quoting ACT replacement and not hard ceiling replacement. Which is going to produce a significant difference in pricing. Therefore, this is RFI #29 submitted by MULE Engineering & Construction for FA8501-18-R-0003, UHHZ 170241: Please clarify if the ceiling work is to include demolition and replacement of the soffits (hard ceiling) as well as the tiled ceiling system. Drawings A103 and A104 indicate new hard ceiling, however it is not explicitly stated in the Statement of Work.

Answer: See attached specification section 09 29 00 (Attachment #35) – Gypsum Board for installation per project drawings.