01 35 26 Governmental Safety Requirements-1111(Nov).pdf

PDF 220 KB Posted

Attached to
Roofing Maintenance, Repair and Installation IDIQ Federal contract opportunity
Solicitation number
FA3020-12-R-0008
Issued by
Department of the Air Force Air Education and Training Command

About this file

01 35 26 Governmental Safety Requirements

View the file

Other files for this federal contract opportunity

Other files attached to Roofing Maintenance, Repair and Installation IDIQ, newest first.
File Type Posted
Amendment 5.pdf PDF
Amendment 4.pdf PDF
amendment 3.doc DOC document
PrepProposal conference.pdf PDF
amendment 1.doc DOC document
amendment 2.doc DOC document
03-A-102-EXISTING- FILL AND NEW BLDG 4477 ROOF PLAN ELEVATION VIEW AND SECTION.pdf PDF
02-A-101-EXISTING- FILL AND NEW BLDG 2160 ROOF PLAN ELEVATION VIEW AND DETAIL.pdf PDF
01-G-001-PROJECT LOCATION PLAN.pdf PDF
Base Pass Forms.doc DOC document
07 51 13 Built Up Asphalt Roofing-1111(Nov).pdf PDF
00 00 00 Cover Stamped 1111(Nov).pdf PDF
Proposal Bldg 2160.xls XLS spreadsheet
Schedule of Material Submittals.xls XLS spreadsheet
07 61 14A Attachment A-SSM Details-1111(Nov).pdf PDF
Schedule B-Basic Year-1206.xls XLS spreadsheet
07 31 13 Asphalt Shingle-1111(Nov).pdf PDF
01 11 02 10A Attachment A-Performance Tables-1201(Jan).pdf PDF
07 51 13A Attachment A-BUR Details-1111(Nov).pdf PDF
Schedule B-Second Option-1206.xls XLS spreadsheet
07 21 16 Blanket Insulation-1111(Nov).pdf PDF
01 33 00 Project Submittals-1111(Nov).pdf PDF
Proposal Bldg 4477.xls XLS spreadsheet
FA3020-12-R-0008 Solicitation.pdf PDF
Past Performance Questionnaire.pdf PDF
01 11 02 10 Summary of Work-1204(Apr).pdf PDF
01 11 02 30 Contractor Quality Control-1111(Nov).pdf PDF
Schedule B Total.doc DOC document
03-A-102.dwf DWF file
02 82 14 00 15 Asbestos Hazard Control Activities-Roofing-1206(Jun).pdf PDF
07 22 00 Roof and Deck Insulation-1111(Nov).pdf PDF
07 95 00 Maintenance and Repair-1204(Apr).pdf PDF
01-G-001.dwf DWF file
OK14.doc DOC document
Disclosure of Lobbying Activities.pdf PDF
01 62 35 Recycled Recovered Materials-1111(Nov).pdf PDF
07 60 00 Flashing and Sheet Metal-1111(Nov).pdf PDF
07 61 14 Steel Standing Seam Roofing-1111(Nov).pdf PDF
WD TX268.doc DOC document
Site Visit Map.doc DOC document
06 10 00 Rough Carpentry-1111(Nov).pdf PDF
01 33 00A Attachment A-Submittals-1206(Jun).pdf PDF
WD TX6.doc DOC document
Asbestos Bldg 4477 Roof Summary.pdf PDF
Schedule B-First Option-1206.xls XLS spreadsheet
00 00 00 TOC-1206(Jun).pdf PDF
02-A-101.dwf DWF file
01 11 02 10B Attachment B-Forms-1206(Jun).pdf PDF
01 11 02 20 Measurement And Payment-1204(Apr).pdf PDF
07 92 00 Joint Sealants-1111(Nov).pdf PDF
Show all 50

Roofing Maintenance, Repair and Installation IDIQ has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

IDIQ ROOF MAINTENANCE/REPAIR/REPLACEMENT VNVP 111080

01 35 26 Government Safety Requirements

Page 1 of 14 Pages

November 2011

01 35 26

GOVERNMENTAL SAFETY REQUIREMENTS

PART 0 – INTENT:

0.1. This guide specification covers the requirements for safety and occupational health requirements for the protection of Contractor and Government personnel, property and resources.

PART 1 - DESCRIPTION OF WORK

1.1. REFERENCES: The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN SOCIETY OF SAFETY ENGINEERS (ASSE/SAFE)

ASSE/SAFE A10.32 (2004) Fall Protection

ASSE/SAFE A10.34 (2001; R 2005), Protection of the Public on or Adjacent to

Construction Sites.

