Atch__14_-_Schedule_of_Values.xlsx
XLSX spreadsheet 22 KB Posted
- Attached to
- Mechanical Electrical IDIQ Federal contract opportunity
- Solicitation number
- FA8501-18-R-0003
About this file
This document contains a schedule of values and federal contract opportunity solicitation. The schedule of values outlines the line items, descriptions, values, percentages, and totals for a construction project with a total bid of $43.72 million. It includes line items for general requirements, existing conditions, concrete, masonry, metals, wood and composites, thermal and moisture protection, openings, finishes, specialties, special construction, fire suppression, plumbing, HVAC, electrical, communications, electronic safety and security, earthwork, exterior improvements, utilities, and closeout documents.
The federal contract opportunity solicitation is for the Mechanical-Electrical Indefinite-Delivery Indefinite-Quantity construction contract to provide mechanical and electrical maintenance support at Robins Air Force Base, Georgia. The work includes a broad range of maintenance, repair, alteration, and new construction for HVAC, controls, underground utilities, boilers, airfield and exterior lighting, fire suppression and alarm systems. The contractor is to provide all material, equipment, labor, and general conditions to accomplish the work required for each individual task order. The solicitation number is FA8501-18-R-0003 and was issued by the Department of the Air Force Materiel Command Lifecycle Management Center.
Attachment #14 - Schedule of Values
View the file
Other files for this federal contract opportunity
Show all 49
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| BLANK SAMPLE SCHEDULE OF VALUES | ||||
| Contract No: FA8501-XX-X-XXXX | ||||
| Project No & Title: UHHZ XXXXXX Construct XXXXXXXXXXXXXXXXXXXXXXX | ||||
| DIVISION 01 - GENERAL REQUIREMENTS | ||||
| LINE NO. | DESCRIPTION | VALUE | PERCENTAGE | TOTAL |
| 1.1 | Project Management | $0.73 | 1.67% | |
| 1.2 | Supervision | $0.97 | 2.22% | |
| 1.3 | Project Trailer (including deliver & return) | $0.05 | 0.11% | |
| 1.4 | Roll-Off Dumpster | $0.53 | 1.21% | |
| 1.5 | Temporary Fence | $0.53 | 1.21% | |
| 1.6 | Bond | $0.13 | 0.30% | |
| 1.7 | Rental Equipment (Lull, Manlift, Boom Truck) | $0.19 | 0.43% | |
| 1.8 | Tools | $0.19 | 0.43% | |
| Division 01 Total | $3.13 | 7.16% | 7.16% | |
| DIVISION 02 - EXISTING CONDITIONS | ||||
| LINE NO. | DESCRIPTION | VALUE | PERCENTAGE | TOTAL |
| 2.1 | Demolition Interior (Electrical) | $0.88 | 2.01% | |
| 2.2 | Demolition Interior (Mechanical) | $0.32 | 0.73% | |
| 2.3 | Demolition (Plumbing) | $0.15 | 0.34% | |
| 2.4 | Demolition (Flooring) | $0.15 | 0.34% | |
| 2.5 | Demolition (Openings) | $0.88 | 2.01% | |
