This is a Special Provisions document for Tinker Air Force Base establishing mandatory requirements for contractors performing work on or near the active airfield, within clear zones, or in primary surfaces.

Runway and taxiway closures must be coordinated with Base Operations, with written closure requests submitted to the Contracting Officer at least 45 calendar days prior to the requested closure date. Requests must include the runway/taxiway nomenclature, specific work area, requested closure date, estimated duration, detailed work description, required equipment list, and personnel estimates. The Contracting Officer coordinates with Base Operations to schedule closures as close as possible to the requested date and duration. Contractors must have personnel, materials, and equipment ready on the approved closure date and complete work within the requested timeframe, as Base Operations cannot typically extend closures. Written notification to the Contracting Officer is required upon work completion.

Safety requirements mandate that all contractor personnel be provided ear plugs and/or ear muffs due to high-level noise from jet aircraft operations, with the government accepting no liability for auditory damage from non-use or improper use of protective equipment. Contractors must maintain clean work sites with no Foreign Object Damage (FOD), prevent material and equipment interference with aircraft, and obtain control tower clearance before crossing active runways or taxiways. Vehicles on landing areas must display approved, mounted, low-intensity amber flashing lights. When repeated crossings are necessary, contractors must use a government-furnished two-way radio exclusively for control tower communication. Height restrictions apply to temporary structures and equipment exceeding 12 feet within 1,000 feet of a runway or 50 feet elsewhere, requiring written approval submitted 21 calendar days in advance. Contractors must remove all materials and equipment to staging areas daily and maintain on-site cleaning equipment. An evacuation area must be identified on the first workday, with contractors required to vacate the work site immediately during aircraft emergencies and move all personnel and equipment to the designated evacuation area.

View the file

Other files

File Type Posted
Solicitation Amendment FA813726R00260001 - CANCELLATION.pdf PDF
250063_Pre-Bid RFI_Responses Round 2 COR.pdf PDF
Solicitation Amendment FA813726R00260001 SF 30.pdf PDF
250063_ATT02_Drawings_Amend_01.pdf PDF
250063_ATT01_SOW_Amend_01.pdf PDF
250063_Prebid RFI Responses.pdf PDF
Site Visit Sign in Sheet - WWYK250063.jpg JPG image
Site Visit Sign In Sheet.jpg JPG image
Solicitation - FA813726R0026.pdf PDF
4500-CIVIL.pdf PDF
esvEH_singledual_2023_V2.pdf PDF
01 32 16.00 20.pdf PDF
03 01 00.pdf PDF
10 44 16.pdf PDF
TAFB B9001 VAV Schedule.pdf PDF
23 00 00.pdf PDF
23 05 48.00 40.pdf PDF
SOW Att 02c_Controlled Area Training - Certificate.pdf PDF
00 71 00.pdf PDF
08 51 23.pdf PDF
23 09 23.02.pdf PDF
00 80 00.pdf PDF
00 70 00.pdf PDF
Solicitation - FA813726R0026.pdf PDF
2026 TAFB Mechanical Standard_signed.pdf PDF
Mechanical Schedules.xls XLS spreadsheet
SOW Att 05_SMS Builder Equipment List_v0 2023 0817.xlsx XLSX spreadsheet
08 81 00.pdf PDF
10 22 13.pdf PDF
08 71 00.pdf PDF
250063 React VII_Hardware schedule 25MAR26 JL.xlsx XLSX spreadsheet
2_-_HE05-JINV-S11EE---GNT---L_001.pdf PDF
2026 TAFB FIRE PROTECTION STANDARD.pdf PDF
23 05 15.pdf PDF
26 51 00 INTERIOR LIGHTING.pdf PDF
overall plan 04.15.2021.pdf PDF
01 33 00.pdf PDF
01 78 23.pdf PDF
ARCH-COMBINED.pdf PDF
01 78 00.pdf PDF
05 40 00.pdf PDF
ELECTRICAL PANEL SCHEDULE U18L.xlsx XLSX spreadsheet
07 21 16.pdf PDF
lrad331965pd_spec.pdf PDF
07 14 00.pdf PDF
28 31 76.pdf PDF
2020 TAFB Facility Standard.pdf PDF
250063_ATT 9_SOW.pdf PDF
REACT VII SA-01.pdf PDF
2026 TAFB Electrical Standard - Signed.pdf PDF
Show 40 more

Latest 50 of 108 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Tinker AFB Tinker General Requirements

SECTION 00 80 05

SPECIAL PROVISIONS FOR WORKING ON OR NEAR THE AIRFIELD ON TINKER AFB

PART 1 GENERAL

The following provisions shall apply when work is required to take place on the active airfield, within the clear zones, or in the primary surfaces as defined by Unified Facilities Criteria 3- 260-1, Airfield and Heliport Planning and Design.

