Atch__14_-_BLANK_SAMPLE_Schedule_of_Values_Template_UNLOCKED.pdf

PDF 120 KB Posted

Attached to
Mechanical Electrical IDIQ Federal contract opportunity
Solicitation number
FA8501-18-R-0003
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Robins Air Force Base

About this file

This document contains a schedule of values template for a federal construction contract and details of a related mechanical and electrical indefinite-delivery indefinite-quantity contract opportunity. The schedule of values template breaks down the construction work into line items by division and subsection with assigned values and percentages, totaling $43.72 for the entire project. The mechanical and electrical IDIQ contract provides maintenance, repair, alteration, and new construction services for mechanical and electrical systems at Robins Air Force Base, including HVAC, controls, distribution systems, boilers, lighting, fire suppression and alarm, among other work. Services will be ordered through task orders under the multiple award contract.

Attachment #14 - Blank Schedule of Values

View the file

Other files for this federal contract opportunity

Other files attached to Mechanical Electrical IDIQ, newest first.
File Type Posted
RFI__6_Answers.pdf PDF
Atch__8_-_AF_Form_3052.xlsx XLSX spreadsheet
Atch__10_-_AF_Form_3065.xlsx XLSX spreadsheet
Atch__9_-_AF_Form_3064.xlsx XLSX spreadsheet
Atch__33_-_Addendum__2_Mech_Elec.pdf PDF
RFI__5_Answer.pdf PDF
Atch__35_-_09_29_00_-_Gypsum_Board.pdf PDF
Atch__34_-_Revised_Project_Table_of_Contents_22_Mar_18.pdf PDF
FA8501-18-R-0003-0002.pdf PDF
Atch__14_-_Schedule_of_Values.xlsx XLSX spreadsheet
RFI__4_Answers.pdf PDF
RFI__3_Answers.pdf PDF
Atch__30_-_VPP_DART-TCIR_Chart.xlsx XLSX spreadsheet
Atch__32_-_CIP_Concrete_Specifications.pdf PDF
Atch__31_-_Addendum__1_Mech-Elec.pdf PDF
RFI__2_Answers.pdf PDF
FA8501-18-R-0003-0001.pdf PDF
RFI__1_Answers.pdf PDF
Site_Visit_Slides_&_Sign_In_Sheet.pdf PDF
Atch__15_-_BLANK_SAMPLE_Dig_Permit_Form_v3.0.pdf PDF
Atch__17_-_BLANK_SAMPLE_DD_Form_1354_Transfer_and_Acceptance_of_DoD_Real_Property.pdf PDF
Atch__2_-_App_C_UHHZ_170241.pdf PDF
Atch__1_-_Mech-Elec_SOW.pdf PDF
Atch__10_-_BLANK_SAMPLE_AF_Form_3065.pdf PDF
Atch__20_-_Best_Practices_for_Landscape_Guidelines_Robins_AFB_3-15-2011.pdf PDF
Atch__12_-_01560_Environmental_Requirements_2018.pdf PDF
Atch__29_-_UHHZ090516_Combined_Drawings.pdf PDF
Atch__4_-_Robins_AFB_Division_1_Specs_and_Forms_REVISED_24_April_2017.pdf PDF
Atch__28_-_UHHZ090516_Combined_Specifications.pdf PDF
Atch__9_-_BLANK_SAMPLE_AF_Form_3064.pdf PDF
Atch__23_-_AFI_31-204_RAFB_Sup_1_Motor_Vehicle_Traffic_Supervision.pdf PDF
Atch__30_-_VPP_DART-TCIR_Chart.xlsx XLSX spreadsheet
Atch__8_-_BLANK_SAMPLE_AF_Form_3052.pdf PDF
Atch__13_-_Wage_Determination.pdf PDF
Atch__5_-_UHHZ170241_BIDDING_SCHEDULE_(TEP).pdf PDF
Atch__11_-_BLANK_SAMPLE_AF_Form_3000_with_digital_signatures.pdf PDF
Atch__26_-_UFC_4_010_05_Sensitive_Compartmented_Information_Facilities_Planning,_Design,_and_Construction.pdf PDF
Atch__18_-_Technical_Spec_for_ICD705_version1.2_April_23_2012.pdf PDF
Atch__19_-_AFSC_Energy_Metering_Requirements_24_June_2016.pdf PDF
Atch__7_-_Robins_AFB_Asbestos_Management_Plan_-_January_2015.pdf PDF
FA8501-18-R-0003.pdf PDF
Atch__16_-_BLANK_SAMPLE_Master_Utility_Outage.pdf PDF
Atch__24_-_Air_Force_Manual_32_1084_Civil_Engineering_Facility_Requirements.pdf PDF
Atch__22_-_BLANK_SAMPLE_AF_Form_66_SUBMITTAL_REGISTER.pdf PDF
Atch__3_-_PROCEDURAL_GUIDE_FOR_DESIGNERS_INCLUDING_AE_FIRMS_29_May_15.pdf PDF
Atch__21_-_Form20SP.STANDARDSensitiveEquipmentPropertyRequest.Revised15July2016.pdf PDF
Atch__27_-_BFS-RAFB_16_FEB_17.pdf PDF
Atch__25_-_AF_Form_2586_Flightline_Driving_Request.pdf PDF
Atch__6_-_Robins_AFB_Architectural_Compatiblity_Standards_18_Aug_2015.pdf PDF
Show all 49

