Attachment 22 Spec 23 04 00 COMMON REQUIREMENTS FOR HVAC Revised 06062023.pdf

PDF 237 KB Posted

Attached to
STB Building Renovation at the Mike Monroney Aeronautical Center (MMAC) Solicitation
Solicitation number
6973GH-23-R-00096
Issued by

About this file

This solicitation seeks proposals for a construction project to renovate the STB Annex at the Mike Monroney Aeronautical Center. The work includes renovations in accordance with the attached specifications and drawings. This is a 100% 8(a) small business set-aside being conducted by the Federal Aviation Administration. The estimate for the project is between $1 million and $5 million. Proposals are due by email only by the closing date specified in the solicitation. Offerors must attend a mandatory pre-proposal site visit and conference scheduled for May 16, 2023 to be eligible for award. Notifications of intent to attend are due by May 12. The selected offeror will be required to perform renovations at the Mike Monroney Aeronautical Center for the Federal Aviation Administration.

View the file

Other files

File Type Posted
Attachment 25 STB Reno Q and A Log3 6.12.23.pdf PDF
Amendment 0006 6973GH-23-R-00096.pdf PDF
Attachment 24 Spec 26 51 00 INTERIOR LIGHTING Revised 06062023.pdf PDF
Attachment 23 Spec 26 05 00 BASIC REQUIREMENTS FOR ELECTRICAL SYSTEMS Revised 06062023.pdf PDF
Amendment 0005 6973GH-23-R-00096.pdf PDF
Attachment 15 08_71_00 USER-DOOR HARDWARE.pdf PDF
Attachment 20 STB Reno Q and A Log1 5.18.23.6.05.23.pdf PDF
Attachment 18 026A STB Annex ACM Photos.pdf PDF
Amendment 0004 6973GH-23-R-00096.pdf PDF
Attachment 19 STB Annex General Representative Work Areas.pdf PDF
Attachment 21 STB Reno Q and A Log2 5.18.23.6.05.23.pdf PDF
Attachment 17 026A STB Annex Asbestos Location Drawings.pdf PDF
Attachment 16 Addendum Drawings.pdf PDF
Amendment 0003 6973GH-23-R-00096.pdf PDF
Attachment 7 Past Performance Survey Revision 1.1 5.24.23.docx DOCX document
Amendment 0002 6973GH-23-R-00096.pdf PDF
Attachment 14 REISSUE-100 Percent Type B FAA-MMAC STB Annex Renovation Drawings.pdf PDF
Site Visit Attendee List 6973GH-23-R-00096 STB Annex Renovation.pdf PDF
Amendment 0001 6973GH-23-R-00096.pdf PDF
SIR 6973GH-23-R-00096.pdf PDF
Attachment 11 Wage Determination OK20230049 02.10.2023.pdf PDF
Attachment 10 Contractor Release.pdf PDF
Attachment 4 SF25 - Performance Bond.pdf PDF
Attachment 13 AMP400-ENV-OC-2.4.3-CC.pdf PDF
Attachment 7 Past Performance Survey.docx DOCX document
Attachment 2 100 Percent Type B FAA-MMAC STB Annex Renovation Drawings.pdf PDF
Attachment 5 SF25A Payment Bond.pdf PDF
Attachment 12 Chapter 33 Construction Safety.pdf PDF
Attachment 3 SOW 2018-006090 STB Annex Renovation 3.13.23.pdf PDF
Attachment 6 SF24 Bid Bond.pdf PDF
Attachment 1 100 Percent Type B FAA-MMAC STB Annex Renovation Specifications.pdf PDF
Attachment 8 Past Performance Experience Form.docx DOCX document
Attachment 9 Client Authorization Letter.docx DOCX document
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Alvine No. 2022 9198 23 04 00 - 1 11/22/2022

SECTION 23 04 00

COMMON REQUIREMENTS FOR HVAC

PART 1 - GENERAL

1.1 SUMMARY

A. This section describes the general requirements of these specifications and shall apply to all phases of the work specified, shown on the drawings, or required to provide for complete installation of all systems for this project.

B. This Section includes the following basic materials and methods to complement other Division 23 Sections.

1.2 WARRANTIES

A. Warrant all materials, workmanship and equipment against defects for a period of one year after the date of substantial completion.

B. Certain equipment shall be warranted beginning at the time of final acceptance or for longer periods of time as specified in those divisions of the Project Manual.

C. Repair or replace, at no additional cost to the Owner, any item which may become defective within the warrant period.

1. Repair or replacement of compressorized equipment shall include a complete refrigerant charge.

D. Any manufacturers' warranties concerning any item installed will run to the benefit of the Owner.

E. The Contractor agrees not to void or impair, or to allow Sub-Contractors to void or impair, any warranties regarding products or items installed as part of this project.

F. The repair of faulty workmanship shall be considered to be included in the contract.

1.3 QUESTIONS OF INTERPRETATION DURING BIDDING PHASE

A. If questions arise during the bidding process regarding the meaning of any portion of the contract documents, the prospective bidder shall submit the questions to the Contracting Officer for clarification.

B. Any definitive interpretation or clarification of the contract documents will be published by addenda, properly issued to each person holding documents, prior to the bid date.

C. Verbal interpretation or explanation not issued in the form of an addendum shall not be considered part of the bidding documents.

D. When submitting questions for clarification, adequate time for issuance and delivery of addenda must be allowed.

E. The Contracting Officer shall be the sole judge regarding interpretations of conflicts within contract documents.

1.4 CONTRACT DOCUMENT DISCREPANCIES

A. If any ambiguities should appear in the contract documents, request clarification from the Contracting Officer before proceeding with the work.

Revised June 6, 2023

Alvine No. 2022 9198 23 04 00 - 2 11/22/2022

B. If the Contractor fails to make such request, no excuse will thereafter be entertained for failure to carry out the work in a manner satisfactory to the Contracting Officer.

C. Should a conflict occur within the contract documents, the Contractor is deemed to have estimated the more expensive way of doing the work unless a written clarification from the Contracting Officer was requested and obtained before submission of proposed methods or materials.