1.1 CLOSURES

a. All runway and taxiway closures require coordination and scheduling with Base Operations. Written requests for closures shall be submitted to the Contracting Officer no less than 45 calendar days prior to the requested date of closure. The request shall include:

1. The nomenclature of the runway/taxiway to be closed

2. The area of the runway/taxiway where the work is to take place

3. The requested date of closure

4. The estimated duration of closure

5. A detailed description of the work to be performed

6. A list of the equipment required to perform the work

7. An estimate of the personnel required to perform the work

b. The Contracting Officer shall coordinate with Base Ops to close the requested runway/taxiway on or as close as possible to the date requested and for the length of time requested. The Contracting Officer shall notify the contractor, in writing, of the date and length of time approved for closure.

c. It is the responsibility of the contractor to have the necessary personnel, materials, and equipment ready to start work on the approved date of closure and to complete the work in the time requested. Under most circumstances, Base Operations will be unable to adjust flight and runway/taxiway utilization schedules to accommodate extensions to closures.

d. The contractor shall notify the Contracting Officer, in writing, when the work on the closed runway/taxiway is complete.

1.2 SAFETY

1.2.1 Personnel

The contractor shall provide all of his personnel ear plugs and/or ear muffs to prevent injury to their auditory systems while working on the Airfield. Jet aircraft operating on the runways, taxiways, and aprons make these areas zones of high-level noise. The government will not be held liable for auditory system damage due to non or improper use of noise protection equipment.

This requirement is in addition to the contractor providing his personnel with safety equipment required by OSHA for the work to be performed.

January 2022 Page 1 Section 00 80 05

1.2.2 Aircraft

The contractor shall maintain a clean work site and shall implement all measures necessary to insure that material and equipment do not interfere with or damage aircraft operating or parked in areas of the airfield that are not closed. NO FOD.

1.3 ACCESS RESTRICTIONS

No unescorted contractor vehicles, equipment, or personnel shall be on or cross any active runway or taxiway unless clearance is requested from, and granted by, the control tower. All contractor vehicles and mechanized equipment operating on the landing areas (the first 1,000 feet from either end of the runway) will be identified by approved, mounted, low intensity, amber flashing lights. When contractor operations require repeated vehicle or personnel crossing of an active runway, taxiway, or other controlled area, a two-way radio, furnished by the Government, will be used to maintain contact with the control tower. Use of the radio for other purposes will be strictly prohibited. The radio will be returned to the Government at the end of each workday, and will be reacquired as necessary.

1.4 HEIGHT RESTRICTIONS

The construction of any temporary structure or the use of any equipment that extends more than 12 feet above the ground within 1000 feet of a runway or that extends 50 feet above the ground elsewhere on Tinker AFB shall be approved by the Government prior to installation or use. Written request for approval shall be submitted to the Contracting Officer no later than 21 calendar days prior to the date needed.

1.5 CLEANLINESS

The contractor shall maintain the cleanliness of his work site and all traversed runways, taxiways, aprons, and ramps at all times. He shall utilize methods and equipment to prevent spilling or dropping materials in these areas and shall utilize whatever method or equipment necessary to insure the removal of loose materials from these areas. The contractor shall remove all material and equipment to his staging area at the end of each work day. No material is to be stockpiled nor equipment stored within 1000 feet of the centerline of a runway.

1.6 EMERGENCIES

1.6.1 Evacuation Area

On the first day of work on the airfield, the contractor, a representative of the Contracting Officer, and a representative of Base Ops shall identify an area a safe distance from the runway where the contractor is to move his personnel and equipment during an aircraft emergency.

1.6.2 Evacuation

During an aircraft emergency, the contractor shall vacate the work site.

He shall move all personnel and equipment to the designated evacuation area. Evacuation orders will be given on short notice and will require expeditious action by the contractor.

January 2022 Page 2 Section 00 80 05

1.7 INSPECTION AND CLEANING

The contractor shall maintain, on site and in good working order, equipment capable of cleaning loose materials from the runway, taxiway, ramp, or apron. The contractor, accompanied by a Government representative, may be required to inspect the entire length of the runway and taxiway to insure that all personnel, debris, material, equipment, and tools have been removed from these areas.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --