Task Assignment Change Order Summary

This document is a Task Assignment Change Order Form (Change Order No. 1) issued by the Florida Department of Environmental Protection (FDEP) for Statewide Contract CN202, Task Assignment 36. The agreement involves FDEP and consultant Michael Baker International, Inc. (MBI), with Jeffrey Whitfield serving as the FDEP Contract Manager and Donnie Bowles as the MBI Project Representative. The project concerns erosion control and access improvements at Wekiwa Springs State Park in Orange County, Florida. The change order was executed on March 4, 2022, with digital signatures from all required approving authorities including the FDEP Budget Representative, Project Manager, Contract Manager, Contract Authority, and the consultant.

This change order adds five new subtasks to the original task assignment signed October 14, 2021, to advance the design phase for erosion control and stabilization improvements at Wekiwa Springs State Park. The added services include: Subtask 2 (Site Survey - $19,515.50), Subtask 3 (Geotechnical Exploration - $4,103.06), Subtask 4 (Environmental Assessment/Data Collection - $2,268.23), Subtask 5 (60% Design Level Review - $14,721.20), and Subtask 6 (100% Design Level Review - $8,965.70). The net increase in task amount is $49,573.69, with no change in task duration (0 days), and the total task amount including all previous change orders is $64,631.89. Payment will be made upon FDEP approval of deliverables for each subtask. The project has an estimated completion duration of 92 calendar days, with subtasks to be performed concurrently where practical. All work is on a fixed-price basis with no reimbursable costs included.

View the file

Other files

File Type Posted
CN-370000-CN202-CMC4.pdf PDF
CN-370000-CN202-T10.pdf PDF
CN-370000-CN202-T12.pdf PDF
CN-370000-CN202-T13CO2.pdf PDF
CN-370000-CN202-T15.pdf PDF
CN-370000-CN202-T16.pdf PDF
CN-370000-CN202-T24.pdf PDF
CN-370000-CN202-T25.pdf PDF
CN-370000-CN202-T2CO2.pdf PDF
CN-370000-CN202-T30.pdf PDF
CN-370000-CN202-T31.pdf PDF
CN-370000-CN202-T32CO3.pdf PDF
CN-370000-CN202-T33CO2.pdf PDF
CN-370000-CN202-T36CO2.pdf PDF
CN-370000-CN202-T38.pdf PDF
CN-370000-CN202-T38CO2.pdf PDF
CN-370000-CN202-T40.pdf PDF
CN-370000-CN202-T44CO1.pdf PDF
CN-370000-CN202-T45CO4.pdf PDF
CN-370000-CN202-T8CO4.pdf PDF
CN-370000-CN202-T8CO6.pdf PDF
CN-370000-CN202-TA14CO3.pdf PDF
CN-370000-CN202-TA17CO2.pdf PDF
CN-370000-CN202-TA2.pdf PDF
CN-370000-CN202-TA20CO1.pdf PDF
CN-370000-CN202-TA21.pdf PDF
CN-370000-CN202-TA22.pdf PDF
CN-370000-CN202-TA28 CO3.pdf PDF
CN-370000-CN202-TA7.pdf PDF
CN-370000-CN202-CMC2.pdf PDF
CN-370000-CN202-T10CO1.pdf PDF
CN-370000-CN202-T11.pdf PDF
CN-370000-CN202-T11.pdf.crdownload CRDOWNLOAD file
CN-370000-CN202-T13.pdf PDF
CN-370000-CN202-T14.pdf PDF
CN-370000-CN202-T14CO1.pdf PDF
CN-370000-CN202-T14CO2.pdf PDF
CN-370000-CN202-T17CO1.pdf PDF
CN-370000-CN202-T19.pdf PDF
CN-370000-CN202-T1CO1.pdf PDF
CN-370000-CN202-T20.pdf PDF
CN-370000-CN202-T20CO2.pdf PDF
CN-370000-CN202-T20CO4.pdf PDF
CN-370000-CN202-T26.pdf PDF
CN-370000-CN202-T28CO1.pdf PDF
CN-370000-CN202-T31CO1.pdf PDF
CN-370000-CN202-T32CO4.pdf PDF
CN-370000-CN202-T33.pdf PDF
CN-370000-CN202-T34.pdf PDF
CN-370000-CN202-T34CO1.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT CHANGE ORDER FORM

(Revised 9-26-2018) Page 1 of 1

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description and Justification of Change:

Change in Task Amount:

Item Reimbursement Fixed Fee Total

Original Task Amount:

Task amount including all previous Change Orders:

Net increase/decrease in task amount for this Change Order:

Total Amounts with all Change Orders:

Change in Task Time:

Original Task Execution Date:

Original Task End Date:

Present Task End Date:

Net Change in Days:

New Task End Date:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 Digit FLAIR Code: Total:

CN202 36 1 61378C

Wekiwa Springs State Park Erosion Control/Access

Michael Baker International, Inc.

