This document provides a submittal schedule for a project to repair asphalt roads at Peterson Air Force Base. The schedule outlines fifteen required submittals including work clearance requests, progress schedules, inspection forms, recovered materials estimates, as-built drawings, materials test results, and shop drawings. Submittal dates range from five days after notice to proceed to fourteen days prior to specified work. Approvals are required from the contractor, contracting engineer, and construction engineer for each submittal. The project completion date will be specified in the awarded contract.

The related federal contract opportunity is a solicitation for multiple award indefinite delivery, indefinite quantity contracts for joint forces paving services at Colorado Department of Defense installations. The 50th Contracting Squadron intends to award up to six firm fixed price contracts with a combined ceiling of $200 million. The initial ordering period will be five years from September 2018 to September 2023, followed by a two year option period. Questions are due by March 13, 2018 and proposals must be delivered per the specified method and time. The Department of the Air Force Space Command is the issuing agency.

Attachment 10 - PAFB Sample Project SUBMITTAL SCHEDULE

View the file

Other files for this federal contract opportunity

Other files attached to Joint Forces Paving (JFP) for Colorado DoD Installations (CODI), newest first.
File Type Posted
JFP_CODI_Industry_Update_13_Nov_18.docx DOCX document
JFP_CODI_Notice_to_Industry_MFR_7_Sep_18.pdf PDF
JFP_CODI_Notice_to_Industry_MFR_13_Aug_18.pdf PDF
JFP_CODI_Notice_to_Industry_MFR_20_July_2018.pdf PDF
JFP_CODI_2_May_18_Questions.pdf PDF
JFP_CODI_Notice_to_Industry_MFR_13_Apr_18.pdf PDF
RFP_Amended_SF_1442_13_Apr_18.pdf PDF
SF_30_13_Apr_18.pdf PDF
Notice_to_Industry_12_Apr_18.pdf PDF
Protest_to_GAO_B-416179_22_Mar_18.pdf PDF
JFP_CODI_Notice_to_Industry_MFR_23_Mar_18.pdf PDF
JFP_CODI_RFQ_Follow_on__QA__21_Mar_18.pdf PDF
JFP_CODI_RFQ_QA_16_Mar_18_Responses.pdf PDF
JFP_CODI_Site_Visit_Q&A_2_Mar_18.pdf PDF
12_Acronyms.pdf PDF
14_TASK_ORDER_PROCEDURES.pdf PDF
3_Contractor_Quality_Control_01440.pdf PDF
13_Contract_Management.pdf PDF
4_Safety_Security_Health_and_Environmental_Requirements_01510.pdf PDF
11_PAFB_Sample_Project_SOW.pdf PDF
8_Ft_Carson_Sample_Project.pdf PDF
5_Airfields_and_Hangars_01540.pdf PDF
7_CODI_PP_Questionnaire.pdf PDF
FA2550-18-R-1004_JFP_CODI_RFP.pdf PDF
6_Task_Order_Close_Out_01700.pdf PDF
1_General_Requirements_01000.pdf PDF
9_PAFB_Sample_Project_DRAWING.dwg DWG drawing
2_Organizational_Guidance_01030.pdf PDF
Show all 28

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet 1

CONTRACT NUMBER:Award Date:
PROJECT NUMBER:Notice to Proceed Date:
PROJECT TITLE: PAFB REPAIR ASPHALT ROADContract Completion Date:
Item No.Description of ItemRequired Submission Date (Calendar Days)Submittal NumberContractor ApprovalCE ApprovalCONS ApprovalRemarks
1AF Form 103, Work Clearance Request14 days prior to work on siteNo AF3000 required
2Final Progress Schedule5 days after NTP
3AF Form 1354Prior to Final Inspection
4Green Procurement Determination FormPrior to 100% Progress Report
5Warranty DocumentationPrior to 100% Progress Report
6Recovered Materials Estimate and Certification FormPrior to 100% Progress Report
7As-builtsPrior to 100% Progress Report
8Concrete mix design14 days prior to work on site
9Asphalt mix design14 days prior to work on site
10Subgrade/base course in-place density results14 days prior to work on site
11Asphalt in-place density test results14 days prior to work on site
12Paint data14 days prior to work on site
13Detectable warning surface data14 days prior to work on site
14Storm drain pipe data14 days prior to work on site
15Inlet/manhole shop drawings14 days prior to work on site

&"Times New Roman,Bold"&24&USUBMITTAL SCHEDULE &KFF0000DATE