Attachment_16_-_Section_02_81_00_Transportation_and_Disposal_of_Hazardous_Materials.pdf

PDF 83 KB Posted

Attached to
Paint and Protective Coatings IDIQ
Solicitation number
FA4419-14-R-0102
Issued by

About this file

Attachment 16 - Section 02 81 00 Transportation and Disposal of Hazardous Materials

View the file

Other files

File Type Posted
Questions_and_Answers.xlsx XLSX spreadsheet
Site_Visit_Presentation.pptx PPTX presentation
Attachment_34_-_Paint_Coefficient_(FINAL).xlsx XLSX spreadsheet
Attachment_10_-_Section_01_37_00_Construction_Schedule.pdf PDF
Attachment_15_-_Section_01_78_00_Project_Closeout.pdf PDF
Attachment_21_-_Section_09_90_00_Paints_and_Coatings.pdf PDF
Attachment_30_-_Wage_Determination-Highway.pdf PDF
Attachment_26_-_Section_32_01_11.51_Rubber_and_Paint_Removal_from_Airfield_Pavements.pdf PDF
Attachment_22_-_Section_09_97_13.00_40_Steel_Coatings.pdf PDF
Attachment_18_-_Section_09_23_00_Gypsum_Plastering.pdf PDF
Attachment_2_-_Section_01_11_00_Summary_of_Work.pdf PDF
Attachment_32_-_Form_66_Submittal_Register.xls XLS spreadsheet
Attachment_24_-_Section_09_97_13.17_Three-Coat_Epoxy_Interior_Coating_of_Welded_Steel_Petroleum_Fuel_Tanks.pdf PDF
Attachment_11_-_Section_01_40_00_Safety.pdf PDF
Attachment_23_-_Section_09_97_13.16_Interior_Coating_of_Welded_Steel_Water_Tanks.pdf PDF
Attachment_12_-_Section_01_50_00_Temporary_Construction_Facilities_and_Controls.pdf PDF
Attachment_35_-_Past_Performance_Questionnaire.pdf PDF
Attachment_28_-_Section_32_17_24.00_10_Pavement_Markings.pdf PDF
Attachment_4_-_Section_01_30_00_Administrative_Requirements.pdf PDF
FA4419-14-R-0102_Paint_and_Protective_Coatings_IDIQ.doc DOC document
Attachment_13_-_Section_01_55_00_Temporary_Environmental_Controls.pdf PDF
Attachment_8_-_Section_01_35_26_Government_Safety_Requirements.pdf PDF
Attachment_20_-_Section_09_64_66_Athletic_Wood_Flooring.pdf PDF
Attachment_7_-_Section_01_35_00_Quality_Control.pdf PDF
Attachment_19_-_Section_09_29_00_Gypsum_Board.pdf PDF
Attachment_31_-_NAF_Provisions_Clauses.pdf PDF
Attachment_5_-_Section_01_30_60_Background_Checks_for_Contractor_Personnel.pdf PDF
Attachment_29_-_Wage_Determination-Building.pdf PDF
Attachment_3_-_Section_01_15_00_Work_Restrictions.pdf PDF
Attachment_27_-_Section_32_17_23.00_20_Pavement_Markings.pdf PDF
Attachment_1_-_Statement_of_Work.pdf PDF
Attachment_33_-_EMS_Training_Statement.pdf PDF
Attachment_25_-_Section_09_97_13.27_Exterior_Coating_of_Steel_Structures.pdf PDF
Attachment_9_-_Section_01_35_40.00_20_Environmental_Management.pdf PDF
Attachment_14_-_Section_01_75_00_Starting_and_Adjusting.pdf PDF
Attachment_17_-_Section_03_01_30.71_Concrete_Rehabilitation.pdf PDF
Attachment_6_-_Section_01_33_00_Submittal_Procedures.pdf PDF
Show all 37

