This solicitation requests proposals for a construction project to renovate the STB Annex at the Mike Monroney Aeronautical Center. The Federal Aviation Administration seeks to complete renovations in accordance with attached specifications and drawings. This is a 100% 8(a) small business set-aside. Proposals are due by email no later than the closing date in the solicitation. Prospective offerors must attend a mandatory pre-proposal conference and site visit on May 16, 2023 to be eligible to bid. Proposals should include the solicitation number in email subject lines and provide company and representative names and contact information when registering for the site visit. The estimated price range for the construction project is $1,000,000 to $5,000,000.

View the file

Other files

File Type Posted
Attachment 25 STB Reno Q and A Log3 6.12.23.pdf PDF
Amendment 0006 6973GH-23-R-00096.pdf PDF
Attachment 24 Spec 26 51 00 INTERIOR LIGHTING Revised 06062023.pdf PDF
Attachment 22 Spec 23 04 00 COMMON REQUIREMENTS FOR HVAC Revised 06062023.pdf PDF
Attachment 23 Spec 26 05 00 BASIC REQUIREMENTS FOR ELECTRICAL SYSTEMS Revised 06062023.pdf PDF
Amendment 0005 6973GH-23-R-00096.pdf PDF
Attachment 15 08_71_00 USER-DOOR HARDWARE.pdf PDF
Attachment 20 STB Reno Q and A Log1 5.18.23.6.05.23.pdf PDF
Attachment 18 026A STB Annex ACM Photos.pdf PDF
Amendment 0004 6973GH-23-R-00096.pdf PDF
Attachment 19 STB Annex General Representative Work Areas.pdf PDF
Attachment 21 STB Reno Q and A Log2 5.18.23.6.05.23.pdf PDF
Attachment 17 026A STB Annex Asbestos Location Drawings.pdf PDF
Attachment 16 Addendum Drawings.pdf PDF
Amendment 0003 6973GH-23-R-00096.pdf PDF
Attachment 7 Past Performance Survey Revision 1.1 5.24.23.docx DOCX document
Amendment 0002 6973GH-23-R-00096.pdf PDF
Attachment 14 REISSUE-100 Percent Type B FAA-MMAC STB Annex Renovation Drawings.pdf PDF
Site Visit Attendee List 6973GH-23-R-00096 STB Annex Renovation.pdf PDF
Amendment 0001 6973GH-23-R-00096.pdf PDF
SIR 6973GH-23-R-00096.pdf PDF
Attachment 11 Wage Determination OK20230049 02.10.2023.pdf PDF
Attachment 10 Contractor Release.pdf PDF
Attachment 4 SF25 - Performance Bond.pdf PDF
Attachment 13 AMP400-ENV-OC-2.4.3-CC.pdf PDF
Attachment 2 100 Percent Type B FAA-MMAC STB Annex Renovation Drawings.pdf PDF
Attachment 5 SF25A Payment Bond.pdf PDF
Attachment 12 Chapter 33 Construction Safety.pdf PDF
Attachment 3 SOW 2018-006090 STB Annex Renovation 3.13.23.pdf PDF
Attachment 6 SF24 Bid Bond.pdf PDF
Attachment 1 100 Percent Type B FAA-MMAC STB Annex Renovation Specifications.pdf PDF
Attachment 8 Past Performance Experience Form.docx DOCX document
Attachment 9 Client Authorization Letter.docx DOCX document
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROCUREMENT SENSITIVE WHEN COMPLETED

FOR OFFICIAL USE ONLY

SIR/RFO No. 6973GH-23-R-00096 STB Annex Renovation

PAST PERFORMANCE SURVEY

To: _______________________________________________________________________ NAME Title

Organization:_____________________________________________________________

Fax No.: _________________________ E-mail Address:_________________________

Phone No.:________________________

Date: __________________________ Number of Pages (including this sheet): 5 in total

Your name was provided as a point of contact for the following:

Contractor Name:_______________________________________________________

Contract Number: _______________________________

Project Title: ___________________________________________________________

In regard to the above contractor’s performance on the referenced contract, please complete the attached Past Performance Survey and return as follows:

Send to: Andre Casiano, Contracting Specialist

E-mail Address: Elizabeth.A.Fikes@faa.gov

For questions, please contact me at telephone 405-954-7850.