| 2.6 | Demolition (Concrete) | $0.88 | 2.01% | |
| 2.7 | Demolition (Ceilings) | $0.88 | 2.01% | |
| 2.8 | Demolition (Walls) | $0.55 | 1.26% | |
| 2.9 | Demolition (Fire Suppression) | $0.88 | 2.01% | |
| 2.10 | Demolition (Fire Alarm System) | $0.68 | 1.56% | |
| 2.11 | Demolition (Communications) | $0.25 | 0.57% | |
| Division 02 Total | $6.50 | 14.87% | 14.87% | |
| DIVISION 03 - CONCRETE | ||||
| LINE NO. | DESCRIPTION | VALUE | PERCENTAGE | TOTAL |
| 3.1 | Concrete Pad (Generator) | $0.32 | 0.73% | |
| 3.2 | Concrete Ceiling {Vault) | $0.68 | 1.56% | |
| 3.3 | Concrete Pad (Mechanical Yard} | $0.87 | 1.99% | |
| 3.4 | Concrete Pad (HVAC Units) | $0.96 | 2.20% | |
| 3.5 | Concrete Reinforcements | $0.14 | 0.32% | |
| 3.6 | Expansion Joints, Contraction Joinls | $0.18 | 0.41% | |
| 3.7 | Concrete Design Mix/Rebar Shop Drawings | $0.10 | 0.23% | |
| 3.8 | Concrete Testing and Reports | $0.08 | 0.18% | |
| Division 03 Total | $3.15 | 7.20% | 7.20% | |
| DIVISION 04 - MASONRY | ||||
| LINE NO. | DESCRIPTION | VALUE | PERCENTAGE | TOTAL |
| 4.1 | Mechanical Yard Masonrv Wall | $0.31 | 0.71% | |
| 4.2 | Generator Pad Masonry Wall | $0.65 | 1.49% | |
| 4.3 | Infill (Front Entry Area) | $0.96 | 2.20% | |
| 4.4 | Masonry Patch Work (Roll-up Door) | $0.96 | 2.20% | |
| 4.5 | Infill (Mechanical Louver Area) | $0.20 | 0.46% | |
| 4.6 | Vault | $0.93 | 2.13% | |
| Division 04 Total | $4.01 | 9.17% | 9.17% | |
| DIVISION 05 - METALS | ||||
| LINE NO. | DESCRIPTION | VALUE | PERCENTAGE | TOTAL |
| 5.1 | Metal Stud Framing (Interior) | $0.78 | 1.78% | |
| 5.2 | Metal Stud Framing Accessories | $0.12 | 0.27% | |
| 5.3 | 0.00% | |||
| Division 05 Total | $0.90 | 2.06% | 2.06% | |
| DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES | ||||
| LINE NO. | DESCRIPTION | VALUE | PERCENTAGE | TOTAL |
| 6.1 | Casework (Women's Restroom) | $0.34 | 0.78% | |
| 6.2 | Casework (Men's Restroom) | $0.34 | 0.78% | |
| 6.3 | Casework (Break Room) | 0.00% | ||
| Division 06 Total | $0.68 | 1.56% | 1.56% | |
| DIVISION 07 - THERMAL AND MOISTURE PROTECTION | ||||
| LINE NO. | DESCRIPTION | VALUE | PERCENTAGE | TOTAL |
| 7.1 | Mineral Fiber Blanket lnsulation (Interior) | $0.54 | 1.24% | |
| 7.2 | Sound Attenuation Fire Blanket in rated walls | $0.14 | 0.32% | |
| 7.3 | Rigid (Polyisocyanurate) Insulation | $0.04 | 0.09% | |
| Division 07 Total | $0.72 | 1.65% | 1.65% | |
| DIVISION 08 - OPENINGS | ||||
| LINE NO. | DESCRIPTION | VALUE | PERCENTAGE | TOTAL |
| 8.1 | Steel Doors and Frames | $0.03 | 0.07% | |
| 8.2 | Prefinished Electric Insulated Overhead Coiling Door | $0.35 | 0.80% | |
| 8.3 | Windows | $0.39 | 0.89% | |
| 8.4 | Door Hsrdware including door cylinders | $0.21 | 0.48% | |
| Division 08 Total | $0.77 | 1.76% | 1.76% | |