Donnie Bowles 904-380-2508 donnie.bowles@mbakerintl.com

Jeffrey Whitfield 850-245-2630 jeffrey.whitfield@floridadep.gov

Change to add development of storm water runoff control and construction documents to original task.

$ 15,058.20 $ 15,058.20 $ 15,058.20 $ 15,058.20 $ 49,573.69 $ 49,573.69

$ 0.00 $ 64,631.89 $ 64,631.89

10/14/2021

2/25/23

2/25/23

2/25/23

Diane Langston A Diane Langston Digitally signed by A Diane Langston Date: 2022.03.03 14:08:16 -05'00'

Andrew Lippens Andrew Lippens Digitally signed by Andrew Lippens Date: 2022.03.03 14:16:11 -05'00'

Jeffrey Whitfield Jeffrey Whitfield Digitally signed by Jeffrey Whitfield Date: 2022.03.03 15:07:29 -05'00'

Jeff Roberts Jeff Roberts Digitally signed by Jeff Roberts Date: 2022.03.04 09:19:25 -05'00'

Michael W. Foster Jr., P.E. Michael W. Foster Jr., P.E.

Digitally signed by Michael W.

Foster Jr., P.E.

Date: 2022.03.04 15:55:37 -05'00'

61378C 37503006080 080039/22 423001 U3200 131500 QK $ 49,573.69

$ 49,573.69

February 25, 2022

Andrew Lippens

Project Manager

Bureau of Design and Construction

Florida Department of Environmental Protection

3900 Commonwealth Boulevard 260K, MS 520

Tallahassee, FL 32399

RE: Statewide Contract: CN202, Task Assignment 36, Change Order 1

Wekiwa Springs Erosion Control & Access, Orange County, FL

Dear Mr. Lippens:

For your review, Michael Baker International, Inc., is attaching change order proposal summary and man-hour documentation for amending the current task assignment to include Survey, Geotechnical exploration and design plans supporting approved Concept Plan 1 from Subtask 1.

Please review the attached Proposal Summary and deliverables and let me know if there are any questions or comments.

Sincerely, Donnie Bowles

Project Manager

Wekiwa Springs State Park – Site Grading Improvements

Wekiwa Springs, Apopka, FL

Statewide Contract CN202, Task Assignment 36, Change Order 1

This Change Order #1 adds in additional scope and subtasks to the original task assignment signed

10/14/2021.

Project Objective: Under the original contract, Michael Baker completed (3) Conceptual Plans for grading improvements at the Wekiwa Springs State Park is in Orange County, Florida. Conceptual Plan

Option 1 was selected as the path forward for improvements at the park.

This change order will proceed with final design for erosion control and stabilization improvements at the park. This change order includes Survey, Geotechnical, Environmental and Civil Engineering services.

The project will be completed with the addition of 5 subtasks outlined below. It is understood with this project being improvements of areas already in use and no significant addition of impervious areas being added, Michael Baker anticipates no municipal permitting and a SJRWMD permit exemption will be issued. The subtasks outlined below will be amended into the current contract to complete the design phase for the Erosion Control and Stabilization Improvements.

• Subtask 2 – Site Survey

• Subtask 3 – Geotechnical Exploration

• Subtask 4 – Environmental Assessment/Data Collection

• Subtask 5 – 60% Design Level Review

• Subtask 6 – Final Design Plans

General Project understandings, guidelines, and coordination was provided by Wekiwa Springs State

Park Services representatives and the FDEP project manager.

Subtask 2: Site Survey

George F Young, Inc. (GFY Inc.) will perform a full topographical survey, necessary for site and drainage/grading design of the existing spring area to the following limits:

• Set Horizontal and Vertical Control at the site

• Topographic Survey on a 25 to 50 foot grid, with all grade breaks

• Locate all visible features as indicated on the attachment

• Wetland Flags as delineated by Environmental Scientist

Assumptions:

• FDEP will provide access to the project area.