Please provide your response no later than June 5, 2023 3:00 p.m. CT

Thank you!

Offeror to complete this page:

1. Name of Contractor: ____________________________________________________

2. Provide a brief description of the renovation project and how it is relevant to the HQB Building Lobby Remodel; e.g., multi-story office, single story office building, hospital, school, warehouse, square footage?

3. Type of contract; e.g., firm fixed-price, cost-reimbursable: __________________________________________

4. Contractor Role (circle one):

Prime Contractor, Mechanical Subcontractor, Electrical Subcontractor, Pool Subcontractor

5. Contract Number (if applicable): _______________________________________________

6. Total Contract Amount - Original contract amount: $____________ Final Contract Amount: $_____________ Provide rationale for the difference________________________________________________________

7. Date of Contract Award: ______________________________________________________

8. Contract Period of Performance: Start Complete _________________

9. Was project completion date consistent with the contract completion date? ___________ If no, explain why___________________________________________________________________________________.

10. Was a deficiency notice issued? ___________ If so, was the issue successfully resolved? ___________

11. Was a Cure Notice issued? _____________ If so, was the issue successfully resolved? _____________

12. Was a Show Cause issued? _____________ If so, was the issue successfully resolved? _____________

Name of Responding Point of Contact: _____________________________________________________

Agency/Organization: _________________________________________________________________

Mailing Address: __________________________________________________________

Telephone Number: __________________________________

E-mail Address: __________________________________ Customer to complete the following pages:

A five level assessment rating system will be used for the following questions as defined below:

Rating
Definition
Exceptional
Performance meets contractual requirements and exceeds many to the Government’s/Owner’s benefit. The category being assessed was accomplished with few minor problems for which corrective actions taken by the contractor were highly effective.
Very Good
Performance meets contractual requirements and exceeds some to the Government’s/Owner’s benefit. The category being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.
Satisfactory
Performance meets contractual requirements. The category being assessed contains some minor problems for which corrective actions taken by the contractor appear to be or were satisfactory.
Marginal
Performance does not meet some contractual requirements. The category being assessed reflects a serious problem for which the contractor has not yet identified corrective actions.
Unsatisfactory
Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The category being assessed contains a serious problem(s) for which the contractor’s corrective actions appear or were ineffective.

1. Quality of Project.

a. How would you rate the quality of the project?

Exceptional( )
Very Good( )
Satisfactory( )
Marginal( )
Unsatisfactory( )

NOTE: If you provide a rating above or below “Satisfactory” you will need to document your rationale for the use of your rating.

2. Scheduling of Project.

a. How would you rate the scheduling of the project?

Exceptional( )
Very Good( )
Satisfactory( )
Marginal( )
Unsatisfactory( )

NOTE: If you provide a rating above or below “Satisfactory” you will need to document your rationale for the use of your rating.

3. Cost Control of Project Modifications.

a. How would you rate the contractor’s cost control of project modifications?

Exceptional( )
Very Good( )
Satisfactory( )
Marginal( )
Unsatisfactory( )

NOTE: If you provide a rating above or below “Satisfactory” you will need to document your rationale for the use of your rating.

4. Management of Subcontractors. (Only answer this question if the contractor being evaluated is the general contractor and not a subcontractor)

a. How would you rate the subcontract management demonstrated by the general contractor

Exceptional( )
Very Good( )
Satisfactory( )
Marginal( )
Unsatisfactory( )

NOTE: If you provide a rating above or below “Satisfactory” you will need to document your rationale for the use of your rating.

5. Would you recommend awarding similar contracts or using the offeror again for future work?

( ) Yes
( ) No

6. Please provide any other comments you may have.