This is a Task Assignment Notification Form and detailed scope of work issued by the Florida Department of Environmental Protection (FDEP) under indefinite delivery contract CN204. The contract engages Wood Environment & Infrastructure Solutions, Inc. to perform professional services at Collier-Seminole State Park. The FDEP Division of Recreation and Parks is the owner agency, with Chris Becker serving as project manager and Jack Brady as contract manager.
The scope of work comprises five tasks valued at $25,149.47 total ($24,061.87 fixed price plus $1,087.60 reimbursable costs): (1) project planning including site reconnaissance and scope of work development ($2,690.27); (2) monitoring equipment procurement of eight LT leveloggers, three LTC leveloggers, one barologger, and related materials ($10,133.19); (3) well drilling oversight and equipment installation at up to eleven monitoring well locations ($6,500.95); (4) ground survey with certified position and elevation data ($5,111.86); and (5) project management and client communications ($713.20). All costs are on a lump-sum fixed-price basis except for reimbursable mileage, lodging, and meal per diem. The project schedule runs from May 20, 2020 through July 31, 2020, contingent on completion prior to the wet season, with payment due upon FDEP approval of deliverables for each subtask. The contract includes COVID-19 provisions allowing schedule adjustments and equitable price adjustments for documented cost increases resulting from pandemic-related disruptions.
View the file
Other files
Show 40 more
Latest 50 of 116 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Wood Environment & Infrastructure Solutions, Inc.
1101 Channelside Drive, Suite 200
Tampa, FL 33602
T: 813-289-0750 www.woodplc.com
‘Wood’ is a trading name for John Wood Group PLC and its subsidiaries
May 14, 2020
Matthew Kruse
Park Manager
Florida Department of Environmental Protection
Division of Recreation and Parks
20200 Tamiami Trail E.
Naples, Florida 34114
RE: DEP Agreement Number CN204
TA33 – Collier-Seminole Monitoring Well Installation Services
Wood Project No. 600639.2
Dear Mr. Kruse:
For your consideration, Wood Environment & Infrastructure Solutions, Inc. (Wood) has provided a proposal summary and labor documentation for the tasks identified below. The following tasks will be performed in accordance with DEP Agreement Number CN204 and will be completed on a lump sum basis:
• Project Planning
• Monitoring Equipment Procurement
• Well Drilling Oversight and Monitoring Equipment Installation
• Survey
• Project Management
Thank you and please contact the undersigned with any questions.
Sincerely, Wood Environment & Infrastructure Solutions, Inc.
Kristen Nowak Michael D. Phelps, PE
Project Manager Office Manager
KN/CS/CM/MP: jrb
Attachment – Equipment Table
Collier-Seminole Monitoring Well Installation Services
DEP Agreement Number CN204, Task Assignment Number 33
TASK 1: PROJECT PLANNING
Description: Wood will provide project planning services for the installation of up to 11 monitoring wells within Collier-Seminole State Park (SP). As part of this task, Wood will conduct a one-day field reconnaissance to see the 11 proposed well locations. Wood assumes a state park employee will provide access to the various well locations and/or accompany Wood staff to these locations. A hand auger boring will be conducted at each location to determine the depth to refusal/rock. If rock is encountered within less than 10 feet below ground surface, FDEP will have to hire a well driller to complete the monitoring well installation under separate contract. To that end, Wood will prepare a scope of work (SOW) that FDEP can use to bid the project. The SOW will include a map with well locations, desired well dimensions (depth, diameter, screen interval), and a list of components the driller will be responsible for such as obtaining appropriate well installation permit from Collier County and the completion of a well installation report for each monitoring well. Based on the accessibility of each proposed well location, which will be determined during the field visit, special drill rig equipment may be required (such as tracks) and will also be a part of the SOW. Prior to the field visit, Wood will prepare a Health and Safety Plan
(HASP).
