6_Task_Order_Close_Out_01700.pdf

PDF 191 KB Posted

Attached to
Joint Forces Paving (JFP) for Colorado DoD Installations (CODI) Federal contract opportunity
Solicitation number
FA2550-18-R-1004
Issued by
Department of the Air Force Space Command

About this file

This solicitation package outlines requirements for multiple award indefinite-delivery, indefinite-quantity contracts to provide joint forces paving services for Colorado Department of Defense installations. Up to six contractors may be awarded contracts with a combined ceiling value of $200 million and performance periods from September 2018 through September 2025. Contractors must be registered in the System for Award Management prior to award. The solicitation seeks questions by March 13, 2018 and proposals by the specified due date and time. The contractor shall sign the SF1442 and all amendments. Debarred or suspended contractors are ineligible. Closeout requirements include inspections, as-built drawings, real property records, operation and maintenance manuals, training, spare parts, and warranty response timeframes.

Attachment 6 - Task Order Close-Out 01700

View the file

Other files for this federal contract opportunity

Other files attached to Joint Forces Paving (JFP) for Colorado DoD Installations (CODI), newest first.
File Type Posted
JFP_CODI_Industry_Update_13_Nov_18.docx DOCX document
JFP_CODI_Notice_to_Industry_MFR_7_Sep_18.pdf PDF
JFP_CODI_Notice_to_Industry_MFR_13_Aug_18.pdf PDF
JFP_CODI_Notice_to_Industry_MFR_20_July_2018.pdf PDF
JFP_CODI_2_May_18_Questions.pdf PDF
JFP_CODI_Notice_to_Industry_MFR_13_Apr_18.pdf PDF
RFP_Amended_SF_1442_13_Apr_18.pdf PDF
SF_30_13_Apr_18.pdf PDF
Notice_to_Industry_12_Apr_18.pdf PDF
Protest_to_GAO_B-416179_22_Mar_18.pdf PDF
JFP_CODI_Notice_to_Industry_MFR_23_Mar_18.pdf PDF
JFP_CODI_RFQ_Follow_on__QA__21_Mar_18.pdf PDF
JFP_CODI_RFQ_QA_16_Mar_18_Responses.pdf PDF
JFP_CODI_Site_Visit_Q&A_2_Mar_18.pdf PDF
13_Contract_Management.pdf PDF
4_Safety_Security_Health_and_Environmental_Requirements_01510.pdf PDF
11_PAFB_Sample_Project_SOW.pdf PDF
8_Ft_Carson_Sample_Project.pdf PDF
5_Airfields_and_Hangars_01540.pdf PDF
7_CODI_PP_Questionnaire.pdf PDF
FA2550-18-R-1004_JFP_CODI_RFP.pdf PDF
1_General_Requirements_01000.pdf PDF
9_PAFB_Sample_Project_DRAWING.dwg DWG drawing
2_Organizational_Guidance_01030.pdf PDF
10_PAFB_Sample_Project_SUBMITTAL_SCHEDULE.xlsx XLSX spreadsheet
12_Acronyms.pdf PDF
14_TASK_ORDER_PROCEDURES.pdf PDF
3_Contractor_Quality_Control_01440.pdf PDF
Show all 28

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Joint Forces Paving for

Colorado DoD Installations (CODI)

SECTION 01700

TASK ORDER CLOSE-OUT

REQUIREMENTS

ATTACHMENT 6

1. INSPECTION

1.1. Notification. Prior to requesting any final inspection, the Contractor shall have performed an internal quality control (QC) pre-final inspection and corrected any noted deficiencies. The Contractor shall provide the c o g n i z a n t Contracting Officer with the pre-final documentation on findings and corrections made when requesting a final. The Contractor shall submit a written request to the cognizant Contracting Officer to schedule the final inspection. The Contractor shall submit the request for final inspection in the method and manner prescribed by the task order. The scheduled final inspection shall be prior to the completion date of the applicable delivery order. This provision in no way restricts the right of the Government to inspect work at any time. Once the Contractor has requested a final inspection, the

Government inspector may conduct a pre-final inspection. The Contractor shall correct any discrepancies noted prior to the final inspection.

