This is Exhibit G, Deliverables, from RFP No. HHS0015252 issued by the Texas Health and Human Services Commission (HHSC) for Document Processing Services. The exhibit outlines 39 specific deliverables that the contractor must submit throughout the contract lifecycle, spanning operational requirements, staffing, facility planning, security, financial management, and quality assurance. Key deliverables include the Contract Monitoring Questionnaire (due within 30 calendar days of the effective date and annually thereafter), document processing procedures and business processes (due within 30 business days of contract effective date), a training plan (due at least 60 calendar days prior to operational start), an organizational chart (due within 30 calendar days after operational start), risk management and readiness assessment plans, business operations plans, configuration management procedures, security management processes, disaster recovery and business continuity plans, quality management plans, communication and coordination plans, and comprehensive turnover and knowledge transfer plans. The contractor must also provide weekly transition phase status reports, quarterly training delivery and organizational chart updates, monthly status and quality management reports, and daily reconciliation reports. Financial deliverables include an accounting policy manual, tangible net worth statements (updated annually between September 1-30), nonexpendable capital item lists, and monthly invoices with detailed supporting documentation.

The deliverables are structured to ensure continuous oversight throughout the contract term, with submission frequencies ranging from one-time submissions for initial plans to daily, weekly, monthly, quarterly, semiannual, and annual reporting requirements. Critical incident and outage notifications must be reported within five minutes of occurrence, with formal incident reports due by close of business the next day. Several deliverables are tied to specific Key Performance Requirements (KPRs), including incident/outage notifications (DP KPR 9), incident reports (DP KPR 10), security management reports (DP KPR 12), and key personnel change notifications (DP KPR 14). The exhibit does not specify pricing, set-asides, or funding amounts; these details are contained in other RFP documents. The contract anticipated start date is September 2026, with the historical contract value estimated at approximately $4.5 million per State Fiscal Year.

View the file

Other files

File Type Posted
Exhibit C, Health and Human Services (HHS) Additional Provisions Version 1.0.pdf PDF
Exhibit T, Document Processing Center Procedures.pdf PDF
Exhibit N, Insurance Requirements.pdf PDF
Exhibit E, Scope of Work (SOW).pdf PDF
ESBD_403025_1749672218586_Exhibit E, Scope of Work (SOW) - Addendum 3.pdf PDF
Exhibit P, Certification Regarding Lobbying.pdf PDF
Exhibit F, Key Performance Requirements (KPR).pdf PDF
Historical Monthly Operational Status Reports.pdf PDF
Exhibit K, Exceptions Form.docx DOCX document
ESBD_403025_1748348929314_PCS 121 HHS0015252 Solicitation Addendum 1.pdf PDF
Exhibit B, Health and Human Services (HHS) Uniform Terms and Conditions Vendor, Version 3.4.pdf PDF
Exhibit O, Federal Assurances - Non-Construction Version 1.1.pdf PDF
Mail Volume by Transaction Type.pdf PDF
Exhibit H, Cost Proposal.xlsx XLSX spreadsheet
Exhibit D, Data Use Agreement, Version 8.5.pdf PDF
Exhibit D-1, Attachment 2 to the DUA, Security and Privacy Inquiry (SPI), Version 2.1.pdf PDF
Exhibit M, Historically Underutilized Business (HUB) Subcontracting Plan (HSP).pdf PDF
ESBD_403025_1749064353539_PCS 121 HHS0015252 Solicitation Addendum 2.pdf PDF
Exhibit J, Kofax Mail Channel - DR Site.pdf PDF
Exhibit I, HHSC Kofax ES-ECM Mail Channel Flow.pdf PDF
ESBD_403025_1749064423974_Attachment to Addendum 2_ Schedule of Events.pdf PDF
ESBD_403025_1748348965142_Attachment 1 to Addendum 1 Pre-Proposal Conference and Attendee Report.pdf PDF
Exhibit Q, Evaluation Tool.pdf PDF
ESBD_403025_1749672189459_PCS 121 HHS0015252 Solicitation Addendum 3.pdf PDF
Exhibit L, Assumptions Form.docx DOCX document
HHSC Equipment Inventory for DPC.pdf PDF
ESBD_403025_1749672239156_Exhibit H, Cost Proposal - Addendum 3.xlsx XLSX spreadsheet
ESBD_403025_1749672263349_HHS Responses to Questions - Addendum 3.pdf PDF
Exhibit A, HHS Solicitation Affirmation, Version 2.6.pdf PDF
Exhibit R, HHS Online Bid Room.pdf PDF
Exhibit S, Federal Funding Accountability and Transparency Act (FFATA) Certification.pdf PDF
ESBD_403025_1747430979739_Exhibits A-D1 (1 of 3).zip ZIP file
ESBD_403025_1747430830207_Procurement Library.zip ZIP file
ESBD_403025_1747430691108_RFP HHS0015252 Document Processing Services.pdf PDF
ESBD_403025_1747431018013_Exhibits E-Q (2 of 3).zip ZIP file
ESBD_403025_1747431048939_Exhibits R-T (3 of 3).zip ZIP file
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP No. HHS0015252 Exhibit G

Exhibit G, Deliverables

Deliverable ID & Description

KPR

No.