D. The Contracting Officer shall be the sole judge regarding interpretations of conflicts within contract documents.

1.5 DEFINITIONS

A. The following definitions shall apply throughout the contract documents:

1. Architect / Engineer: Architect or Engineer

2. Code: All applicable national, state and local code

3. Mechanical: All plumbing, HVAC, & fire protection work required by the Contract Documents

4. Electrical: All electrical and fire alarm work required by the Contract Documents

5. Contractor: Any Contractor performing work required by the Contract Documents

6. Indicated: Noted, scheduled or specified

7. Selected: Selected by the Architect or Engineer

8. Provide: Furnish, install, connect and tested complete and ready for use

9. Furnish: Supply and deliver to the site ready for installation

10. Install: Install complete, per Contract Documents and manufacturer's requirements.

11. Finished Spaces: Spaces other than mechanical and electrical equipment rooms, furred spaces, pipe and duct shafts, unheated spaces immediately below roof, spaces above ceilings, unexcavated spaces, crawl spaces, and tunnels.

12. Exposed, Interior Installations: Exposed to view indoors. Examples include finished occupied spaces and mechanical equipment rooms.

13. Exposed, Exterior Installations: Exposed to view outdoors, or subject to outdoor ambient temperatures and weather conditions. Examples include rooftop locations.

14. Concealed, Interior Installations: Concealed from view and protected from physical contact by building occupants. Examples include above ceilings and in duct shafts.

15. Concealed, Exterior Installations: Concealed from view and protected from weather conditions and physical contact by building occupants, but subject to outdoor ambient temperatures. Examples include installations within unheated shelters.

16. Dry Locations: A location not normally subject to dampness or wetness. A location classified as dry may be temporarily subject to dampness or wetness, as in the case of a building under construction.

17. Damp Locations: Locations protected from weather and not subject to saturation with water or other liquids but subject to moderate degrees of moisture.

a. Examples of such locations include partially protected locations under canopies, marquees, roofed open porches, and like locations, and interior locations subject to moderate degrees of moisture, such as some basements, some barns, and some cold storage warehouses.

18. Wet Locations: Installations underground or in concrete slabs or masonry in direct contact with the earth; in locations subject to saturation with water or other liquids, such as vehicle washing areas; and in unprotected locations exposed to weather.

Alvine No. 2022 9198 23 04 00 - 3 11/22/2022

1.6 SYMBOLS

A. Items of equipment and materials are indicated on the drawings in accordance with the symbols shown on the plans.

1.7 ABBREVIATIONS

A. Refer to abbreviations list shown on the Drawings.

B. The following abbreviations apply throughout the Contract Documents:

1. ABS: Acrylonitrile-butadiene-styrene plastic.

2. ADA: Americans with Disabilities Act

3. AHJ: Authority Having Jurisdiction

4. AMCA: Air Moving Council of America

5. ANSI: American National Standards Institute

6. ARI: American Refrigeration Institute

7. ASHRAE: American Society of Heating, Refrigerating and Air Conditioning Engineers

8. ASME: American Society of Mechanical Engineers

9. ASTM Specification: Standard specifications of the American Society for Testing Materials

10. CPVC: Chlorinated polyvinyl chloride plastic.

11. CR: Chlorosulfonated polyethylene synthetic rubber.

12. EPDM: Ethylene propylene diene terpolymer rubber.

13. FM: Factory Mutual Engineering Corporation

14. IRI: Industrial Risk Insurers

15. NEC: National Electrical Code, latest edition

16. NEMA: National Electrical Manufacturers Association

17. NFPA: National Fire Protection Association

18. NP: Nylon plastic.

19. NPS: Nominal Pipe Size

20. PE: Polyethylene plastic.

21. PVC: Polyvinyl chloride plastic.

22. SMACNA: Sheet Metal and Air Conditioning Contractors National Association

23. UL or Underwriters: Underwriters Laboratories, Inc.

1.8 CODES

A. The work shall be performed by persons skilled in the trade involved and shall be done in a manner consistent with normal industry standards.

B. All work shall conform to all applicable sections of currently adopted editions of the following codes, standards, and specifications:

1. International Building Code (IBC)

2. International Fire Code (IFC)

3. International Energy Conservation Code (IECC)

4. International Fuel Gas Code (IFGC)

5. International Plumbing Code (IPC)

6. International Mechanical Code (IMC)

7. Safety and Health Regulations for Construction

8. Occupational Safety and Health Standards (OSHA), National Consensus Standards and Established Federal Standards

9. National Electrical Code (NEC)

10. National Fire Protection Association (NFPA)

11. Life Safety Code (NFPA 101)

Alvine No. 2022 9198 23 04 00 - 4 11/22/2022

12. American Gas Association (AGA)

13. Underwriters' Laboratories, Inc. (UL)

14. National Electrical Safety Code (NESC)

15. All applicable national, state and local codes and amendments.

1.9 PERMITS

A. The Contractors shall familiarize themselves with all requirements regarding all permits, fees, etc., and shall comply with them.

B. All permits, licenses, inspections and arrangements required for the work shall be obtained by the Contractor at his expense.

C. All utilities shall be installed in accordance with the local rules and regulations and all charges shall be paid by the Contractor.

1.10 CODE COMPLIANCE

A. Work shall be in accordance with all applicable codes. Where the codes and drawings do not agree, the code shall take precedence; however, code shall take precedence over what is shown only when it is more stringent than that indicated. Items that are allowed by codes which are less stringent than that shown on the drawings shall not be substituted.

B. Drawings, plans, and schematics and diagrams indicate the general location and the arrangement of systems. Wherever practical, install systems as indicated.

C. Where the National Electrical Code or applicable codes require controllers to be marked with a Short Circuit Current Rating (SCCR), the equipment shall be manufactured as required such that the SCCR of the equipment meets or exceeds the available short circuit current at the equipment.

1.11 MATERIALS AND EQUIPMENT MANUFACTURERS

A. Options in selecting materials and equipment are limited by requirements of the contract documents and governing regulations. They are not controlled by industry traditions or procedures experienced on previous construction projects.

B. Materials and equipment shall be provided in accordance with the following:

1. Primary Design Products: Primary design products are those products around which the project was designed in terms of capacity, performance, physical size and quality.