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA4419-14-R-0102

Attachment 16

SECTION 02 81 00

TRANSPORTATION AND DISPOSAL OF HAZARDOUS MATERIALS

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

40 CFR 261 Identification and Listing of Hazardous Waste

40 CFR 262 Standards Applicable to Generators of Hazardous Waste

40 CFR 263 Standards Applicable to Transporters of Hazardous

Waste

40 CFR 264 Standards for Owners and Operators of Hazardous

Waste Treatment, Storage, and Disposal Facilities

40 CFR 265 Interim Status Standards for Owners and Operators of

Hazardous Waste Treatment, Storage, and Disposal

Facilities

40 CFR 266 Standards for the Management of Specific Hazardous

Wastes and Specific Types of Hazardous Waste

Management Facilities

40 CFR 268 Land Disposal Restrictions

40 CFR 270 EPA Administered Permit Programs: The Hazardous

Waste Permit Program

40 CFR 279 Standards for the Management of Used Oil

40 CFR 300 National Oil and Hazardous Substances Pollution

Contingency Plan

40 CFR 302 Designation, Reportable Quantities, and Notification

40 CFR 61 National Emission Standards for Hazardous Air

Pollutants

40 CFR 761 Polychlorinated Biphenyls (PCBs) Manufacturing, Processing, Distribution in Commerce, and Use

Prohibitions

49 CFR 107 Hazardous Materials Program Procedures

49 CFR 172 Hazardous Materials Table, Special Provisions, Hazardous Materials Communications, Emergency

Response Information, and Training Requirements

49 CFR 173 Shippers - General Requirements for Shipments and

Packagings

49 CFR 178 Specifications for Packagings

ALTUS AFB INSTRUCTIONS

AAFBI 32-7001 Environmental Compliance

1.2 DEFINITIONS

1.2.1 Hazardous Material

A substance or material which has been determined by the Secretary of Transportation to be capable of posing an unreasonable risk to health, safety, and property when transported in commerce, and which has been so designated pursuant to the Hazardous Materials

Transportation Act, 49 U.S.C. Appendix Section 1801 et seq. The term includes materials designated as hazardous materials under the provisions of 49 CFR 172, Sections

.101 and .102 and materials which meet the defining criteria for hazard classes and divisions in 49 CFR 173. EPA designated hazardous wastes are also hazardous materials.

1.2.2 Hazardous Waste

A waste which meets criteria established in RCRA or specified by the EPA in 40 CFR

261 or which has been designated as hazardous by a RCRA authorized state program.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for [Contractor Quality Control approval.] [information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.] Submit the following in accordance with Section 01 33 00

SUBMITTAL PROCEDURES:

SD-03 Product Data

Onsite Hazardous Waste Management[G]

Notices of Non-Compliance and Notices of Violation

Packaging Notifications file://52aggn-as-sps02/eda/JOBS/IDIQ/pulldata/01%2033%2000.sec

SD-06 Test Reports

Recordkeeping[G]

Spill Response

Exception Report[G]

SD-07 Certificates

Certification

Security Plan

Transportation and Disposal Coordinator[G]

Training[G]

EPA Offsite Policy

Certificates of Disposal

Shipping Documents and Packagings Certification[G]

Waste Minimization[G]

1.4 QUALITY ASSURANCE

1.4.1 Transportation and Disposal Coordinator

Designate, by position and title, one person to act as the Transportation and Disposal

Coordinator (TDC) for this contract. The TDC shall serve as the single point of contact for all environmental regulatory matters and shall have overall responsibility for total environmental compliance at the site including, but not limited to, accurate identification and classification of hazardous waste and hazardous materials; determination of proper shipping names; identification of marking, labeling, packaging and placarding requirements; completion of waste profiles, hazardous waste manifests, asbestos waste shipment records, PCB manifests, bill of ladings, exception and discrepancy reports; and all other environmental documentation. The TDC shall have, at a minimum, one year of specialized experience in the management and transportation of hazardous waste and have been Department of Transportation certified under 49 CFR 172, Subpart H.

1.4.2 Training

The Contractor's hazardous materials employees shall be trained, tested, and certified to safely and effectively carry out their assigned duties in accordance with [Section 01 35

29.13 HEALTH, SAFETY, AND EMERGENCY RESPONSE PROCEDURES FOR

CONTAMINATED SITES]. The Contractor's employees transporting hazardous materials or preparing hazardous materials for transportation, including samples, shall be trained, tested, and certified in accordance with 49 CFR 172, Subpart H, including security awareness and any applicable security plans. Where shipment of hazardous materials by air may be occurring, such as for sample shipments, the Contractor's hazardous material employees shall also be trained on IATA DGR. Contractor employees making determinations that shipments do not constitute DOT regulated hazardous materials shall also be trained, tested, and certified in accordance with 49 CFR

172, Subpart H.

1.4.3 Certification

The Contractor and/or subcontractors transporting hazardous materials shall possess a current certificate of registration issued by the Research and Special Programs

Administration (RSPA), U.S. Department of Transportation, when required by 49 CFR

107, Subpart G. Submit copies of the certificates or written statements certifying exemption from these requirements.