1.2. Final Inspection. The Contractor shall ensure the job site is thoroughly cleaned after construction. The Government will not accept the work until the site satisfies the final inspection. The Contractor, Government Inspector, and cognizant Contracting Officer (or designee) shall all participate in the final inspection. The Contractor shall correct any discrepancies noted within the time period specified at the task order level. The cognizant Contracting Officer reserves the right to decline the Contractor’s request for a final inspection or suspend a final inspection when it is evident that the Contractor is not ready for the inspection. The time period required for advance notice prior to a requested re-inspection for completed punch list items shall be specified at the task order level. As much as ten percent of the total value of each delivery order may be retained until all discrepancies are corrected.

2. PROJECT CLOSE OUT REQUIREMENTS

2.1. The Government requires the following information (as applicable) for record and operation purposes. Final payment will not be made until receipt of these documents, materials, and services.

2.2. As-Built Drawings.

2.2.1. During the progress of the work, the Contractor shall keep a careful record at the job site of all changes and corrections from the layouts shown on the drawings, if applicable, regardless of whether they are a part of the construction effort or not. The Contractor shall enter such changes and corrections to the contract or record drawings, and submit drawings to the c o g n i z a n t Contracting Officer in accordance with the schedule specified at the task order level. This shall include any hidden or subsurface data discovered during construction. The Contractor shall enter such changes and corrections on a copy of the task order proposal drawings, if drawings were made available, and provide the c o g n i z a n t Contracting Officer with a copy of the updated drawings. If the Contractor fails to maintain the record drawings as required herein, the cognizant Contracting Officer may determine that satisfactory progress has not been achieved for the period in question.

Final payment will be withheld until as-built record drawings are submitted to and approved by the cognizant Contracting Officer. The required format for as-built drawings will be specified at the task order level.

2.2.2. The as-built drawings shall indicate all physical changes to the construction area and the actual location of any subsurface utility lines.

The drawings shall also show, by offset dimensions to two permanently fixed surface features, the end of each run including each change in direction in sufficient detail that anyone may determine the location of these lines and appurtenances in the event the surface openings or indicators become covered over or obscured. The drawings shall indicate all valves, splice boxes, and similar appurtenances by dimensions along the utility run from a reference point. The drawings shall also note the average depth below the surface of each run, size and type of material.

2.2.3. At the time of beneficial occupancy of each structure involved under the contract, the Contractor shall submit as-built drawings that meet this requirement. All drawings shall conform to standard drafting practices and include such supplementary notes, legends, and details as required.

The Contractors shall dimension all utilities from a known point, or an existing permanent object, to the centerline of the ditch or structure. The

Government will review the as-builts for accuracy and, if found in error, will return the drawings to the Contractor for further revision.

2.2.3.1. The Contractor shall submit one full set of paper copies with red lines indicating changes from the original set of drawings. The drawings shall show any hidden, subsurface, or corrected layout information that the Contractor discovered during construction regardless of whether they were a part of the construction effort or not. The legibility and clear portrayal of the as-built construction on the marked prints (hard copy) are subject to the approval of the cognizant Contracting Officer.

2.2.4. There may be instances when record drawings will not be to the advantage of the Government or the Contractor. In these instances, the cognizant Contracting Officer or his/her representative may determine record drawings or as-builts are not necessary. This determination will be specified at the task order level.

2.3. Real Property Records. The Contractor shall prepare and submit a DD Form

1354, Transfer and Acceptance of DoD Real Property, for all installed property. The Contractor shall submit the real property records to the cognizant

Contracting Officer upon final inspection.

2.3.1. The Contractor shall meet with the cognizant Contracting Officer to get direction and example documents on the format and content of the DD

Form 1354. The Government will provide the Contractor with an electronic format that can be used to fill out the form. The form shall include all G overnment-furnished and contractor-furnished items installed by the Contractor.