• Wetland delineation flags are located prior to survey crew arrival.

Deliverables:

• (6) copies of the survey, signed and sealed by a Professional Surveyor and Mapper, licensed by the

State of Florida.

• Electronic version of the survey in AutoCAD 2018 "DWG" transmitted by electronic means

Performance Measure: Final deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Subtask 2: Site Survey

Company Classification Rate Hours Cost

MBI Project Manager $238.84 3 $716.52

GFY Inc. Prof. Surveyor/Mgr. $147.80 15 $2,217.00

GFY Inc. Prof. Surveyor $119.30 9 $1,073.70

GFY Inc. 2 Man Survey Crew $109.48 92 $10,072.16

GFY Inc. CADD Technician $74.06 72 $5,332.32

GFY Inc. Clerical $51.90 2 $103.80

Totals (Subtask 2) 193 $19,515.50

Subtask 3: Geotechnical Exploration

PSI Intertek will perform necessary geotechnical investigations required for regrading and stabilization.

The following is part of the scope of services:

• Review readily available published geologic and topographic information. This published information will be obtained from the appropriate quadrangle map published by the United

States Geological Survey (USGS) and the “Soil Survey of Orange County, Florida” published by the United States Department of Agriculture (USDA) Soil Conservation Service (SCS).

• Execute a program of subsurface sampling and field testing. As requested, the following geotechnical exploration borings will be performed:

o Perform up to three (3) Hand Auger (HA) borings to maximum depths of five feet or to depths at which hand auger refusal is experienced whichever condition is achieved first.

o Boring locations shall be located in the field using recreational-grade GPS equipment in locations determined to be accessible for performing the hand auger borings. In the event borings are found to be inaccessible or blocked due to underground utilities, they will be offset to the nearest accessible location.

• Visually classify and stratify representative soil samples in the laboratory using the Unified Soil

Classification System (USCS). Identify soil conditions at each boring location and form an opinion of the overall site soil stratigraphy.

• Collect groundwater level measurements in the borings and estimate seasonal high groundwater levels.

• Perform up to two (2) field tests to provide data regarding the infiltration rate of the soil within or near the areas labelled “Focus Area 1” and “Focus Area 2” on the provided site plan as requested. The exact nature of the testing program will be determined by site accessibility. We anticipate infiltration testing can be completed with Double-Ring Infiltrometer (DRI) testing.

• Prepare a brief geotechnical exploration data report for proposed site summarizing the information obtained from the field-testing program results and presenting the subsurface soil and groundwater conditions encountered.

Assumptions:

The proposed number of test borings and infiltration tests have been assumed based on the grading and stabilization improvements confirmed from the onsite scoping meeting conducted on August 8, 2021.

Deliverable:

PSI Intertek will provide a geotechnical exploration report in electronic (PDF) version.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Subtask 3: Geotechnical Exploration

Company Classification Rate Unit Qty Cost

Intertek PSI 0088 Ground Surface DRI $526.00 Each 2 $1,052.00

Intertek PSI 0104 Natural Moisture $12.00 Each 3 $36.00

Intertek PSI 0106 Single sieve Grain Analysis $35.00 Each 2 $70.00

Intertek PSI 0109 Plastic Limit $45.00 Each 1 $45.00

Intertek PSI 0110 Liquid Limit $45.00 Each 1 $45.00

Field and Lab Totals $1,248.00

MBI Project Manager $238.84 Hour 2 $477.68

Intertek PSI 0100 Truck/MB & 2-Person Crew $198.00 Hour 4 $792.00

Intertek PSI 0143 Chief Engineer $189.00 Hour 2 $378.00

Intertek PSI 0147 Engineer Intern $77.88 Hour 11 $856.68

Intertek PSI 0148 CADD $75.00 Hour 4 $300.00

Intertek PSI 0149 Clerical $50.70 Hour 1 $50.70

Labor Totals 24 $2,855.06

Totals (Subtask 3) $4,103.06

Subtask 4: Environmental Assessment/Data Collection

Michael Baker International (MBI) will collect and review the following data prior to conducting the field surveys for the project:

• National Resource Conservation Service soils data;

• St, Johns River Water Management District (SJRWMD) land use, cover, and forms classification system (FLUCFCS) data;

• National Wetland Inventory data;

• U.S. Fish and Wildlife Service (FWS) protected species data for Highlands County;

• Florida Natural Areas Inventory (FNAI) protected species tracking list for Highlands County; and,

• United States Geological Survey contour mapping.