1.4.4 Laws and Regulations Requirements

Work shall meet or exceed the minimum requirements established by Federal, state, and local laws and regulations which are applicable. These requirements are amended frequently and compliance with amendments is required as they become effective. In the event that compliance exceeds the scope of work or conflicts with specific requirements of the contract, notify the Contracting Officer immediately.

PART 2 PRODUCTS

2.1 MATERIALS

Provide all the materials required for the packaging, labeling, marking, placarding and transportation of hazardous wastes and hazardous materials in conformance with Department of Transportation standards, IATA DGR, and EP 415-1-266. Details in this specification shall not be construed as establishing the limits of the Contractor's responsibility.

2.1.1 Packaging

Provide bulk and non-bulk containers for packaging hazardous materials/wastes consistent with the authorizations referenced in the Hazardous Materials Table in 49 CFR

172, Section .101, Column 8. Bulk and non-bulk packaging shall meet the corresponding specifications in 49 CFR 173 referenced in the Hazardous Materials Table, 49 CFR 172, Section .101. Each packaging shall conform to the general packaging requirements of

Subpart B of 49 CFR 173, to the requirements of 49 CFR 178 at the specified packing group performance level, to the requirements of special provisions of column 7 of the

Hazardous Materials Table in 49 CFR 172, Section .101, and shall be compatible with the material to be packaged as required by 40 CFR 262. Also provide other packaging related materials such as materials used to cushion or fill voids in over packed containers, etc. Sorbent materials shall not be capable of reacting dangerously with, being decomposed by, or being ignited by the hazardous materials being packaged.

Additionally, sorbents used to treat free liquids to be disposed of in landfills shall be non-biodegradable as specified in 40 CFR 264, Section .314. In addition, packaging notifications will be provided to the Government in accordance with 49 CFR 172, Section

.178.2(c) regarding type and dimensions of closures, including gaskets, needed to satisfy performance test requirements.

2.1.2 Markings

Provide markings for each hazardous material/waste package, freight container, and transport vehicle consistent with the requirements of 49 CFR 172, Subpart D and 40 CFR

262, Section .32 (for hazardous waste) 40 CFR 761, Section .45 (for PCBs) 40 CFR 61, Section .149(d) (for asbestos) EP 415-1-266 (for FUSRAP radionuclides). Markings shall be capable of withstanding, without deterioration or substantial color change, a 180 day exposure to conditions reasonably expected to be encountered during container storage and transportation.

2.1.3 Labeling

Provide primary and subsidiary labels for hazardous materials/wastes consistent with the requirements in the Hazardous Materials Table in 49 CFR 172, Section .101, Column 6.

Labels shall meet design specifications required by 49 CFR 172, Subpart E including size, shape, color, printing, and symbol requirements. Labels shall be durable and weather resistant and capable of withstanding, without deterioration or substantial color change, a 180 day exposure to conditions reasonably expected to be encountered during container storage and transportation.

2.1.4 Placards

For each offsite shipment of hazardous material/waste, provide primary and subsidiary placards consistent with the requirements of 49 CFR 172, Subpart F. Placards shall be provided for each side and each end of bulk packaging, freight containers, transport vehicles, and rail cars requiring such placarding. Placards may be plastic, metal, or other material capable of withstanding, without deterioration, a 30 day exposure to open weather conditions and shall meet design requirements specified in 49 CFR 172, Subpart

F.

2.1.5 Spill Response Materials

Provide spill response materials including, but not limited to, containers, adsorbent, shovels, and personal protective equipment. Spill response materials shall be available at all times in which hazardous materials/wastes are being handled or transported. Spill response materials shall be compatible with the type of material being handled.

2.2 EQUIPMENT AND TOOLS

Provide miscellaneous equipment and tools necessary to handle hazardous materials and hazardous wastes in a safe and environmentally sound manner.

PART 3 EXECUTION

3.1 ONSITE HAZARDOUS WASTE MANAGEMENT

These paragraphs apply to Government owned waste only. Contractors are prohibited by 10

U.S.C. 2692 from storing Contractor owned waste onsite for any length of time. The