| DIVISION 09 - FINISHES | ||||
| LINE NO. | DESCRIPTION | VALUE | PERCENTAGE | TOTAL |
| 9.1 | Gypsum Board and mud, tape, corner beads | $0.30 | 0.69% | |
| 9.2 | Paints and Coatings | $0.11 | 0.25% | |
| 9.3 | Epoxy Flooring | $0.06 | 0.14% | |
| 9.4 | Acoustlcal Ceiling Tile and Grid | $0.16 | 0.37% | |
| 9.5 | Porcelain Tile | $0.42 | 0.96% | |
| 9.6 | Carpet Tiles | $0.73 | 1.67% | |
| 9.7 | Vinyl Composition Tile | $0.24 | 0.55% | |
| 9.8 | Rubber Base | $0.11 | 0.25% | |
| Division 09 Total | $1.78 | 4.07% | 4.07% | |
| DIVISION 10 - SPECIALTIES | ||||
| LINE NO. | DESCRIPTION | VALUE | PERCENTAGE | TOTAL |
| 10.1 | Toilet Accessories | $0.15 | 0.34% | |
| 10.2 | Interior Signage | $0.86 | 1.97% | |
| 10.3 | 0.00% | |||
| Division 10 Total | $1.01 | 2.31% | 2.31% | |
| DIVISION 13 - SPECIAL CONSTRUCTION | ||||
| LINE NO. | DESCRIPTION | VALUE | PERCENTAGE | TOTAL |
| 13.1 | Steel Deck Vault | $0.55 | 1.26% | |
| 13.2 | Steel I-beam (Openings) | $0.90 | 2.06% | |
| 13.3 | Steel louvers (Mech Yard) | $0.78 | 1.78% | |
| 13.4 | Steel Gate (Generator) | $0.58 | 1.33% | |
| 13.5 | Steel Gate (Generator) | $0.58 | 1.33% | |
| 13.6 | Pre-engineered Metal Building | $0.75 | 1.72% | |
| 13.7 | Pre-engineered Metal Building Wall Roof panels | $0.12 | 0.27% | |
| 13.8 | Pre-engineered Metal Building Accessories | $0.07 | 0.16% | |
| Division 13 Total | $4.14 | 9.47% | 9.47% | |
| DIVISION 21 - FIRE SUPPRESSION | ||||
| LINE NO. | DESCRIPTION | VALUE | PERCENTAGE | TOTAL |
| 21.1 | Riser, Dbl Check Valves, Tamper & Flow Switches | $0.02 | 0.05% | |
| 21.2 | Wet Pipe Fire Sprinkler Piping | $0.14 | 0.32% | |
| 21.3 | Testing | $0.78 | 1.78% | |
| Division 21 Total | $0.94 | 2.15% | 2.15% | |
| DIVISION 22 - PLUMBING | ||||
| LINE NO. | DESCRIPTION | VALUE | PERCENTAGE | TOTAL |
| 22.1 | Plumbing (Fixtures) | $0.09 | 0.21% | |
| 22.2 | Plumbing Piping& Materials | $0.73 | 1.67% | |
| 22.3 | 0.00% | |||
| Division 22 Total | $0.82 | 1.88% | 1.88% | |
| DIVISION 23 - HEATING, VENTILATION AND AIR CONDITIONING | ||||
| LINE NO. | DESCRIPTION | VALUE | PERCENTAGE | TOTAL |
| 23.1 | HVAC Air Handlers | $0.11 | 0.25% | |
| 23.2 | Acoustics Duct Silencers | $0.18 | 0.41% | |
| 23.3 | Exhaust & Supply Fans | $0.35 | 0.80% | |
| 23.4 | Boiler & Computer Room Units (CRAC) | $0.58 | 1.33% | |
| 23.5 | Variable Air Volume 0JAV) Boxes | $0.74 | 1.69% | |
| 23.6 | Fire Smoke Dampers & Louvers | $0.35 | 0.80% | |
| 23.7 | Testing, Adjusting & Balancing of HVAC Sys | $0.11 | 0.25% | |
| 23.8 | Thermal lnsulation for Mechanical Sys | $0.35 | 0.80% | |
| 23.9 | Duct Insulation | $0.23 | 0.53% | |
| 23.10 | Duct Work & Duct Work Accessories | $0.50 | 1.14% | |
| 23.11 | Diffusers, Registers & Grills | $0.22 | 0.50% | |
| 23.12 | HVAC Controls | $0.70 | 1.60% | |
