This document is an evaluation narrative for BPM003384 - Nara Sin, which reviews proposals from multiple engineering and consulting firms for a project involving dam, hydrology, and boating access work. The companies evaluated include Cardno, DOWL, J2, JE Fuller, Natural Channel Design, Next Gen, Stantec, Tetra Tech, and Wilson. The document appears to be an internal assessment of each firm's project experience, design philosophy, understanding of common problems, and overall proposal quality, likely for a competitive solicitation in Arizona.

The evaluation focuses on each firm's relevant experience with dam inspections, Emergency Action Plans (EAPs), ALERT systems, hydrology, hydraulics, and boating access projects. Key evaluation criteria include project-specific expertise, design approach, quality assurance/quality control processes, and proposal presentation. While no specific contract details are provided, the narrative suggests the solicitation is seeking a firm with comprehensive technical capabilities in dam-related engineering, particularly for projects involving AZGFD (Arizona Game and Fish Department) and potential boating infrastructure improvements. The reviewers noted varying strengths among the proposing firms, with some having more direct experience in dam and boating access projects than others.

View the file

Other files

File Type Posted
BPM003384_-_Evaluation_SPO_Form_120_-_Procurement_Disclosure_Statement_narasin.pdf PDF
COI_Stantec_Consulting_Serv_CGL_AL_WC_5-1-22_to_5-1-23_0001.pdf PDF
Evaluation_Narrative_for_BPM003384_-NS.pdf PDF
Evaluation_for_Committee_Members_-drodriguez.pdf PDF
Proposal_Score_Sheet_BPM003384.xlsx XLSX spreadsheet
Proposal_Score_Sheet_BPM003384.xlsx_-_drodriguez.pdf PDF
RFP_BPM003384_Hydro_Eng_Services_Award_Determination_signed.pdf PDF
ST5322_1.PDF PDF
ST9C6B_1.PDF PDF
STAZMail_10-14-21_-_NOA_-_BPM003384__Hydro_Engineering_Services_-_Stantec.pdf PDF
STAZ_Mail_-_Stantec_Insurance_Certification_10-11-21_10.40am.pdf PDF
Stantec_BAFO_Sheet_9-22-21.xlsx XLSX spreadsheet
Stantec_Negotiations_Sheet_8-10-21Stantec.xlsx XLSX spreadsheet
THE_STATE_OF_ARIZONA__17936182.pdf PDF
pds_drodriguez_pg1.jpeg JPEG file
BPM003384_Hydro_Eng_-Price_Negotiations_6-29-21Stantec.pdf PDF
EXECUTIVE_SUMMARY_BPM003384.pdf PDF
RFP_BPM003384_Hydro_Eng_Services_Award_Determination.docx DOCX document
Stantec_AZ_Corp_Commision_report.docx DOCX document
TO_Stantec_BAFO_Sheet_9-15-21.xlsx XLSX spreadsheet
BPM003384_Due_Diligence_Check_List.pdf PDF
BPM003_2.PDF PDF
CTR057596_Stantec_Hydrological_Engineering_Services_executed.pdf PDF
Evaluation_Score_BPM003384.pdf PDF
Evaluation_Team_Meeting_Sign_in_Sheet.docx DOCX document
RFP_BPM003384_Hydro_Eng_Services_Award_Determination.pdf PDF
SAM_EntityInformation-Stantec.pdf PDF
ST15C8_1.PDF PDF
STAZMA_2.PDF PDF
STAZMA_3.PDF PDF
STB9E1_1.PDF PDF
Stantec-AZ_SOQ_Stantec.pdf PDF
Stantec-O_A_signed.pdf PDF
StantecInsurance.pdf PDF
Stantec_Insurance_Certification_10-1-21_to_10-1-22.pdf PDF
Stantec_Insurance_Certification_5-1-21_to_5-1-22.pdf PDF
Stantec_Negotiations_Sheet_8-17-21-Stantec.xlsx XLSX spreadsheet
Stantec_Negotiations_Sheet_8-17-21Stantec.pdf PDF
THE_STATE_OF_ARIZONA__17936187.pdf PDF
hydro_evals_June_2021_gbleyl.pdf PDF
CTR057596_YR5_Contract_Renewal_AZGFD_Signed.pdf PDF
CTR057596_Yr_4_Renewal.pdf PDF
Guidelines_for_Evaluation_for_Committee_Members.pdf PDF
Proposal_Score_Sheet_BPM003384_-_NS.pdf PDF
STAZMA_1.PDF PDF
STAZMA_4.PDF PDF
STAZMail_to_Unsucessfuls-_10-14-21_Solicitation_-_BPM003384__Hydro_Engineering_Services.pdf PDF
STAZ_Mail_-_BPM003384_-_Evaluation_Committee_ENGSERVICES-_HYDRO.pdf PDF
STAZ_Mail_-_Request_BAFO__BPM003384_-TO_9.16.21Stantec.pdf PDF
YR3_RENEWAL_CTR057596_-_Hydrological_Engineering_Services.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Evaluation Narrative for BPM003384 – Nara Sin

