CN-370000-CN204-T9CO1.pdf
PDF 60 KB Posted
- Contract number
- CN204
- Issued by
- Florida
About this file
This is a Change Order document issued by the Department of Environmental Protection (FDEP) for a task assignment related to continuing professional services. The change order modifies Task Assignment No. 9 under Contract CN204 with vendor AMEC/David Soler, P.E., for work at Bahia Honda District 5 Solar. The document is signed by multiple FDEP representatives including Project Manager Theresa Carron, Contract Manager Mac Roth, Consultant Jose R. Perez, and Contract Authority Michael W. Foster Jr., P.E., with signatures dated between January 27, 2016 and February 8, 2016.
The change order provides additional time only due to permits still outstanding and does not modify the fixed price contract terms. The original task amount was $15,262.03 with an original completion date of February 1, 2016. The change order extends the project completion by 120 days to May 31, 2016, with a new task completion date of May 31, 2016. The total task days remain at 152 days, and the net change to the contract is zero dollars, maintaining the original task amount of $15,262.03. The encumbrance information indicates the allocation is for "TIME ONLY," confirming that no additional compensation is authorized beyond the original fixed price.
View the file
Other files
Show 40 more
Latest 50 of 116 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .