Conc_A_Ramp_Level_Pricing_Table_Template.xlsx
XLSX spreadsheet 12 KB Posted
- Attached to
- Concourse A Ramp Level Office Upgrades
- Solicitation number
- 26-020-ITB
- Issued by
- Bell County, Kentucky
About this file
This is a pricing table template prepared by the Kenton County Airport Board (KCAB) for the Concourse A Ramp Level Office Upgrades project at Cincinnati/Northern Kentucky International Airport (CVG) in Hebron, Kentucky. The template establishes the framework for general contractor bids covering approximately 20,000 square feet of renovation work on the Ramp Level of Concourse A. The project scope includes multiple divisions of work such as general conditions, demolition, drywall, acoustical ceilings, flooring (tile and carpet), painting, accessories, sprinkler systems, plumbing, HVAC, electrical, security, access control, phone and data systems, and fire alarm technology. A pre-bid meeting and site visit are scheduled for Wednesday, April 1, 2026 at 10:00 am at CVG Airport's Main Terminal. Written questions must be submitted by 11:59 pm on Friday, April 17, 2026, with answers posted by Tuesday, April 21, 2026 at 11:59 pm. Bids are due by Thursday, April 30, 2026 at 2:00 pm, with no late submissions accepted unless extended by KCAB addendum.
The pricing template requires bidders to structure their submissions using lump sum (LS) pricing for major work divisions unless quantities are specified, supplemented by unit prices for designated items including painting (per square foot), carpet tile installation (per square foot), floor demolition and prep (per square foot), and acoustical ceiling work (per square foot). The template also includes sections for labor rates broken down by classification (laborer, carpenter, and MEP/apprentice positions for electrical, plumbing, and HVAC trades), allowances for moving materials and dumpster services, unforeseen conditions, and alternates. Bidders are required to provide a list of subcontractors organized by division of work. The project will operate under a phased construction approach due to approximately 50 percent occupancy during renovation, with critical Airport Operations and Housekeeping functions requiring careful coordination to maintain operational continuity throughout the construction period.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pricing_Table_Template
| Table Name | Line Item | Description | Unit of Measure | Quantity | Taxable | Unit Cost | Custom1 | Custom2 | Custom3 | Custom4 | Custom5 | Section Header |
| Table 1 | 1 | Example 1 (required column) | Unit 1 (required column) | 1 | TRUE | |||||||
| Table 1 | 2 | Example 2 | Unit 2 | 1 | ||||||||
| Table 1 | Example Section Header | TRUE | ||||||||||
| Table 1 | 3 | Example 3 | Unit 3 | 1 | ||||||||
| Table 2 | 4 | Table 2 Example 1 | Table 2 Unit 1 | |||||||||
| Table 2 | 5 | Table 2 Example 2 | Table 2 Unit 2 |
| Breakout per | Division of work | |
| General Conditions | ||
| Demo | LS, unless we have quantities | |
| GWB | LS, unless we have quantities | |
| Acoustical Ceilings | LS, unless we have quantities | |
| Tile Flooring | LS, unless we have quantities | |
| Carpet Flooring | LS, unless we have quantities | |
| Painting | LS, unless we have quantities | |
| Accessories | LS, unless we have quantities | |
| Sprinkler | LS, unless we have quantities | |
| Plumbing | LS, unless we have quantities | |
| HVAC | LS, unless we have quantities | |
| Electric | ||
| Security Access | ||
| Phone & Data | ||
| Fire Alarm and Technology | ||
| All other scope of work not included in any other bid tab. |
Alternates
| Unit Prices | ||||
| Painting | 1 Coat Primer or blockfill, 2 Coats finish | SF | 1 | |
| Carpet Tile | Adhesive, Carpet, Installation | SF | ||
| Floor Demo & Prep | Carpet removal & minor prep | SF | ||
| Acoustical Ceiling | Grid and pad | SF |
| Allowances | |
| Moving materials | |
| Dumpster | |
| Unforseen Conditions |
| Labor Rates | Laborer |
| Carpenter | |
| MEP / Each | Apprentice |
| Elec, Plumb, HVAC |
List of Subcontractors Require the contreactor to provide a list of contractors per division of work.