| Division 23 Total | $4.42 | 10.11% | 10.11% | |
| DIVISION 26 - ELECTRICAL | ||||
| LINE NO. | DESCRIPTION | VALUE | PERCENTAGE | TOTAL |
| 26.1 | Electrical Conduit, Fillings, Boxes | $0.24 | 0.55% | |
| 26.2 | Electrical Wire & Cable | $0.93 | 2.13% | |
| 26.3 | Interior Distribution Systems | $0.91 | 2.08% | |
| 26.4 | Low Voltage SwitchQear | $0.23 | 0.53% | |
| 26.5 | Switchboards & Panel Boards | $0.51 | 1.17% | |
| 26.6 | Interior lighting | $0.11 | 0.25% | |
| 26.7 | Electrical Exterior Underground | $0.75 | 1.72% | |
| 26.8 | Electric Meter | $0.07 | 0.16% | |
| Division 26 Total | $3.68 | 8.42% | 8.42% | |
| DIVISION 27 - COMMUNICATIONS (IF REQUIRED AS A PART OF CONTRACT) | ||||
| LINE NO. | DESCRIPTION | VALUE | PERCENTAGE | TOTAL |
| 27.1 | Comm Piping, Fittings and Boxes | $0.88 | 2.01% | |
| 27.2 | Communications Wire | $0.44 | 1.01% | |
| 27.3 | Communications Cable Tray | $0.80 | 1.83% | |
| 27.4 | Testing | $0.06 | 0.14% | |
| Division 27 Total | $2.18 | 4.99% | 4.99% | |
| DIVISION 28 - ELECTRONIC SAFETY AND SECURITY | ||||
| LINE NO. | DESCRIPTION | VALUE | PERCENTAGE | TOTAL |
| 28.1 | Fire Alarm System Conduit & Fittings | $0.17 | 0.39% | |
| 28.2 | Fire Alarm Panel and Power Boosters | $0.96 | 2.20% | |
| 28.3 | Fire Alarm Programming & Testing | $0.05 | 0.11% | |
| 28.4 | MNS Conduit and Fittings | $0.47 | 1.08% | |
| 28.5 | MNS Panels | $0.40 | 0.91% | |
| 28.6 | FA/MNS Programming & Testing | $0.29 | 0.66% | |
| Division 28 Total | $2.34 | 5.35% | 5.35% | |
| DIVISION 31 - EARTHWORK | ||||
| LINE NO. | DESCRIPTION | VALUE | PERCENTAGE | TOTAL |
| 31.1 | Landscaping (Demo) | $0.06 | 0.14% | |
| 31.2 | Landscaping (Sod and Watering) | $0.06 | 0.14% | |
| 31.3 | Soii Compaction Test | $0.15 | 0.34% | |
| Division 31 Total | $0.27 | 0.62% | 0.62% | |
| DIVISION 32 - EXTERIOR IMPROVEMENTS | ||||
| LINE NO. | DESCRIPTION | VALUE | PERCENTAGE | TOTAL |
| 32.1 | Bollards | $0.58 | 1.33% | |
| 32.2 | Concrete Sidewalks | $0.05 | 0.11% | |
| 32.3 | Fog Seal (Parking Lot) | $0.63 | 1.44% | |
| 32.4 | Curb Stops (Parking Lot) | $0.05 | 0.11% | |
| 32.5 | Restnping (Parking Lot) | $0.29 | 0.66% | |
| Division 32 Total | $1.60 | 3.66% | 3.66% | |
| DIVISION 33 - UTILITIES | ||||
| LINE NO. | DESCRIPTION | VALUE | PERCENTAGE | TOTAL |
| 33.1 | Natural Gas | $0.63 | 1.44% | |
| 33.2 | Gas Meter | $0.05 | 0.11% | |
| 33.3 | 0.00% | |||
| Division 33 Total | $0.68 | 1.56% | 1.56% |
| CLOSE-OUT DOCUMENTS | ||||
| LINE NO. | DESCRIPTION | VALUE | PERCENTAGE | TOTAL |
| A | As-Built Drawings | 0.00% | ||
| B | Warranties | |||
| C | O&M Manuals (Paper Copy and CD/DVD's) | 0.00% | ||
| D | Roof Inspection Reports | 0.00% | ||
| Close-out Total | $0.00 | 0.00% | 0.00% | |
| BID TOTAL | $43.72 | 100.00% | 100.00% |