250063_Pre-Bid RFI_Responses Round 2 COR.pdf

PDF 290 KB Posted

Attached to
WWYK250063 - INSTALL REACT VII FACILITY, B9001, POST V19
Solicitation number
FA813726R0026
Issued by

About this file

This is a Pre-Bid Request for Information (RFI) Response memorandum from the Department of the Air Force, 72d Air Base Wing (AFMC) at Tinker Air Force Base, Oklahoma, dated 21 August 2026, for Project WWYK250063 - Install REACT VII Facility, B9001, Post V19.

The memorandum addresses ten pre-bid RFIs submitted by the contractor(s) and provides government responses to clarify project requirements. Key clarifications include: (1) no contractor-provided arc flash/coordination study is required; (2) telecommunications scope is limited to pathway infrastructure only, including in-wall outlet backboxes, conduits, pull strings, and raceways routed approximately 100 feet to Telecommunications Room 1 (TR-1) at Column Post T18, with the government responsible for all active network hardware, cabling, and system testing; (3) abandoned electrical components designated for removal and reinstallation may be demolished and removed back to source; (4) Detail 2 on FA-101 applies to all pipe and raceways through fire-rated walls and vertical penetrations through the mezzanine deck; (5) blank boxes on drawing E-101 represent low-power Government-Furnished Equipment powered by existing 120V receptacles; (6) debris containment netting must meet specified requirements including high-density polyethylene material, ¼" mesh, NFPA 701 flame retardant standards, and accommodate 2" movement between structures; (7) Door 103A (Type 5) requires a 90-minute fire rating and motor operation; and (8) Door 105A is an LHR 3070 Type 7 door with 45-minute fire rating. Project contacts include Cole Hixon (Project Manager), Mark Williams (Construction Inspector), Joshua Wheeler (CSAG Program Manager), and Billy Deal (Contracting Officer Representative).

View the file

Other files

File Type Posted
250063_ATT01_SOW_Amend_01.pdf PDF
Site Visit Sign In Sheet.jpg JPG image
Solicitation - FA813726R0026.pdf PDF
250063_ATT 4_ODS.pdf PDF
WWYK250063-04March2026 1.docx DOCX document
250063_ATT 3_RMDF.pdf PDF
23 00 00.pdf PDF
23 07 00.pdf PDF
23 31 13.00 40.pdf PDF
23 08 00.pdf PDF
03 01 00.pdf PDF
23 64 26.pdf PDF
10 14 00.20.pdf PDF
23 05 48.00 40.pdf PDF
07 84 00.pdf PDF
23 03 00.pdf PDF
01 50 00.pdf PDF
00 80 00.pdf PDF
01 42 00.pdf PDF
UMRL.pdf PDF
PILE SCHEDULE.xlsx XLSX spreadsheet
HELICAL PILES NOTES.docx DOCX document
z400i.pdf_safe.pdf PDF
ELECTRICAL COMBINED.pdf PDF
220042 As Built Drawings.pdf PDF
250063_ATT 10_Submittal Register.xlsx XLSX spreadsheet
26 05 73 POWER STUDIES.pdf PDF
26 20 00.pdf PDF
09 90 00.pdf PDF
23 09 13.pdf PDF
23 36 00.00 40.pdf PDF
08 71 00.pdf PDF
05 40 00.pdf PDF
10 14 00.10.pdf PDF
08 33 23.pdf PDF
08 11 13.pdf PDF
07 92 00.pdf PDF
01 33 16.00 10.pdf PDF
01 32 16.00 20.pdf PDF
image.png PNG image
250063 React VII_Hardware schedule 25MAR26 JL.xlsx XLSX spreadsheet
JOIST SPECIAL INSPECTIONS.xlsx XLSX spreadsheet
ELECTRICAL PANEL SCHEDULE U18L.xlsx XLSX spreadsheet
esvEH_singledual_2023_V2.pdf PDF
lk406gn05t4_spec.pdf PDF
2_-_HE05-JINV-S11EE---GNT---L_001.pdf PDF
ERV Schedule_TAFB B9001_O-212477.xlsx XLSX spreadsheet
4500-CIVIL.pdf PDF
250063_ATT 10_Submittal Register.pdf PDF
250063_ATT 9_SOW.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

HEADQUARTERS 72D AIR BASE WING (AFMC)

TINKER AIR FORCE BASE OKLAHOMA

21 August 26

MEMORANDUM FOR AFSC/PZIOC (ATTN: Tamra Torres)

THROUGH: 72 ABW/CENM

FROM: 72 ABW/CEED

Tepa Companies

SUBJECT: Pre-Bid RFI Responses Project: WWYK250063 - INSTALL REACT VII FACILITY, B9001, POST V19

Reference: Memo, 13 August 2026, Pre-Bid RFIs, WWYK250063 - INSTALL REACT VII

FACILITY, B9001, POST V19

1. This office reviewed the referenced RFIs for the subject project and provided answers below. Please forward to the contractor(s) for their use in preparing proposals.

(1) With the drawings having an arc flash/coordination study on the drawing sheet E-602, will a contractor provided arc flash/coordination study be required on this project?

Government Response: No. The Arc Flash and Coordination Study shown on drawing E- 602 is for information only. A new, contractor-provided study is not required for this project.

(2) If arc flash/coordination study is required. How far upstream is the contractor supposed to go with the arc flash/coordination study based on General note 4 E-602.

Government Response: See response to RFI #1. No new study is required.

