Attachment 25 STB Reno Q and A Log3 6.12.23.pdf

PDF 102 KB Posted

Attached to
STB Building Renovation at the Mike Monroney Aeronautical Center (MMAC) Solicitation
Solicitation number
6973GH-23-R-00096
Issued by

About this file

This document contains a federal solicitation for construction services. The Federal Aviation Administration seeks proposals to complete renovations to the STB Annex Building at the Mike Monroney Aeronautical Center. Prospective offerors must be 8(a) certified small disadvantaged businesses. Services include demolition, new construction, and elevator modernization. The project estimate is between $1-5 million. The mandatory pre-proposal conference will be held on May 16, 2023 and proposals are due by email only by the date specified in the solicitation. Offerors must RSVP for and attend the pre-proposal conference, and the site visit is required for proposal consideration.

View the file

Other files

File Type Posted
Amendment 0006 6973GH-23-R-00096.pdf PDF
Attachment 24 Spec 26 51 00 INTERIOR LIGHTING Revised 06062023.pdf PDF
Attachment 22 Spec 23 04 00 COMMON REQUIREMENTS FOR HVAC Revised 06062023.pdf PDF
Attachment 23 Spec 26 05 00 BASIC REQUIREMENTS FOR ELECTRICAL SYSTEMS Revised 06062023.pdf PDF
Amendment 0005 6973GH-23-R-00096.pdf PDF
Attachment 15 08_71_00 USER-DOOR HARDWARE.pdf PDF
Attachment 20 STB Reno Q and A Log1 5.18.23.6.05.23.pdf PDF
Attachment 18 026A STB Annex ACM Photos.pdf PDF
Amendment 0004 6973GH-23-R-00096.pdf PDF
Attachment 19 STB Annex General Representative Work Areas.pdf PDF
Attachment 21 STB Reno Q and A Log2 5.18.23.6.05.23.pdf PDF
Attachment 17 026A STB Annex Asbestos Location Drawings.pdf PDF
Attachment 16 Addendum Drawings.pdf PDF
Amendment 0003 6973GH-23-R-00096.pdf PDF
Attachment 7 Past Performance Survey Revision 1.1 5.24.23.docx DOCX document
Amendment 0002 6973GH-23-R-00096.pdf PDF
Attachment 14 REISSUE-100 Percent Type B FAA-MMAC STB Annex Renovation Drawings.pdf PDF
Site Visit Attendee List 6973GH-23-R-00096 STB Annex Renovation.pdf PDF
Amendment 0001 6973GH-23-R-00096.pdf PDF
SIR 6973GH-23-R-00096.pdf PDF
Attachment 11 Wage Determination OK20230049 02.10.2023.pdf PDF
Attachment 10 Contractor Release.pdf PDF
Attachment 4 SF25 - Performance Bond.pdf PDF
Attachment 13 AMP400-ENV-OC-2.4.3-CC.pdf PDF
Attachment 7 Past Performance Survey.docx DOCX document
Attachment 2 100 Percent Type B FAA-MMAC STB Annex Renovation Drawings.pdf PDF
Attachment 5 SF25A Payment Bond.pdf PDF
Attachment 12 Chapter 33 Construction Safety.pdf PDF
Attachment 3 SOW 2018-006090 STB Annex Renovation 3.13.23.pdf PDF
Attachment 6 SF24 Bid Bond.pdf PDF
Attachment 1 100 Percent Type B FAA-MMAC STB Annex Renovation Specifications.pdf PDF
Attachment 8 Past Performance Experience Form.docx DOCX document
Attachment 9 Client Authorization Letter.docx DOCX document
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

No. Question Response

1. Exterior doors from first floor – Demo Note 3 on Sheet A‐202 says “Existing exterior elevator doors to remain,” whereas construction Note 9 on the same sheet says “Install new elevator doors and frames.” Does FAA require the exterior doors to be retained or replaced? If replaced, what type of door and frame are required, as these doors are omitted from the Door & Frame Schedule, Sheet A‐ 402?

The existing elevator has elevator doors and frames In the shaft and then secondary doors and frames that can be closed off so there is no elevator access that are not part of the elevator shaft or elevator itself. Demo note 3 refers to the elevator shaft doors being demolished and replaced. Demo note 4 refers to the radio frequency shielded secondary doors and frames being removed that are not part of the elevator shaft. Note 9 is referring the to the elevator shaft doors which are to be replaced with new. On the first floor the secondary door and frame is removed and not replaced since the elevator does not need to be closed off with RF Shielded doors anymore. Elevator shaft doors are not on the door schedule as they are part of the elevator package that needs to be provided

2. Interior doors from basement, first floor, and second floor – The notes on Sheets A‐201, A‐202, and A‐203 say to “install new elevator doors and frames.” However, none of these doors are referenced in the Door & Frame Schedule, Sheet A‐402? What type of door and frame are required?

The “new elevator doors and frames” are referring to the elevator shaft doors. Same as above, Elevator shaft doors are not on the door schedule as they are part of the elevator package that needs to be provided.

SIR 6973GH‐23‐R‐00096

STB Annex Renovation

Questions & Answers Log # 3 / June 12th 2023

Elevator Doors

File details come from the government source that posted it. Updated .