Attachment 1 100 Percent Type B FAA-MMAC STB Annex Renovation Specifications.pdf

PDF 6 MB Posted

Attached to
STB Building Renovation at the Mike Monroney Aeronautical Center (MMAC) Solicitation
Solicitation number
6973GH-23-R-00096
Issued by

About this file

This document outlines a federal solicitation for construction project renovation services. The Federal Aviation Administration's Mike Monroney Aeronautical Center is seeking proposals to complete renovations to the STB Annex building in accordance with the attached specifications and drawings. This is a 100% 8(a) small business set-aside. The estimated price range for the contract is $1,000,000 to $5,000,000. Proposals are due by email only by the closing date specified in the solicitation. A mandatory pre-proposal site visit will be held on May 16, 2023; offerors must notify the contracting officer by May 12 if they plan to attend. The selected offeror will be expected to complete the STB building renovations at the MMAC facility.

View the file

Other files

File Type Posted
Attachment 25 STB Reno Q and A Log3 6.12.23.pdf PDF
Amendment 0006 6973GH-23-R-00096.pdf PDF
Attachment 24 Spec 26 51 00 INTERIOR LIGHTING Revised 06062023.pdf PDF
Attachment 22 Spec 23 04 00 COMMON REQUIREMENTS FOR HVAC Revised 06062023.pdf PDF
Attachment 23 Spec 26 05 00 BASIC REQUIREMENTS FOR ELECTRICAL SYSTEMS Revised 06062023.pdf PDF
Amendment 0005 6973GH-23-R-00096.pdf PDF
Attachment 15 08_71_00 USER-DOOR HARDWARE.pdf PDF
Attachment 20 STB Reno Q and A Log1 5.18.23.6.05.23.pdf PDF
Attachment 18 026A STB Annex ACM Photos.pdf PDF
Amendment 0004 6973GH-23-R-00096.pdf PDF
Attachment 19 STB Annex General Representative Work Areas.pdf PDF
Attachment 21 STB Reno Q and A Log2 5.18.23.6.05.23.pdf PDF
Attachment 17 026A STB Annex Asbestos Location Drawings.pdf PDF
Attachment 16 Addendum Drawings.pdf PDF
Amendment 0003 6973GH-23-R-00096.pdf PDF
Attachment 7 Past Performance Survey Revision 1.1 5.24.23.docx DOCX document
Amendment 0002 6973GH-23-R-00096.pdf PDF
Attachment 14 REISSUE-100 Percent Type B FAA-MMAC STB Annex Renovation Drawings.pdf PDF
Site Visit Attendee List 6973GH-23-R-00096 STB Annex Renovation.pdf PDF
Amendment 0001 6973GH-23-R-00096.pdf PDF
SIR 6973GH-23-R-00096.pdf PDF
Attachment 11 Wage Determination OK20230049 02.10.2023.pdf PDF
Attachment 10 Contractor Release.pdf PDF
Attachment 4 SF25 - Performance Bond.pdf PDF
Attachment 13 AMP400-ENV-OC-2.4.3-CC.pdf PDF
Attachment 7 Past Performance Survey.docx DOCX document
Attachment 2 100 Percent Type B FAA-MMAC STB Annex Renovation Drawings.pdf PDF
Attachment 5 SF25A Payment Bond.pdf PDF
Attachment 12 Chapter 33 Construction Safety.pdf PDF
Attachment 3 SOW 2018-006090 STB Annex Renovation 3.13.23.pdf PDF
Attachment 6 SF24 Bid Bond.pdf PDF
Attachment 8 Past Performance Experience Form.docx DOCX document
Attachment 9 Client Authorization Letter.docx DOCX document
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

xxx / FAA-MMAC STB Annex Renovation

00.01.01 - 1 100% SPECIFICATIONS

100% SPECIFICATIONS

FAA-MMC: STB Annex Renovation Work Order: 2018-006090 Oklahoma City, OK

00.01.07 - 1 SEAL AND SIGNATURE PAGE

SEAL AND SIGNATURE PAGE

ARCHITECT

(Sections denoted in the Table of Contents with the designation ARCH after the section name are prepared by the Architect)

The Small Group 108 South Broadway Edmond, OK 73034 Phone 405.840.1111 Fax 405.840.1191

Contact:

Thomas Small, AIA

ARCHITECT

MECH/PLUMBING ENGINEER

(Sections denoted in the Table of Contents with the designation MECH/PLUM after the section name are prepared by the Mechanical/Plumbing Engineer)

Alvine Engineering 1001 W, Wilshire Blvd., Suite 102

OKC, OK 73116

Phone 405.936.3480

Contact:

Edward Kongs, P.E.

MECH/PLUMBING

ELECTRICAL ENGINEER

(Sections denoted in the Table of Contents with the designation ELECT after the section name are prepared by the Electrical Engineer)

CEC

4555 W. Memorial Rd Oklahoma City, OK 73142 Phone 405.753.4200

Contact:

Julian Horner, P.E.

ELECTRICAL

11/22/2022

C.A. NO. 842

EXPIRES 30/JUNE/2024

10-25-22

11/26/2022

00.01.10 - 1 TABLE OF CONTENTS

TABLE OF CONTENTS

DIVISION 00 -- PROCUREMENT AND CONTRACTING REQUIREMENTS

00.01.07 - SEALS PAGE

00.01.10 - TABLE OF CONTENTS

SPECIFICATIONS

DIVISION 01 -- GENERAL REQUIREMENTS

01.10.00 - SUMMARY (ARCH)

01.20.00 - PRICE AND PAYMENT PROCEDURES (ARCH)

01.30.00 - ADMINISTRATIVE REQUIREMENTS (ARCH)

01.40.00 - QUALITY REQUIREMENTS (ARCH)

01.50.00 - TEMPORARY FACILITIES AND CONTROLS (ARCH)

01.60.00 - PRODUCT REQUIREMENTS (ARCH)

01.70.00 - EXECUTION AND CLOSEOUT REQUIREMENTS (ARCH)

01.74.19 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL (ARCH)

01.78.00 - CLOSEOUT SUBMITTALS (ARCH)

DIVISION 02 -- EXISTING CONDITIONS

02.41.00 - DEMOLITION (ARCH)

DIVISION 05 -- METALS

05.52.13 - PIPE AND TUBE RAILINGS (ARCH)

DIVISION 06 -- WOOD, PLASTICS, AND COMPOSITES

06.10.00 - ROUGH CARPENTRY (ARCH)