2. Primary design products are indicated by use of a single manufacturer's name, model number or similar data on drawings or schedules or within the specifications.

3. Provide primary design products unless substitutions are made in accordance with the following paragraphs.

4. Acceptable Equivalent Substitutions: Acceptable equivalent substitutions are products of manufactures other than those listed for the primary design products.

Equivalent acceptable substitutions shall meet each of the following requirements:

a. The product shall be manufactured by one of the acceptable manufacturers listed in the Project Manual, drawings, or addenda.

b. The product shall meet or exceed the requirements of the contract documents in terms of quality, performance, suitability, appearance, and physical characteristics.

c. The Contractor providing the substitution shall bear the total cost of all changes due to substitutions. These costs may include additional

Alvine No. 2022 9198 23 04 00 - 5 11/22/2022 compensation to the Architect / Engineer for redesign and evaluation services, increased cost of work by the Owner or other Contractors, and similar considerations.

d. Performance Requirements: Where the contract documents list performance requirements or describe a product or assembly generically, provide products that comply with the specific requirements indicated and that are recommended by the manufacturer for the respective application.

e. Compliance with Standards, Codes and Regulations: Where the specifications require only compliance with an imposed standard, code or regulation, the Contractor has the option of selecting a product that complies with specification requirements, including the standards, codes and regulations.

f. Proposed substitutions will be judged on the basis of quality, performance, appearance and on the governing space limitations. The reputation of the manufacturer, delivery time requirements, and the availability of repair or replacement parts may also be considered.

g. The Architect / Engineer shall be the sole and final judge as to the suitability of substitution items.

1.12 SUBMITTALS

A. Shop Drawings, Product Data and Samples:

1. Other section in the Project Manual shall be adhered to if more stringent than the following paragraphs.

2. When required by other sections of this Project Manual, submit shop drawings, product data or samples to the Architect / Engineer for review.

3. Submittals deemed unnecessary by the Architect / Engineer shall be returned indicating “No Action Taken”.

4. A completed copy of the transmittal form included with the Project Manual shall accompany each submittal.

5. Submittals shall be numbered consecutively.

6. Unless otherwise noted, submit one copy electronically of shop drawings and product data for review. Review comments will be returned electronically. A hard copy of the electronic submittal will be returned if requested.

a. Shop drawings and product data shall be in original searchable PDF format.

7. Shop drawings are drawings, diagrams, schedules and other data specifically prepared for this project by the Contractor, Manufacturer, Supplier, or Distributor to illustrate some portion of the work. Shop Drawings shall also detail fabrication and installation for metal and wood supports and anchorage for mechanical materials and equipment.

a. Shop drawings shall be drawn to accurate scale and of adequate size to illustrate required details.

8. Product data are illustrations, standard schedules, performance charts, instruction brochures, diagrams and other information furnished by the Contractor, Manufacturer, Supplier, or Distributor to illustrate a material, product or system for some portion of the work.

9. All submittals shall clearly indicate proposed items, capacities, characteristics and details in conformance with contract documents. All equipment items shall be marked with the same item number as used on drawings or schedules.

Capacities, dimensions and special features required shall be certified by the manufacturer.

10. Submittals shall indicate manufacturer's delivery time for the item after review by the Architect / Engineer.

Alvine No. 2022 9198 23 04 00 - 6 11/22/2022

11. The Architect / Engineer shall review or take other appropriate action upon the Contractor's submittals such as shop drawings, product data and samples, but only to determine conformance with the design concept of the work and the information given in the contract documents.

12. Contractor shall not be relieved of responsibility for any deviation from the requirements of the contract documents by the Architect / Engineer's review of shop drawings, product data or samples.

13. Contractor shall not be relieved from responsibility for errors or omissions in the shop drawings, product data or samples by the Architect / Engineer's review of those drawings.

14. No portion of the work requiring submission of a shop drawing, product data or sample shall be commenced until the submittal has been reviewed by the Architect / Engineer. All such portions of the work shall be in accordance with reviewed submittals.

B. Operation and Maintenance Manuals:

1. Prepare three (3) operation and maintenance manuals for the equipment furnished. Manuals shall be submitted to the Architect / Engineer for review and distribution to the Owner not less than 30 days prior to substantial completion of the project. Manuals not meeting the following requirements may be rejected by the Architect / Engineer.

2. Each manual shall be assembled in a three-ring binder with hard cover and plastic finish. Binders shall not exceed a 3-inch thickness. Where more than one binder is required, the manuals shall be separated into a logical grouping, i.e., “Mechanical”, “Electrical”, “Maintenance”, “Operation”, “Parts”, Shop Drawings”, etc. Where loose-leaf inserts are used, the sheets shall be reinforced to prevent tearing from continuous usage. Each binder shall have the following information clearly printed on its front cover:

a. Project name and address.

b. Portion of the work covered by each volume (if more than one volume in the set). Where more than one volume is required, label each volume as “Volume _____ of _____”.

c. Name, address and telephone number of Contractor and all Sub- Contractors including night or emergency number.

3. Manual shall include, but shall not be limited to, the following:

a. A Complete Index. Contractor may submit the index to the Architect / Engineer for review prior to submittal of complete manuals if desired.

b. Identify equipment included in the O&M manuals by the equipment mark used in the contract drawings.

c. Names, Addresses and Telephone Numbers. This list shall include the manufacturer and local representative who stocks or furnishes repair parts for all items of equipment and shall be typed on a single page in front of the binder.

d. Startup, Operation and Shutdown Procedures. Provide a written description of procedures for startup, operation and shutdown of each mechanical item or system. This description shall include motors to start, valves to open, etc., in proper sequence, and the location of switches, starters, pushbuttons and valves. Description shall include item references or labels used in the contract documents unless otherwise instructed in advance by the Owner.

e. Equipment Accessory Schedule. Upon completion of the work, furnish the Owner with a complete equipment accessory schedule listing each piece of equipment and the related size, type, number required and the manufacturer of all renewable items.

f. Manufacturer's Operation and Maintenance Manuals and Parts Lists.