ASSE/SAFE Z359.1. (2007), Safety Requirements for Personal Fall Arrest

Systems, Subsystems and Components.

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 10 (2010) Standard for Portable Fire Extinguishers

NFPA 241 (2009) Standard for Safeguarding Construction, Alteration, and

Demolition Operations

NFPA 306 (2009) Standard for Control of Gas Hazards in Vessels

NFPA 51B (2009) Standard for Fire Prevention During Welding, Cutting, and

Other Hot Work

NFPA 70 (2008; AMD 1 2008) National Electrical Code

NFPA 70E (2009; Errata 09-1) Standard for Electrical Safety in the Workplace

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

29 CFR 1910 Occupational Safety and Health Standards

29 CFR 1910.146 Permit-required Confined Spaces

29 CFR 1919 Gear Certification

29 CFR 1926 Safety and Health Regulations for Construction

29 CFR 1926.500 Fall Protection

01 35 26 Government Safety Requirements

Page 2 of 14 Pages

November 2011

1.2. SUBMITTALS: Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES: Government acceptance is required for submittals with a "G" designation.

SD-01 Preconstruction Submittals:

Accident Prevention Plan (APP); G

SD-06 Test Reports

Reports

Submit reports as their incidence occurs, in accordance with the requirements of the paragraph entitled, "Reports."

Accident Reports

SD-07 Certificates

Confined Space Entry Permit

Hot work permit

License Certificates

1.3. DEFINITIONS:

a. Competent Person for Fall Protection: A person who is capable of identifying hazardous or dangerous conditions in the personal fall arrest system or any component thereof, as well as their application and use with related equipment, and has the authority to take prompt corrective measures to eliminate the hazards of falling.

b. High Visibility Accident: Any mishap which may generate publicity and/or high visibility.

c. Medical Treatment: Treatment administered by a physician or by registered professional personnel under the standing orders of a physician. Medical treatment does not include first aid treatment even through provided by a physician or registered personnel.

d. Qualified Person for Fall Protection ; A person with a recognized degree or professional certificate and with extensive knowledge, training and experience in the field of fall protection; who is capable of performing design, analysis, and evaluation of fall protection systems and equipment.

e. Recordable Injuries or Illnesses: Any work-related injury or illness that results in:

(1) Death, regardless of the time between the injury and death, or the length of the illness;

(2) Days away from work (any time lost after day of injury/illness onset);

(3) Restricted work;

(4) Transfer to another job;

01 35 26 Government Safety Requirements

Page 3 of 14 Pages

November 2011

(5) Medical treatment beyond first aid;

(6) Loss of consciousness; or

(7) A significant injury or illness diagnosed by a physician or other licensed health care professional, even if it did not result in (1) through (6) above.

f. "USACE" property and equipment specified in USACE EM 385-1-1 should be interpreted as Government property and equipment.

1.4. REGULATORY REQUIREMENTS: In addition to the detailed requirements included in the provisions of this contract, comply with the most recent addition of USACE EM 385-

1-1. Submit matters of interpretation of standards to the appropriate administrative agency for resolution before starting work. Where the requirements of this specification, applicable laws, criteria, ordinances, regulations, and referenced documents vary, the most stringent requirements govern.

1.5. SITE QUALIFICATIONS, DUTIES AND MEETINGS

1.5.1. Personnel Qualifications:

1.5.1.1. Site Safety and Health Officer (SSHO): The contractor shall provide a

Safety oversight team that includes a minimum of one (1) Competent Person at each project site to function as the Safety and Health Officer (SSHO). The SSHO shall be at the work site at all times, unless specified differently in the contract, to perform safety and occupational health management, surveillance, inspections, and safety enforcement for the Contractor, and their training, experience, and qualifications shall be as required by EM 385-1-1 paragraph 01.A.17 and all associated sub-paragraphs. A Competent Personal shall be provided for all of the hazards identified in the Contractor's Safety and Health Program in accordance with the accepted Accident Prevention Plan, and shall be on-site at all times when the work that presents the hazards associated with their professional expertise is being performed. The credentials of the Competent Persons(s) shall be approved by the Contracting Officer. The Contractor Quality Control (QC) person can be the

SSHO on this project.

1.5.1.2. Competent Person for Confined Space Entry: Provide a competent person for confined space meeting the definition and requirements of EM 385-1-1. The

Contractor Quality Control (QC) person can be the Competent Person for Confined

Space Entry on this project.

