Attachment_14_-_Section_01_75_00_Starting_and_Adjusting.pdf

PDF 209 KB Posted

Attached to
Paint and Protective Coatings IDIQ Federal contract opportunity
Solicitation number
FA4419-14-R-0102
Issued by
Department of the Air Force Air Education and Training Command

About this file

Attachment 14 - Section 01 75 00 Starting and Adjusting

View the file

Other files for this federal contract opportunity

Other files attached to Paint and Protective Coatings IDIQ, newest first.
File Type Posted
Questions_and_Answers.xlsx XLSX spreadsheet
Site_Visit_Presentation.pptx PPTX presentation
Attachment_22_-_Section_09_97_13.00_40_Steel_Coatings.pdf PDF
Attachment_23_-_Section_09_97_13.16_Interior_Coating_of_Welded_Steel_Water_Tanks.pdf PDF
Attachment_4_-_Section_01_30_00_Administrative_Requirements.pdf PDF
FA4419-14-R-0102_Paint_and_Protective_Coatings_IDIQ.doc DOC document
Attachment_13_-_Section_01_55_00_Temporary_Environmental_Controls.pdf PDF
Attachment_7_-_Section_01_35_00_Quality_Control.pdf PDF
Attachment_34_-_Paint_Coefficient_(FINAL).xlsx XLSX spreadsheet
Attachment_9_-_Section_01_35_40.00_20_Environmental_Management.pdf PDF
Attachment_17_-_Section_03_01_30.71_Concrete_Rehabilitation.pdf PDF
Attachment_6_-_Section_01_33_00_Submittal_Procedures.pdf PDF
Attachment_30_-_Wage_Determination-Highway.pdf PDF
Attachment_10_-_Section_01_37_00_Construction_Schedule.pdf PDF
Attachment_2_-_Section_01_11_00_Summary_of_Work.pdf PDF
Attachment_28_-_Section_32_17_24.00_10_Pavement_Markings.pdf PDF
Attachment_8_-_Section_01_35_26_Government_Safety_Requirements.pdf PDF
Attachment_20_-_Section_09_64_66_Athletic_Wood_Flooring.pdf PDF
Attachment_29_-_Wage_Determination-Building.pdf PDF
Attachment_27_-_Section_32_17_23.00_20_Pavement_Markings.pdf PDF
Attachment_33_-_EMS_Training_Statement.pdf PDF
Attachment_3_-_Section_01_15_00_Work_Restrictions.pdf PDF
Attachment_16_-_Section_02_81_00_Transportation_and_Disposal_of_Hazardous_Materials.pdf PDF
Attachment_25_-_Section_09_97_13.27_Exterior_Coating_of_Steel_Structures.pdf PDF
Attachment_1_-_Statement_of_Work.pdf PDF
Attachment_15_-_Section_01_78_00_Project_Closeout.pdf PDF
Attachment_21_-_Section_09_90_00_Paints_and_Coatings.pdf PDF
Attachment_26_-_Section_32_01_11.51_Rubber_and_Paint_Removal_from_Airfield_Pavements.pdf PDF
Attachment_18_-_Section_09_23_00_Gypsum_Plastering.pdf PDF
Attachment_32_-_Form_66_Submittal_Register.xls XLS spreadsheet
Attachment_11_-_Section_01_40_00_Safety.pdf PDF
Attachment_24_-_Section_09_97_13.17_Three-Coat_Epoxy_Interior_Coating_of_Welded_Steel_Petroleum_Fuel_Tanks.pdf PDF
Attachment_12_-_Section_01_50_00_Temporary_Construction_Facilities_and_Controls.pdf PDF
Attachment_35_-_Past_Performance_Questionnaire.pdf PDF
Attachment_19_-_Section_09_29_00_Gypsum_Board.pdf PDF
Attachment_31_-_NAF_Provisions_Clauses.pdf PDF
Attachment_5_-_Section_01_30_60_Background_Checks_for_Contractor_Personnel.pdf PDF
Show all 37

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA4419-14-R-0102

Attachment 14

SECTION 01 75 00

STARTING AND ADJUSTING

Part 1 General

1.1 Summary

This section covers requirements for system testing and acceptance. Requirements of this section may be amended based upon project specific criteria identified by separate Task Order.

1.2 Submittals

1.2.1 Certifications:

1.2.1.1Verification of successful test

1.2.1.2 Training qualifications and licenses of personnel performing operational tests and adjustments.

1.2.2 Shop Drawings:

1.2.2.1 Diagrams and schedules illustrating portions of the system.

1.2.2.2 Drawings illustrating coordination of system with interdisciplinary work, existing work, and multiple systems.

1.2.3 Manufacturer’s Instructions:

Procedural requirements for initial checkout, startup, and adjusting to ensure safe operation during acceptance testing and commissioning.

1.2.4 Test Report:

Comply with means and methods specified by separate Task Order for successful system operation.

1.3 Pre-Test Requirements

1.3.1 Provide equipment and services to meet testing requirements. Provide clearly defined acceptance criteria to establish baseline for testing, adjusting, and system operation and maintenance.

1.3.2 Government reserves option to elect performance of acceptance testing by internal personnel or designated third party. Regardless of who performs acceptance testing, the

Contractor will remain responsible for meeting the requirements for acceptance.

1.4 Tests Required

FA4419-14-R-0102

Attachment 14

Perform tests to verify proper functioning of fire protection and suppression system; surveillance and security systems; HVAC equipment; electrical equipment; fluid and gas systems; hydraulic and pneumatic systems; energy control and monitoring systems; boiler systems; and other assemblies and components that need to be tested as an interrelated whole.

1.4.1 Factory Test: Submit certified test report performed at the factory to verify proper build. Report will be used to verify no shipping damage and proper installation.

1.4.2 Functional Field Test

1.4.2.1 Perform functional field tests, in the presence of designated Government personnel, to verify system and components have been properly installed and system functions properly.

1.4.2.2 Include Manufacturer’s verification that field installation complied with

Manufacturer’s standards and instructions.

1.4.2.3 Acceptance will be issued when system has performed per other sections and referenced industry standards.

1.4.3 Final Acceptance Test: Perform a formal test, in the presence of designated

Government personnel. Provide full documentation using approved recording forms.

Include description of testing procedures stating step by step instructions followed to verify system parameters, components and function.

Part 2 Products

Not Used

Part 3 Execution

Not Used

-- End of Section --