Requirements Due Date Frequency

DP 005-D

Contract

Monitoring Questionnaire (CMQ) and

Requirements

RFP

N/A

Contractor shall submit a Contract Monitoring Questionnaire (CMQ).

The Contractor shall include all requirements outlined in Exhibit E, Scope of Work (SOW), Section 2.4, Contract Monitoring Questionnaire (CMQ) and Requirements.

Within thirty (30) calendar days after effective date and annually thereafter within sixty (60) calendar days prior to the end of each State

Fiscal Year

One-time then annually

DP 016-D

Document Processing

Procedures and Business Processes

Contractor shall submit document processing procedures and business processes.

Contractor shall include all requirements outlined in Exhibit E, Scope of Work (SOW), Section 3, Operational Requirements.

business days after

Contract Effective Date and anytime thereafter when specified by

HHSC

One-time, or as requested by HHSC

DP 017-D

Document Processing

Procedures and Business Processes

Contractor shall submit annual updates to the document processing procedures and business process.

Contractor shall include all requirements outlined in Exhibit E, Scope of Work (SOW), Section 3, Operational Requirements.

No less than thirty (30) calendar days prior to the end of each operational year of the

Annually

Deliverable ID & Description

KPR

DP 022-D

Training Plan RFP

Contractor shall submit a Training Plan.

Contractor shall ensure to include all requirements outlined in Exhibit E, Scope of Work (SOW), Section 3.3.1, Training Plan.

No less than sixty (60) calendar days prior to the operational start date or by the date specified by HHSC and anytime thereafter when specified by HHSC

DP 023-D

The Contractor shall submit all initial curricula, training materials, and tools for review and approval.

HHSC reserves the right to request training material and tools at its discretion.

The Contractor shall ensure to include all requirements outlined in Exhibit E, Scope of Work (SOW), Section 3.3.1, Training Plan.

Thirty (30) calendar days prior to initial training delivery dates

DP 028-D

The Contractor shall submit a quarterly Training Delivery Completion and Status Report.

(SOW), Section 3.3.1, Training Plan.

Tenth (10th) business day of each calendar quarter

(i.e., Jan – March due by the tenth (10th) business day of April).

Quarterly

Deliverable ID & Description

KPR

DP 034-D

Key Personnel & Organizational

DP

KPR 14

Contractor shall submit notification to HHSC in writing for a Key Personnel vacancy for any reason or prior to making any changes in Key Personnel other than changes due to resignation, death, or military recall. Notification must include a plan to recruit Key Personnel.

The Contractor shall ensure to include all requirements outlined in Exhibit E, Scope of Work (SOW), Section 3.4, Key Personnel and Organizational Requirements.

Fourteen (14) calendar days prior to a Key Personnel vacancy will occur for any reason or prior to making any changes in Key Personnel

As Required

DP 037-D

Key Personnel Resumes and References

The Contractor shall submit resumes and references of proposed replacement Key Personnel for HHSC review prior to making a job offer.

The Contractor shall ensure to include all requirements

Within seven (7) calendar days from notification of a resignation or request for removal

DP 038-D

Initial Organizational

Chart

The Contractor shall submit an initial organizational chart.

Contractor shall include names and positions of all personnel assigned to this Contract. The organizational chart must designate who are Key Personnel and indicate which positions are eligible for telework.

The Contractor shall ensure to include all requirements

Within thirty (30) calendar days after the operational start date

One-time

Deliverable ID & Description

KPR

DP 039-D

Quarterly Updated

Organizational Chart

Contractor shall submit an updated organizational chart on a quarterly basis identifying the names and positions of all personnel assigned to this Contract. The organizational chart must designate who are Key Personnel, and indicate which positions are eligible for telework. List the date any vacancy occurred for a given position and include an identifier for any changes to the organizational chart from the previous submission (i.e., Jan – March due by the tenth (10th) business day of April).

The Contractor shall ensure to include all requirements

Tenth (10th) business day of each calendar quarter

Quarterly

DP 040-D

Notification of Key

Personnel Redirected

The Contractor shall submit notification to HHSC in writing and request approval to Key Personnel being temporarily redirected to perform functions other than the responsibilities of their current position.