1.5.2. Personnel Duties:

1.5.2.1. Site Safety and Health Officer (SSHO): Failure to perform the below duties will result in dismissal of the superintendent. and/or QC Manager, and a project work stoppage. The project work stoppage will remain in effect pending approval of a suitable replacement.

a. Conduct daily safety and health inspections and maintain a written log which includes area/operation inspected, date of inspection, identified hazards, 01 35 26 Government Safety Requirements

Page 4 of 14 Pages

November 2011 recommended corrective actions, estimated and actual dates of corrections.

Attach safety inspection logs to the Contractors' daily report.

b. Conduct mishap investigations and complete required reports. Maintain the

OSHA Form 300 and Daily Production reports for prime and sub-contractors.

c. Maintain applicable safety reference material on the job site.

d. Attend the pre-construction conference, pre-work meetings including preparatory inspection meeting, and periodic in-progress meetings.

e. Implement and enforce accepted APPS.

f. Maintain a safety and health deficiency tracking system that monitors outstanding deficiencies until resolution. Maintain a list of unresolved safety and health deficiencies on the safety bulletin board.

g. Ensure sub-contractor compliance with safety and health requirements.

h. Maintain a list of hazardous chemicals on site and their material safety data sheets.

1.5.3. Meetings

1.5.3.1. Preconstruction Conference:

a. Contractor representatives who have a responsibility or significant role in accident prevention on the project shall attend the preconstruction conference.

This includes the project superintendent, site safety and health officer, quality control supervisor, or any other assigned safety and health professionals who participated in the development of the APP and special plans, program and procedures associated with it).

b. Discuss the details of the submitted APP to include incorporated plans, programs, and procedures that will be developed and implemented during the performance of the contract.

c. Deficiencies in the submitted APP will be brought to the attention of the

Contractor at the preconstruction conference, and the Contractor shall revise the plan to correct deficiencies and re-submit it for acceptance. Do not begin work until there is an accepted APP.

1.5.3.2. Safety Meetings: Conduct and document meetings as required by EM 385-

1-1. Attach minutes showing contract title, signatures of attendees and a list of topics discussed to the Contractors' daily report.

1.6. ACCIDENT PREVENTION PLAN (APP):

1.6.1. General:

1.6.1.1. Use a qualified person to prepare the written site-specific APP. Prepare the

APP in accordance with the format and requirements of USACE EM 385-1-1 and as supplemented herein. Cover all paragraph and subparagraph elements in USACE

EM 385-1-1, Appendix A, "Minimum Basic Outline for Accident Prevention Plan".

01 35 26 Government Safety Requirements

Page 5 of 14 Pages

November 2011

Specific requirements for some of the APP elements are described below. The APP shall be job-specific and address any unusual or unique aspects of the project or activity for which it is written. The APP shall interface with the Contractor's overall safety and health program. Include any portions of the Contractor's overall safety and health program referenced in the APP in the applicable APP element and made site-specific. The Government considers the Prime Contractor to be the "controlling authority" for all work site safety and health of the subcontractors. Contractors are responsible for informing their subcontractors of the safety provisions under the terms of the contract and the penalties for noncompliance, coordinating the work to prevent one craft from interfering with or creating hazardous working conditions for other crafts, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out. The APP shall be signed by the person and firm (senior person) preparing the APP, the Contractor, the on-site superintendent, the designated site safety and health officer, the Contractor Quality control Manager, and any designated CSP and/or CIH.

1.6.1.2. Submit the APP to the Contracting Officer 15 calendar days prior to the date of the preconstruction conference for acceptance. Work cannot proceed without an accepted APP.

1.6.1.3. Once accepted by the Contracting Officer, the APP and attachments will be enforced as part of the contract. Disregarding the provisions of this contract or the accepted APP will be cause for stopping of work, at the discretion of the

Contracting Officer, until the matter has been rectified.

1.6.1.4. Once work begins, changes to the accepted APP shall be made with the knowledge and concurrence of the Contracting Officer, project superintendent, SSHO and quality control manager. Should any severe hazard exposure, i.e.

imminent danger, become evident, stop work in the area, secure the area, and develop a plan to remove the exposure and control the hazard. Notify the

Contracting Officer within 24 hours of discovery. Eliminate/remove the hazard. In the interim, take all necessary action to restore and maintain safe working conditions in order to safeguard onsite personnel, visitors, the public (as defined by

ASSE/SAFE A10.34,) and the environment.