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DIVISION 01 - GENERAL REQUIREMENTS

LINE NO. DESCRIPTION VALUE PERCENTAGE

1.1 Project Management $0.73 1.67%

1.2 Supervision $0.97 2.22%

1.3 Project Trailer (including deliver & return) $0.05 0.11%

1.4 Roll-Off Dumpster $0.53 1.21%

1.5 Temporary Fence $0.53 1.21%

1.6 Bond $0.13 0.30%

1.7 Rental Equipment (Lull, Manlift, Boom Truck) $0.19 0.43%

1.8 Tools $0.19 0.43%

Division 01 Total $3.13 7.16%

DIVISION 02 - EXISTING CONDITIONS

LINE NO. DESCRIPTION VALUE PERCENTAGE

2.1 Demolition Interior (Electrical) $0.88 2.01%

2.2 Demolition Interior (Mechanical) $0.32 0.73%

2.3 Demolition (Plumbing) $0.15 0.34%

2.4 Demolition (Flooring) $0.15 0.34%

2.5 Demolition (Openings) $0.88 2.01%

2.6 Demolition (Concrete) $0.88 2.01%

2.7 Demolition (Ceilings) $0.88 2.01%

2.8 Demolition (Walls) $0.55 1.26%

2.9 Demolition (Fire Suppression) $0.88 2.01%

2.10 Demolition (Fire Alarm System) $0.68 1.56%

2.11 Demolition (Communications) $0.25 0.57%

Division 02 Total $6.50 14.87%

DIVISION 03 - CONCRETE

LINE NO. DESCRIPTION VALUE PERCENTAGE

3.1 Concrete Pad (Generator) $0.32 0.73%

3.2 Concrete Ceiling {Vault) $0.68 1.56%

3.3 Concrete Pad (Mechanical Yard} $0.87 1.99%

3.4 Concrete Pad (HVAC Units) $0.96 2.20%

3.5 Concrete Reinforcements $0.14 0.32%

3.6 Expansion Joints, Contraction Joinls $0.18 0.41%

3.7 Concrete Design Mix/Rebar Shop Drawings $0.10 0.23%

3.8 Concrete Testing and Reports $0.08 0.18%

Division 03 Total $3.15 7.20%

BLANK SAMPLE SCHEDULE OF VALUES

Contract No: FA8501-XX-X-XXXX Project No & Title: UHHZ XXXXXX Construct XXXXXXXXXXXXXXXXXXXXXXX