The Contractor shall ensure to include all requirements

Ten (10) calendar days prior to Key Personnel being temporarily redirected to perform functions other than the responsibilities of their current position

DP 043-D

Transition Phase

Work Plan

The Contractor shall submit a Transition Phase Work Plan.

The Contractor shall ensure to include all requirements

3.5, Transition Phase Requirements.

Within forty-five (45) calendar days after the

Contract’s Effective Date

Deliverable ID & Description

KPR

DP 046-D

Weekly Transition

Phase Status Report

The Contractor shall submit a weekly Transition Phase Status Report. HHSC will inform the Contractor when the weekly transition phase status report submission period begins and ends.

The Contractor shall ensure to include all requirements

3.5, Transition Phase Requirements.

By 5:00 p.m. CST, the

Monday following the last day of the week covered by the report

Weekly

DP 049-D

Facility and Business Structure Transition

Plan

The Contractor shall submit a Facility and Business Structure Transition Plan.

The Contractor shall ensure to include all requirements

3.5.4, Facility and Business Structure Transition Plan.

Within sixty (60) calendar days after the Effective Date or by the date

DP 051-D

Risk Management

The Contractor shall submit a Risk Management Plan, including an Issue Resolution and Notification Process.

The Contractor shall ensure to include all requirements

3.6, Risk Management and Issue Resolution Plan.

days prior to the operational start date or by the date specified by HHSC and anytime thereafter when specified by HHSC

Deliverable ID & Description

KPR

DP 059 -D

Readiness Assessment

The Contractor shall submit a Readiness Assessment Plan for the operations and systems.

The Contractor shall ensure to include all requirements

3.7, Readiness Assessment Process.

Effective Date or by the date specified by HHSC

DP 067-D

Report

The Contractor shall submit the results of the Readiness Assessment Plan in a Readiness Assessment Report.

The Contractor shall ensure to include all requirements

3.7, Readiness Assessment Process.

Within fifteen (15) completion of the

Process

DP 070-D

Business Operations

The Contractor shall submit an initial Business Operations

The Contractor shall ensure to include all requirements

3.8.1, Business Operations Plan.

Thirty (30) calendar days prior to the scheduled operational start date or by the date specified by HHSC and anytime

Deliverable ID & Description

KPR

DP 072-D

Contractor shall submit a detailed six-month (6) evaluation report of the Business Operations Plan. The reporting period begins on the operational start date.

The Contractor shall ensure to include all requirements days after the end of the six-month (6) reporting period covered by the report

Semiannually

DP 073-D

The Contractor shall submit a daily reconciliation report via e-mail providing an end-to-end count of transactions.

The Contractor shall ensure to include all requirements

By noon, 12:00 p.m. CST, the next business day

Daily

DP 074-D

The Contractor shall submit a Monthly Status Report.

HHSC will inform the Contractor when the monthly status report submission period begins.

The Contractor shall ensure to include all requirements

Within ten (10) business days following the last day of the previous month

Monthly

Deliverable ID & Description

KPR

DP 079-D

Configuration Management

Contractor shall submit a Configuration Management Plan including an overall approach for tracking and managing hardware and software inventories including version control.

Contractor shall ensure to include all requirements

3.9.2, Configuration Management.

days after Effective Date or by the date specified by HHSC and anytime

DP 084-D

Security Management

The Contractor shall submit a Security Management Process Plan.

The Contractor shall ensure to include all requirements

3.10, Security Management.

Within thirty-five (35)

Effective Date or by the date specified by HHSC and anytime thereafter when specified by HHSC

DP 088-D

Security Management

KPR 12

The Contractor shall submit a report of security systems issues detailing the security violation, when and how discovered, operational impacts, and corrective measures to detect and prevent future violations.

The Contractor shall ensure to include all requirements

3.10, Security Management.

Within one (1) calendar day of discovery

Deliverable ID & Description

KPR

DP 089-D

Disaster Recovery and Business Continuity

The Contractor shall submit a Disaster Recovery Plan and a Business Continuity Plan specific to the transition and on-going operations.

The Contractor shall ensure to include all requirements

3.11, Disaster Recovery and Business Continuity.

Effective Date or by the date specified by HHSC

DP 090-D

Disaster Recovery and Business Continuity

The Contractor shall submit annual updates to the Disaster Recovery Plan and the Business Continuity Plan.

The Contractor shall ensure to include all requirements

Thirty (30) calendar days prior to the end of the operational year of the

Contract or within thirty

(30) days following a

Disaster Recovery exercise

Annually/As Required

DP 093-D

Incident/Outages

Notification

KPR 9

Contractor must report all incidents/outages to HHSC via e-mail or telephone if e-mail is unavailable.