DIVISION 08 -- OPENINGS

08.11.13 - HOLLOW METAL DOORS AND FRAMES (ARCH)

08.14.16 - FLUSH WOOD DOORS (ARCH)

08.43.13 - ALUMINUM-FRAMED STOREFRONTS (ARCH)

08.71.00 - DOOR HARDWARE (ARCH)

08.80.00 - GLAZING (ARCH)

DIVISION 09 -- FINISHES

09.21.16 - GYPSUM BOARD ASSEMBLIES (ARCH)

09.30.00 - TILING (ARCH)

09.51.00 - ACOUSTICAL CEILINGS (ARCH)

09.65.00 - RESILIENT FLOORING (ARCH)

09.68.13 - TILE CARPETING

09.91.23 - INTERIOR PAINTING (ARCH)

DIVISION 10 -- SPECIALTIES

10.14.00 - SIGNAGE (ARCH)

10.21.13.13 - METAL TOILET COMPARTMENTS (ARCH)

10.28.00 - TOILET, BATH, AND LAUNDRY ACCESSORIES (ARCH)

DIVISION 12 -- FURNISHINGS

12.36.00 - COUNTERTOPS (ARCH)

00.01.10 - 2 TABLE OF CONTENTS

DIVISION 14 -- CONVEYING EQUIPMENT

14.24.13 - HYDRAULIC FREIGHT ELEVATORS (ARCH)

DIVISION 21 -- FIRE SUPPRESSION

21.05.00 - COMMON REQUIREMENTS FOR FIRE SUPPRESSION (MECH/PLUMB)

21.05.00 - COMMON WORK RESULTS FOR FIRE SUPPRESSION (MECH/PLUMB)

21.13.00 - FIRE-SUPPRESSION SPRINKLER SYSTEMS (MECH/PLUMB)

DIVISION 22 -- PLUMBING

22.04.00 - COMMON REQUIREMENTS FOR PLUMBING (MECH/PLUMB)

22.05.53 - IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT (MECH/PLUMB)

22.07.19 - PLUMBING PIPING INSULATION (MECH/PLUMB)

22.10.05 - PLUMBING PIPING (MECH/PLUMB)

22.10.06 - PLUMBING PIPING SPECIALTIES (MECH/PLUMB)

22.30.00 - PLUMBING EQUIPMENT (MECH/PLUMB)

22.40.00 - PLUMBING FIXTURES (MECH/PLUMB)

DIVISION 23 -- HEATING, VENTILATING, AND AIR-CONDITIONING (HVAC)

23.04.00 - COMMON REQUIREMENTS FOR HVAC (MECH/PLUMB)

23.05.19 - METERS AND GAUGES FOR HVAC PIPING (MECH/PLUMB)

23.05.23 - GENERAL-DUTY VALVES FOR HVAC PIPING (MECH/PLUMB)

23.05.53 - IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT (MECH/PLUMB)

23.05.93 - TESTING, ADJUSTING, AND BALANCING FOR HVAC (MECH/PLUMB)

23.07.13 - DUCT INSULATION (MECH/PLUMB)

23.07.19 - HVAC PIPING INSULATION (MECH/PLUMB)

23.09.13 - INSTRUMENTATION AND CONTROL DEVICES FOR HVAC (MECH/PLUMB)

23.09.23 - DIRECT-DIGITAL CONTROL SYSTEM FOR HVAC (MECH/PLUMB)

23.09.93 - SEQUENCE OF OPERATIONS FOR HVAC CONTROLS (MECH/PLUMB)

23.21.13 - HYDRONIC PIPING (MECH/PLUMB)

23.21.14 - HYDRONIC SPECIALTIES (MECH/PLUMB)

23.31.00 - HVAC DUCTS AND CASINGS (MECH/PLUMB)

23.33.00 - AIR DUCT ACCESSORIES (MECH/PLUMB)

23.36.00 - AIR TERMINAL UNITS (MECH/PLUMB)

23.73.23 - CUSTOM CENTRAL-STATION AIR-HANDLING UNITS (MECH/PLUMB)

23.81.26 - SMALL-CAPACITY SPLIT-SYSTEM AIR CONDITIONERS (MECH/PLUMB)

23.82.00 - CONVECTION HEATING AND COOLING UNITS (MECH/PLUMB)

DIVISION 26 -- ELECTRICAL

26.05.00 - BASIC REQUIREMENTS FOR ELECTRICAL SYSTEMS (ELECT)

26.05.03 - DEMOLITION OF ELECTRICAL SYSTEMS (ELECT)

26.05.06 - TEMPORARY ELECTRICAL FACILITIES (ELECT)

26.05.19 - LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES (ELECT)

26.05.26 - GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS (ELECT)

26.05.33 - RACEWAY FOR ELECTRICAL SYSTEMS (ELECT)

26.05.33.16 - BOXES FOR ELECTRICAL SYSTEMS (ELECT)

00.01.10 - 3 TABLE OF CONTENTS

26 05.34 - CONDUIT (ELECT)

26.05.53 - IDENTIFICATION FOR ELECTRICAL SYSTEMS (ELECT)

26.05.73 - SHORT CIRCUIT AND PROTECTIVE DEVICE COORDINATION STUDY (ELECT)

26.09.23 - LIGHTING CONTROL DEVICES (ELECT)

26.22.13 - TRANSFORMERS (ELECT)

26.24.13 - SWITCHBOARDS (ELECT)

26.24.16 - PANELBOARDS (ELECT)

26.27.26 - WIRING DEVICES (ELECT)

26.28.16 - ENCLOSED SWITCHES (ELECT)

26.29.13 - ENCLOSED CONTROLLERS (ELECT)

26.43.00 - SURGE PROTECTIVE DEVICES (ELECT)

26.51.00 - INTERIOR LIGHTING (ELECT)

DIVISION 27 -- COMMUNICATIONS

27.00.00 - DIVISION 27 TELECOMMUNICATIONS STANDARDS FOR THE MMAC

27.51.16 - PUBLIC ADDRESS SYSTEMS (ELECT)

DIVISION 28 -- ELECTRONIC SAFETY AND SECURITY

28 16.00 - SECURITY SYSTEM (ELECT)

28 31.00 - FIRE DETECTION AND ALARM (ELECT)

END OF SECTION

01.10.00 - 1 SUMMARY

SECTION 01.10.00

SUMMARY

PART 1 GENERAL

1.01 PROJECT

A. Project Name: FAA-MMC: STB Annex Renovation.

B. Owner's Name: FAA.

C. Architect's Name: Small Architects.

D. The Project consists of the alteration of of an existing building that includes accessibility upgrades to the existing building entries, stair guardrail/handrails, and restrooms, as well as a freight elevator replacement, finish upgrades, and electrical and mechanical upgrades.

