This document is a Task Assignment Notification Form and supporting proposal from the Florida Department of Environmental Protection (FDEP) assigning work to WSP USA Environmental and Infrastructure, Inc. under Contract No. CN204. The project, known as the Card Sound Road Restoration Project, is located in Monroe County, Florida, and involves the removal of non-permitted structures and shoreline restoration on FDEP State Lands. The assignment was executed on June 28, 2023, with FDEP's Contract Manager Ralph Perkins overseeing the work and WSP's representative Greg Corning serving as the primary consultant contact.
The contract scope of work encompasses design, permitting, and bidding phase services for the removal of two non-permitted houses, associated docks, parking areas, boat ramps, and shoreline restoration. The project is structured in four main tasks: (1) Data Compilation and Environmental Resource Assessment including benthic surveys, wetland delineation, and vegetation surveys; (2) Restoration and Mitigation Plan development with unified mitigation assessment and W.A.T.E.R. score analysis; (3) Design deliverables at 30%, 60%, and 100% completion levels; and (4) Permitting services for multiple agencies including the South Florida Water Management District, Army Corps of Engineers, and Florida Fish and Wildlife Conservation Commission. The total contract value is $60,510.88, comprised of $58,843.88 in fixed price costs and $1,667.00 in reimbursable expenses. The project completion date is set for June 30, 2024, with Task 1 commencing upon execution and subsequent tasks to follow a sequential schedule totaling approximately 20 weeks of work.
View the file
Other files
Show 40 more
Latest 50 of 116 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT NOTIFICATION FORM
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description of Task:
Project Manager:
Schedule Start Date: Fixed Price Cost:
Completion Date: Cost Reimbursement not to exceed:
Total Task Amount:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 digit FLAIR Code: Total:
CN204 TA48 FDEP State Lands SL002
Monroe County Card Sound Road Restoration Project
WSP USA Environmental and Infrastructure, Inc.
Greg Corning (314) 920-8359 Greg.Corning@wsp.com
Ralph Perkins (850) 245-2460 Ralph.Perkins@FloridaDEP.com
Continue to provide design, permitting, and bidding phase services for the removal of two non-permitted houses, associated docks, parking areas, boat ramp, and for shoreline restoration as per the attached proposal dated May 21, 2023.
James Post
Upon Execution $ 58,843.88 6/30/2024 $ 1,667.00
$ 60,510.88
Grady A, Smith, FDEP Grady Smith Digitally signed by Grady Smith Date: 2023.06.27 12:28:49 -04'00' 06/27/2023
James Post James Post Digitally signed by James Post Date: 2023.06.28 09:40:03 -04'00'
Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2023.06.28 13:16:40 -04'00'
Greg Corning
Michael W. Foster Jr., P.E.
SL002 N/A 37102300000 100718/00 LATF42300 N/A 139900 QC $ 60,510.88
$ 60,510.8837-20-2-423001-37100400-00-100718-0
06/28/2023
Michael W. Foster Jr., P.E.
Digitally signed by Michael W.
Foster Jr., P.E.
Date: 2023.07.07 16:13:17 -04'00'
May 21, 2023
Mr. Byron Ward Operations Manager BSOLI-Land and Recreation Florida Department of Environmental Protection 3900 Commonwealth Boulevard 260K, MS 520 Tallahassee, FL 32399
Via email: Byron.Ward@Floridadep.gov
RE: Proposal for Card Sound Road Restoration Project Southeast District-Monroe County FDEP Contract No. CN204 Task Assignment Number 48 (TA 48) WSP Project No. 600408.16
Dear Mr. Ward:
For your consideration, WSP USA Environment & Infrastructure Solutions, Inc. (WSP) has provided to Florida Department of Environmental Protection (FDEP) a proposal summary and labor documentation for the tasks identified below for Southeast District – Card Sound Road Restoration Project.
FDEP and WSP had an informal meeting on March 21, 2023, to discuss the removal of several structures adjacent to Card Sound Road in Monroe County. The intent of the project is to remove illegal structures from state lands and restore the area to a natural shoreline with WSP offering design and permitting support for the project.
The northern site (site 1) consists of a wood frame structure on stilts as well as a dock which begins with an access boardwalk near the north corner of the structure and wraps around the west, south, and east sides. Various benthic resources including seagrasses and macroalgae appeared to be growing within the anticipated impact area and should be identified and located with a benthic survey. The northern side of the structures face Card Sound Road with mixed native/non-native vegetation growing to the shoulder of the highway.
The southern site (site 2) consists of two sheds, a residential building on piles, covered and uncovered dock area, boat ramp, mooring piles, and various concrete shoreline stabilization. The benthic and terrestrial resource communities appeared similar to the northern site.