Alvine No. 2022 9198 23 04 00 - 7 11/22/2022

g. Emergency Procedures. Provide a written description of emergency operating procedures or a list of service organizations (including addresses and telephone numbers) capable of rendering emergency services to the various parts of the system.

h. One copy of all shop drawings and product data, clearly marked for each item furnished using the designation label specified or indicated on Drawings.

i. Signed letters of certification of inspection and similar information.

j. All manufacturers' warranty information.

k. Provide documentation that training was performed for each item specified to include Owner training. Include name of Owner’s representative(s) present, date and time of training.

l. Normal Maintenance Schedule. Include a listing of work to be performed at various time intervals; i.e., 30, 90, 180 days and yearly.

m. Provide documentation that Extra Materials were received by the Owner for each section requiring Extra Materials.

C. Division 23 Specific Submittals

1. Product Data: For the following:

a. Transition fittings.

b. Dielectric fittings.

c. Mechanical sleeve seals.

d. Escutcheons.

e. Access doors.

2. Welding certificates.

3. Coordination Drawings: For access panel and door locations.

1.13 OPERATING TRAINING

A. Complete operating instructions for each system and item of equipment shall be provided to the Owner's designated personnel.

B. Operation and Maintenance Manuals must be reviewed and accepted by the Architect / Engineer and provided to the Owner prior to operating training.

C. Training shall be scheduled at the convenience of the Owner. A minimum of 8 hours of training shall be provided.

D. Training shall include instructions on the following:

1. Startup and shutdown procedures

2. Periodic maintenance

3. Emergency operation

4. Safety

E. In addition to the instructions required above, wherever possible perform the operations being described in order to fully illustrate system operation.

F. At the completion of training, turn over to the Owner all required keys and special tools for installed equipment. Each key or tool shall be labeled with its use.

1.14 QUALITY ASSURANCE

A. Steel Support Welding: Qualify processes and operators according to AWS D1.1, “Structural Welding Code-Steel”.

B. Steel Pipe Welding: Qualify processes and operators according to ASME Boiler and Pressure Vessel Code: Section IX, “Welding and Brazing Qualifications”.

1. Comply with provisions in ASME B31 Series, “Code for Pressure Piping”.

Alvine No. 2022 9198 23 04 00 - 8 11/22/2022

2. Certify that each welder has passed AWS qualification tests for welding processes involved and that certification is current.

C. Electrical Characteristics for Mechanical Equipment: Equipment of higher electrical characteristics may be furnished provided such proposed equipment is approved in writing and connecting electrical services, circuit breakers, and conduit sizes are appropriately modified. If minimum energy ratings or efficiencies are specified, equipment shall comply with requirements.

1.15 DELIVERY, STORAGE, AND HANDLING

A. Deliver pipes and tubes with factory-applied end caps. Maintain end caps through shipping, storage, and handling to prevent pipe end damage and to prevent entrance of dirt, debris, and moisture.

1.16 COORDINATION

A. Drawings, plans, and schematics and diagrams indicate the general location and the arrangement of systems. Wherever practical, install systems as indicated.

B. Provide offsets and elevation changes in piping, conduit and ductwork as required to complete the Layout and Coordination Process. Offsets and elevation change information shall be indicated in the coordination process documentation and must be submitted for review.

C. Arrange for spaces, chases, slots, and openings in building structure during progress of construction to allow for system installations.

D. Coordinate arrangement, mounting, and support of equipment.

1. To allow maximum possible headroom unless specific mounting heights that reduce headroom are indicated.

2. To provide for ease of disconnecting the equipment with minimum interference to other installations.

3. To allow right of way for piping and conduit installed at required slope.

E. Coordinate chases, slots, inserts, sleeves, and openings with general construction work and arrange in building structure during progress of construction to facilitate the installations that follow.

1. Set inserts and sleeves in poured-in-place concrete, masonry work, and other structural components as they are constructed.

F. Sequence, coordinate, and integrate installing materials and equipment for efficient flow of the Work. Coordinate installing large equipment requiring positioning before closing in the building.

G. Coordinate service connections to components furnished by utility companies.

1. Coordinate installation and connection of exterior underground and overhead utilities and services, including provision for metering components.

2. Comply with requirements of authorities having jurisdiction and of utility company providing water, gas, electrical power and other services.

H. Coordinate location of access panels and doors for items that are concealed by finished surfaces.

I. Coordinate testing of items, so equipment and systems that are functionally interdependent are tested to demonstrate successful interoperability.

Alvine No. 2022 9198 23 04 00 - 9 11/22/2022

1.17 STRUCTURAL COORDINATION

A. In cases where the Contractor determines that superimposed loads such as suspended or floor mounted mechanical, electrical, plumbing system or equipment exist which exceed design loads indicated on structural contract documents, Contractor shall submit load data to Design Professionals for review prior to proceeding with work.

B. Distribute the maximum load hung from any structural member for mechanical, electrical, plumbing, ductwork, piping, etc. over the member’s tributary area in a way that the design superimposed dead loads listed in structural contract documents are not exceeded. The Contractor shall coordinate the loads and provide additional support or distribution framing as required achieving the allowable load distribution.

C. Connections of systems designed by Contractor’s engineer such as, but not limited to mechanical, electrical, plumbing loads are assumed to impose vertical and/or horizontal loads on the base building structural members without generating torsion in the supporting structural members. Contractor is responsible for designing, furnishing and installing all supplementary bracing members as required to prevent torsion on the base building structure.

D. Coordinate locations of new fire suppression, plumbing and HVAC penetrations through existing structure and construction. Utilize all existing documentation of conditions for coordination. Verify penetrations utilizing GPR (Ground Penetrating Radar) as necessary to confirm penetration locations.

PART 2 - PRODUCTS

2.1 PERFORMANCE, CAPACITIES AND CHARACTERISTICS

A. See Drawings for Equipment Schedules with Equipment Performance Requirements when capacities and characteristics are not indicated in the specifications.

2.2 EQUIPMENT SHORT CIRCUIT CURRENT RATING

A. Where the National Electrical Code or applicable codes require equipment to be marked with a Short Circuit Current Rating (SCCR), the equipment shall be manufactured as required such that the SCCR of the equipment meets or exceeds the available short circuit current at the equipment. Acceptable methods of complying with this requirement are as follows:

1. Provide SCCR rating at the equipment that meets or exceeds the available short circuit current at the switchboard or panelboard where the equipment circuit originates.

