Attachment 12 - Section 01 50 00 Temporary Construction Facilities and Controls

View the file

Other files for this federal contract opportunity

Other files attached to Paint and Protective Coatings IDIQ, newest first.
File Type Posted
Questions_and_Answers.xlsx XLSX spreadsheet
Site_Visit_Presentation.pptx PPTX presentation
Attachment_22_-_Section_09_97_13.00_40_Steel_Coatings.pdf PDF
Attachment_23_-_Section_09_97_13.16_Interior_Coating_of_Welded_Steel_Water_Tanks.pdf PDF
Attachment_4_-_Section_01_30_00_Administrative_Requirements.pdf PDF
FA4419-14-R-0102_Paint_and_Protective_Coatings_IDIQ.doc DOC document
Attachment_13_-_Section_01_55_00_Temporary_Environmental_Controls.pdf PDF
Attachment_7_-_Section_01_35_00_Quality_Control.pdf PDF
Attachment_34_-_Paint_Coefficient_(FINAL).xlsx XLSX spreadsheet
Attachment_14_-_Section_01_75_00_Starting_and_Adjusting.pdf PDF
Attachment_9_-_Section_01_35_40.00_20_Environmental_Management.pdf PDF
Attachment_17_-_Section_03_01_30.71_Concrete_Rehabilitation.pdf PDF
Attachment_6_-_Section_01_33_00_Submittal_Procedures.pdf PDF
Attachment_30_-_Wage_Determination-Highway.pdf PDF
Attachment_10_-_Section_01_37_00_Construction_Schedule.pdf PDF
Attachment_2_-_Section_01_11_00_Summary_of_Work.pdf PDF
Attachment_28_-_Section_32_17_24.00_10_Pavement_Markings.pdf PDF
Attachment_8_-_Section_01_35_26_Government_Safety_Requirements.pdf PDF
Attachment_20_-_Section_09_64_66_Athletic_Wood_Flooring.pdf PDF
Attachment_29_-_Wage_Determination-Building.pdf PDF
Attachment_27_-_Section_32_17_23.00_20_Pavement_Markings.pdf PDF
Attachment_33_-_EMS_Training_Statement.pdf PDF
Attachment_3_-_Section_01_15_00_Work_Restrictions.pdf PDF
Attachment_16_-_Section_02_81_00_Transportation_and_Disposal_of_Hazardous_Materials.pdf PDF
Attachment_25_-_Section_09_97_13.27_Exterior_Coating_of_Steel_Structures.pdf PDF
Attachment_1_-_Statement_of_Work.pdf PDF
Attachment_15_-_Section_01_78_00_Project_Closeout.pdf PDF
Attachment_21_-_Section_09_90_00_Paints_and_Coatings.pdf PDF
Attachment_26_-_Section_32_01_11.51_Rubber_and_Paint_Removal_from_Airfield_Pavements.pdf PDF
Attachment_18_-_Section_09_23_00_Gypsum_Plastering.pdf PDF
Attachment_32_-_Form_66_Submittal_Register.xls XLS spreadsheet
Attachment_11_-_Section_01_40_00_Safety.pdf PDF
Attachment_24_-_Section_09_97_13.17_Three-Coat_Epoxy_Interior_Coating_of_Welded_Steel_Petroleum_Fuel_Tanks.pdf PDF
Attachment_35_-_Past_Performance_Questionnaire.pdf PDF
Attachment_19_-_Section_09_29_00_Gypsum_Board.pdf PDF
Attachment_31_-_NAF_Provisions_Clauses.pdf PDF
Attachment_5_-_Section_01_30_60_Background_Checks_for_Contractor_Personnel.pdf PDF
Show all 37

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA4419-14-R-0102

Attachment 12

SECTION 01 50 00

TEMPORARY CONSTUCTION FACILITIES AND CONTROLS

Part 1 General

1.1 Summary

This section covers requirements for non-permanent buildings and equipment, safety systems, vehicles, utilities, and signage pertinent to installation of the work required by each separate

Task Order. Requirements of this section may be amended based upon project specific criteria identified by separate Task Order.

1.2 Referenced Standards

Comply with publications listed below to the extent applicable.

AWWA C511 Standard for Reduced-Pressure Principle Backflow Prevention

Assembly

FCCCHR List List of Approved Backflow Prevention Assemblies

FCCCHR Manual Manual of Cross-Connection Control

NFPA 241 Safeguarding Construction, Alteration and Demolition

Operations

NFPA 70 National Electrical Code

MUTCD Manual of Uniform Traffic Control Devices

10 CFR 1910 Occupational Safety and Health Standards

29 CFR 1926 Safety and Health Regulations for Construction

29 CFR 1926.500 Fall Protection

EM 385-1-1 USACE Safety and Health Requirements Manual

Wherein standards appear to conflict, the more stringent requirement will prevail.