E. Contractor to develop detailed construction plan with phasing so the simulator bay is down only the minimal amount of time. Simulator down time to be scheduled in July 2024 only so AHU replacement must be done within that month timeframe. The user will relocate occupants in the rest of the building as needed during construction.

1. Prior to shutting down the AHU for replacement, all temporary power and cooling must be in place and functioning for the simulator bay per the mechancial and electrical drawings.

Temporary cooling shall be verified and balanced prior to use. Temporary cooling must be provided for the simulator bay at all times during AHU shutdown and replacement. All AHU replacement components must be on site prior to the AHU shutdown.

2. Verify with the FAA the temporary system is complete and ready for shutdown

3. Take AHU offline, hydronic ally, and electrically isolated.

4. AHU to be down a maximum of 4 weeks for replacement.

F. Concurrently with the AHU replacement the follwoing work may be done.

1. Demolition of the existing bathrooms on two floors. Due to the waste and vent risers being relocated the four restrooms being renovated will not be able to be active during the renovation. Users in the similator bay will have to use restrooms in the main building.

2. Replacement of the storm water sump pump (GC to coordinate with the weather forcast.)

3. Replacement of fire protection heads in rooms noted on drawings.

4. Replacement of Variable Air Volume Terminals.

G. GC to test and balance new AHU to verify automatic controls operation of new air handling unit is functioning properly.

H. GC to test and balance new Variable Air Volume Terminals. Verify automatic controls operation of new Variable Air Volume Terminals.

I. Temporary cooling and power may be removed from simulator bay when all new HVAC is functioning properly.

J. Refer to Electrical Design Narrative and drawings for phasing requipments for equiment change over.

K. Architectural finish work can be done at any time as determined by the contract within the project timeframe as long as the user requirements listed under section 104 of this specification are met.

1.02 WORK DESCRIPTION

A. Work Location: Federal Aviation Administration Mike Monrony Aeronautical Center.

B. Completion of Work: The contractor shall be required to (a) commence work under this contract within the designated calendar days after the date the contractor receives the Notice to Proceed, (b) execute the Work diligently, and (c) complete the entire Work ready for occupancy and use no later than 210 days after the Notice to Proceed.

C. NO WORK CAN COMMENCE ON SITE UNTIL ALL NEW MATERIALS/EQUIPMENT ARE ON

SITE OR PURCHASED AND LOCALLY STORED.

01.10.00 - 2 SUMMARY

D. Work includes: All labor, materials, and equipment neccessary to renovate the building as indicated on the contract documents.

E. All work on OCAT Facilities must comply with all Federal, State, and City laws, codes, regulations, ordinances, and standards.

F. Contractor must obtain any licenses or permits required to accomplish the work.

G. Any natural gas work performed upstream of the regulator must be performed by an OQ qualified contractor under the OCAT/MMAC Operator Qualification Plan.

H. Any Medium Voltage work must be performed by the OCAT approved contractor.

I. The MMAC is on OCAT leased land and adjacent to runways. Airway clearance is required by registering objects over 27' high. The contractor shall perform the survey for crane use and obtain approval from the director of Airport Operations. A survey is required at the conclusion of the project to register a new building, light poles, and constructed objects over 27' high. Allow 45 days for airway clearance to be obtained.

J. General contractor is to maintain existing roof warranties at all times.

K. All Structural modifications, change, or additions to plumbing and or other utilities must have

Director of Airports approval. Any penetration thru the roof is considered a structural change.

L. Scope of alterations work is indicated on drawings.

1.03 OWNER OCCUPANCY

A. Owner intends to continue to occupy portions of the existing building during the entire construction period. The work includes demolition of a portion of the existing exterior wall at the modified entries. The Contractor is responsible to make sure each day's work is completely weather-tight and secure at the close of the work day.

B. Cooperate with Owner to minimize conflict and to facilitate Owner's operations.

C. Work Sequence: Contractor shall submit a detailed construction phasing schedule describing when each phase of constrution is scheduled.

1.04 CONTRACTOR USE OF SITE AND PREMISES

A. Provide access to and from site as required by law and by Owner:

1. Emergency Building Exits During Construction: Keep all exits required by code open during construction period; provide temporary exit signs if exit routes are temporarily altered.

2. Contractor to provide accessible and safe path for users from exterior building entrance to Room 102 at all times during construction. Work after hours and on weekends may be required to accommodate this.

3. Contractor to provide accessible and safe path for users from exterior building entrance to Room 108B at all times during construction. It is acceptable to have user enter room 108B from Room 102.

4. Contractor to provide accessible and safe path for users from exterior building entrance to Room 116 at all times during construction. Work after hours and weekends may be required to accommodate this. Room 116 is to be operational at all times during construction.

5. Do not obstruct roadways, sidewalks, or other public ways without permit.

B. Security Requirements: Contractor shall comply with all applicable Department of

Transportation (DOT), FAA, and MMAC security directives while performing Work of this Contract.

C. Time Restrictions: Work shall be conducted between 7:00 a.m. and 4:30 p.m. on normal government work days. No Work shall occur at night, or on Saturday's, Sundays, or designated government holidays unless approved by the Contracting Officer seven (7) days in advance.

1. Limit conduct of expecially noisy work including but not limited to jackhammering and cutting to after 3pm on weekdays or weekends as to not disrupt building occupants.

D. Existing building spaces may not be used for storage.

01.10.00 - 3 SUMMARY

E. Utility Outages and Shutdown: Coordinate with the Contracting Office and Project Manager at (405)954-7356. Outages affecting FAA Operations are required to be accomplished at night, or on Saturday's, Sunday's, or designated government holidays. Prior to any outage or shutdown, fourteen (14) working days notification must be made to coordinate scheduling of any Work to be performed during any hours.

1. Prevent accidental disruption of utility services to other facilities.

F. Hearing protection must be worn in Rooms B05 and B05A if the pump is running.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

01.20.00 - 1 PRICE AND PAYMENT

PROCEDURES

SECTION 01.20.00

PRICE AND PAYMENT PROCEDURES

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Procedures for preparation and submittal of applications for progress payments.