2. Provide calculations, based on the available short circuit current at the switchboard or panelboard where the equipment circuit originates, that document the actual short circuit current available at the equipment. The SCCR rating of the equipment shall meet or exceed this calculated value.

2.3 MATERIALS

A. Unless otherwise specified, all materials and equipment shall be new, unused and undamaged. Materials and equipment shall be the current and standard designs of manufacturers regularly engaged in their production.

2.4 MATERIALS AND EQUIPMENT FURNISHED BY OTHERS

A. Where materials and equipment are indicated as furnished by others and installed or connected under this contract, it shall be the Contractor's responsibility to verify installation details and requirements.

Alvine No. 2022 9198 23 04 00 - 10 11/22/2022

2.5 QUANTITY OF SPECIFIED ITEMS REQUIRED

A. Wherever in these specifications an article, device or piece of equipment is referred to in the singular number; such reference shall apply to as many such articles as are shown on the drawings or required to complete the installation.

2.6 PIPE AND PIPE FITTINGS

A. Refer to individual piping Sections for pipe and fitting materials and joining methods.

B. Pipe Threads: ASME B1.20.1 for factory-threaded pipe and pipe fittings.

2.7 JOINING MATERIALS

A. Refer to individual piping sections for special joining materials not listed below.

B. Pipe-Flange Gasket Materials: Suitable for chemical and thermal conditions of piping system contents.

1. ASME B16.21, nonmetallic, flat, asbestos-free, 1/8-inch maximum thickness, unless thickness or specific material is indicated.

a. Full-Face Type: For flat-face, Class 125, cast-iron and cast-bronze flanges.

b. Narrow-Face Type: For raised-face, Class 250, cast-iron and steel flanges.

2. AWWA C110, rubber, flat face, 1/8 inch thick, unless otherwise indicated; and full-face or ring type, unless otherwise indicated.

C. Flange Bolts and Nuts: ASME B18.2.1, carbon steel, unless otherwise indicated.

D. Solder Filler Metals: ASTM B32, lead-free alloys. Include water-flushable flux according to ASTM B813.

E. Brazing Filler Metals: AWS A5.8, BCuP Series, copper-phosphorus alloys for general-duty brazing, unless otherwise indicated; and AWS A5.8, BAg1, silver alloy for refrigerant piping, unless otherwise indicated.

F. Welding Filler Metals: Comply with AWS D10.12 for welding materials appropriate for wall thickness and chemical analysis of steel pipe being welded.

G. Flanged, Ductile-Iron Pipe Gasket, Bolts, and Nuts: AWWA C110, rubber gasket, carbon-steel bolts and nuts.

H. Couplings: Iron-body sleeve assembly, fabricated to match OD of plain-end, pressure pipes.

1. Sleeve: ASTM A 126, Class B, gray iron.

2. Followers: ASTM A 47 malleable iron or ASTM A 536 ductile iron.

3. Gaskets: Rubber.

4. Bolts and Nuts: AWWA C111.

5. Finish: Enamel paint.

I. Press Fittings:

1. Stainless Steel Pipe:

a. Stainless steel fitting shall conform to material and sizing requirements of ASTM A312 or ASTM A554.

b. Sealing elements shall be EPDM or FKM, depending on application.

Sealing elements shall be factory installed or an alternative supplied by the fitting manufacturer.

2. Copper Tube:

Alvine No. 2022 9198 23 04 00 - 11 11/22/2022

a. Copper and copper alloy press fitting shall conform to material requirements of ASME B16.18 or ASME 16.22 AND Performance criteria of IAPMO PS 117.

b. Sealing elements shall be EPDM. Sealing elements shall be factory installed or an alternative supplied by the fitting manufacturer.

c. On sizes 1/2" to 4" the fitting shall have a feature that assures leakage of liquids and/or gases from inside the system past the sealed elementof an unpressed connection. this function feature shall provide an easy indication of an unsealed connection.

J. Grooved Couplings:

1. General:

a. Couplings shall be two-piece, housing cast with offsetting angle-pattern bolt pads.

b. Installation ready rigid coupling for direct stab installation without field disassembly.

2. Steel Pipe:

a. Manufactured in two segments of cast ductile iron, conforming to ASTM A-536, Grade 65-45-12. Gaskets shall be pressure-responsive synthetic rubber, grade to suit the intended service, conforming to ASTM D-2000.

b. Mechanical Coupling bolts shall be zinc plated ASTM B-633 heat treated carbon steel track head conforming to ASTM A-449 and ASTM A-183, minimum tensile strength 110,000 psi.

1) Rigid Type: Coupling housings with offsetting, angle-pattern bolt pads shall be used to provide system rigidity and support and hanging in accordance with ANSI B31.1, B31.9, and NFPA 13.

a) 2” through 12”: Gasket shall be Grade “EHP” EPDM compound with red color code designed for operating temperatures from -30 deg F to +250 deg F.

2) Flexible Type: Use in locations where vibration attenuation and stress relief are required. Flexible couplings may be used in lieu of flexible connectors at equipment connections. Three couplings, for each connector, shall be placed in close proximity to the vibration source.

a) 2” through 8”: Gasket shall be Grade “EHP” EPDM compound with red color code designed for operating temperatures from -30 deg F to +250 deg F.

c. Flange Adapters: For use with grooved end pipe and fittings, flat faced, for mating to ANSI Class 125 / 150 flanges.

d. Grooved couplings shall meet the requirements of ASTM F-1476.

e. Gasket: Synthetic rubber conforming to steel pipe outside diameter and coupling housing, manufactured of elastomers as designated in ASTM D-2000.

f. Gaskets used for potable water applications shall be UL classified in accordance with ANSI/NSF-61 for potable water service.