2.4. Operation and Maintenance Manuals/Data. The Contractor shall furnish four copies (unless otherwise specified at the task order level) of Operation and

Maintenance (O&M) manuals for any product installed in the construction project to the c o g n i z a n t Contracting Officer i n t h e m a n n e r a n d m e t h o d p r e s c r i b ed a t t h e t a s k o r d e r l ev e l . O&M manuals shall be provided and approved in the time period specified at the task order level, before the project can be considered completed. Until the O&M manuals are submitted to the cognizant Contracting Officer, the Contractor shall be held responsible for all service calls and recurring maintenance.

2.4.1. The manuals shall contain complete instructions for operation, inspection, testing and maintenance of the system, and shall include part breakdown diagrams. If applicable, the manuals shall also contain complete wiring schematics and diagrams. O&M manuals shall contain the processes or methods of providing optimum efficiency of the product as described within the specifications. Further, the maintenance portions of these O&M manuals shall be explicit so that the unskilled craftsman may use these manuals to maintain the equipment in a condition of good and serviceable repair and operating at peak efficiency.

2.4.2. The Contractor shall organize O&M data into suitable sets of manageable size. The Contractor shall provide the cognizant

Contracting Officer all paperwork that was shipped with or attached to the product or material including: installation or maintenance instructions for the product or material part number listing care and/or cleaning instructions, removing and replacing information, warranty information, toll or toll-free numbers for information, and operator manuals(s). O&M manuals shall be the manufacturers' printed and bound reference instructions and guides. Photocopies of printed material are not acceptable. All words shall be legible, and all photographs and graphics shall be clear and easy to read.

2.4.3. Where required by the various technical sections, parts lists indicating source and current unit prices shall be provided by the Contractor with cover indicating the contents by equipment or system name and project title and shall be submitted with the related O&M manuals.

2.4.4. The Contractor shall organize all documents into a presentable and usable format. The Contractor shall index each item separately in the

Table of Contents and tab each item within the text with reference to the index. This requirement shall include, but not be limited to, the following:

2.4.4.1. Start Up Instructions

2.4.4.2. Shutdown Instructions

2.4.4.3. Maintenance Schedule

2.4.4.4. Maintenance Instructions

2.4.4.5. Trouble-Shooting Guide

2.4.4.6. Parts List

2.4.4.7. Parts Breakdown Diagram

2.4.4.8. Technical Engineering Data

2.4.4.9. Shop Drawings

2.4.4.10. Updated As-Built Drawings

2.4.4.11. Remarks

2.4.4.12. Shop Training

2.4.4.13. Extended Warranties

2.5. Training. Any required training shall be provided to the Government after the final inspection for each task order. Training shall be accomplished on all key components/items listed at the task order level.

2.6. Spare Parts and Maintenance Materials. Spare parts and maintenance materials shall be provided by the Contractor prior to the final inspection for each task order. These parts shall be provided on all items listed at the task order level.

3. WARRANTIES/WARRANTY RESPONSE: With the close- out documentation and prior to final payment, the Contractor shall provide any and all guarantees, warranties, and bonds as specified in contract clauses and individual sections of work.

These are in addition to the one-year warranty that, under FAR 52.246-21, Warranty of

Construction, applies to all materials and workmanship on every delivery order. The

Contractor shall honor all warranty requirements by responding and initiating corrective action on all warranty work within the following timeframes:

3.1. Routine Calls: The Contractor shall respond within the time period specified by the c o g n i z a n t Contracting Officer, and must accomplish the work within the time period specified at the task order level.

3.2. Urgent Calls: The Contractor shall respond within 24 hours of notification and complete corrective action within the time period specified at the task order level.

3.3. Emergency calls: The Contractor shall respond within the time period specified at the task order level and complete corrective action within the time period specified by the cognizant Contracting Officer.

3.3.1. The cognizant Contracting Officer will determine the category of the call

(routine, urgent, or routine). The corrective action shall include making temporary repairs, if necessary, until more permanent repairs can be made or replacement parts ordered. The Contractor shall complete all warranty work to the complete satisfaction of the cognizant Contracting

Officer in accordance with the applicable specifications. If the Contractor fails to honor warranty requirements (to include making temporary repairs), the Government may correct the deficiency and bill the

Contractor for the repairs, in addition to any other remedies that may be available.

END OF SECTION 01700