B. Documentation of changes in Contract Sum and Contract Time.

C. Change procedures.

D. Correlation of Contractor submittals based on changes.

E. Procedures for preparation and submittal of application for final payment.

1.02 SCHEDULE OF VALUES

A. Electronic media printout including equivalent information will be considered in lieu of standard form specified; submit draft to Architect for approval.

B. Forms filled out by hand will not be accepted.

C. Submit Schedule of Values in duplicate within 15 days after date of Owner-Contractor

Agreement.

D. Format: Utilize the Table of Contents of this Project Manual. Identify each line item with number and title of the specification section. Identify site mobilization.

1.03 APPLICATIONS FOR PROGRESS PAYMENTS

A. Payment Period: Submit at intervals stipulated in the Agreement.

B. Electronic media printout including equivalent information will be considered in lieu of standard form specified; submit sample to Architect for approval.

C. Forms filled out by hand will not be accepted.

D. Execute certification by signature of authorized officer.

E. Use data from approved Schedule of Values. Provide dollar value in each column for each line item for portion of work performed and for stored products.

F. List each authorized Change Order as a separate line item, listing Change Order number and dollar amount as for an original item of work.

G. Submit one electronic and hard copies if required by lender of each Application for Payment.

H. Include the following with the application:

1. Transmittal letter as specified for submittals in Section 01.30.00.

2. Construction progress schedule, revised and current as specified in Section 01.30.00.

3. Affidavits attesting to off-site stored products.

I. When Architect requires substantiating information, submit data justifying dollar amounts in question. Provide one copy of data with cover letter for each copy of submittal. Show application number and date, and line item by number and description.

1.04 MODIFICATION PROCEDURES

A. For minor changes not involving an adjustment to the Contract Sum or Contract Time, Architect will issue instructions directly to Contractor.

B. For other required changes, Architect will issue a document signed by Owner instructing

Contractor to proceed with the change, for subsequent inclusion in a Change Order.

1. The document will describe the required changes and will designate method of determining any change in Contract Sum or Contract Time.

2. Promptly execute the change.

C. For changes for which advance pricing is desired, Architect will issue a document that includes a detailed description of a proposed change with supplementary or revised drawings and specifications, a change in Contract Time for executing the change with a stipulation of any

01.20.00 - 2 PRICE AND PAYMENT

PROCEDURES

overtime work required and the period of time during which the requested price will be considered valid. Contractor shall prepare and submit a fixed price quotation within 14 days.

D. Contractor may propose a change by submitting a request for change to Architect, describing the proposed change and its full effect on the work, with a statement describing the reason for the change, and the effect on the Contract Sum and Contract Time with full documentation.

Document any requested substitutions in accordance with Section 01.60.00.

E. Computation of Change in Contract Amount: As specified in the Agreement and Conditions of the Contract.

1. For change requested by Architect for work falling under a fixed price contract, the amount will be based on Contractor's price quotation.

2. For change requested by Contractor, the amount will be based on the Contractor's request for a Change Order as approved by Architect.

3. For pre-determined unit prices and quantities, the amount will based on the fixed unit prices.

F. Substantiation of Costs: Provide full information required for evaluation.

1. On request, provide the following data:

a. Quantities of products, labor, and equipment.

b. Taxes, insurance, and bonds.

c. Overhead and profit.

d. Justification for any change in Contract Time.

e. Credit for deletions from Contract, similarly documented.

G. Execution of Change Orders: Architect will issue Change Orders for signatures of parties as provided in the Conditions of the Contract.

H. After execution of Change Order, promptly revise Schedule of Values and Application for Payment forms to record each authorized Change Order as a separate line item and adjust the Contract Sum.

I. Promptly revise progress schedules to reflect any change in Contract Time, revise sub-schedules to adjust times for other items of work affected by the change, and resubmit.

J. Promptly enter changes in Project Record Documents.

1.05 APPLICATION FOR FINAL PAYMENT

A. Prepare Application for Final Payment as specified for progress payments, identifying total adjusted Contract Sum, previous payments, and sum remaining due.

PART 2 PRODUCTS - NOT USED

01.30.00 - 1 ADMINISTRATIVE

REQUIREMENTS

SECTION 01.30.00

ADMINISTRATIVE REQUIREMENTS

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Preconstruction meeting.

B. Progress meetings.

C. Construction progress schedule.

D. Submittals for review, information, and project closeout.

E. Number of copies of submittals.

F. Requests for Interpretation (RFI) procedures.

G. Submittal procedures.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION

3.01 PRECONSTRUCTION MEETING

A. Owner/FAA will schedule a meeting after Notice of Award.

B. Attendance Required:

1. Owner/FAA.

2. Architect.

3. Contractor.

C. Agenda:

1. Distribution of Contract Documents.

2. Submission of list of subcontractors, list of products, schedule of values, and progress schedule.

3. Designation of personnel representing the parties to Contract, Owner/FAA and Architect.

4. Procedures and processing of field decisions, submittals, substitutions, applications for payments, proposal request, Change Orders, and Contract closeout procedures.

5. Scheduling.

D. Record minutes and distribute copies within two days after meeting to participants, with two copies to Architect, Owner/FAA, participants, and those affected by decisions made.

3.02 PROGRESS MEETINGS

A. Schedule and administer meetings throughout progress of the work at maximum bi-monthly intervals.

B. Make arrangements for meetings, prepare agenda with copies for participants, preside at meetings.

C. Attendance Required:

1. Contractor.

2. Owner/FAA.

3. Architect.

4. Contractor's superintendent.

5. Major subcontractors.

D. Agenda:

1. Review minutes of previous meetings.

2. Review of work progress.

3. Field observations, problems, and decisions.

4. Identification of problems that impede, or will impede, planned progress.

5. Review of submittals schedule and status of submittals.

6. Maintenance of progress schedule.

01.30.00 - 2 ADMINISTRATIVE

REQUIREMENTS

7. Corrective measures to regain projected schedules.

8. Planned progress during succeeding work period.

9. Maintenance of quality and work standards.

10. Effect of proposed changes on progress schedule and coordination.

11. Other business relating to work.

E. Record minutes and distribute copies within two days after meeting to participants, with copies to Architect, Owner, participants, and those affected by decisions made.