3. Copper Tube:

a. 2" through 8": Ductile iron cast housings, complete with a synthetic rubber gasket of a pressure-responsive design, with plated nuts and bolts to secure unit together.

b. Couplings shall be manufactured to connect copper tubing sized tube and fittings. (Flaring of tube and fitting ends to IPS dimensions is not allowed.)

c. Coupling Housings: Ductile iron conforming to ASTM A-536, Grade 65- 45-12, coated with copper colored alkyd enamel. Housings cast with offsetting, angle-pattern bolt pads to provide rigidity.

Alvine No. 2022 9198 23 04 00 - 12 11/22/2022

d. Coupling Gaskets: Gasket shall be Grade “EHP” EPDM compound with red color code designed for operating temperatures from -30 deg F to +250 deg F.

4. Transition coupling:

a. Provide per coupling manufacturer recommendations.

2.8 TRANSITION FITTINGS

A. AWWA Transition Couplings: Same size as, and with pressure rating at least equal to and with ends compatible with, piping to be joined.

1. Manufacturers:

a. Cascade Waterworks Mfg. Co.

b. Dresser Industries, Inc.; DMD Div.

c. Ford Meter Box Company, Incorporated (The); Pipe Products Div.

d. JCM Industries.

e. Smith-Blair, Inc.

f. Viking Johnson.

2. Aboveground Pressure Piping: Pipe fitting.

2.9 DIELECTRIC FITTINGS

A. General: Fitting with insulating material isolating joined dissimilar metals, to prevent galvanic action and stop corrosion. Dielectric unions shall not be used.

B. Description: Combination of copper alloy and ferrous; threaded, solder, plain, and weld-neck end types and matching piping system materials.

C. Insulating Material: Suitable for system fluid, pressure, and temperature.

D. Dielectric Flanges: Factory-fabricated, companion-flange assembly, for 150- or 300-psig minimum working pressure as required to suit system pressures.

1. Manufacturers:

a. Central Plastics Co.

b. Watts Industries, Inc.; Water Products Div.

E. Dielectric-Flange Insulation Kits: Field-assembled, companion-flange assembly, full-face or ring type. Components include neoprene or phenolic gasket, phenolic or polyethylene bolt sleeves, phenolic washers, and steel backing washers.

1. Manufacturers:

a. Calpico, Inc.

b. Central Plastics Co.

2. Provide separate companion flanges and steel bolts and nuts for 150- or 300-psig minimum working pressure as required to suit system pressures.

F. Dielectric Couplings: Galvanized-steel coupling with inert and noncorrosive, thermoplastic lining; threaded ends; and 300-psig minimum working pressure at 225 degrees F.

1. Manufacturers:

a. Calpico, Inc.

b. Lochinvar Corp.

G. Dielectric Nipples: Electroplated steel nipple with inert and noncorrosive, thermoplastic lining; plain, threaded, or grooved ends; and 300-psig minimum working pressure at 225 degrees F.

1. Manufacturers:

a. Grinnell Corp.; Grinnell Supply Sales Co.

b. Victaulic Co. of America.

Alvine No. 2022 9198 23 04 00 - 13 11/22/2022

2.10 SLEEVES

A. Galvanized-Steel Sheet: 0.0239-inch minimum thickness; round tube closed with welded longitudinal joint.

B. Steel Pipe: ASTM A53, Type E, Grade B, Schedule 40, galvanized, plain ends.

C. Cast Iron: Cast or fabricated “wall pipe” equivalent to ductile-iron pressure pipe, with plain ends and integral waterstop, unless otherwise indicated.

D. Stack Sleeve Fittings: Manufactured, cast-iron sleeve with integral clamping flange.

Include clamping ring and bolts and nuts for membrane flashing.

1. Underdeck Clamp: Claming ring with set screws.

2.11 ESCUTCHEONS

A. Description: Manufactured wall and ceiling escutcheons and floor plates, with an ID to closely fit around pipe, tube, and insulation of insulated piping and an OD that completely covers opening.

B. One-Piece, Deep-Pattern Type: Deep-drawn, box-shaped brass with polished chrome-plated finish.

C. One-Piece, Cast Brass Type: With set screw.

1. Finish: Polished chrome-plated.

D. Split-Casting, Cast-Brass Type: With concealed hinge and set screw.

1. Finish: Polished chrome-plated.

E. One-Piece, Stamped-Steel Type: With set screw and chrome-plated finish.

F. Split-Plate, Stamped-Steel Type: With concealed hinge, set screw, and chrome-plated finish.

G. One-Piece, Floor-Plate Type: Cast-iron floor plate.

H. Split-Casting, Floor-Plate Type: Cast brass with concealed hinge and set screw.

2.12 SEALANTS AND FIRESTOPPING

A. Manufacturers:

1. Sealants:

a. Dow Corning

b. Pecora

c. Sonneborn

d. Tremco

2. Firestopping Materials and Systems:

a. A/D Fire Protection Systems Inc: www.adfire.com.

b. 3M Fire Protection Products: www.3m.com/firestop.

c. Hilti, Inc: www.us.hilti.com.

d. Nelson FireStop Products: www.nelsonfirestop.com.

e. Specified Technologies, Inc: www.stifirestop.com.

f. Tremstop Fyre-Sil Sealant - Tremco Sealants & Coatings

B. Silicone Sealant: Single component, air curing, non-staining, non-bleeding, capable of continuous water immersion, non-sagging type for application in vertical joints and in horizontal joints, color as selected.

C. Primer: Non-staining type, recommended by sealant manufacturer to suit application.

Alvine No. 2022 9198 23 04 00 - 14 11/22/2022

D. Joint Cleaner: Non-corrosive and non-staining type, recommended by sealant manufacturer; compatible with joint forming materials.

E. Joint Backing: ANSI/ASTM D1056; round, closed cell, polyethylene foam rod; oversized 30% to 50% larger than joint width.

F. Bond Breaker: Pressure sensitive tape recommended by sealant manufacturer to suit application.

G. Firestopping Materials and Systems:

1. Subject to compliance with the requirements of Division 07 Fire and Smoke Protection.

2.13 ACCESS DOORS

A. Manufacturers:

1. Access Doors:

a. J. L. Industries

b. Karp Associates, Inc.

c. Larsons Mfg. Co.

d. Milcor, Inc.

e. Miller Limited Partnership

f. Nystrom, Inc.

