This document outlines a federal contract opportunity for joint forces paving services across Colorado Department of Defense installations. The solicitation seeks multiple award indefinite-delivery, indefinite-quantity firm-fixed-price contracts for paving, sidewalk, and site work with a maximum combined ceiling value of $200 million over a seven-year period from September 2018 to September 2025. The 50th Contracting Squadron intends to award up to six Multiple Award Task Order Contracts by September 2018. Questions regarding this solicitation are due in writing to the contracting points of contact by March 13, 2018. Offerors must be registered in the System for Award Management prior to award.
The accompanying file provides questions and answers related to sample paving projects at Fort Carson and Peterson Air Force Base, addressing issues such as contaminated base course, material recycling requirements, storm drain protection, tree replacement specifications, and abatement of stormwater lines.
Site Visit Questions and Answers. Answers to all sample project site visit questions received by the 27 February 2018 deadline.
View the file
Other files for this federal contract opportunity
Show all 28
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MASTER OF SPACE
2 March 2018
Questions and Answers
Questions – Ft Carson Sample Project Answer – Ft Carson Sample Project
1. Should bidders assume there is any contaminated base course?
No.
2. Can any material be recycled on post? No, haul all materials off post. 10% shall be recycled.
3. What should be done with storm drain inlets? Protect and install thickened edge expansion joint around inlet.
4. Section 2.1.1.2 – Should the removed existing base material be replaced with C-Dot Class 5 base course? Is there a percentage of base material that should assumed to be removed and replaced in the proposal?
Assume only regrading (no import of base course) will be required for gravel adjacent to integral curbs.
5. Section 2.2.16.1 - Which project personnel will be required to submit driver’s license and registration information at the time proposal submission?
None.
6. Section 2.2.16.3 - How much time per employee should be assumed for Antiterrorism (AT) Level 1 Training and the annual OPSEC training?
3 (three) hours.
7. Section 2.2.16.4 - How much time per employee should be assumed for iWATCH Training?
1 (one) hour.
8. Section 2.2.16.5 - Will access cards be valid for the entire duration of the contract?
No, access cards will be granted for awarded task orders for the duration of the task order.
Question – Peterson AFB Sample Project Answer – Peterson AFB Sample Project
1. Should bidders assume the waterline will not be disturbed by stormwater line placement?
Yes.
2. Can smaller trees be used to replace mature trees, and if so what size?
Yes. 3" caliper.
3. Does the stormwater line have to be fully abated and removed?
Yes.