3.03 CONSTRUCTION PROGRESS SCHEDULE

A. If preliminary schedule requires revision after review, submit revised schedule within 10 days.

B. Within 10 days after joint review, submit complete schedule.

C. Submit updated schedule with each Application for Payment.

3.04 REQUESTS FOR INTERPRETATION (RFI)

A. Preparation: Prepare an RFI immediately upon discovery of a need for interpretation of

Contract Documents. Failure to submit a RFI in a timely manner is not a legitimate cause for claiming additional costs or delays in execution of the work.

1. Prepare a separate RFI for each specific item.

a. Review, coordinate, and comment on requests originating with subcontractors and/or materials suppliers.

B. Content: Include identifiers necessary for tracking the status of each RFI, and information necessary to provide an actionable response.

C. Attachments: Include sketches, coordination drawings, descriptions, photos, submittals, and other information necessary to substantiate the reason for the request.

D. Review Time: Architect will respond and return RFIs to Contractor within seven calendar days of receipt. For the purpose of establishing the start of the mandated response period, RFIs received after 12:00 noon will be considered as having been received on the following regular working day.

E. Responses: Content of answered RFIs will not constitute in any manner a directive or authorization to perform extra work or delay the project. If in Contractor's belief it is likely to lead to a change to Contract Sum or Contract Time, promptly issue a notice to this effect, and follow up with an appropriate Change Order request to Owner.

3.05 SUBMITTALS FOR REVIEW

A. When the following are specified in individual sections, submit them for review:

1. Product data.

2. Shop drawings.

3. Samples for selection.

4. Samples for verification.

5. Contractor Waste Management Plan prepared in accordance with FAA Contracting AMS

Clause 3.6.3-22, January 2020..

B. Samples will be reviewed for aesthetic, color, or finish selection.

3.06 SUBMITTALS FOR INFORMATION

A. When the following are specified in individual sections, submit them for information:

1. Design data.

2. Certificates.

3. Test reports.

4. Inspection reports.

5. Manufacturer's instructions.

6. Manufacturer's field reports.

7. Monthly Waste Management Reports.

8. Other types indicated.

01.30.00 - 3 ADMINISTRATIVE

REQUIREMENTS

3.07 SUBMITTALS FOR PROJECT CLOSEOUT

A. Submit Correction Punch List for Substantial Completion.

B. Submit Final Correction Punch List for Substantial Completion.

C. When the following are specified in individual sections, submit them at project closeout in compliance with requirements of Section 01.78.00 - Closeout Submittals:

1. Project record documents.

2. Operation and maintenance data.

3. Warranties.

4. Bonds.

5. Other types as indicated.

3.08 NUMBER OF COPIES OF SUBMITTALS

A. Electronic Documents: Submit one electronic copy in PDF format; an electronically-marked up file will be returned. Create PDFs at native size and right-side up; illegible files will be rejected.

B. Samples: Submit the number specified in individual specification sections; two of which will be retained - one by the Owner/FAA and the Architect.

1. Retained samples will not be returned to Contractor unless specifically so stated.

3.09 SUBMITTAL PROCEDURES

A. General Requirements:

1. Identify: Project; Contractor; subcontractor or supplier; pertinent drawing and detail number; and specification section number and article/paragraph, as appropriate on each copy.

2. Apply Contractor's stamp, signed or initialed certifying that review, approval, verification of products required, field dimensions, adjacent construction work, and coordination of information is in accordance with the requirements of the work and Contract Documents.

a. Submittals from sources other than the Contractor, or without Contractor's stamp will not be acknowledged, reviewed, or returned.

B. Transmit each submittal with approved form.

01.40.00 - 1 QUALITY REQUIREMENTS

SECTION 01.40.00

QUALITY REQUIREMENTS

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Submittals.

B. Testing and inspection agencies and services.

C. Control of installation.

D. Tolerances.

E. Defect Assessment.

1.02 SUBMITTALS

A. See Section 01.30.00 - Administrative Requirements, for submittal procedures.

B. Design Data: Submit for Owner/FAA and Architect's knowledge for the limited purpose of assessing conformance with information given and the design concept expressed in the contract documents, or for Owner's information.

C. Test Reports: After each test/inspection, promptly submit Electronic copies of report to Owner/FAA, the Architect and to Contractor.

1. Include:

a. Date issued.

b. Project title and number.

c. Name of inspector.

d. Date and time of sampling or inspection.

e. Identification of product and specifications section.

f. Location in the Project.

g. Type of test/inspection.

h. Date of test/inspection.

i. Results of test/inspection.

j. Compliance with Contract Documents.

k. When requested by Owner/FAA or Architect, provide interpretation of results.

2. Test report submittals are for Owner/FAA and Architect's knowledge for the limited purpose of assessing conformance with information given and the design concept expressed in the contract documents, or for Owner's information.

1.03 TESTING AND INSPECTION AGENCIES AND SERVICES

A. Contractor shall employ and pay for services of an independent testing agency to perform other specified testing.

B. Employment of agency in no way relieves Contractor of obligation to perform Work in accordance with requirements of Contract Documents.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION

3.01 CONTROL OF INSTALLATION

A. Monitor quality control over suppliers, manufacturers, products, services, site conditions, and workmanship, to produce work of specified quality.

B. Comply with manufacturers' instructions, including each step in sequence.

C. Should manufacturers' instructions conflict with Contract Documents, request clarification from

Owner/FAA before proceeding.

D. Comply with specified standards as minimum quality for the Work except where more stringent tolerances, codes, or specified requirements indicate higher standards or more precise workmanship.

01.40.00 - 2 QUALITY REQUIREMENTS

E. Have work performed by persons qualified to produce required and specified quality.

F. Verify that field measurements are as indicated on shop drawings or as instructed by the manufacturer.

G. Secure products in place with positive anchorage devices designed and sized to withstand stresses, vibration, physical distortion, and disfigurement.

3.02 TOLERANCES

A. Monitor fabrication and installation tolerance control of products to produce acceptable Work.

Do not permit tolerances to accumulate.

B. Comply with Manufacturer's tolerances. Should manufactures' tolerances conflict with Contract Documents, request clarification from the Owner/FAA before proceeding.