(3) The SOW is unclear on the extent of the telecommunication scope. Please provide more information on the telecommunication SOW.

a) Is the contractor to only provide inwall boxes and "stub-ups" for the base com to install the data? Yes. The contractor’s telecommunications physical scope of work is strictly limited to pathway infrastructure. The contractor shall provide and install all in-wall outlet backboxes, conduits, and pull strings.

b) Is the contractor to provide raceways back to the nearest communication rack in 9001. If so where is this rack located? Yes. The contractor shall install continuous raceways/conduits with pull strings routed from the new outlet locations back to the nearest existing telecommunications cable tray system.

The nearest active communications rack is located in Telecommunications Room 1 (TR-1) at Column Post T18, approximately 100 feet east of the project site. Conduit pathways must route back to the cable tray serving this terminal space.

c) Is the contractor to supply a full telecom system including wall mounted rack and fiber back to nearest telecommunication fiber rack within 9001. If so, where is the fiber rack located? No. The contractor is not responsible for supplying active network hardware, racks, fiber backbones, patch panels, or cabling. All cable pulling, terminations, patch panels, active electronics, and system testing will be performed by the Government (Base Communications) after construction completion.

c. Other? N/A

(4) For any electrical component on the east wall, that is to be removed and reinstalled for the fire rated wall, is abandoned after investigation; can these components be demoed and removed back to source as opposed to being reinstalled?

Government Response: Yes. If an electrical component (e.g., conduit, box, device) that is designated to be removed and reinstalled is found to be abandoned in place, the contractor shall remove the component and its associated wiring back to its source panel or junction box as part of the demolition scope.

(5) Is the Detail 2 on FA-101 applicable to all pipe and raceways through a fire rated wall? Is this applicable for ALL wall penetrations within this space, per detail note "1/2" MIN.

ANNULAR SPACE FILLED WITH FIRE RATED MATERIAL FOR FIRE RATED WALL

OR SILICON FOAM FOR NON-FIRE RATED WALL." Would this also be applicable for vertical penetrations through the mezzanine deck?

Government Response: Yes.

(6) What are the blank boxes drawn on E-101?

Government Response: The blank boxes shown on drawing E-101 represent low-power Government-Furnished Equipment (GFE). Their electrical power requirements are fully supported by, and shall be powered from, the adjacent 120V utility duplex receptacles already shown on the drawings. No dedicated branch circuits, disconnect switches, or specialized electrical hookups are required for this equipment.

(7) Please provide the specifications for the netting system referenced in SOW Section

4.2.6 and Drawing A-103, including the specification for the hardware and attachments needed to install the netting.

Government Response: The Debris containment netting system shall meet or exceed the following requirements:

a) Material/ Polymer type: Knitted High Density virgin Polyethylene (HDPE).

b) Mesh size/ Weight: ¼” x ¼”/ 3.0 – 4.5 ounces per square Yard.

c) Net Breaking Strength: 50 – 100 Lbs. per mesh square area.

d) Flame retardant Standards: meet NFPA 701 requirements, Test Method II.

e) Surface Burning: meet or exceed ASTM E 84/ Class1 requirements.

f) Reinforced Perimeter Border: Hemmed or reinforced edge borders.

g) Reinforced grommets spaced @ a maximum of 18” on center.

h) System attachment to existing girts at a minimum 3 feet above the guard rail with spacing to be a minimum of 18” on center.

i) Reinforced Borders: Must withstand 112 to 180 pounds per fastening point.

j) Hardware Attachment: Secure clips/snap Hooks/ SST wire rope/continuous

Unistrut/attachment to the wall girts above guard railing height and to the toe boards.

k) Netting to accommodate 2” movement between existing and the new React VII Structures.

l) Submit shop drawings.

m) Per SOW Revision 1 Issued 04 Aug 2026, refer to 1.1; Assemblies, framework, fixtures, or apparatus not readily identified on the project drawings, specifications, or this Statement of Work (SOW) shall be provided by the Contractor as required for a complete, fully operating, and functioning system or systems ready for use by the Government.

(8) What is the required fire rating for rolling steel Door Type 5 (Door 103A) — 1-hour, 2-hour, or 3-hour? The Door Schedule on A-602 lists this door as "90 MIN" (see Fire Rating column), but please confirm this is correct given the door type/location.

Government Response: The rating is 90 Minutes ( 1-1/2 hour) for Door 103A. Refer also to door schedule, door frame schedule and door Type 5 on Drawing A-601. The coiling overhead door systems must be installed per NFPA 80.

(9) Please confirm whether Door Type 5 (103A) is chain hoist operated or specify the intended means of operation.

Government Response: Door Type 5 (103A) is motor operated. Refer to Door Type 5 and Door Schedule on Drawing A-601.

(10) Specifications were not provided for the Type 6 grille door (Door 105A). Please provide the applicable specifications section and/or manufacturer performance criteria for this door.

Government Response: Door 105A is a LHR 3070 Type 7 door with a 45 minute fire rating. Door 105 is a Type 6 steel coiling overhead door. The coiling overhead door system must be installed per NFPA 80. Refer to Drawing A-601. This project does not have Grill type doors.

2. The points of contact for this project are:

a. Cole Hixon, Project Manager. PH: 736-7085

b. Mark Williams, Construction Inspector. PH: 582-9042

c. Joshua Wheeler, CSAG Program Manager. PH: 582-4826

d. Billy Deal, Contracting Officer Representative (COR). PH: 739-4975

COLE HIXON BILLY DEAL

Senior Project Manager Mechanical Engineer/COR 72d Civil Engineering Directorate (Tepa) 72d Civil Engineering Directorate

2026-08-25T07:26:50-0500
HIXON.WILLIAM.COLE.1609684727
2026-08-25T10:58:21-0500
DEAL.BILLY.LEE.III.1164437694

File details come from the government source that posted it. Updated .