013001 submittal descriptions.doc

DOC document 33 KB Posted

Attached to
Construct Addition/Fire Suppression B104
Solicitation number
FA6656-09-R-0005
Issued by

About this file

Specification Section 01 30 10 Submittal Descriptions

View the file

Other files

File Type Posted
Q Aas of 28 August 2009 B104.doc DOC document
Attendes Site VisitB104.xls XLS spreadsheet
scan166.pdf PDF
Q Aas of20 August 2009 B104.doc DOC document
FA665609R0005Amendment1B104.doc DOC document
scan165.pdf PDF
scan168.pdf PDF
scan169.pdf PDF
scan164.pdf PDF
scan167.pdf PDF
WDupdateB104.doc DOC document
Q Aas of 19 August 2009 B104.doc DOC document
SiteVisitMinutesB104.docx DOCX document
Attendes Site VisitB104.xls XLS spreadsheet
SolDocB104.doc DOC document
230713 - ductwork insulation.doc DOC document
260529 - hangers and supports for electrical systems.doc DOC document
095113 - acoustical panel ceilings.doc DOC document
312300 excavation and fill.doc DOC document
072216 roof board insulation.doc DOC document
081113 hollow-metal doors and frame.doc DOC document
329213 hydro-mulching.doc DOC document
081416 flush wood doors.doc DOC document
a_01.pdf PDF
220529 - pipe hangers supports for plumbing piping.doc DOC document
s_01.pdf PDF
s_06.pdf PDF
122100 window blinds.doc DOC document
FA665609R0005Atch4ResQues.doc DOC document
e_02.pdf PDF
013280 removal of asbestos.doc DOC document
083100 access doors and panels.doc DOC document
262726 - wiring devices.doc DOC document
238126 - duct-free split system air conditioners.doc DOC document
054000_cold formed metal framing.doc DOC document
f_01.pdf PDF
220719 - plumbing piping insulation.doc DOC document
260101 - electrical demolition.doc DOC document
s_03.pdf PDF
072719 plastic sheet air barriers.doc DOC document
USAFR Asbestos Areas1.pdf PDF
052100_steel joist framingf.doc DOC document
024119.13 selective building demolition.doc DOC document
p_02.pdf PDF
p_03.pdf PDF
223000 - plumbing equipment.doc DOC document
260526 - grounding and bonding for electrical systems.doc DOC document
AF Form 3065.pdf PDF
335100 - natural-gas distribution.doc DOC document
a_03.pdf PDF
Show 40 more

Latest 50 of 145 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Section 01 30 01

SUBMITTAL DESCRIPTIONS

Part 1 – GENERAL

1.01 Related Documents

A.

Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.02

SUBMITTAL CLASSIFICATION

A.

Related Documents: Other requirements pertaining to submittals are included in:

1.

The Contract Clauses.

2.

Section 01 33 00 – Submittal Procedures.

B.

Submittals required by the Contract Clauses and other non‑technical parts of the Contract are not included in this Section.

C.

The submittals described below are those required and further described in other sections of the specifications.

1.

Submittal Description No. 1 (SD‑01) – Data: Submittals that provide calculations, descriptions, or documentation regarding the Work.

2.

Submittal Description No. 2 (SD‑02) – Not Used.

3.

Submittal Description No. 3 (SD‑03) – Not Used.

4.

Submittal Description No. 4 (SD‑04) – Drawings: Submittals that graphically show:

a.

Relationship of various components of the Work.

b.

Schematic diagrams of systems.

c.

Details of fabrication.

d.

Layouts of particular elements.

e.

Connections.

f.

Other relational aspects of the work.

5.

Submittal Description No. 5 (SD‑05) – Not Used.

6.

Submittal Description No. 6 (SD‑06) – Instructions: Preprinted materials describing installation of a product, system, or material, including special notices and material safety data sheets, if any, concerning impedances, hazards, and safety precautions.

7.

Submittal Description No. 7 (SD‑07) – Schedules: Tabular lists showing location, features, or other pertinent information regarding products, materials, equipment, or components to be used in the Work.

8.

Submittal Description No. 8 (SD‑08) – Statements: Documents, required of the Contractor, or through the Contractor from a Supplier, Installer, Manufacturer, or other lower tier Contractor, the purposes of which is to confirm the quality or orderly progression of a portion of the Work by:

Documenting procedures.

Acceptability of methods or personnel.

Qualifications.

Other verifications of quality.

9.

Submittal Description No. 9 (SD‑09) – Reports: Reports of inspections or tests, including analysis and interpretation of test results. Each report shall be properly identified, signed, and dated. Test methods used shall be identified and test results shall be recorded.

10.

Submittal Description No. 10 (SD‑10) – Not Used.

11.

Submittal Description No. 11 (SD‑11) – Not Used.

12.

Submittal Description No. 12 (SD‑12) – Not Used.

13.

Submittal Description No. 13 (SD‑13) – Certificates: Statements signed by an official authorized to certify on behalf of the Manufacturer of a product, system, or material, attesting that the product, system, or material meets specified requirements. The statement shall:

Be dated after the award of this Contract.

State the Contractor’s name and address.

Name the Project and its location.

List the specific requirements that are being certified.

14.

Submittal Description No. 14 (SD‑14) – Samples: Samples, including both fabricated and unfabricated physical examples of materials, products, and units of the Work – as complete units or as portions of units of the Work.

15.

Submittal Description No. 15 (SD‑015) – Not Used.

16.

Submittal Description No. 16 (SD‑16) – Not Used.

17.

Submittal Description No. 17 (SD‑17) – Not Used.

18.

Submittal Description No. 18 (SD‑18) – Records: Documentation required to record compliance with technical or administrative requirements.

19.

Submittal Description No. 19 (SD‑19) – Operation and Maintenance Manuals: Data that forms a part of an operation and maintenance manual.

PART 2 – PRODUCTS – Not Used PART 3 – Execution – Not Used

End of Section 01 30 01

THIS PAGE IS INTENTIONALLY BLANK.

01 30 01-2

SUBMITTAL DESCRIPTIONS

12910-330

Revised 3/2/09

12910-330

SUBMITTAL DESCRIPTIONS

01 30 01-1