DIVISION 04 - MASONRY

LINE NO. DESCRIPTION VALUE PERCENTAGE

4.1 Mechanical Yard Masonrv Wall $0.31 0.71%

4.2 Generator Pad Masonry Wall $0.65 1.49%

4.3 Infill (Front Entry Area) $0.96 2.20%

4.4 Masonry Patch Work (Roll-up Door) $0.96 2.20%

4.5 Infill (Mechanical Louver Area) $0.20 0.46%

4.6 Vault $0.93 2.13%

Division 04 Total $4.01 9.17%

DIVISION 05 - METALS

LINE NO. DESCRIPTION VALUE PERCENTAGE

5.1 Metal Stud Framing (Interior) $0.78 1.78%

5.2 Metal Stud Framing Accessories $0.12 0.27%

5.3 0.00%

Division 05 Total $0.90 2.06%

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

LINE NO. DESCRIPTION VALUE PERCENTAGE

6.1 Casework (Women's Restroom) $0.34 0.78%

6.2 Casework (Men's Restroom) $0.34 0.78%

6.3 Casework (Break Room) 0.00%

Division 06 Total $0.68 1.56%

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

LINE NO. DESCRIPTION VALUE PERCENTAGE

7.1 Mineral Fiber Blanket lnsulation (Interior) $0.54 1.24%

7.2 Sound Attenuation Fire Blanket in rated walls $0.14 0.32%

7.3 Rigid (Polyisocyanurate) Insulation $0.04 0.09%

Division 07 Total $0.72 1.65%

DIVISION 08 - OPENINGS

LINE NO. DESCRIPTION VALUE PERCENTAGE

8.1 Steel Doors and Frames $0.03 0.07%

8.2 Prefinished Electric Insulated Overhead Coiling D $0.35 0.80%

8.3 Windows $0.39 0.89%

8.4 Door Hsrdware including door cylinders $0.21 0.48%

Division 08 Total $0.77 1.76%

DIVISION 09 - FINISHES

LINE NO. DESCRIPTION VALUE PERCENTAGE

9.1 Gypsum Board and mud, tape, corner beads $0.30 0.69%

9.2 Paints and Coatings $0.11 0.25%

9.3 Epoxy Flooring $0.06 0.14%

9.4 Acoustlcal Ceiling Tile and Grid $0.16 0.37%

9.5 Porcelain Tile $0.42 0.96%

9.6 Carpet Tiles $0.73 1.67%

9.7 Vinyl Composition Tile $0.24 0.55%

9.8 Rubber Base $0.11 0.25%

Division 09 Total $1.78 4.07%

DIVISION 10 - SPECIALTIES

LINE NO. DESCRIPTION VALUE PERCENTAGE

10.1 Toilet Accessories $0.15 0.34%

10.2 Interior Signage $0.86 1.97%

10.3 0.00%

Division 10 Total $1.01 2.31%

DIVISION 13 - SPECIAL CONSTRUCTION

LINE NO. DESCRIPTION VALUE PERCENTAGE

13.1 Steel Deck Vault $0.55 1.26%

13.2 Steel I-beam (Openings) $0.90 2.06%

13.3 Steel louvers (Mech Yard) $0.78 1.78%

13.4 Steel Gate (Generator) $0.58 1.33%

13.5 Steel Gate (Generator) $0.58 1.33%

13.6 Pre-engineered Metal Building $0.75 1.72%

13.7 Pre-engineered Metal Building Wall Roof panels $0.12 0.27%

13.8 Pre-engineered Metal Building Accessories $0.07 0.16%

Division 13 Total $4.14 9.47%

DIVISION 21 - FIRE SUPPRESSION

LINE NO. DESCRIPTION VALUE PERCENTAGE

21.1 Riser, Dbl Check Valves, Tamper & Flow Switches $0.02 0.05%

21.2 Wet Pipe Fire Sprinkler Piping $0.14 0.32%

21.3 Testing $0.78 1.78%

Division 21 Total $0.94 2.15%

DIVISION 22 - PLUMBING

LINE NO. DESCRIPTION VALUE PERCENTAGE

22.1 Plumbing (Fixtures) $0.09 0.21%