Cardno Project Experience

Hydrology/Hydraulic projects in AZ. No dam specific projects.

Overall Experience Most boat ramp experience was in FL.

Design Philosophy, Process, QA/QC Good understanding of tight time constraints. I like the assignment of one main PM to coordinate budget, schedule, and design.

Common Problems Good understanding of boat ramps and Dam engineer. No ALERT design experience.

Overall Quality of Proposal Excellent cover letter, well organized proposal. Section 1 felt crammed.

DOWL

Relevant dam experience on AZGFD projects.

Overall Experience Only dock experience was a pier replacement in OR.

Design Philosophy, Process, QA/QC I like that they provided a Dams team and a Boating/Rec team in their org chart.

Good Project flow chart

Common Problems Good understanding of differences between vested parties and perspectives.

Good understanding of budget gaps from limited design information.

Well organized proposal that flowed well and was easy to read.

J2

Projects listed were not dam or boating related.

Overall Experience ALERT design management is a need

Design Philosophy, Process, QA/QC Four key components are good.

Plan, Do, Check, Act

Common Problems Good understanding of Hydrology and Hydraulics and boating access problems

Overall Quality of Proposal Clean proposal, well laid out, easy to read, good balance of text/graphics.

JE Fuller Project Experience

Good experience with dams, EAPs and ALERT systems

Overall Experience ALERT systems experience is a plus

No listed boating experience

Design Philosophy, Process, QA/QC Good understanding of ALERT system purpose and priorities

Common Problems Good understanding of issues with dam projects.

Team resumes were provided twice.

Natural Channel Design

Hydrology and hydraulic experience, not directly tied to dam or boating access however.

Overall Experience Most experience is in wildlife habitat/hydrology

Design Philosophy, Process, QA/QC All geomorphology, stream habitat restoration

Oxbow as a sub

Common Problems Good understanding of permitting and issues with multiple stakeholders and funding sources

Overall Quality of Proposal Well laid out, easy to read.

Next Gen

SVMPO?

Overall Experience No mention of specific dam, ALERT, or boating access projects.

Design Philosophy, Process, QA/QC Good process for typical land use, hydrologic/hydraulic analyses

Common Problems Communication is key

Proposal should be provided as one complete PDF.

Stantec

Dam inspections for FCDMC.

Dam EAP

Overall Experience Good experience with dams and EAPs

Some ALERT staff, no boating access

Design Philosophy, Process, QA/QC Collaboration and communication

Common Problems No specifics to problems approached with dam/boating projects

Overall Quality of Proposal Clean, easy to read proposal

Tetra Tech Project Experience

Relevant dam and EAP projects.

Overall Experience Good overall dam experience, with some boat ramp at Park Moabi

Design Philosophy, Process, QA/QC Good design and QA/QC philosophy

Common Problems Roadways/utilities mentioned, but nothing else with dam or boating access

Overall Quality of Proposal Well organized, clean, easy to read.

Wilson

Some dam and boating experience

Overall Experience Some dam and boating experience, out of state.

Some ALERT and EAP

Design Philosophy, Process, QA/QC Listed good points, like cost control and schedule control.

Common Problems Good understanding of ALERT, EAP, dam project problems

Well organized, clean, easy to read.