C. Adjust products to appropriate dimensions; position before securing products in place.

3.03 TESTING AND INSPECTION

A. Testing Agency Duties:

1. Provide qualified personnel at site. Cooperate with the Owner/FAA and Contractor in prerformance of services.

2. Perform specified sampling and testing of products in accordance with specified standards.

3. Ascertain compliance of materials and mixes with requirements of Contract Documents.

4. Promptly notify Owner/FAA and Contractor of observed irregularities or non-conformance of Work for Products.

5. Perform additional tests and inspedtions required by the Owner/FAA.

6. Submit reports of all tests/inspections specified.

B. Limits on Testing/Inspection Agency Authority:

1. Agency may not release, revoke, alter, or enlarge on requirements of Contract Documents.

2. Agency may not approve or accept any portion of the Work.

3. Agency may not assume any duties of Contractor.

4. Agency has no authority to stop the Work.

C. Contractor Responsibilities:

1. Deliver to agency at designated location, adequate samples of materials proposed to be used that require testing, along with proposed mix designs.

2. Cooperate with laboratory personnel, and provide access to the Work and to manufacturers' facilities.

3. Provide incidental labor and facilities:

a. To provide access to Work to be tested/inspected.

b. To obtain and handle samples at the site or at source of Products to be tested/inspected.

c. To facilitate tests/inspections.

d. To provide storage and curing of test samples.

4. Notify Owner/FAA and laboratory 24 hours prior to expected time for operations requiring testing/inspection services.

5. Employ services of an independent qualified testing laboratory and pay for additional samples, tests, and inspections required by Contractor beyond specified requirements.

D. Re-testing required because of non-conformance to specified requirements shall be performed by the same testing agency on instructions by the Owner/FAA.

E. Re-testing required because of non-compliance with specified requirements shall be paid for by Contractor.

3.04 DEFECT ASSESSMENT

A. Replace Work or portions of the Work not complying with specified requirements.

01.40.00 - 3 QUALITY REQUIREMENTS

B. If, in the opinion of the Owner/FAA, it is not practical to remove and replace the work, the Contracting Officer will direct an appropriate remedy or adust payment.

01.50.00 - 1 TEMPORARY FACILITIES AND

CONTROLS

SECTION 01.50.00

TEMPORARY FACILITIES AND CONTROLS

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Temporary utilities.

B. Temporary telecommunications services.

C. Temporary sanitary facilities.

D. Temporary Controls: Barriers, enclosures, and fencing.

E. Security requirements.

F. Vehicular access and parking.

G. Waste removal facilities and services.

H. Field offices.

1.02 TEMPORARY UTILITIES

A. FAA shall provide and pay for all electrical power, lighting, water, heating and cooling, and ventilation required for construction purposes.

B. Use trigger-operated nozzles for water hoses, to avoid waste of water.

1.03 TELECOMMUNICATIONS SERVICES

A. Provide, maintain, and pay for telecommunications services to field office at time of project mobilization.

B. Telecommunications services shall include:

1. Windows-based personal computer dedicated to project telecommunications, with necessary software and laser printer.

2. Internet Connections: Minimum of one; DSL modem or faster.

3. Email: Account/address reserved for project use.

1.04 TEMPORARY SANITARY FACILITIES

A. Provide and maintain required facilities and enclosures. Provide at time of project mobilization.

B. Maintain daily in clean and sanitary condition.

1.05 BARRIERS

A. Provide barriers to prevent unauthorized entry to construction areas, to prevent access to areas that could be hazardous to workers or the public, to allow for owner's use of site and to protect existing facilities and adjacent properties from damage from construction operations and demolition.

B. Interior dust barriers must be installed at all times in areas of construction. NO DUST will be allowed into the Simulator Bay area. Temporary walls shall be installed with plastic and zippered openings to prevent dust from traveling. Contractor is responsible for all dust control.

C. Protect non-owned vehicular traffic, stored materials, site, and structures from damage.

1.06 FENCING

A. Provide 6 foot (1.8 m) high fence around construction site; equip with vehicular and pedestrian gates with locks.

1.07 SECURITY - SEE SECTION 01.35.53

A. Provide security and facilities to protect Work, existing facilities, and Owner's operations from unauthorized entry, vandalism, or theft.

1.08 VEHICULAR ACCESS AND PARKING

A. Comply with regulations relating to use of streets and sidewalks, access to emergency facilities, and access for emergency vehicles.

01.50.00 - 2 TEMPORARY FACILITIES AND

CONTROLS

B. Coordinate access and haul routes with governing authorities and Owner.

C. Provide and maintain access to fire hydrants, free of obstructions.

D. Provide means of removing mud from vehicle wheels before entering streets.

E. Provide temporary parking areas to accommodate construction personnel. When site space is not adequate, provide additional off-site parking.

1.09 WASTE REMOVAL

A. See Section 01.74.19 - Construction Waste Management and Disposal, for additional requirements.

B. Provide waste removal facilities and services as required to maintain the site in clean and orderly condition.

C. Provide containers with lids. Containers are to remain covered at all times when not actively in use. Remove trash from site periodically.

1.10 FIELD OFFICES

A. Office: Weathertight, with lighting, electrical outlets, heating, cooling equipment, and equipped with sturdy furniture, drawing rack, and drawing display table.

B. Provide space for Project meetings, with table and chairs to accommodate 6 persons.

C. Locate offices a minimum distance of 30 feet (10 m) from existing and new structures.

1.11 REMOVAL OF UTILITIES, FACILITIES, AND CONTROLS

A. Remove temporary utilities, equipment, facilities, materials, prior to Date of Substantial

Completion inspection.

B. Remove underground installations to a minimum depth of 2 feet (600 mm). Grade site as indicated.

C. Clean and repair damage caused by installation or use of temporary work.

PART 2 PRODUCTS - NOT USED

01.60.00 - 1 PRODUCT REQUIREMENTS

SECTION 01.60.00

PRODUCT REQUIREMENTS

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Re-use of existing products.

B. Transportation, handling, storage and protection.

C. Product option requirements.

D. Substitution limitations.

E. Procedures for Owner-supplied products.

1.02 RELATED REQUIREMENTS

A. Section 01.74.19 - Construction Waste Management and Disposal: Waste disposal requirements potentially affecting product selection, packaging and substitutions.

1.03 SUBMITTALS

A. Product Data Submittals: Submit manufacturer's standard published data. Mark each copy to identify applicable products, models, options, and other data. Supplement manufacturers' standard data to provide information specific to this Project.

B. All chemicals, lubricants, paints, solvents, sealants, adhesives, patching materials, cements, foam insulation and gypsum wall board and other materials that my potentially contain asbestos or other hazardous substances must have Material Safety Data Sheets (SDS) submitted prior to installation.

C. Shop Drawing Submittals: Prepared specifically for this Project; indicate utility and electrical characteristics, utility connection requirements, and location of utility outlets for service for functional equipment and appliances.