B. Prime coated 14 gauge steel, flush, with screwdriver operated cam lock, frame to accommodate construction type; size as indicated.

2.14 ELECTRICAL WIRE

A. All wiring materials covered by this section shall be in accordance with the latest revision of the National Electrical Code and applicable local codes and shall carry the UL label where applicable.

B. All wiring running exposed in return air plenums shall be plenum-rated cable for fire and smoke spread.

2.15 LOW VOLTAGE CONTROL WIRE AND CABLE

A. All wiring materials section shall be in accordance with the latest revision of the National Electrical Code and applicable local codes and shall carry the UL label where applicable.

B. Analog Input, Analog Output, Binary Input, Binary Output, 24 VAC, and General Purpose Cabling:

1. Cable shall consist of copper conductors not less than #18 AWG stranded.

2. Cable shall be two- or three-conductor twisted cable with a drain wire.

3. Cable shall have a 100 percent overall shield.

4. Cable shall be plenum rated.

5. Cable shall meet or exceed NEC voltage rating of 300 volts.

6. Cable shall be NEC type CMP.

7. Cable shall meet or exceed UL temperature rating of +60 deg C.

8. Cable shall be labeled at a minimum of every 18 inches with the DDC system manufacturer's name and the type of signal carried within the cable, i.e., analog input, analog output, binary input, binary output, 24 VAC.

C. Primary and Secondary Communications Network Cabling:

1. Cable shall be of type recommended by the DDC system manufacturer.

2. Cable shall be shielded.

3. Cable shall be plenum rated.

Alvine No. 2022 9198 23 04 00 - 15 11/22/2022

4. Cable shall meet or exceed NEC voltage rating of 150 volts.

5. Cable shall meet or exceed UL temperature rating of +60 deg C.

PART 3 - EXECUTION

3.1 GENERAL

A. Fabrication, erection, and installation of the complete mechanical system shall be done by qualified personnel experienced in such work and shall proceed in an orderly manner so as not to hold up the progress of the project.

B. The Contractor shall check all areas and surfaces where mechanical equipment or materials are to be installed and report any unsatisfactory conditions before starting work.

C. Commencement of work signifies the Contractor's acceptance of the conditions as fit and proper for the execution of the mechanical work.

D. Equipment and systems shall be installed in accordance with manufacturer's instructions, requirements, or recommendations.

3.2 DELIVERY AND STORAGE OF MATERIALS

A. Take provisions for the delivery and safe storage of materials and shall make the required arrangements with other Contractors for the introduction into the building of equipment too large to pass through finished openings.

B. Materials shall be delivered at such stages of the work as will expedite the work as a whole and shall be marked and stored in such a way as to be easily checked and inspected.

C. Contractor shall be responsible for adequately protecting all supplies and equipment during cold weather.

D. All items subject to cold weather damage shall be protected by covering, insulating, or storing in a heated space.

3.3 COOPERATION WITH OTHER CONTRACTORS

A. Perform the work in conformance with the construction called for by other trades and afford other Contractors reasonable opportunity for the execution of their work.

B. Properly connect and coordinate the mechanical work with the work of other Contractors at such time and in such a manner as not to delay or interfere with their work.

C. Examine the contract documents for the General, Mechanical, and Electrical work and the work of other trades. Coordinate work accordingly.

D. Promptly report to the Architect / Engineer any delay or difficulties encountered in the installation of the mechanical work which might prevent prompt and proper installation of work required from other trades.

E. Systems Test and Balance Contractors or personnel shall coordinate their work with the contractors who installed the systems being tested or balanced.

F. The Temperature Control Contractor or personnel shall be present during systems test and balance.

Alvine No. 2022 9198 23 04 00 - 16 11/22/2022

3.4 COORDINATION OF WORK

A. The list below is the precedence of assigned work items for space priority in descending order. Items not listed shall have the same precedence as similar items.

1. Reflected ceiling with all light fixtures, access above light fixtures required for maintenance, sprinkler head locations, and all ceiling fixtures and devices.

2. Space designed for future utility placement.

3. Gravity flow plumbing waste, roof drainage, and other systems that rely upon gravity for flow.

4. Ductwork and appurtenances, except that external bracing shall be relocated to accommodate local interference.

5. Fire sprinkler piping.

6. Cable tray with access identification 8 inches horizontal to 6 inches above tray.

7. Electrical conduit over 2 inches in diameter.

8. HVAC piping except for pressurized domestic water piping.

9. Plumbing vents.

10. Electrical conduit under 2 inches in diameter.

B. Plan all work so it proceeds with a minimum of interference with other trades.

C. It shall also be the responsibility of the Mechanical Contractor to inform the Contractor of all openings required in the building construction for the installation of the mechanical work.

D. The Contractor shall cooperate with all other contractors in furnishing material and information, in proper sequence, for the correct location of all sleeves, inserts, foundations, wiring, etc.

E. Provisions shall be made for all special frames, openings, and sleeves as required.

F. The Contractor shall pay for extra cutting and patching made necessary by his failure to properly direct such work at the correct time.

3.5 ELECTRICAL WIRING

A. Install wiring in accordance with National Electric Code, ANSI/NFPA 70.

B. All wiring materials covered by this section shall be in accordance with the latest revision of the National Electrical Code and applicable local codes and shall carry the UL label where applicable. All wiring running exposed in air plenums shall be plenum cable.

C. Install wiring (low and line voltage) in metal raceways or conduit unless inside control cabinet or unit enclosures.

1. For concealed, plenum-rated wiring and cabling may be used.

D. Low voltage wiring not installed in conduit shall be supported every five feet from the building structure utilizing metal hangers designed for this application. Wiring shall be installed parallel to the building structural lines. All wiring shall be installed in accordance with local code requirements. Exposed wiring shall only be allowed in concealed accessible locations.

E. Low voltage control wiring and 24 VAC can be run in the same conduit. Power wiring 120 VAC and greater must be in a separate conduit.

F. Fastening shall be secured to walls or ceilings by means of appropriate screws, expansion screws anchors, toggle bolts, hollow wall screw anchors, nylon expansion anchors, or expansion shields. All-purpose plastic anchors are not acceptable.

