This document provides a submittal schedule for a project to repair asphalt roads at Peterson Air Force Base. The schedule outlines fifteen required submittals including work clearance requests, progress schedules, inspection forms, recovered materials estimates, as-built drawings, materials test results, and shop drawings. Submittal dates range from five days after notice to proceed to fourteen days prior to specified work. Approvals are required from the contractor, contracting engineer, and construction engineer for each submittal. The project completion date will be specified in the awarded contract.
The related federal contract opportunity is a solicitation for multiple award indefinite delivery, indefinite quantity contracts for joint forces paving services at Colorado Department of Defense installations. The 50th Contracting Squadron intends to award up to six firm fixed price contracts with a combined ceiling of $200 million. The initial ordering period will be five years from September 2018 to September 2023, followed by a two year option period. Questions are due by March 13, 2018 and proposals must be delivered per the specified method and time. The Department of the Air Force Space Command is the issuing agency.
Attachment 10 - PAFB Sample Project SUBMITTAL SCHEDULE
View the file
Other files for this federal contract opportunity
Show all 28
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet 1
| CONTRACT NUMBER: | Award Date: | ||||||
| PROJECT NUMBER: | Notice to Proceed Date: | ||||||
| PROJECT TITLE: PAFB REPAIR ASPHALT ROAD | Contract Completion Date: | ||||||
| Item No. | Description of Item | Required Submission Date (Calendar Days) | Submittal Number | Contractor Approval | CE Approval | CONS Approval | Remarks |
| 1 | AF Form 103, Work Clearance Request | 14 days prior to work on site | No AF3000 required | ||||
| 2 | Final Progress Schedule | 5 days after NTP | |||||
| 3 | AF Form 1354 | Prior to Final Inspection | |||||
| 4 | Green Procurement Determination Form | Prior to 100% Progress Report | |||||
| 5 | Warranty Documentation | Prior to 100% Progress Report | |||||
| 6 | Recovered Materials Estimate and Certification Form | Prior to 100% Progress Report | |||||
| 7 | As-builts | Prior to 100% Progress Report | |||||
| 8 | Concrete mix design | 14 days prior to work on site | |||||
| 9 | Asphalt mix design | 14 days prior to work on site | |||||
| 10 | Subgrade/base course in-place density results | 14 days prior to work on site | |||||
| 11 | Asphalt in-place density test results | 14 days prior to work on site | |||||
| 12 | Paint data | 14 days prior to work on site | |||||
| 13 | Detectable warning surface data | 14 days prior to work on site | |||||
| 14 | Storm drain pipe data | 14 days prior to work on site | |||||
| 15 | Inlet/manhole shop drawings | 14 days prior to work on site |
&"Times New Roman,Bold"&24&USUBMITTAL SCHEDULE &KFF0000DATE