1.6.1.5. Copies of the accepted plan will be maintained at the Contracting Officer's office and at the job site.

1.6.1.6. Continuously reviewed and amended the APP, as necessary, throughout the life of the contract. Incorporate unusual or high-hazard activities not identified in the original APP as they are discovered.

1.6.2. EM 385-1-1 Contents: In addition to the requirements outlines in Appendix A of

USACE EM 385-1-1, the following is required:

a. Names and qualifications (resumes including education, training, experience and certifications) of all site safety and health personnel designated to perform work on this project to include the designated site safety and health officer and other

01 35 26 Government Safety Requirements

Page 6 of 14 Pages

November 2011 competent and qualified personnel to be used such as CSPs, CIHs, STSs, CHSTs.

Specify the duties of each position.

b. Qualifications of competent and of qualified persons. As a minimum, designate and submit qualifications of competent persons for each of the following major areas: scaffolding; fall protection; hazardous energy; confined space; health hazard recognition, personal protective equipment and clothing to include selection, use and maintenance.

c. Confined Space Entry Plan. Develop a confined and/or enclosed space entry plan in accordance with USACE EM 385-1-1, applicable OSHA standards 29 CFR

1910, 29 CFR 1915, and 29 CFR 1926, OSHA Directive 2.100, and any other federal, state and local regulatory requirements identified in this contract. Identify the qualified person's name and qualifications, training, and experience. Delineate the qualified person's authority to direct work stoppage in the event of hazardous conditions. Include procedure for rescue by contractor personnel and the coordination with emergency responders. (If there is no confined space work, include a statement that no confined space work exists and none will be created.)

d. Fall Protection and Prevention (FP&P) Program Documentation. The program documentation shall be site specific and address all fall hazards in the work place and during different phases of construction. Address how to protect and prevent workers from falling to lower levels when they are exposed to fall hazards above 6 feet. A qualified person for fall protection shall prepare and sign the program documentation. Include fall protection and prevention systems, equipment and methods employed for every phase of work, responsibilities, assisted rescue, self-rescue and evacuation procedures, training requirements, and monitoring methods.

Revise the Fall Protection and Prevention Program documentation every six months, reflecting any changes during the course of construction due to changes in personnel, equipment, systems or work habits. Keep and maintain the accepted Fall

Protection and Prevention Program documentation at the job site for the duration of the project. Include the Fall Protection and Prevention Program documentation in the Accident Prevention Plan (APP).

e. Asbestos Hazard Abatement Plan. The safety and health aspects of asbestos work, prepared in accordance with Section 02 82 14.00 10 ASBESTOS

ABATEMENT 02 82 16.00 20 ENGINEERING CONTROL OF ASBESTOS

CONTAINING MATERIALS.

f. Site Safety and Health Plan. The safety and health aspects prepared in accordance with Section 01 35 29.13. HEALTH, SAFETY, AND EMERGENCY RESPONSE

PROCEDURES FOR CONTAMINATED SITES.

1.7. DISPLAY OF SAFETY INFORMATION: On a task order by task order basis, contractor shall develop method to provide a safety board at each job site. Where size, duration, or logistics of project do not facilitate a bulletin board, an alternative method, acceptable to the Contracting Officer, that is accessible and includes all mandatory information for employee and visitor review, shall be deemed as meeting the requirement

01 35 26 Government Safety Requirements

Page 7 of 14 Pages

November 2011 for a bulletin board. Include and maintain information on safety bulletin board as required by EM 385-1-1, section 01.A.06. Additional items required to be posted include:

a. Confined space entry permit.

b. Hot work permit.

1.8. SITE SAFETY REFERENCE MATERIALS: Maintain safety-related references applicable to the project, including those listed in the article "References." Maintain applicable equipment manufacturer's manuals.

1.9. EMERGENCY MEDICAL TREATMENT: Contractors will arrange for their own emergency medical treatment. Government has no responsibility to provide emergency medical treatment.

1.10. REPORTS:

1.10.1. Accident Reports:

a. Conduct an accident investigation for recordable injuries and illnesses, as defined in 1.3.h and property damage accidents resulting in at least $2,000 in damages, to establish the root cause(s) of the accident, complete the Navy Contractor

Significant Incident Report (CSIR) from USACE Accident Report Form 3394 and provide the report to the Contracting Officer within 5 calendar day(s) of the accident. The Contracting Officer will provide copies of any required or special forms.

b. Conduct an accident investigation for any weight handling equipment accident

(including rigging gear accidents) to establish the root cause(s) of the accident, complete the WHE Accident Report (Crane and Rigging Gear) form and provide the report to the Contracting Officer within 30 calendar days of the accident. Do not proceed with crane operations until cause is determined and corrective actions have been implemented to the satisfaction of the contracting officer. The

Contracting Officer will provide a blank copy of the accident report form.]