Deliverable: The deliverable will include a Scope of Work in pdf format to be emailed to the
Collier-Seminole SP park manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 1
Firm Name Position Classification Hourly
Rate Hours
Total Fixed
Price Cost
Wood Project Engineer, Geologist, Scientist, Project Manager
$123.00 3 $369.00
Wood Technician $72.00 6 $432.00
Wood Senior Technician $85.00 18 $1,530.00
Wood Project Admin $55.30 2 $110.60
Wood Senior Engineer, Geologist, Scientist, Project Manager
$157.00 1 $157.00
Fixed Price Total Cost $2,598.60
Reimbursable Cost:
Mileage (@ $0.445 per mile) $91.67 Wood Miami Office to Project Site (Roundtrip) = 206 miles
Reimbursable Total
Cost $91.67
➢ Total for Subtask 1: $2,690.27
TASK 2: MONITORING EQUIPMENT PROCUREMENT
Description: Wood will procure eight Solinst LT leveloggers for continuous water level monitoring, three Solinst LTC leveloggers for continuous water level and conductivity monitoring, one baralogger to adjust the loggers for barometric pressure, and additional equipment needed to install the loggers such as wire, hooks, and an optical reader.
Deliverable: The deliverable will include an email to the Collier-Seminole SP park manager confirming receipt of the well monitoring equipment with an invoice from the vendor.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 2
Firm Name Position Classification Hourly
Rate Hours
Total Fixed Price
Cost
Wood Project Engineer, Geologist, Scientist, Project Manager
$123.00 2 $246.00
Wood Senior Technician $85.00 2 $170.00
Wood Project Admin $55.30 2 $110.60
Wood LT Levelogger $598.00 8 $4,784.00
Wood LTC Levelogger $1,366.00 3 $4,098.00
Wood Barologger $319.00 1 $319.00
Wood Monitoring Equipment Materials (wire, hooks, optical reader) $343.00 1 $343.00
Wood Shipping Costs $62.59 1 $62.59
Fixed Price Total Cost $10,133.19
➢ Total for Subtask 2: $10,133.19
TASK 3: WELL DRILLING OVERSIGHT AND MONITORING EQUIPMENT INSTALLATION
Description: Wood will provide oversight during the drilling and installation of the monitoring wells. Upon completion of each well installation, Wood will develop the well (i.e. purge five to ten gallons of water using a submersible pump) and will install the monitoring equipment (i.e.
continuously recording logger). This task assumes five days for well installation and does not include driller fees, which will be bid under separate contract. Note that well installation should be conducted prior to or following the wet season for accessibility reasons.
Deliverable: The deliverable will include an email to the Collier-Seminole SP park manager confirming completion of the well installation and a photo of each well.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 3
Firm Name Position Classification Hourly
Rate Hours
Total Fixed
Price Cost
Wood Project Engineer, Geologist, Scientist, Project Manager
$123.00 4 $492.00
Wood Senior Technician $85.00 64 $5,440.00
Wood Project Admin $55.30 2 $110.60
Fixed Price Total Cost $6,042.60
Reimbursable Cost:
Mileage (@ $0.445 per mile) $458.35 Wood Miami Office to Project Site (Roundtrip) = 206 miles x 5 days
Reimbursable Total
Cost $458.35
➢ Total for Subtask 3: $6,500.95
TASK 4: SURVEY
Description: Wood will conduct a ground survey to obtain position and elevation data at each of the installed wells. Elevation data will include both top of casing (TOC) and ground surface elevations. Survey and mapping services and deliverables will be certified as meeting or exceeding, in quality and precision, the standards applicable for this work, as set forth in Chapter 472, F.S.
Horizontal Datum will be referenced to the Florida State Plan Coordinate System, West Zone
(0902), Units US Survey Feet, North American Datum of 1983 (NAD83/2011) Current Adjustment including the most recent NSRS adjustment. Vertical Datum will be referenced to the North
American Vertical Datum of 1988 (NAVD 88), Units US Survey Feet, using the most recent geoid model to compute orthometric heights based on GPS derived ellipsoid heights.