1.3 Submittals

1.3.1 Other

Work Site Lay-Down Plan

1.4 Site Plan

1.4.1 Contractor Office Area: Indicate size and location to include trailer(s) with ADA modifications, trash enclosure, perimeter fencing and entry point, vehicular parking area and project sign.

1.4.2 Lay-Down Plan: Indicate size and location of material storage area, vehicle and equipment parking area, barriers, trash enclosures, sanitation equipment, perimeter fencing and access point. Indicate existing equipment and restricted zones related to safety, security, fire protection and utility services within 100 feet of area. Indicate storage location of hazardous materials by types.

1.5 Quality Control

1.5.1 Use only experienced installers to connect backflow prevention devices.

1.5.2 Restore damaged Government property back to condition equal to or better than that which existed before occurrence of event and as otherwise acceptable to the

Government. Accomplish restoration either by replacement or by repair using new materials and skilled workers experienced in the trade(s) required.

1.5.3 Delivery and Storage of Material and Equipment: Deliver products to the job site in manufacturer’s unopened shipping containers with labels attached and legible. Comply with manufacturer’s printed storage instructions and with requirements specified herein.

1.6 Government Furnished Services

1.6.1 Electrical and Water: Services will be provided at individual work sites in

“reasonable quantities” from existing outlets where available. Contractor will employ means and methods to conserve energy and resource use.

1.6.2 Pest and Weed Control: Pest (insect and rodent) and weed control services will be provided at the Contractor’s office area and separate work sites on an “as needed” basis.

Scheduling will be subject to available manpower at time of request. Submit service request to the CO for coordination.

Part 2 Products

2.1 Contractor Office Area (optional)

Office and storage trailers will be the product of commercial manufacturers, designed for local weather conditions, in good repair without visible damage or deterioration, and approved by the

Government. Use of portable weights (sand bags, tires, other) on roofs is prohibited.

2.2 Signage (optional)

Design, construction and location of exterior signage at Contractor office area and job site will be subject to Government approval.

2.3 Barricades and Fencing

2.3.1 Fencing: Provide systems designed and installed to resist a 250 lb. horizontal force distributed over a 2 x 4 foot area.

2.3.1.1 Chain Link: Galvanized steel. 2-inch diamond mesh fabric. 54-96 inches high.

2.3.1.2 Safety – High density extruded plastic netting. UV stabilized. Orange color. 54-

72 inches high.

2.3.1.3 Posts – Steel. Designed for specific application.

2.4 Severe Weather Protection

Maintain adequate materials of type and quantity required to protect exposed materials and equipment from severe weather. Store items at readily accessible locations to ensure ability to deploy within a very short time period.

Part 3 Execution

3.1 Construction Vehicles

3.1.1 Restrict haul routes and equipment/vehicle parking to existing roadways and paved areas unless approved otherwise by the Government.

3.1.2 Provide temporary traffic regulation and warning signs near work sites to protect workers and alert non-construction vehicle traffic of potential on-going construction hazards. Comply with MUTCD. Maintain devices and controls until need is no longer warranted.

3.1.3 Contractor Employee Parking: Restrict employee POV parking to existing paved areas. Provide employee transportation to work site where paved areas are unavailable for purpose of minimizing damage to unpaved surface areas.

3.1.4 Construction Equipment Parking and Circulation Lanes

3.1.4.1 Protect unpaved areas adjacent to the work site by restricting parking to minimum area necessary for safe circulation and maintaining circulation routes within the limits of construction to maximum extent practical.

3.1.4.2 Park equipment vehicles within fenced areas during non-working hours.

3.1.5 Dust Control: When dust is deemed a nuisance or pollutant, remedy condition by hosing, sprinkling or use of other method acceptable to the Government. Continue actions until condition is corrected. Corrective action will be provided without additional cost to the Government.

3.1.6 Wash mud from truck and equipment tires before traveling on paved areas.

Cleaning concrete truck chutes and dumping residual concrete, asphalt, gravel, fill and other similar materials on Government property is prohibited.

3.1.7 Cover open trucks to prevent materials and debris from scattering during travel.

3.2 Fencing and Barriers

3.2.1 Place where required to secure job site perimeter and ensure safe pedestrian and vehicular circulation within and adjacent to work sites. Provide entry onto job site only at designated access points.

3.2.2 Ensure barricades are easily identified in both daylight and night conditions by means of visual warning devices

3.2.3 Provide additional controls within the job site to limit access to hazardous areas such as open excavations.

3.2.4 Maintain fencing system in good repair for duration of operations at the job site.

3.2.5 Locate in a manner that does not obstruct fire egress points and travel routes from building, fire hydrants, and emergency vehicle access to building perimeter. Coordinate location with Base Fire Department.