1.10.2. Accident Notification: Notify the Contracting Officer as soon as practical, but not later than four hours, after any accident meeting the definition of Recordable

Injuries or Illnesses or High Visibility Accidents, property damage equal to or greater than $2,000, or any weight handling equipment accident. Within notification include contractor name; contract title; type of contract; name of activity, installation or location where accident occurred; date and time of accident; names of personnel injured; extent of property damage, if any; extent of injury, if known, and brief description of accident

(to include type of construction equipment used, PPE used, etc.). Preserve the conditions and evidence on the accident site until the Government investigation team arrives on-site and Government investigation is conducted.

1.11. HOT WORK:

1.11.1. Submit and obtain a written permit prior to performing "Hot Work" (welding, cutting, etc.) or operating other flame-producing/spark producing devices, from the

Base Fire Department. A permit is required from the Explosives Safety Office for work

01 35 26 Government Safety Requirements

Page 8 of 14 Pages

November 2011 in and around where explosives are processed, stored, or handled. CONTRACTORS

ARE REQUIRED TO MEET ALL CRITERIA BEFORE A PERMIT IS ISSUED. The

Contractor will provide at least two (2) twenty (20) pound 4A:20 BC rated extinguishers for normal "Hot Work". All extinguishers shall be current inspection tagged, approved safety pin and tamper resistant seal. It is also mandatory to have a designated FIRE WATCH for any "Hot Work" done at this activity. The Fire Watch shall be trained in accordance with NFPA 51B and remain on-site for a minimum of 30 minutes after completion of the task or as specified on the hot work permit.

1.11.2. When starting work on the facility, require personnel to familiarize themselves with their location, the nearest fire alarm boxes and the nearest phone that can be used in an emergency situation.

1.12. FACILITY OCCUPANCY CLOSURE: Streets, walks, and other facilities occupied and used by the Government shall not be closed or obstructed without written permission from the Contracting Officer.

1.13. SEVERE STORM PLAN: In the event of a severe storm warning, the Contractor must:

a. Secure outside equipment and materials and place materials that could be damaged in protected areas.

b. Check surrounding area, including roof, for loose material, equipment, debris, and other objects that could be blown away or against existing facilities.

c. Ensure that temporary erosion controls are adequate.

1.14. CONFINED SPACE ENTRY REQUIREMENTS.: Contractors entering and working in confined spaces performing shipyard industry work are required to follow the requirements of OSHA 29 CFR Part 1915 Subpart B. Contractors entering and working in confined spaces performing general industry work are required to follow the requirements of

OSHA 29 CFR Part 1926.

PART 2 - PRODUCTS

2.1. FALL PROTECTION ANCHORAGE: Leave in place fall protection anchorage, conforming to ASSE/SAFE Z359.1, installed under the supervision of a qualified person in fall protection, for continued customer use and so identified by signage stating the capacity of the anchorage (strength and number of persons who may be tied-off to it at any one time).

PART 3 - EXECUTION

3.1. CONSTRUCTION AND/OR OTHER WORK: Comply with USACE EM 385-1-1, NFPA 241, the APP, Federal and/or State OSHA regulations, and other related submittals and activity fire and safety regulations. The most stringent standard prevails.

3.1.1. Hazardous Material Use: Each hazardous material must receive approval from the Contracting Office or the construction inspector prior to being brought onto the job site or prior to any other use in connection with this contract. Allow a minimum of 10 working days for processing of the request for use of a hazardous material.

01 35 26 Government Safety Requirements

Page 9 of 14 Pages

November 2011

3.1.2. Hazardous Material Exclusions: Notwithstanding any other hazardous material used in this contract, radioactive materials or instruments capable of producing ionizing/non-ionizing radiation (with the exception of radioactive material and devices used in accordance with USACE EM 385-1-1 such as nuclear density meters for compaction testing and laboratory equipment with radioactive sources) as well as materials which contain asbestos, mercury or polychlorinated biphenyls, di-isocynates, lead-based paint are prohibited. The Contracting Officer, upon written request by the

Contractor, may consider exceptions to the use of any of the above excluded materials.