D. Sample Submittals: Illustrate functional and aesthetic characteristics of the product, with integral parts and attachment devices. Coordinate sample submittals for interfacing work.

1. For selection from standard finishes, submit samples of the full range of the manufacturer's standard colors, textures, and patterns.

PART 2 PRODUCTS

2.01 EXISTING PRODUCTS

A. Do not use materials and equipment removed from existing premises unless specifically required or permitted by Contract Documents.

B. Unforeseen historic items encountered remain the property of the Owner; notify Owner promptly upon discovery; protect, remove, handle, and store as directed by Owner.

C. Existing materials and equipment indicated to be removed, but not to be re-used, relocated, reinstalled, delivered to the Owner, or otherwise indicated as to remain the property of the Owner, become the property of the Contractor; remove from site.

2.02 NEW PRODUCTS

A. Provide new products unless specifically required or permitted by Contract Documents.

2.03 PRODUCT OPTIONS

A. Products Specified by Reference Standards or by Description Only: Use any product meeting those standards or description.

B. Products Specified by Naming One or More Manufacturers: Use a product of one of the manufacturers named and meeting specifications, no options or substitutions allowed.

C. Products Specified by Naming One or More Manufacturers with a Provision for Substitutions:

Submit a request for substitution for any manufacturer not named.

01.60.00 - 2 PRODUCT REQUIREMENTS

2.04 MAINTENANCE MATERIALS

A. Furnish extra materials, spare parts, tools, and software of types and in quantities specified in individual specification sections.

B. Deliver to Project site; obtain receipt prior to final payment.

PART 3 EXECUTION

3.01 SUBSTITUTION LIMITATIONS

A. Contracting Officer will consider requests for Substitutions only within ten (10) days after award of Contract.

B. Substitutions may be considered when a Product becomes unavailable through no fault of the Contractor.

C. Document each request with complete data substantiating compliance of proposed Substitution with Contract Documents.

D. A request constitutes a representation that the Contractor:

1. Has investigated proposed Product and determined that it meets or exceeds the quality level of the specified Product.

2. Will provide the same warranty for the Substitution as for the specified Product.

3. Will coordinate installation and make changes to other Work, which may be required for the Work to be completed with no additional cost to the FAA.

4. Waives claims for additional costs or time extension, which may subsequently become apparent.

5. Will reimburse Contracting Officer for review or redesign services associated with re-approval for authorities.

E. Substitutions will not be considered when they are indicated or implied on shop drawing or

Product data submittals, without separate written request, or when acceptance will require revision to the Contract Documents.

F. Substitution Submittal Procedure:

1. Submit three (3) copies of request for Substitution for consideration.

2. Submit shop drawings, Product data, and certified test results attesting to the proposed

Product equivalence.

3. The Contracting Officer will notify Contractor in writing of decision to accept or reject request.

G. If request for substitution is not accepted by the Contracting Officer, Contractor is responsible for supplying item as origionally specified or an acceptable substitution without additional cost to the FAA.

H. Substitution Submittal Procedure:

1. Submit one copy of request for substitution for consideration. Limit each request to one proposed substitution.

3.02 OWNER-SUPPLIED PRODUCTS

A. Owner's Responsibilities:

1. Arrange for and deliver Owner reviewed shop drawings, product data, and samples, to

Contractor.

2. Arrange and pay for product delivery to site.

3. On delivery, inspect products jointly with Contractor.

4. Submit claims for transportation damage and replace damaged, defective, or deficient items.

5. Arrange for manufacturers' warranties, inspections, and service.

B. Contractor's Responsibilities:

1. Review Owner reviewed shop drawings, product data, and samples.

2. Receive and unload products at site; inspect for completeness or damage jointly with

Owner.

01.60.00 - 3 PRODUCT REQUIREMENTS

3. Handle, store, install and finish products.

4. Repair or replace items damaged after receipt.

3.03 TRANSPORTATION AND HANDLING

A. Package products for shipment in manner to prevent damage; for equipment, package to avoid loss of factory calibration.

B. If special precautions are required, attach instructions prominently and legibly on outside of packaging.

C. Coordinate schedule of product delivery to designated prepared areas in order to minimize site storage time and potential damage to stored materials.

D. Transport and handle products in accordance with manufacturer's instructions.

E. Transport materials in covered trucks to prevent contamination of product and littering of surrounding areas.

F. Promptly inspect shipments to ensure that products comply with requirements, quantities are correct, and products are undamaged.

G. Provide equipment and personnel to handle products by methods to prevent soiling, disfigurement, or damage, and to minimize handling.

H. Arrange for the return of packing materials, such as wood pallets, where economically feasible.

3.04 STORAGE AND PROTECTION

A. Designate receiving/storage areas for incoming products so that they are delivered according to installation schedule and placed convenient to work area in order to minimize waste due to excessive materials handling and misapplication. See Section 01.74.19.

B. Store and protect products in accordance with manufacturers' instructions.

C. Store with seals and labels intact and legible.

D. Store sensitive products in weathertight, climate-controlled enclosures in an environment favorable to product.

E. For exterior storage of fabricated products, place on sloped supports above ground.

F. Provide off-site storage and protection when site does not permit on-site storage or protection.

G. Protect products from damage or deterioration due to construction operations, weather, precipitation, humidity, temperature, sunlight and ultraviolet light, dirt, dust, and other contaminants.

H. Comply with manufacturer's warranty conditions, if any.

I. Cover products subject to deterioration with impervious sheet covering. Provide ventilation to prevent condensation and degradation of products.

J. Prevent contact with material that may cause corrosion, discoloration, or staining.

K. Provide equipment and personnel to store products by methods to prevent soiling, disfigurement, or damage.

L. Arrange storage of products to permit access for inspection. Periodically inspect to verify products are undamaged and are maintained in acceptable condition.

01.70.00 - 1 EXECUTION AND CLOSEOUT

REQUIREMENTS

SECTION 01.70.00

EXECUTION AND CLOSEOUT REQUIREMENTS

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Examination, preparation, and general installation procedures.

B. Requirements for alterations work, including selective demolition, ______.

C. Pre-installation meetings.

D. Cutting and patching.

E. Surveying for laying out the work.

F. Cleaning and protection.

G. Closeout procedures, including Contractor's Correction Punch List, except payment procedures.

H. General requirements for maintenance service.

1.02 QUALIFICATIONS

A. For surveying work, employ a land surveyor registered in the State in which the Project is located and acceptable to Owner/FAA. Submit evidence of surveyor's Errors and Omissions insurance coverage in the form of an Insurance Certificate. Employ only individual(s) trained and experienced in collecting and recording accurate data relevant to ongoing construction activities, B. For design of temporary shoring and bracing, employ a Professional Engineer experienced in design of this type of work and licensed in the State in which the Project is located.