3.2.6 Space posts at 8-foot maximum. Use weighted, tip-proof bases where located on paved surfaces.

3.3 Protection of Government Property:

3.3.1 Protect Government property within and adjacent to the work site from dirt, air borne particulates, wear and damage by construction operations using means and methods appropriate for the type of property being protected and conditions at the work site. Ensure means of anchorage does not damage supporting element.

3.3.2 Protect landscaping within and adjacent to the work site from damage by construction operations. Do not cover exposed root systems with excavated soil. Secure low hanging limbs.

3.3.3 Maintain protection devices in good repair for duration of construction activities.

Remove when deemed no longer necessary.

3.3.4 Provide durable covers over interior finishes to prevent dust accumulation on surfaces or penetration into adjacent occupied spaces. Inspect daily to prevent compromise of cover function. Remove at end of each work day when required to clear designated facility exit corridors.

3.3.5 Provide prior notification to Contracting Officer and Facility Manager when construction operations pose risk of damage to POVs and Government equipment parked adjacent to or near the work site.

3.4 Sanitation

3.4.1 Government toilets will not be available for Contractor use unless specified otherwise by separate Task Order.

3.4.2 Provide portable, self-contained chemical type toilets at individual work sites as required. Locate within work site out of the public view.

3.4.2.1 Units will have self-closing doors.

3.4.2.2 Secure structure to ground to prevent dislodgement during inclement weather conditions, to include but not limited to resisting sustained winds of 90 mph.

3.4.2.3 Provide routine servicing (not less than once every two weeks). Maintain in a clean, fully stocked condition at all times without nuisance.

3.4.3 Wherein Work is primarily interior in scope, verify availability of restrooms, eating areas, elevators and stairways for Contractor use with the Facility Manager.

3.5 Material & Equipment Storage (Lay-Down Area)

3.5.1 Comply with Safety requirements. Remove temporary connections at end of each working day. Leave area unencumbered by materials or equipment for easy accessibility by Base Fire Department personnel.

3.5.2 Stack materials (new, salvaged) in an organized, safe and sound manner, and with clear and open corridors on all sides adequate for routine inspections.

3.5.3 Store demolition oversized for dumpster in a neat and organized manner until time scheduled for removal from Base property. Remove from Base within 5 working days.

3.5.4 Secure equipment operating cabs against unauthorized access during non-working hours.

3.6 Waste Management

3.6.1 All waste generated by the Work, unless identified by separate Task Order to be salvaged, will become the property of the Contractor and removed from Government property.

3.6.2 Comply with waste management requirements for Temporary Environmental

Controls described herein.

3.6.3 Dumping or burying construction waste and debris on Base property is prohibited unless approved otherwise.

3.7 Interruption (scheduled) of Utility Service and Line Locates

3.7.1 All cost for interruption and restoration of Base services under the control of private enterprise will be borne solely by the Contractor.

3.7.2 Indicate activities that require utility interruption on the Construction Progress

Schedule as part of QC responsibilities. Provide CO, CR, and Facility Manager (when applicable) additional notification 5 working days prior to event date. Indicate:

a) Type of system involved

b) Nature of work involved

c) Location of work

d) Extended area impacted (if applicable)

e) Duration of outage.

3.7.3 Schedule work to minimize impact upon Government operations. Perform work during non-standard work periods when directed by the Government.

3.7.4 Obtain Government confirmation of function and operational status of unknown underground lines and other obstructions when uncovered. Await direction from

Government before proceeding with work in the area. Normal response time to

Contractor request for clarification will be 5 working days following date RFC received by Government.

3.7.5 Location of Underground Utility Lines and Equipment

3.7.5.1 Submit Work Clearance Request (AF Form 103) for Government location services. Allow minimum of 10 working days for compliance with request. Obtain location services directly from companies owning and maintaining private lines on

Base. Contractor will be responsible for maintaining line locate markings.

3.7.5.2 Provide Government with report illustrating and describing location, elevation, size and use of all uncovered lines and equipment.

3.8 Cleanup and Site Remediation

3.8.1 Perform daily cleaning to keep work site and adjacent areas free of debris and clutter. Keep materials (new and demolished) in organized, neat grouping.

3.8.2 Demolished Materials and Equipment: Remove large items (oversized for dumpster), not identified for salvage, from Base property within 5 working days following removal.

3.8.5 Promptly remove temporary facilities and controls from the work site when no longer required. Obliterate all signs of temporary construction and vestiges of construction.

3.9 Security

3.9.1. Provide adequate outside security lighting at temporary facilities as part of

Contractor responsibility for security of its property and work areas under its control on

Base property. Monitoring by Base security personnel will be provided only to the extent of normal operational procedures.

3.9.2. Keep on hand adequate resources to secure work sites in event of severe weather and Government (emergency) directive. Means and methods will ensure securing sites within 1 hour of first awareness or Government notification.

-- End of Section --