The Radiation Safety Officer (RSO) must be notified prior to excepted items of radioactive material and devices being brought on base.

3.1.3. Unforeseen Hazardous Material: The design should have identified materials such as PCB, lead paint, and friable and non-friable asbestos and other OSHA regulated chemicals (i.e. 29 CFR Part 1910.1000). If material, not indicated, that may be hazardous to human health upon disturbance during construction operations is encountered, stop that portion of work and notify the Contracting Officer immediately.

Within 14 calendar days the Government will determine if the material is hazardous. If material is not hazardous or poses no danger, the Government will direct the Contractor to proceed without change. If material is hazardous and handling of the material is necessary to accomplish the work, the Government will issue a modification pursuant to

"FAR 52.243-4, Changes" and "FAR 52.236-2, Differing Site Conditions."

3.2. PRE-OUTAGE COORDINATION MEETING: Contractors are required to apply for utility outages at least 3 days in advance. As a minimum, the request should include the location of the outage, utilities being affected, duration of outage and any necessary sketches. Special requirements for electrical outage requests are contained elsewhere in this specification section. Once approved, and prior to beginning work on the utility system requiring shut down, attend a pre-outage coordination meeting with the Contracting Officer, construction inspector, using agencies, and utility representative to review the scope of work and the lock-out/tag-out procedures for worker protection. No work will be performed on energized electrical circuits unless proof is provided that no other means exist.

3.3. CONTROL OF HAZARDOUS ENERGY (LOCKOUT/TAGOUT): Contractor shall ensure that each employee is familiar with and complies with these procedures and USACE

EM 385-1-1, Section 12, Control of Hazardous Energy. Contracting Officer will, at the

Contractor's request, apply lockout/tagout tags and take other actions that, because of experience and knowledge, are known to be necessary to make the particular equipment safe to work on for government owned and operated systems. No person, regardless of position or authority, shall operate any switch, valve, or equipment that has an official lockout/tagout tag attached to it, nor shall such tag be removed except as provided in this section. No person shall work on any energized equipment including, but not limited to activities such as erecting, installing, constructing, repairing, adjusting, inspecting, un-jamming, setting up, trouble shooting, testing, cleaning, dismantling, servicing and maintaining machines equipment of processes until an evaluation has been conducted identifying the energy source and the procedures which will be taken to ensure the safety of personnel. When work is to be performed on electrical circuits, only qualified personnel shall perform work on electrical circuits. A supervisor who is required to enter an area protected by a lockout/tagout tag will

01 35 26 Government Safety Requirements

Page 10 of 14 Pages

November 2011 be considered a member of the protected group provided he notifies the holder of the tag stub each time he enters and departs from the protected area. Identification markings on building light and power distribution circuits shall not be relied on for established safe work conditions. Before clearance will be given on any equipment other than electrical (generally referred to as mechanical apparatus), the apparatus, valves, or systems shall be secured in a passive condition with the appropriate vents, pins, and locks. Pressurized or vacuum systems shall be vented to relieve differential pressure completely. Vent valves shall be tagged open during the course of the work. Where dangerous gas or fluid systems are involved, or in areas where the environment may be oxygen deficient, system or areas shall be purged, ventilated, or otherwise made safe prior to entry.

3.3.1. Tag Placement: Lockout/tagout tags shall be completed in accordance with the regulations printed on the back thereof and attached to any device which, if operated, could cause an unsafe condition to exist. If more than one group is to work on any circuit or equipment, the employee in charge of each group shall have a separate set of lockout/tagout tags completed and properly attached. When it is required that certain equipment be tagged, the Government will review the characteristics of the various systems involved that affect the safety of the operations and the work to be done; take the necessary actions, including voltage and pressure checks, grounding, and venting, to make the system and equipment safe to work on; and apply such lockout/tagout tags to those switches, valves, vents, or other mechanical devices needed to preserve the safety provided. This operation is referred to as "Providing Safety Clearance."

3.3.2. Tag Removal: When any individual or group has completed its part of the work and is clear of the circuits or equipment, the supervisor, project leader, or individual for whom the equipment was tagged shall turn in his signed lockout/tagout tag stub to the

Contracting Officer. That group's or individual's lockout/tagout tags on equipment may then be removed on authorization by the Contracting Officer.