Deliverable: The deliverable will include a memorandum with a table summarizing the locations and elevations of each installed monitoring well in pdf format to be delivered to the Collier-
Seminole SP park manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 4
Firm Name Position Classification Hourly
Rate Hours
Total Fixed
Price Cost
Wood Project Engineer, Geologist, Scientist, Project Manager
$123.00 1 $123.00
Wood Survey Tech I $63.59 48 $3,052.32
Wood Survey Tech II $92.05 8 $736.40
Wood Prof. Surveyor/Manager $165.64 4 $662.56
Fixed Price Total Cost $4,574.28
Reimbursable Cost:
Mileage (@ $0.445 per mile)
$193.58 Wood Orlando Office to Project Site (Roundtrip) = 435 miles
Lodging $200.00 1 night per $100 x 2
Meals Per Diem $144.00 2 staff x 2 days x $36
Reimbursable Total
Cost $537.58
➢ Total for Subtask 4: $5,111.86
TASK 5: PROJECT MANAGEMENT
Description: Wood will provide FDEP with project management services including client communications, preparation of project updates, quality assurance/quality control, and invoicing.
Deliverable: The deliverable will include biweekly status update emails to be delivered to the
Collier-Seminole SP park manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 5
Firm Name Position Classification Hourly
Rate Hours
Total Fixed
Price Cost
Wood Project Engineer, Geologist, Scientist, Project Manager
$123.00 4 $492.00
Wood Project Admin $55.30 4 $221.20
Fixed Price Total Cost $713.20
➢ Total for Subtask 5: $713.20
Project Schedule:
Activity Commence Complete*
SubTask 1 5/20/2020 6/1/2020
SubTask 2 5/20/2020 6/20/2020
SubTask 3 6/15/2020 7/1/2020
SubTask 4 6/25/2020 7/31/2020
SubTask 5 5/20/2020 7/31/2020
*This schedule assumes monitoring well installation will occur prior to the wet season (July).
The schedule will need to be pushed into the next dry season (October 2020) if it cannot be completed during this timeframe.
Summary of Fees:
SubTask SubTask Fixed Price Cost SubTask Reimbursable
SubTask 1 $2,598.60 $91.67
SubTask 2 $10,133.19 $0.00
SubTask 3 $6,042.60 $458.35
SubTask 4 $4,574.28 $537.58
SubTask 5 $713.20 $0.00
Total Fixed Price Cost: $24,061.87
Total Reimbursable Cost: $1,087.60
Overall Total Cost: $25,149.47
Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.
COVID-19
Notwithstanding anything mentioned in this proposal, if Wood’s work is delayed, disrupted, suspended, or otherwise impacted as a direct or indirect result of COVID-19 (coronavirus), including, but not limited to, by (1) disruptions to material and/or equipment supply; (2) illness of
Wood’s or Subcontractors’ workforce and/or unavailability of labor; (3) government quarantines, closures, or other mandates, restrictions, and/or directives; (4) Wood's or Subcontractors’ restrictions and/or directives; and/or (5) fulfillment of Wood’s or Subcontractors’ contractual or legal health and safety obligations associated with COVID-19; then, Wood shall be entitled to a reasonable adjustment to the schedule and duration to account for such delays, disruptions, suspensions, and impacts.
To the extent the causes identified herein result in an increase in the price of labor, materials, or equipment used in the performance of these services, Wood may be entitled to a mutually-agreed upon equitable adjustment to the price for such increases, provided Wood presents documentation of such increases (including the original prices).
ATTACHMENT
Equipment Table
EQUIPMENT TABLE
DESCRIPTION UNIT
UNIT
RATE
EQUIPMENT
LT Levelogger Each $598.00
LTC Levelogger Each $1,366.00
Barologger Each $319.00
Monitoring Equipment Materials (wire, hooks, optical reader) Each $343.00
Shipping Costs Each $62.59