RFI__5_Answer.pdf
PDF 58 KB Posted
- Attached to
- Mechanical Electrical IDIQ Federal contract opportunity
- Solicitation number
- FA8501-18-R-0003
About this file
This document contains a request for information response and details of a federal contract opportunity. The request for information response clarifies that specification section 09 29 00 for gypsum board installation applies to the ceiling work on the project per the drawings. The federal contract opportunity is a mechanical-electrical indefinite-delivery indefinite-quantity construction contract to provide mechanical and electrical maintenance support at Robins Air Force Base, Georgia. Work will include a range of HVAC, controls, utility distribution, boiler, lighting, fire suppression and alarm system repairs, renovations, upgrades and new construction. The contractor will furnish all materials, equipment, labor and general conditions for each task order.
RFI #5 Answers
View the file
Other files for this federal contract opportunity
Show all 49
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Request for Information # 5
FA8501-18-R-0003
1. Drawings A103 and A104, reflected ceiling, clearly show new ceiling soffits of GWB. The demolition and replacement appear to show complete ceiling replacement for both ACT and GWB ceiling, up to the lanes. However, you did not include a spec for GWB and framing, and the Statement of Work does not explicitly mention replacement of the hard ceiling. So we have contractors that are only quoting ACT replacement and not hard ceiling replacement. Which is going to produce a significant difference in pricing. Therefore, this is RFI #29 submitted by MULE Engineering & Construction for FA8501-18-R-0003, UHHZ 170241: Please clarify if the ceiling work is to include demolition and replacement of the soffits (hard ceiling) as well as the tiled ceiling system. Drawings A103 and A104 indicate new hard ceiling, however it is not explicitly stated in the Statement of Work.
Answer: See attached specification section 09 29 00 (Attachment #35) – Gypsum Board for installation per project drawings.