Alvine No. 2022 9198 23 04 00 - 17 11/22/2022

G. Control panels shall be mounted on vibration-free walls or freestanding structural supports. Panels shall be located as indicated or approved by the Owner's Representative.

H. Locate circuits, relays, transformers, or other equipment that contains or must be connected to voltages exceeding 130 volts, in separate cabinets, which may be adjacent to control panels; permanently label "DANGER 277 VOLTS" or appropriate volts.

I. All wiring in mechanical rooms shall be in conduit. Minimum control wiring conduit size shall be 3/4 inch.

J. Provide with 120v AC, 20 amp dedicated emergency power circuit to each programmable control unit, panel and transformer.

K. Provide extension of 120v, 20 amp circuits and circuit breakers from emergency power panels for all BMCS equipment, transformers and panel power. Provide and install local UPS power supplies for all BMCS system panels and equipment.

3.6 CONTROL WIRING AND POWER CONNECTIONS

A. Provide all incidental control power and wiring required to make the equipment or systems fully operational. Coordinate with equipment manufacture incidental wiring requirements.

B. Unless indicted elsewhere, provide line voltage, 120VAC, 20 amp dedicated control power circuits and LAN outlet to each of the following and as indicated:

1. Control panel, 1 circuit.

2. Air handling Unit, 1 circuit.

3. Air terminal unit transformers, 1 circuit per 20 terminal units.

4. Power supply and transformer panel. 1 circuit can power 20 terminal units.

5. Coordinate required 120V power circuits and LAN outlets with Electrical Contractor.

C. Incidental control wiring includes but not limited to:

1. Air Handling Units:

a. Fans

b. Damper Operators

c. Lights

d. Valve Operators

2. HVAC Controls (Including but not limited to):

a. Control Relays

b. Air Terminal Units

c. Control Dampers and Valves

d. Temperature, Flow and Occupancy Sensors

e. Current Sensors

f. Transmitters

3. Variable Frequency Controls.

3.7 LAYING OUT WORK

A. Carefully lay out all work in advance of installation using data and measurements from the site, the appropriate architectural and structural drawings, and shop drawings.

B. Equipment layout and all system layouts shall confirm adequate clearances for installation, operation, maintenance, and code-required clearances from the structure or other equipment and systems. Provide offsets and elevation changes in piping, conduit and ductwork as required to complete the Layout and Coordination Process. Offsets and

Alvine No. 2022 9198 23 04 00 - 18 11/22/2022 elevation change information shall be indicated in the coordination process documentation and must be submitted for review.

C. The layout shall not cause problems of operation, maintenance, or clearance for items installed by other Contractors.

D. Prior to installation of any work, make certain the location does not conflict with other items in or near the same location.

E. If the layouts so prepared indicate that the required conditions cannot be met in the space provided, inform the Architect / Engineer prior to installation and shall request clarification.

F. Failure to properly coordinate and lay out the work will require correction by the Contractors at their own expense.

3.8 DATA AND MEASUREMENTS

A. Mechanical and electrical drawings are diagrammatic or schematic. Do not scale drawings.

B. The data given herein and on the drawings is as accurate as could be secured; absolute accuracy is not guaranteed.

C. Obtain exact locations, measurements, levels, etc., at the site and shall adapt their work to actual conditions.

D. Examine the general construction, mechanical, electrical, and other applicable drawings and the Specifications.

E. Only architectural drawings, structural drawings, and site measurements may be utilized in calculations.

F. Layout and coordinate all work prior to installation to provide clearances for operation, maintenance and codes. Verify non-interference with other work.

3.9 POSITION OF DEVICES

A. Locate devices mounted on finished surfaces with regard to paneling, furring, trim, etc.

Where several devices occur in a room, they shall be symmetrically arranged as reviewed by the Architect / Engineer.

B. Devices improperly located or installed shall be repaired, replaced or relocated at the Contractor's expense.

C. Devices shall be set plumb or horizontal and shall extend to the finished surface of the wall, ceiling, or floor without projecting beyond the surface.

D. Devices shown on wood trim, cases, or other fixtures shall be installed symmetrically and, where necessary, shall be set with the long dimension of the plate horizontal.

E. Coordinate their respective devices so as not to destroy the aesthetic effect of the surface in which the devices are mounted.

F. Coordinate the locations of all mechanical items with work furnished by other trades to avoid interference.

G. If the required coordination is not done, the outlets or devices shall be removed and relocated if so directed by the Architect / Engineer and the damaged surfaces repaired at the Contractor's expense.

Alvine No. 2022 9198 23 04 00 - 19 11/22/2022

H. Devices shall be installed at the height shown below unless otherwise noted. All heights of devices are measured from finished floor to centerline of device.

I. Heights may be adjusted to correspond to nearest masonry course or as necessary to clear wall-mounted cabinets, fin tube convectors, unit heaters, etc.

1. Temperature control panels: 60 inches

2. Thermostats: 48 inches

3. Carbon dioxide (CO2) sensors: 48 inches

3.10 PROTECTION OF APPARATUS

A. Take such precautions as necessary to properly protect all apparatus, fixtures, appliances, material, equipment, and installations from damage of any kind.

B. Failure to provide such protection to the satisfaction of the Architect / Engineer shall be sufficient cause for the rejection of any particular piece(s) of material, apparatus, equipment, etc., concerned.

3.11 ACCESS TO EQUIPMENT

A. All motors, terminal boxes, valves, control devices, specialties, etc., shall be located to provide for easy access for operation, repair and maintenance; if concealed, access doors shall be provided.

B. Access doors required for access to equipment requiring inspection or service shall be provided.

C. Provide all access doors not already furnished by other Contractors but which are required for access to mechanical equipment.

D. Doors shall be 12 inches by 12 inches unless shown otherwise.

E. Person access doors shall be 18 inches by 18 inches minimum.

3.12 EXAMINATION OF PREMISES

A. Examine the premises and all conditions thereon and/or therein. The bid proposal shall take into consideration all such conditions which may affect the work under this contract.

3.13 ROADWAYS,…

This is the start of the file's text. The full file is on GovTribe.