3.4. FALL HAZARD PROTECTION AND PREVENTION PROGRAM: Establish a fall protection and prevention program, for the protection of all employees exposed to fall hazards. Within the program include company policy, identify responsibilities, education and training requirements, fall hazard identification, prevention and control measures, inspection, storage, care and maintenance of fall protection equipment and rescue and evacuation procedures.

3.4.1. Training: Institute a fall protection training program. As part of the Fall Hazard

Protection and Prevention Program, provide training for each employee who might be exposed to fall hazards. Provide training by a competent person for fall protection in accordance with USACE EM 385-1-1, Section 21.B.

3.4.2. Fall Protection Equipment and Systems: Enforce use of the fall protection equipment and systems designated for each specific work activity in the Fall Protection and Prevention Plan at all times when an employee is exposed to a fall hazard. Protect employees from fall hazards as specified in EM 385-1-1, Section 21. In addition to the required fall protection systems, safety skiff, personal floatation devices, life rings etc., are required when working above or next to water in accordance with USACE EM 385-

1-1, Paragraphs 21.N through 21.N.04. Personal fall arrest systems are required when

01 35 26 Government Safety Requirements

Page 11 of 14 Pages

November 2011 working from an articulating or extendible boom, swing stages, or suspended platform.

In addition, personal fall arrest systems are required when operating other equipment such as scissor lifts if the work platform is capable of being positioned outside the wheelbase. The need for tying-off in such equipment is to prevent ejection of the employee from the equipment during raising, lowering, or travel. Fall protection must comply with 29 CFR 1926.500, Subpart M, USACE EM 385-1-1 and ASSE/SAFE

A10.32.

3.4.2.1. Personal Fall Arrest Equipment: Personal fall arrest equipment, systems, subsystems, and components shall meet ASSE/SAFE Z359.1. Only a full-body harness with a shock-absorbing lanyard or self-retracting lanyard is an acceptable personal fall arrest body support device. Body belts may only be used as a positioning device system

(for uses such as steel reinforcing assembly and in addition to an approved fall arrest system). Harnesses shall have a fall arrest attachment affixed to the body support

(usually a Dorsal D-ring) and specifically designated for attachment to the rest of the system. Only locking snap hooks and carabiners shall be used. Webbing, straps, and ropes shall be made of synthetic fiber. The maximum free fall distance when using fall arrest equipment shall not exceed 6 feet. The total fall distance and any swinging of the worker (pendulum-like motion) that can occur during a fall shall always be taken into consideration when attaching a person to a fall arrest system.

3.4.3. Fall Protection for Roofing Work: Implement fall protection controls based on the type of roof being constructed and work being performed. Evaluate the roof area to be accessed for its structural integrity including weight-bearing capabilities for the projected loading.

a. Low Sloped Roofs:

(1) For work within 6 feet of an edge, on low-slope roofs, Protect personnel from falling by use of personal fall arrest systems, guardrails, or safety nets.

(2) For work greater than 6 feet from an edge, erect and install warning lines in accordance with 29 CFR 1926.500 and USACE EM 385-1-1.

b. Steep-Sloped Roofs: Work on steep-sloped roofs requires a personal fall arrest system, guardrails with toe-boards, or safety nets. This requirement also includes residential or housing type construction.

3.4.4. Existing Anchorage: Certified (or re-certified) by a qualified person for fall protection existing anchorages, to be used for attachment of personal fall arrest equipment in accordance with ASSE/SAFE Z359.1. Exiting horizontal lifeline anchorages must be certified (or re-certified) by a registered professional engineer with experience in designing horizontal lifeline systems.

3.4.5. Horizontal Lifelines: Design, install, certify and use under the supervision of a qualified person horizontal lifelines for fall protection as part of a complete fall arrest system which maintains a safety factor of 2 (29 CFR 1926.500).

3.4.6. Guardrails and Safety Nets: Design, install and use guardrails and safety nets in accordance with EM 385-1-1 and 29 CFR 1926 Subpart M.

01 35 26 Government Safety Requirements

Page 12 of 14 Pages

November 2011

3.4.7. Rescue and Evacuation Procedures: When personal fall arrest systems are used, the contractor must ensure that the mishap victim can self-rescue or can be rescued promptly should a fall occur. Prepare a Rescue and Evacuation Plan and include a detailed discussion of the following: methods of rescue; methods of self-rescue;

equipment used; training requirement; specialized training for the rescuers; procedures for requesting rescue and medical assistance; and transportation routes to a medical facility. Include the Rescue and Evacuation Plan in the Fall Protection and Prevention

(FP&P) Plan, and the Accident Prevention Plan (APP).