A benthic resource survey, wetland delineation, and vegetation survey are recommended to be included in the scope of work. In the event the project is anticipated to impact regulated natural resources, a restoration and mitigation proposal should be performed.
See the site maps in the attachments at the end of this document.
5015 S. Florida Avenue, Ste 301 Lakeland, Florida 33813
The following tasks will be performed in accordance with FDEP Contract No. CN204 and will be completed on a lump sum basis:
Site Evaluation, Design & Permitting Services, Thank you and please contact the undersigned with any questions.
Sincerely, WSP USA Environment & Infrastructure, Inc.
Greg Corning Assistant Vice President, Civil Engineer FL Civil Design Team Lead 1 (314) 920-8359 Greg.Corning@wsp.com
GC/sg
Monroe County – Card Sound Road Restoration Project FDEP Contract No. CN204, Task Assignment Number TA47
Task 1: Data Compilation and Environmental Resource Assessment
Description: WSP will conduct site visits to the project area to assess current conditions.
WSP will go to the site to assess existing structures environmental resources present. A benthic and vegetation survey will be performed to define regulated resources and calculate any anticipated impacts of the project to create a mitigation proposal to be included with permit applications. A wetland delineation will also be performed to define the jurisdictional line. Refer to the attached maps for the proposed survey and assessment boundaries.
Deliverable: The deliverable will include a biological report in PDF format to be delivered to the FDEP project manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost
WSP
Associate Engineer; Geologist;
Scientist; Planner; Project Manager $206.42 7.5 $1,548.15
WSP Senior Engineer, Geologist, Scientist, Project Manager
$164.23 30 $4,926.90
WSP Project Engineer, Geologist, Scientist, Project Manager
$123.00 30 $3,690.00
WSP Senior Inspector $95.99 14 $1,343.86 WSP Senior CADD $133.89 6 $803.34 WSP Project Coordinator $75.32 3.25 $244.79
Fixed Price Total Cost $12,557.04
Reimbursable Cost:
Hotel $700.00 4 hotel stays @ $175 / per night (1 staff, 5 days field work)
Company Vehicle $378.25 4 days of travel (850 Miles) @ $0.445 / per mile
Per diem $258.75 3 full days @ $69 / per day & 1 travel days @ $51.75 (1 staff)
GPS Rental $330.00 3 days @ $110.00 / per day (1 staff)
Reimbursable Total Cost $1,667.00
Total for Task 1: $14,224.04
Task 2: Restoration and Mitigation Plan
Description: WSP will provide a restoration and mitigation plan for the project areas to offset any unavoidable environmental impacts. (Refer to the attached maps for the limits of project area).
The restoration and mitigation plan will include a unified mitigation assessment (UMAM) and Everglades Mitigation Bank W.A.T.E.R. Score analysis as well as an on-site restoration plan to conform with all applicable local, state, and federal regulatory environmental resource permit codes.
The restoration plan will include the species of native vegetation, size of plants, and site plan. The restoration plan will also include a threshold for success for survivorship of plantings, as well as procedures to follow should survivorship fall below the established threshold. Finally, WSP will create a monitoring schedule for submission to FDEP.
Deliverable: The deliverable to include Unified Mitigation Assessment, W.A.T.E.R. score analysis, and restoration plan.
Performance Measure: Deliverables will be reviewed by FDEP to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Firm Name Position Classification Hourly Rate Hours Total Fixed Price
Cost
WSP
Associate Engineer;
Geologist; Scientist;
Planner; Project Manager
$206.42 8 $1,651.36
WSP
Senior Engineer, Geologist, Scientist, Project Manager
$164.23 12 $1,970.76
WSP
Project Engineer, Geologist, Scientist, Project Manager
$123.00 40 $4,920.00
WSP Senior CADD $133.89 24 $3,213.36
WSP Project Coordinator $75.32 4 $301.28
Fixed Price Total Cost $12,056.76
Total for Task 2: $12,056.76
Task 3: Design
Task 3A: 30% Schematic Design
Description: WSP will review applicable building codes, floodplain regulations, local zoning regulations, land use, and development codes.
WSP will prepare the 30% Schematic Design Drawings for the proposed restoration. 30% Schematic Design Drawings will be formatted to FDEP standards and are anticipated to include the following sheets: Cover, Existing Conditions (Surveys), and Proposed Site Plan.
Deliverable: Electronic transmission containing 30% Schematic Design.