The Contractor shall ensure to include all requirements

Within five (5) minutes of an incident/outage occurring

Deliverable ID & Description

KPR

DP 094-D

Incident/Outage

Report

KPR 10

Contractor shall submit an Incident Report to HHSC via the formal communications process detailing the incident, when and how discovered, system and operational impacts, and corrective measures to detect and prevent future incidents.

The Contractor shall ensure to include all requirements

By closing of next business day of reported incident/outage notification

DP 095-D

Quality Management

The Contractor shall submit an initial Quality Management Plan.

The Contractor shall ensure to include all requirements

3.12.1, Quality Management Plan.

Forty-five (45) calendar days prior to the scheduled operational start date

DP 096-D

Quality

Contractor shall submit an Annual Quality Management

Forty-five (45) calendar days prior to the end of each operational year of the

Deliverable ID & Description

KPR

DP 097-D

Quality

Contractor shall submit a monthly Quality Management Report to HHSC.

The Contractor shall ensure to include all requirements business days following the end of the reporting month

DP 110-D

Communication and Coordination

The Contractor shall submit an initial Communication and Coordination Plan.

(SOW), Section 3.13, Communication and Coordination Plan.

days after Effective Date or by the date specified by

HHSC

DP 111-D

Communication and Coordination Plan

The Contractor shall submit an annual Communications and Coordination Plan.

outlined in Exhibit E, Scope of Work (SOW), Section 3.13, Communication and Coordination

Every twelve (12) months from the approval date of the initial Communication and Coordination Plan

Deliverable ID & Description

KPR

DP 112-D

Turnover Plan

Contractor shall submit an Operations Turnover Plan.

(SOW), Section 3.14.2, Turnover Plan.

days after the Transition Phase is complete or date

DP 113-D

The Contractor shall submit annual revisions of the Operations Turnover Plan.

(SOW), Section 3.14.2, Turnover Plan.

Sixty (60) calendar days prior to the end of each operational year of the

Six (6) months prior to the end of the Contract or upon request by HHSC

Annually/ or as

DP 119-D

Contractor shall submit a comprehensive Knowledge Transfer Plan, including all materials useful and necessary to perform all job duties, along with identifying subject matter experts.

3.14.2, Turnover Plan.

prior to the end of the

Deliverable ID & Description

KPR

DP 122-D

Facilities and Business Structure

The Contractor shall submit a Facilities and Business Structure Turnover Plan.

3.14.3, Facilities and Business Structure Turnover days after the Transition

Phase is complete

DP 124-D

Facilities and Business Structure

The Contractor shall submit an Annual Facilities and Business Structure Turnover Plan.

3.14.3, Facilities and Business Structure Turnover prior to the end of each operational year of the

Contract

Six (6) months prior to the end of the Contract or upon request by HHSC

Annually, or as

DP 125-D

Turnover Results

The Contractor shall submit a Turnover Results Report.

3.14.4, Turnover Results.

completion of turnover activities or by the date

Deliverable ID & Description

KPR

DP 133-D

Financial Accounting

The Contractor shall submit a final Accounting Policy Manual which includes any modifications necessary due to contract negotiations and all the proposed accounting policies and procedures the Contractor must follow during the duration of any Contract resulting from the RFP.

(SOW), Section 4.2.3, Financial Accounting Requirements.

Effective Date

DP 144-D

Financial Report

Contractor shall submit a tangible net worth prepared by a Certified Public Accountant for the most recent State Fiscal Year end and for each State Fiscal Year during the term of the Contract Term resulting from this RFP. The Contractor must submit their annual updates to their statement of tangible net worth between September 1 and September 30 of each State Fiscal Year.

4.2.6, Financial Report Requirements.

Effective Date

No later than thirty (30) calendar days after the end of each State Fiscal Year

One-time, revised annually

DP 145-D

The Contractor shall submit a list of all nonexpendable capital items acquired under the Contract.

4.2.6, Financial Report Requirements.

end of the transition period end of each State Fiscal quarter when

One time, Quarterly as required

Deliverable ID & Description

KPR

No.

Requirements Due Date Frequency nonexpendable capital items are acquired

DP 146-D

Prepare an invoice for payment for each month during the term of the Contract Term. In addition, Contractor will supply detailed information in an electronic format that supports the monthly invoice. HHSC reserves the right to request financial information and supporting information in a format that will allow HHSC to verify reported costs most efficiently and comply with its State and federal financial reporting requirements.

The Contractor shall ensure to include all requirements outlined in Exhibit E, Scope of Work (SOW), Section 4, Financial Requirements.

calendar days following the end of the previous month.

File details come from the government source that posted it. Updated .