3.5. SCAFFOLDING: When scaffolding is used on a task order, provide employees with a safe means of access to the work area on the scaffold. Climbing of any scaffold braces or supports not specifically designed for access is prohibited. Access scaffold platforms greater than 20 feet maximum in height by use of a scaffold stair system. Do not use vertical ladders commonly provided by scaffold system manufacturers for accessing scaffold platforms greater than 20 feet maximum in height. The use of an adequate gate is required. Ensure that employees are qualified to perform scaffold erection and dismantling. Do not use scaffold without the capability of supporting at least four times the maximum intended load or without appropriate fall protection as delineated in the accepted fall protection and prevention plan. Stationary scaffolds must be attached to structural building components to safeguard against tipping forward or backward. Give special care to ensure scaffold systems are not overloaded. Side brackets used to extend scaffold platforms on self-supported scaffold systems for the storage of material is prohibited. The first tie-in shall be at the height equal to 4 times the width of the smallest dimension of the scaffold base. Place work platforms on mud sills. Scaffold or work platform erectors shall have fall protection during the erection and dismantling of scaffolding or work platforms that are more than six feet.

Delineate fall protection requirements when working above six feet or above dangerous operations in the Fall Protection and Prevention (FP&P) Plan.

3.6. EQUIPMENT

3.6.1. Material Handling Equipment

a. Material handling equipment such as forklifts shall not be modified with work platform attachments for supporting employees unless specifically delineated in the manufacturer's printed operating instructions.

b. The use of hooks on equipment for lifting of material must be in accordance with manufacturer's printed instructions.

c. Operators of forklifts or power industrial trucks shall be licensed in accordance with OSHA.

3.6.2. USE OF EXPLOSIVES: Explosives shall not be used or brought to the project site.

3.7. ELECTRICAL

3.7.1. Conduct of Electrical Work: Underground electrical spaces must be certified safe for entry before entering to conduct work. Cables that will be cut must be positively identified and de-energized prior to performing each cut. Positive cable identification

01 35 26 Government Safety Requirements

Page 13 of 14 Pages

November 2011 must be made prior to submitting any outage request for electrical systems.

Arrangements are to be coordinated with the Contracting Officer and Station Utilities for identification. The Contracting Officer will not accept an outage request until the

Contractor satisfactorily documents that the circuits have been clearly identified.

Perform all high voltage cable cutting remotely using hydraulic cutting tool. When racking in or live switching of circuit breakers, no additional person other than the switch operator will be allowed in the space during the actual operation. Plan so that work near energized parts is minimized to the fullest extent possible. Use of electrical outages clear of any energized electrical sources is the preferred method. When working in energized substations, only qualified electrical workers will be permitted to enter.

When work requires Contractor to work near energized circuits as defined by the NFPA

70, high voltage personnel must use personal protective equipment that includes, as a minimum, electrical hard hat, safety shoes, insulating gloves with leather protective sleeves, fire retarding shirts, coveralls, face shields, and safety glasses. In addition, provide electrical arc flash protection for personnel as required by NFPA 70E.

Insulating blankets, hearing protection, and switching suits may also be required, depending on the specific job.

3.7.2. Portable Extension Cords: Size portable extension cords in accordance with manufacturer ratings for the tool to be powered and protected from damage.

Immediately removed from service all damaged extension cords. Portable extension cords shall meet the requirements of NFPA 70E and OSHA electrical standards.

3.8. WORK IN CONFINED SPACES: Comply with the requirements in Section 34 of

USACE EM 385-1-1, OSHA 29 CFR 1910.146 and OSHA 29 CFR 1926.21(b)(6). Any potential for a hazard in the confined space requires a permit system to be used.

a. Entry Procedures. Prohibit entry into a confined space by personnel for any purpose, including hot work, until the qualified person has conducted appropriate tests to ensure the confined or enclosed space is safe for the work intended and that all potential hazards are controlled or eliminated and documented. (See Section 34 of USACE EM

385-1-1 for entry procedures.) All hazards pertaining to the space shall be reviewed with each employee.

b. Forced air ventilation is required for all confined space entry operations and the minimum air exchange requirements must be maintained to ensure exposure to any hazardous atmosphere is kept below its' action level.

c. Sewer wet wells require continuous atmosphere monitoring with audible alarm for toxic gas detection.

-- End of Section –

01 35 26 Government Safety Requirements

Page 14 of 14 Pages

November 2011

THIS PAGE LEFT BLANK