MBI will collect the data from the agencies listed to confirm permit exemptions. Should a permit be required based on the findings and assessment, MBI will submit for approval a change order fee proposal to obtain any permits deemed required by governing agencies.

Deliverable:

Anticipated Environmental Permitting Summary Letter Report in report in electronic (PDF) version.

Assumptions:

1. If it is determined that special purpose protected species surveys are necessary, this will be provided under a separate agreement.

2. Protected species permitting and mitigation are not included.

3. Section 7 Consultation with the U.S. Fish and Wildlife Service is not included.

4. Wekiwa Springs is a water that is retained for USACE Section 404 jurisdiction and permitting authority.

5. If it is determined that SJRWMD Environmental Resource Permitting or USACE Section 404

Permitting is required, this would be provided under a separate agreement.

6. Wetland mitigation planning, if necessary, will be provided under a separate agreement.

7. Coordination with the State Historic Preservation Office is not included.

8. Discussion of potential for County permitting will not be included in the Anticipated Permitting

Summary Letter Report.

Subtask 4: Environmental Assessment/Data Collection

Company Classification Rate Hours Cost

MBI Project Manager $238.84 1 $238.84

MBI Environmental Scientist $106.81 19 $2,029.39

Totals (Subtask 4) 20 $2,268.23

Subtask 5: 60% Design Level Review

Michael Baker will provide design services based on the approved conceptual layout 1 from Subtask 1.

The design will also include the minor regrading and stabilization of the Canoe Launch, regrading at the concession area at the top of the canoe launch, minor regrading, and stabilization along the maintenance trail to the north and minor regrading between the spring and the parking lot. Design Plans produced shall include:

• Cover Sheet

• General Notes

• Existing Conditions and Demolition Plan

• Site Improvement Plan

• Site Grading Plan

• Construction Details

• Estimated Construction Cost

Main improvements at the spring will be per Conceptual Plan Option 1 that was selected by FDEP.

Stabilization products used for the final improvements shall be approved by FDEP prior to final design.

Deliverables:

• 60% Design Level Plans

• Estimated Construction Cost per Conceptual layout

Subtask 5: 60% Design Level Review

Company Classification Rate Hours Cost

MBI Project Manager $238.84 20 $4,776.80

MBI Senior Engineer $149.58 20 $2,991.60

MBI Designer $115.88 60 $6,952.80

Totals (Subtask 5) 100 $14,721.20

Subtask 6: Final Construction Plans

Based on FDEP review and Comments, Michael Baker will incorporate comments and design revisions.

Finalize the design and produce Final Construction Plans. Final Construction Plans produced shall include:

• Cover Sheet

• General Notes

• Existing Conditions and Demolition Plan

• Site Improvement Plan

• Site Grading Plan

• Construction Details

• Estimated Construction Cost

Final Construction Plans will be produced based on the original design intent and FDEP Review comments.

Deliverables:

• Digitally Signed and Sealed Construction Plans (PDF Format)

• Estimated Construction Cost

Subtask 6: 100% Design Level Review

Company Classification Rate Hours Cost

MBI Project Manager $238.84 15 $3,582.60

MBI Senior Engineer $149.58 5 $747.90

MBI Designer $115.88 40 $4,635.20

Totals (Subtask 6) 60 $8,965.70

Summary of Fees:

Subtask Subtask Fixed

Price Cost

Subtask

Reimbursable

Subtask 2: Site Survey $19,515.50 --

Subtask 3: Geotechnical Exploration $4,103.06 --

Subtask 4: Environmental

Assessment/Data Collection $2,268.23 --

Subtask 5: 60% Design Level Review $14,721.20 --

Subtask 6: 100% Design Level Review $8,965.70 --

Total Fixed Price Cost $49,573.69 --

Total Reimbursable Cost -- --

Overall Total Cost $49,573.69

Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.

Project Schedule:

Project Schedule is based on estimated duration of calendar days to complete each subtask. Schedule dates will be established after approved and executed contract has been received. Where most practical, subtasks will be worked on concurrently.

Activity

Subtask

Duration

(Calendar Days)

Subtask 2: Site Survey 21

Subtask 3: Geotechnical Exploration 14

Subtask 4: Environmental Assessment 7

Subtask 5: 60% Design Level Review 30

Subtask 6: 100% Design Level Review 20

Total Estimated Duration 92