Attachment_10_-_Section_01_37_00_Construction_Schedule.pdf

PDF 90 KB Posted

Attached to
Paint and Protective Coatings IDIQ Federal contract opportunity
Solicitation number
FA4419-14-R-0102
Issued by
Department of the Air Force Air Education and Training Command

About this file

Attachment 10 - Section 01 37 00 Construction Schedule

View the file

Other files for this federal contract opportunity

Other files attached to Paint and Protective Coatings IDIQ, newest first.
File Type Posted
Questions_and_Answers.xlsx XLSX spreadsheet
Site_Visit_Presentation.pptx PPTX presentation
Attachment_22_-_Section_09_97_13.00_40_Steel_Coatings.pdf PDF
Attachment_23_-_Section_09_97_13.16_Interior_Coating_of_Welded_Steel_Water_Tanks.pdf PDF
Attachment_4_-_Section_01_30_00_Administrative_Requirements.pdf PDF
FA4419-14-R-0102_Paint_and_Protective_Coatings_IDIQ.doc DOC document
Attachment_13_-_Section_01_55_00_Temporary_Environmental_Controls.pdf PDF
Attachment_7_-_Section_01_35_00_Quality_Control.pdf PDF
Attachment_34_-_Paint_Coefficient_(FINAL).xlsx XLSX spreadsheet
Attachment_14_-_Section_01_75_00_Starting_and_Adjusting.pdf PDF
Attachment_9_-_Section_01_35_40.00_20_Environmental_Management.pdf PDF
Attachment_17_-_Section_03_01_30.71_Concrete_Rehabilitation.pdf PDF
Attachment_6_-_Section_01_33_00_Submittal_Procedures.pdf PDF
Attachment_30_-_Wage_Determination-Highway.pdf PDF
Attachment_2_-_Section_01_11_00_Summary_of_Work.pdf PDF
Attachment_28_-_Section_32_17_24.00_10_Pavement_Markings.pdf PDF
Attachment_8_-_Section_01_35_26_Government_Safety_Requirements.pdf PDF
Attachment_20_-_Section_09_64_66_Athletic_Wood_Flooring.pdf PDF
Attachment_29_-_Wage_Determination-Building.pdf PDF
Attachment_27_-_Section_32_17_23.00_20_Pavement_Markings.pdf PDF
Attachment_33_-_EMS_Training_Statement.pdf PDF
Attachment_3_-_Section_01_15_00_Work_Restrictions.pdf PDF
Attachment_16_-_Section_02_81_00_Transportation_and_Disposal_of_Hazardous_Materials.pdf PDF
Attachment_25_-_Section_09_97_13.27_Exterior_Coating_of_Steel_Structures.pdf PDF
Attachment_1_-_Statement_of_Work.pdf PDF
Attachment_15_-_Section_01_78_00_Project_Closeout.pdf PDF
Attachment_21_-_Section_09_90_00_Paints_and_Coatings.pdf PDF
Attachment_26_-_Section_32_01_11.51_Rubber_and_Paint_Removal_from_Airfield_Pavements.pdf PDF
Attachment_18_-_Section_09_23_00_Gypsum_Plastering.pdf PDF
Attachment_32_-_Form_66_Submittal_Register.xls XLS spreadsheet
Attachment_11_-_Section_01_40_00_Safety.pdf PDF
Attachment_24_-_Section_09_97_13.17_Three-Coat_Epoxy_Interior_Coating_of_Welded_Steel_Petroleum_Fuel_Tanks.pdf PDF
Attachment_12_-_Section_01_50_00_Temporary_Construction_Facilities_and_Controls.pdf PDF
Attachment_35_-_Past_Performance_Questionnaire.pdf PDF
Attachment_19_-_Section_09_29_00_Gypsum_Board.pdf PDF
Attachment_31_-_NAF_Provisions_Clauses.pdf PDF
Attachment_5_-_Section_01_30_60_Background_Checks_for_Contractor_Personnel.pdf PDF
Show all 37

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA4419-14-R-0102

Attachment 10

SECTION 01 37 00

CONSTRUCTION SCHEDULE

Part 1 General

1.1 Scope and Objective

Scheduling of all project construction sequences and activities is required. Develop a construction schedule for each project Task Order, if required.

1.2 Quality Control

1.2.1 Confirm that the schedule accurately reflects labor availability and delivery of pertinent material and equipment necessary to meet the Contract Performance Period.

1.2.2 Format schedule in the form of a time scaled Line or Bar Chart.

1.3 Submittals

Submit the following in accordance Section 01 33 00 Submittal Procedures.

Construction Progress Schedule

Part 2 Products

Not Used

Part 3 Execution

3.1 General

3.1.1 Show a reasonable and realistic sequence in which work activities will be performed. Indicate start and finish dates.

3.1.2 Indicate critical path activities where applicable.

3.1.3 Schedule operations by different trades to be performed concurrently to maximum extent practical.

3.1.4. Indicate an appropriate level of detail to include the following:

3.1.4.1 Submittal approval

3.1.4.2 Procurement periods (fabrication and delivery) of critical components.

Highlight components requiring extended lead times for procurement.

3.1.4.3 Scheduled utility interruptions and durations.

3.1.4.4 Outage, testing and curing periods.

3.1.4.5 Need date of GFP.

3.1.4.6 Changes and delays (upon occurrence)

3.1.5 Electronically Generated Schedules: Ensure program calculations provide dates that accurately reflect data contained in daily or weekly progress reports. Calculate percentage complete and remaining duration of activity as independent functions.

3.2 Work Progress Report

3.2.1 Maintain a record of the current status of construction activities. Record activities on a daily or weekly basis to document progress.

3.2.2 Include comparative data indicating:

a) Actual vs. scheduled percentages of work completed

b) Value of work installed

c) Revised vs. originally scheduled completion dates

d) Revised vs. original project costs

e) Detailed description of differences (where occur) and causes.

3.2.3 Document ancillary conditions impacting the work.

a) Date, start and stop time, and weather conditions

b) Description of work performed, location and number of personnel, actions by trade and subcontractor

c) Test and control actions performed to include results. Indicate corrective action if unsatisfactory results achieved.

d) Type and quantity of materials both at the site and incorporated into the work

e) Project related offsite actions

f) Safety issues and related actions

g) QC issues and related actions

h) Incidental events (delays, conflicts, other)

3.2.4 Provide means to correct delays to the work. Identify adjustments to the remaining schedule that will minimize impact upon scheduled project completion date.

3.2.5 Organize data for inclusion on AF Form 3064 (Contract Progress Schedule) if requested by the Government. Use continuous left-to-right flow diagram to indicate progress.

3.2.6 Submit reports as acceptable to the Contracting Officer.

-- End of Section --