Contractor is responsible for ensuring compliance with all Federal, state, and local hazardous waste laws and regulations and shall verify those requirements when preparing reports, waste shipment records, hazardous waste manifests, or other documents. Identify hazardous wastes using criteria set forth in 40 CFR 261 or all applicable state and local laws, regulations, and ordinances. When accumulating hazardous waste onsite, comply with generator requirements in 40 CFR 262 and any applicable state or local law or regulations. Onsite accumulation times shall be restricted to applicable time frames referenced in 40 CFR 262, Section .34 and any applicable state or local law or regulation. Accumulation start dates shall commence when waste is first generated (i.e. containerized or otherwise collected for discard). Only use containers in good condition and compatible with the waste to be stored. Ensure containers are closed except when adding or removing waste, and immediately mark all hazardous waste containers with the words "hazardous waste" and other information required by 40 CFR 262, Section .32 and any applicable state or local law or regulation as soon as the waste is containerized. An additional marking shall be placed on containers of "unknowns" designating the date sampled, and the suspected hazard. Inspect containers for signs of deterioration and for responding to any spills or leaks. Inspect all hazardous waste areas weekly and provide written documentation of the inspection. Include date and time of inspection, name of individual conducting the inspection, problems noted, and corrective actions taken on the inspection logs.

3.1.1 Hazardous Waste Classification

Identify, in consultation with the Contracting Officer, all waste codes applicable to each hazardous waste stream based on requirements in 40 CFR 261 or any applicable state or local law or regulation. Also identify all applicable treatment standards in 40 CFR 268 and state land disposal restrictions and make a determination as to whether or not the waste meets or exceeds the standards. Waste profiles, analyses, classification and treatment standards information shall be submitted to Contracting Officer for review and approval.

3.1.2 Management Plan

Prepare a plan detailing the manner in which hazardous wastes will be managed and describing the types and volumes of hazardous wastes anticipated to be managed as well as the management practices to be utilized. The plan shall identify the method to be used to ensure accurate piece counts and/or weights of shipments; shall identify waste minimization methods; shall propose facilities to be utilized for treatment, storage, and/or disposal; shall identify areas onsite where hazardous wastes are to be handled; and shall identify whether transfer facilities are to be utilized; and if so, how the wastes will be tracked to ultimate disposal. Submit the plan prior to start of work. Written documentation of weekly hazardous waste inspections shall be submitted on a monthly basis.

3.2 OFFSITE HAZARDOUS WASTE MANAGEMENT

Use RCRA Subtitle C permitted facilities which meet the requirements of 40 CFR 264 or facilities operating under interim status which meet the requirements of 40 CFR 265. Offsite treatment, storage, and/or disposal facilities with significant RCRA violations or compliance problems (such as facilities known to be releasing hazardous constituents into ground water, surface water, soil, or air) shall not be used. Submit Notices of Non-Compliance and Notices of Violation by a Federal, state, or local regulatory agency issued to the Contractor in relation to any work performed under this contract. Immediately provide copies of such notices to the

Contracting Officer. Also furnish all relevant documents regarding the incident and any information requested by the Contracting Officer, and coordinate its response to the notice with the Contracting Officer or the designated representative prior to submission to the notifying authority. Also furnish a copy to the Contracting Officer of all documents submitted to the regulatory authority, including the final reply to the notice, and all other materials, until the matter is resolved.

3.2.1 Treatment, Storage, and/or Disposal Facility and Transporter

Provide the Contracting Officer with EPA ID numbers, names, locations, and telephone numbers of TSD facilities and transporters. This information shall be contained in the

Hazardous Waste Management Plan and shall be approved by the Contracting Officer prior to waste disposal.

3.2.2 Status of the Facility

Facilities receiving hazardous waste shall be permitted in accordance with 40 CFR 270 or operating under interim status in accordance with 40 CFR 265 requirements, or permitted by a state authorized by the Environmental Protection Agency to administer the RCRA permit program. Additionally, prior to using a TSD Facility, contact the EPA Regional

Offsite Coordinator specified in 40 CFR 300, Section .440, to determine the facility's status, and document all information necessary to satisfy the requirements of the EPA

Offsite policy and submit this information to the Contracting Officer.

3.2.3 Shipping Documents and Packaging Certification

Prior to shipment of any hazardous material offsite and a minimum of 14 days prior to anticipated pickup, the Contractor's TDC shall provide for review written certification to the Contracting Officer that hazardous materials have been properly packaged, labeled, and marked in accordance with Department of Transportation and EPA requirements.

Packaging assurances shall be furnished by the designated disposal facility not later than

35 days after acceptance of the shipment. The Contractor's TDC shall also provide written certification regarding waste minimization efforts documenting that efforts have been taken to reduce the volume and toxicity of waste to the degree economically practicable and that the method of treatment, storage, or disposal selected minimizes threats to human health and the environment.

