Q Aas of 28 August 2009 B104.doc
DOC document 33 KB Posted
- Attached to
- Construct Addition/Fire Suppression B104
- Solicitation number
- FA6656-09-R-0005
About this file
Solicitation FA6656-09-R-0005 Correction to Question 24
View the file
Other files
Show 40 more
Latest 50 of 145 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation #FA6656-09-R-0005 Construct Addition/Fire Suppression B104 Questions with Answers/Clarifications as of 28 August 2009:
Correction
24. The finish schedule on sheet A-11 is showing CT2/P1 for the wall finishes in Rooms 105 and 110. The interior elevations for these two rooms on sheet A-08 is showing full height ceramic tile (CT2/CT3). Please clarify your intent.
Response: Follow scheme shown in the interior elevations for these two rooms as detailed on Sheet A-08 and use full height ceramic tile with accent ceramic tile (CT2/CT3) as per Air Force material board color selection.