Performance Measure: Deliverables will be reviewed by FDEP to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Firm Name Position Classification Hourly Rate Hours Total Fixed Price
Cost
WSP Senior CADD $133.89 24 $3,213.36
WSP
Project Engineer, Geologist, Scientist, Project Manager
$123.00 36 $4,428
WSP Project Coordinator $75.32 2 $150.64
WSP
Senior Engineer, Geologist, Scientist, Project Manager
$164.23 6 $985.38
WSP
Associate Engineer;
Geologist; Scientist;
Planner; Project Manager
$206.42 8 $1,651.36
Fixed Price Total Cost $10,428.74
Total for Task 3A: $10,428.74
Task 3B: 60% Development Documents
Description: Following the FDEP review of the 30% Schematic Design Drawings, WSP will prepare 60% Development Document Drawings for the proposed improvements. The 60% Development Document Drawings will include the plans noted in 30% Schematic Design Drawings along with a grading plan and design details.
Deliverable: Electronic transmission containing 60% Development Document Drawing and Opinion of Probable Construction Costs Files (PDF).
Performance Measure: Deliverables will be reviewed by FDEP to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Firm Name
Position Classification Hourly Rate
Hours Total Fixed Price Cost
WSP Senior CADD $133.89 24 $3,213.36
WSP Project Engineer, Geologist, Scientist, Project Manager
$123.00 24 $2,952
WSP Senior Engineer, Geologist, Scientist, Project Manager
$164.23 6 $985.38
WSP
Associate Engineer;
Geologist; Scientist; Planner;
Project Manager
$206.42 6 $1,238.52
WSP Project Coordinator $75.32 2 $150.64
Fixed Price Total Cost $8,539.90
Total for subtask 3B: $8,539.90
Task 3C: 100% Construction Documents
Description: Following the Department review of the Development Documents and incorporation of any agency comments during permitting, WSP will prepare 100% Construction Document Plans for the proposed improvements.
Deliverable: Electronic transmission containing 100% Construction Document Plans in PDF (signed and sealed), and Construction (100%) Document Opinion of Probable Construction Costs in pdf.
Performance Measure: Deliverables will be reviewed by the FDEP to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
WSP Senior CADD $133.89 12 $1,606.68
WSP Project Engineer, Geologist, Scientist, Project Manager
$123.00 12 $1,476
WSP Senior Engineer, Geologist, Scientist, Project Manager
$164.23 4 $656.92
WSP
Associate Engineer;
Geologist; Scientist; Planner;
Project Manager
$206.42 4 $825.68
WSP Project Coordinator $75.32 2 $150.64
Fixed Price Total Cost $4,715.92
Total for Task 3C: $4,715.92
Task 4: Permitting
Description: WSP will prepare and submit permit applications using the 60% Design Documents to the South Florida Water Management District, Department of Army Corps of Engineers, Florida Fish and Wildlife Conservation Commission (if needed), and the Florida Keys National Marine Sanctuary (if needed).
WSP will apply for the permits cited above on behalf of FDEP as well as respond to Requests for Additional Information (RAI) from each agency.
Any permit and / or mitigation fees will be paid by FDEP.
Deliverable: WSP will submit the electronic permit package to FDEP for review and signature prior to submitting to the appropriate agencies. WSP will provide electronic copies of the permits to
FDEP.
Performance Measure: Deliverables will be reviewed by the FDEP to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Firm Name Position Classification Hourly
Rate Hours Total Fixed Price Cost
WSP Senior CADD $133.89 8 $1,071.12
WSP Project Engineer, Geologist, Scientist, Project Manager
$123.00 36 $4,428.00
WSP Senior Engineer, Geologist, Scientist, Project Manager
$164.23 12 $1,970.76
WSP
Associate Engineer; Geologist;
Scientist; Planner; Project Manager
$206.42 6 $1,238.52
WSP Senior Inspector 95.99 16 $1,535.84
WSP Project Coordinator $75.32 4 $301.28
Fixed Price Total Cost $10,545.52
Total for Task 4: $10,545.52
Project Schedule
The below project schedule assumes a project start date of May 21, 2023.
ACTIVITY DURATION
Task 1: Data Compilation and Feasibility Analysis
4 weeks
Task 2: Restoration and Mitigation Plan 4 weeks
Task 3A: 30% Schematic Design 4 weeks
Task 3B: 60% Development Documents 6 weeks
Task 3C: 100% Construction Documents 2 weeks
Task 4: Permitting 36 weeks
Summary of Fees
TASK TASK FIXED PRICE COST TASK REIMBURSABLE
Task 1: Data Compilation and Feasibility Analysis
$12,557.04 $1,667.00
Task 2: Restoration and Mitigation Plan
$12,056.76
Task 3A: 30% Schematic Design $10,428.74 Task 3B: 60% Development Documents
$8,539.90
Task 3C: 100% Construction Documents
$4,715.92
Task 4: Permitting $10,545.52 Total Fixed Price Cost: $58,843.88
Total Reimbursable Cost: $1,667.00 Overall Total Cost: $60,510.88
Payment will be made upon approval of deliverables for each task by the FDEP in the amount specified.