PART 2 PRODUCTS

2.01 PATCHING MATERIALS

A. New Materials: As specified in product sections; match existing products and work for patching and extending work.

B. Type and Quality of Existing Products: Determine by inspecting and testing products where necessary, referring to existing work as a standard.

C. Product Substitution: For any proposed change in materials, submit request for substitution described in Section 01.60.00 - Product Requirements.

PART 3 EXECUTION

3.01 EXAMINATION

A. Verify that existing site conditions and substrate surfaces are acceptable for subsequent work.

Start of work means acceptance of existing conditions.

B. Verify that existing substrate is capable of structural support or attachment of new work being applied or attached.

C. Examine and verify specific conditions described in individual specification sections.

D. Take field measurements before confirming product orders or beginning fabrication, to minimize waste due to over-ordering or misfabrication.

E. Verify that utility services are available, of the correct characteristics, and in the correct locations.

F. Prior to Cutting: Examine existing conditions prior to commencing work, including elements subject to damage or movement during cutting and patching. After uncovering existing work, assess conditions affecting performance of work. Beginning of cutting or patching means acceptance of existing conditions.

3.02 PREPARATION

A. Clean substrate surfaces prior to applying next material or substance.

01.70.00 - 2 EXECUTION AND CLOSEOUT

REQUIREMENTS

B. Seal cracks or openings of substrate prior to applying next material or substance.

C. Apply manufacturer required or recommended substrate primer, sealer, or conditioner prior to applying any new material or substance in contact or bond.

3.03 PREINSTALLATION MEETINGS

A. When required in individual specification sections, convene a preinstallation meeting at the site prior to commencing work of the section.

B. Require attendance of parties directly affecting, or affected by, work of the specific section.

C. Notify FAA Inspectors and Architect four days in advance of meeting date.

D. Prepare agenda and preside at meeting:

1. Review conditions of examination, preparation and installation procedures.

2. Review coordination with related work.

E. Record minutes and distribute copies within two days after meeting to participants, with two copies to Architect, Owner, participants, and those affected by decisions made.

3.04 LAYING OUT THE WORK

A. Verify locations of survey control points prior to starting work.

B. Promptly notify Owner/FAA of any discrepancies discovered.

C. Protect survey control points prior to starting site work; preserve permanent reference points during construction.

D. Promptly report to Owner/FAA the loss or destruction of any reference point or relocation required because of changes in grades or other reasons.

E. Replace dislocated survey control points based on original survey control. Make no changes without prior written notice to Owner/FAA.

F. Utilize recognized engineering survey practices.

G. Establish elevations, lines and levels. Locate and lay out by instrumentation and similar appropriate means:

1. Site improvements including pavements; stakes for grading, fill and topsoil placement;

utility locations, slopes, and invert elevations.

2. Grid or axis for structures.

3. Building foundation, column locations, ground floor elevations.

H. Periodically verify layouts by same means.

I. Maintain a complete and accurate log of control and survey work as it progresses.

3.05 GENERAL INSTALLATION REQUIREMENTS

A. Install products as specified in individual sections, in accordance with manufacturer's instructions and recommendations, and so as to avoid waste due to necessity for replacement.

B. Make vertical elements plumb and horizontal elements level, unless otherwise indicated.

C. Install equipment and fittings plumb and level, neatly aligned with adjacent vertical and horizontal lines, unless otherwise indicated.

D. Make consistent texture on surfaces, with seamless transitions, unless otherwise indicated.

E. Make neat transitions between different surfaces, maintaining texture and appearance.

3.06 ALTERATIONS

A. Drawings showing existing construction and utilities are based on casual field observation and existing record documents only.

1. Verify that construction and utility arrangements are as indicated.

2. Report discrepancies to Architect before disturbing existing installation.

3. Beginning of alterations work constitutes acceptance of existing conditions.

B. Remove existing work as indicated and as required to accomplish new work.

01.70.00 - 3 EXECUTION AND CLOSEOUT

REQUIREMENTS

1. Remove items indicated on drawings.

2. Relocate items indicated on drawings.

3. Where new surface finishes are to be applied to existing work, perform removals, patch, and prepare existing surfaces as required to receive new finish; remove existing finish if necessary for successful application of new finish.

4. Where new surface finishes are not specified or indicated, patch holes and damaged surfaces to match adjacent finished surfaces as closely as possible.

C. Services (Including but not limited to HVAC, Plumbing, Fire Protection, and Electrical):

Remove, relocate, and extend existing systems to accommodate new construction.

1. Maintain existing active systems that are to remain in operation; maintain access to equipment and operational components; if necessary, modify installation to allow access or provide access panel.

2. Where existing systems or equipment are not active and Contract Documents require reactivation, put back into operational condition; repair supply, distribution, and equipment as required.

3. Where existing active systems serve occupied facilities but are to be replaced with new services, maintain existing systems in service until new systems are complete and ready for service.

a. Disable existing systems only to make switchovers and connections; minimize duration of outages.

b. Provide temporary connections as required to maintain existing systems in service.

4. Verify that abandoned services serve only abandoned facilities.

5. Remove abandoned pipe, ducts, conduits, and equipment, including those above accessible ceilings; remove back to source of supply where possible, otherwise cap stub and tag with identification; patch holes left by removal using materials specified for new construction.

D. Protect existing work to remain.

1. Prevent movement of structure; provide shoring and bracing if necessary.

2. Perform cutting to accomplish removals neatly and as specified for cutting new work.

3. Repair adjacent construction and finishes damaged during removal work.

E. Adapt existing work to fit new work: Make as neat and smooth transition as possible.

F. Patching: Where the existing surface is not indicated to be refinished, patch to match the surface finish that existed prior to cutting. Where the surface is indicated to be refinished, patch so that the substrate is ready for the new finish.

G. Refinish existing surfaces as indicated:

1. Where rooms or spaces are indicated to be refinished, refinish all visible existing surfaces to remain to the specified condition for each material, with a neat transition to adjacent finishes.

2. If mechanical or electrical work is exposed accidentally during the work, re-cover and refinish to match.

H. Remove demolition…