Attachment 10 - Section 01 37 00 Construction Schedule
View the file
Other files for this federal contract opportunity
Show all 37
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA4419-14-R-0102
Attachment 10
SECTION 01 37 00
CONSTRUCTION SCHEDULE
Part 1 General
1.1 Scope and Objective
Scheduling of all project construction sequences and activities is required. Develop a construction schedule for each project Task Order, if required.
1.2 Quality Control
1.2.1 Confirm that the schedule accurately reflects labor availability and delivery of pertinent material and equipment necessary to meet the Contract Performance Period.
1.2.2 Format schedule in the form of a time scaled Line or Bar Chart.
1.3 Submittals
Submit the following in accordance Section 01 33 00 Submittal Procedures.
Construction Progress Schedule
Part 2 Products
Not Used
Part 3 Execution
3.1 General
3.1.1 Show a reasonable and realistic sequence in which work activities will be performed. Indicate start and finish dates.
3.1.2 Indicate critical path activities where applicable.
3.1.3 Schedule operations by different trades to be performed concurrently to maximum extent practical.
3.1.4. Indicate an appropriate level of detail to include the following:
3.1.4.1 Submittal approval
3.1.4.2 Procurement periods (fabrication and delivery) of critical components.
Highlight components requiring extended lead times for procurement.
3.1.4.3 Scheduled utility interruptions and durations.
3.1.4.4 Outage, testing and curing periods.
3.1.4.5 Need date of GFP.
3.1.4.6 Changes and delays (upon occurrence)
3.1.5 Electronically Generated Schedules: Ensure program calculations provide dates that accurately reflect data contained in daily or weekly progress reports. Calculate percentage complete and remaining duration of activity as independent functions.
3.2 Work Progress Report
3.2.1 Maintain a record of the current status of construction activities. Record activities on a daily or weekly basis to document progress.
3.2.2 Include comparative data indicating:
a) Actual vs. scheduled percentages of work completed
b) Value of work installed
c) Revised vs. originally scheduled completion dates
d) Revised vs. original project costs
e) Detailed description of differences (where occur) and causes.
3.2.3 Document ancillary conditions impacting the work.
a) Date, start and stop time, and weather conditions
b) Description of work performed, location and number of personnel, actions by trade and subcontractor
c) Test and control actions performed to include results. Indicate corrective action if unsatisfactory results achieved.
d) Type and quantity of materials both at the site and incorporated into the work
e) Project related offsite actions
f) Safety issues and related actions
g) QC issues and related actions
h) Incidental events (delays, conflicts, other)
3.2.4 Provide means to correct delays to the work. Identify adjustments to the remaining schedule that will minimize impact upon scheduled project completion date.
3.2.5 Organize data for inclusion on AF Form 3064 (Contract Progress Schedule) if requested by the Government. Use continuous left-to-right flow diagram to indicate progress.
3.2.6 Submit reports as acceptable to the Contracting Officer.
-- End of Section --