3.2.4 Transportation

Prior to conducting hazardous materials activities, the Contractor responsible for pre-transportation activities shall either certify to the Government that a Security Plan is in place which meets the requirements of 49 CFR 172, Subpart I or in the event that the types or amounts of hazardous materials are excluded from the security planning requirements, a written statement to that effect detailing the basis for the exception. Use manifests for transporting hazardous wastes as required by 40 CFR 263 or any applicable state or local law or regulation. Transportation shall comply with all requirements in the

Department of Transportation referenced regulations in the 49 CFR series. Prepare hazardous waste manifests for each shipment of hazardous waste shipped offsite.

Manifests shall be completed using instructions in 40 CFR 262, Subpart B and any applicable state or local law or regulation. Submit manifests and waste profiles to

Contracting Officer for review and approval. Prepare land disposal restriction notifications as required by 40 CFR 268 or any applicable state or local law or regulation for each shipment of hazardous waste. Submit notifications with the manifest to the

Contracting Officer for review and approval. In accordance with DOT 4500.9R, inspect motor vehicles used to transport hazardous materials in accordance the 49 CFR and DOT safety regulations and complete DD Form 626, Motor Vehicle Inspection.

3.2.5 Treatment and Disposal of Hazardous Wastes

The hazardous waste shall be transported to an approved hazardous waste treatment, storage, or disposal facility within 90 days of the accumulation start date on each container. Ship hazardous wastes only to facilities which are properly permitted to accept the hazardous waste or operating under interim status. Ensure wastes are treated to meet land disposal treatment standards in 40 CFR 268 prior to land disposal. Propose TSD facilities via submission of the Hazardous Waste Management Plan, subject to the approval of the Contracting Officer. Submit Certificates of Disposal documenting the ultimate disposal, destruction or placement of [hazardous wastes, CERCLA remediation waste, polychlorinated biphenyls (PCBs), and/or asbestos within 180 days of initial shipment. Receipt of these certificates will be required for final payment.

3.3 RADIOACTIVE MATERIALS MANAGEMENT

In consultation with the Contracting Officer , evaluate, prior to shipment of any material offsite, whether the material is regulated as a hazardous waste in addition to being regulated as a radioactive material; this shall be done for the purpose of determining proper shipping descriptions, marking requirements, etc., as described below.

3.3.1 Identification of Proper Shipping Names

Use 49 CFR 172, Section .101 to identify proper shipping names for each hazardous material (including hazardous wastes) to be shipped offsite. Submit proper shipping names to the Contracting Officer in the form of draft shipping documents for review and approval.

3.3.2 Packaging, Labeling, and Marking

Package, label, and mark hazardous materials/wastes using the specified materials and in accordance with the referenced authorizations. Mark each container of hazardous waste of 110 gallons or less with the following:

"HAZARDOUS WASTE - Federal Law Prohibits Improper Disposal.

If found, contact the nearest police or public safety authority or the U.S. Environmental

Protection Agency.

Generator's name _____________________________________

Manifest Document Number ___________________________".

3.3.3 Shipping Documents

Ensure that each shipment of hazardous material sent offsite is accompanied by properly completed shipping documents. This includes shipments of samples that may potentially meet the definition of a Department of Transportation regulated hazardous material.

3.3.3.1 PCB Waste Shipment Documents

Prepare hazardous waste manifests for each shipment of PCB waste shipped offsite.

Complete manifests using instructions in 40 CFR 761, Sections .207 and .208 and all other applicable requirements. Submit documents to Contracting Officer for review and approval.

3.3.3.2 Asbestos Waste Shipment Documents

Prepare waste shipment records, as required by 40 CFR 61, for shipments of asbestos.

Submit waste shipment records to the Contracting Officer for review and approval.

Waste shipment records shall be signed by the Contractor.

3.3.3.3 Other Hazardous Material Shipment Documents

Prepare a bill of lading for each shipment of hazardous material which is not accompanied by a hazardous waste manifest or asbestos waste shipment record which fulfills the shipping paper requirements. The bill of lading shall satisfy the requirements of 49 CFR 172, Subpart C, [and 40 CFR 279 if shipping used oil] and any applicable state or local law or regulation, and shall be submitted to the Contracting

Officer for review and approval. For laboratory samples and treatability study samples, prepare bills of lading and other documentation as necessary to satisfy conditions of the sample exclusions in 40 CFR 261, Section .4(d) and (e) and any applicable state or local law or regulation. Bill of ladings requiring shipper's certifications shall be signed by the Contractor.

