This document includes drawings and specifications for an asbestos abatement project at the STB Annex building on the Mike Monroney Aeronautical Center campus. The Federal Aviation Administration is seeking proposals to complete construction work including removal of 105 linear feet of stair stringers, 215 linear feet of cove base, and 150 linear feet of brown mastic from square ducts containing asbestos. Proposals are due by email no later than the closing date of May 16, 2023, and prospective offerors must attend a mandatory pre-proposal conference on that date to tour the site. The project value is estimated between $1 million and $5 million. This opportunity is reserved exclusively for eligible 8(a) small disadvantaged businesses pursuant to FAA Acquisition Management System Clause 3.6.1-8.

View the file

Other files

File Type Posted
Attachment 25 STB Reno Q and A Log3 6.12.23.pdf PDF
Amendment 0006 6973GH-23-R-00096.pdf PDF
Attachment 24 Spec 26 51 00 INTERIOR LIGHTING Revised 06062023.pdf PDF
Attachment 22 Spec 23 04 00 COMMON REQUIREMENTS FOR HVAC Revised 06062023.pdf PDF
Attachment 23 Spec 26 05 00 BASIC REQUIREMENTS FOR ELECTRICAL SYSTEMS Revised 06062023.pdf PDF
Amendment 0005 6973GH-23-R-00096.pdf PDF
Attachment 15 08_71_00 USER-DOOR HARDWARE.pdf PDF
Attachment 20 STB Reno Q and A Log1 5.18.23.6.05.23.pdf PDF
Attachment 18 026A STB Annex ACM Photos.pdf PDF
Amendment 0004 6973GH-23-R-00096.pdf PDF
Attachment 19 STB Annex General Representative Work Areas.pdf PDF
Attachment 21 STB Reno Q and A Log2 5.18.23.6.05.23.pdf PDF
Attachment 16 Addendum Drawings.pdf PDF
Amendment 0003 6973GH-23-R-00096.pdf PDF
Attachment 7 Past Performance Survey Revision 1.1 5.24.23.docx DOCX document
Amendment 0002 6973GH-23-R-00096.pdf PDF
Attachment 14 REISSUE-100 Percent Type B FAA-MMAC STB Annex Renovation Drawings.pdf PDF
Site Visit Attendee List 6973GH-23-R-00096 STB Annex Renovation.pdf PDF
Amendment 0001 6973GH-23-R-00096.pdf PDF
SIR 6973GH-23-R-00096.pdf PDF
Attachment 11 Wage Determination OK20230049 02.10.2023.pdf PDF
Attachment 10 Contractor Release.pdf PDF
Attachment 4 SF25 - Performance Bond.pdf PDF
Attachment 13 AMP400-ENV-OC-2.4.3-CC.pdf PDF
Attachment 7 Past Performance Survey.docx DOCX document
Attachment 2 100 Percent Type B FAA-MMAC STB Annex Renovation Drawings.pdf PDF
Attachment 5 SF25A Payment Bond.pdf PDF
Attachment 12 Chapter 33 Construction Safety.pdf PDF
Attachment 3 SOW 2018-006090 STB Annex Renovation 3.13.23.pdf PDF
Attachment 6 SF24 Bid Bond.pdf PDF
Attachment 1 100 Percent Type B FAA-MMAC STB Annex Renovation Specifications.pdf PDF
Attachment 8 Past Performance Experience Form.docx DOCX document
Attachment 9 Client Authorization Letter.docx DOCX document
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Stair Stringer – 105 LF

Cove Base – 215 LF

Square Duct Brown Mastic – 150 LF

Asbestos Locations Building: 026A – STB Annex

Date: 12-06-22

Note: The information displayed comes from the asbestos sampling events performed on 10-17-22 & 11-17-22 in support of AMP 400 Project 2018006090 026A-STB Annex Renovation (Type B 95% Review). Sampling was limited to the materials in the areas that could potentially be disturbed during this subject project.

Asbestos Locations Building: 026A – STB Annex

Date: 12-06-22

Stair Stringer – 105 LF

Cove Base – 215 LF

Square Duct Brown Mastic – 150 LF

Note: The information displayed comes from the asbestos sampling events performed on 10-17-22 & 11-17-22 in support of AMP 400 Project 2018006090 026A-STB Annex

Date: 12-06-22

Sq. duct mastic in mech room shown on page 4 of 4

Stair Stringer – 105 LF

Cove Base – 215 LF

Square Duct Brown Mastic – 150 LF

Note: The information displayed comes from the asbestos sampling events performed on 10-17-22 & 11-17-22 in support of AMP 400 Project 2018006090 026A-STB Annex

Date: 12-06-22

Square Duct Brown Mastic – 150 LF

Note: The information displayed comes from the asbestos sampling events performed on 10-17-22 & 11-17-22 in support of AMP 400 Project 2018006090 026A-STB Annex

Hangar 9 updated Asbestos Location Drawings.vsdx
Page-1
Page-2
Page-3
Page-4

File details come from the government source that posted it. Updated .