22.2 Plumbing Piping& Materials $0.73 1.67%

22.3 0.00%

Division 22 Total $0.82 1.88%

DIVISION 23 - HEATING, VENTILATION AND AIR CONDITIONING

LINE NO. DESCRIPTION VALUE PERCENTAGE

23.1 HVAC Air Handlers $0.11 0.25%

23.2 Acoustics Duct Silencers $0.18 0.41%

23.3 Exhaust & Supply Fans $0.35 0.80%

23.4 Boiler & Computer Room Units (CRAC) $0.58 1.33%

23.5 Variable Air Volume 0JAV) Boxes $0.74 1.69%

23.6 Fire Smoke Dampers & Louvers $0.35 0.80%

23.7 Testing, Adjusting & Balancing of HVAC Sys $0.11 0.25%

23.8 Thermal lnsulation for Mechanical Sys $0.35 0.80%

23.9 Duct Insulation $0.23 0.53%

23.10 Duct Work & Duct Work Accessories $0.50 1.14%

23.11 Diffusers, Registers & Grills $0.22 0.50%

23.12 HVAC Controls $0.70 1.60%

Division 23 Total $4.42 10.11%

DIVISION 26 - ELECTRICAL

LINE NO. DESCRIPTION VALUE PERCENTAGE

26.1 Electrical Conduit, Fillings, Boxes $0.24 0.55%

26.2 Electrical Wire & Cable $0.93 2.13%

26.3 Interior Distribution Systems $0.91 2.08%

26.4 Low Voltage SwitchQear $0.23 0.53%

26.5 Switchboards & Panel Boards $0.51 1.17%

26.6 Interior lighting $0.11 0.25%

26.7 Electrical Exterior Underground $0.75 1.72%

26.8 Electric Meter $0.07 0.16%

Division 26 Total $3.68 8.42%

DIVISION 27 - COMMUNICATIONS (IF REQUIRED AS A PART OF CONTRACT)

LINE NO. DESCRIPTION VALUE PERCENTAGE

27.1 Comm Piping, Fittings and Boxes $0.88 2.01%

27.2 Communications Wire $0.44 1.01%

27.3 Communications Cable Tray $0.80 1.83%

27.4 Testing $0.06 0.14%

Division 27 Total $2.18 4.99%

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

LINE NO. DESCRIPTION VALUE PERCENTAGE

28.1 Fire Alarm System Conduit & Fittings $0.17 0.39%

28.2 Fire Alarm Panel and Power Boosters $0.96 2.20%

28.3 Fire Alarm Programming & Testing $0.05 0.11%

28.4 MNS Conduit and Fittings $0.47 1.08%

28.5 MNS Panels $0.40 0.91%

28.6 FA/MNS Programming & Testing $0.29 0.66%

Division 28 Total $2.34 5.35%

DIVISION 31 - EARTHWORK

LINE NO. DESCRIPTION VALUE PERCENTAGE

31.1 Landscaping (Demo) $0.06 0.14%

31.2 Landscaping (Sod and Watering) $0.06 0.14%

31.3 Soii Compaction Test $0.15 0.34%

Division 31 Total $0.27 0.62%

DIVISION 32 - EXTERIOR IMPROVEMENTS

LINE NO. DESCRIPTION VALUE PERCENTAGE

32.1 Bollards $0.58 1.33%

32.2 Concrete Sidewalks $0.05 0.11%

32.3 Fog Seal (Parking Lot) $0.63 1.44%

32.4 Curb Stops (Parking Lot) $0.05 0.11%

32.5 Restnping (Parking Lot) $0.29 0.66%

Division 32 Total $1.60 3.66%

DIVISION 33 - UTILITIES

LINE NO. DESCRIPTION VALUE PERCENTAGE

33.1 Natural Gas $0.63 1.44%

33.2 Gas Meter $0.05 0.11%

33.3 0.00%

Division 33 Total $0.68 1.56%

CLOSE-OUT DOCUMENTS

LINE NO. DESCRIPTION VALUE PERCENTAGE

A As-Built Drawings 0.00% B Warranties C O&M Manuals (Paper Copy and CD/DVD's) 0.00% D Roof Inspection Reports 0.00%

Close-out Total $0.00 0.00%

BID TOTAL $43.72 100.00%