3.4 OBTAINING EPA ID NUMBERS

Complete EPA Form 8700-12, Notification of Hazardous Waste Activity, and submit to the

Contracting Officer for review and approval. Allow a minimum of 30 days for processing the application and assigning the EPA ID number. Shipment shall be made not earlier than one week after receipt of the EPA ID number.

3.5 SPECIAL REQUIREMENTS FOR ASBESTOS WASTES

If work involves asbestos containing wastes, manage these wastes in accordance with specification Section.

3.6 WASTE MINIMIZATION

Minimize the generation of hazardous waste to the maximum extent practicable and take all necessary precautions to avoid mixing clean and contaminated wastes. Identify and evaluate recycling and reclamation options as alternatives to land disposal. Requirements of 40 CFR

266 shall apply to: hazardous wastes recycled in a manner constituting disposal; hazardous waste burned for energy recovery; lead-acid battery recycling; and hazardous wastes with economically recoverable precious metals. Submit written certification that waste minimization efforts have been undertaken to reduce the volume and toxicity of waste to the degree economically practicable and that the method of treatment, storage, or disposal selected minimizes threats to human health and the environment.

3.7 RECORDKEEPING

The Contractor is responsible for maintaining adequate records to support information provided to the Contracting Officer regarding exception reports, annual reports, and biennial reports; maintaining asbestos waste shipment records for a minimum of 3 years from the date of shipment or any longer period required by any applicable law or regulation or any other provision of this contract; and maintaining bill of ladings for a minimum of 375 days from the date of shipment or any longer period required by any applicable law or regulation or any other provision of this contract. Submit information necessary to file state annual or EPA biennial reports for all hazardous waste transported, treated, stored, or disposed of under this contract. Do not forward these data directly to the regulatory agency but to the Contracting

Officer at the specified time. The submittal shall contain all the information necessary for filing of the formal reports in the form and format required by the governing Federal or state regulatory agency. A cover letter shall accompany the data to include the contract number, Contractor name, and project location. In the events that a manifest copy documenting receipt of hazardous waste at the treatment storage and disposal facility is not received within 35 days of shipment initiation, or that a manifest copy documenting receipt of PCB waste at the designated facility is not received within 35 days of shipment initiation, prepare and submit an exception report to the Contracting Officer within 37 days of shipment initiation.

3.8 SPILL RESPONSE

In the event of a spill or release of a hazardous substance (as designated in 40 CFR 302), or pollutant or contaminant, or oil (as governed by the Oil Pollution Act (OPA), 33 U.S.C. 2701 et seq.), notify the Contracting Officer immediately. Any direction from the Contracting

Officer concerning a spill or release shall not be considered a change under the contract. If the spill exceeds a reporting threshold, follow the pre-established procedures for immediate reporting to the Contracting Officer. Comply with all applicable requirements of Federal, state, or local laws or regulations regarding any spill incident.

3.9 EMERGENCY CONTACTS

The Contractor is responsible for complying with the emergency contact provisions in 49 CFR

172, Section .604. Whenever the Contractor ships hazardous materials, provide a 24 hr emergency response contact and phone number of a person knowledgeable about the hazardous materials being shipped and who has comprehensive emergency response and incident mitigation information for that material, or has immediate access to a person who possesses such knowledge and information. The phone shall be monitored on a 24 hour basis at all times when the hazardous materials are in transportation, including during storage incidental to transportation. Ensure that information regarding this emergency contact and phone number are placed on all hazardous material shipping documents. Designate an emergency coordinator and post the following information at areas in which hazardous wastes are managed:

a. The name of the emergency coordinator.

b. Phone number through which the emergency coordinator can be contacted on a 24 hour basis.

c. The telephone number of the local fire department.

d. The location of fire extinguishers and spill control materials.

Attachment A

SAMPLE OFF-SITE POLICY CERTIFICATION MEMO

Project/Contract #:

Waste Stream:

Primary TSD Facility, EPA ID # and Location:

Alter. TSD Facility, EPA

ID # and Location:

EPA Region Contact

I (617) 918-1752

II (212) 637-4130

III (214) 814-5267

IV (404) 562-8591

V (312) 353-8207

VI (214) 665-2282

VII (913) 551-7154

VIII (303) 312-6419

IX (415) 972-3304

X (206) 553-2859

EPA representative contacted:

EPA representative phone number:

Date contacted:

Comment:

The above EPA representative was contacted on __________. As of that date the above sites were considered acceptable in accordance with the Off-Site

Policy in 40 CFR 300.440.

Date: Signature:

Phone number:

-- End of Section --