B08_Attach_16_SubmittalList_Estimate.xlsx
XLSX spreadsheet 72 KB Posted
- Attached to
- ACAD 312255 - Rehabilitate Schoodic Water System
- Solicitation number
- 140P2022R0043
About this file
This document contains a submittal list and review estimate template for a federal construction project to rehabilitate water and wastewater systems at Acadia National Park in Maine. The template provides instructions for completing submittal requirements for over 100 construction submittals across various specification sections. It also includes an estimate of the review time required from multiple engineering disciplines to evaluate action submittals. The related solicitation is for design and construction services for Project ACAD 312255 with the goal of rehabilitating the Schoodic water system. Engineering firms would use this template to estimate the level of effort needed to review submittals and negotiate the scope of work and pricing for providing construction administration and submittal review services during the project.
View the file
Other files
Show all 41
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Instructions
| Submittal List with Review Estimate Instructions | |
| National Park Service (NPS) - Denver Service Center (DSC) | 1-27-21 | |
| DESIGN SERVICES (Construction Documents (CD) Phase) | |
| Responsible Party: Design Architect/Engineer (A/E) | |
| 1 | Enter Park Acronym, Project Management Information System (PMIS) Number, and Project Title. |
| 2 | Record construction submittal requirements. Complete Specification Section, Paragraph Number, and Description sections. Insert additional rows as required for sections containing multiple submittals. |
| 3 | In Requirements section, enter X for submittal requirements where applicable. Insert additional columns as needed under Informational or Action. Refer to Specification Section 01 33 23 for clarification. (Action submittals require Government resposive action and Informational submittals do not.) Division 1 Specifications submittals are Information submittals. |
| 4 | Attach black and white version to Specification Section 01 33 23 in project manual. Delete instructional note on top of page. |
| CONSTRUCTION SERVICES (Construction Phase) | |
| Responsible Party: Construction Contracting Officer Representative (COR) | |
| 1 | Use Submittal List submitted with Final Construction Documents. Copy/paste submittal information into Submittal List with Review Estimate Template. If amendments issued, adjust submittal requirements as necessary. |
| 2 | Attach this template to Architect/Engineer (A/E) Construction Services Scope of Services. |
| 3 | Use Review Estimate to estimate time required for Architect/Engineer to accomplish Action submittal reviews. Enter estimated whole or partial number of hours per discipline. |
| 4 | Add discipline heading column as required. |
| 5 | Use total number of hours per discipline at bottom of template and apply hourly rates listed in Indefinite Delivery/Indefinite Quantity (IDIQ) contract (using appropriate option period rates) to formulate Government estimate for submittal reviews. |
| 6 | Use information from this template to negotiate submittal review portion of Architect/Engineer Construction Services task order. |
| 7 | Provide template to Construction Management Representative (CMR) to show submittals they are responsible for and submittals to be forwarded to the Architect/Engineer. All Informational submittals will be reviewed by Construction Management Representative. |
| Responsible Party: Architect/Engineer (A/E) | |
| 1 | Indicate level of effort required for each Action submittal review by entering number of whole or partial hours for each discipline under Architect/Engineer Review Time section. |
| 2 | All Informational submittals will be reviewed by Construction Management Representative (CMR). |
| 3 | Use total number of hours per discipline at bottom of template and apply hourly rates listed in Indefinite Delivery/Indefinite Quantity (IDIQ) contract (using appropriate option period rates) to formulate estimate. |
| 4 | Use this estimate to negotiate submittals review portion of Architect/Engineer Construction Services portion of the task order. |
&8&K01+024Submittal List with Review Estimate Instructions | National Park Service (NPS) - Denver Service Center (DSC) &8&K01+024page &P of &N
TOC
| Submittal List with Review Estimate Template |
| National Park Service (NPS) - Denver Service Center (DSC) | 1-27-21 |
| SUBMITTAL LIST | ACTION SUBMITTAL | ||||||||||||
| REVIEW ESTIMATE | |||||||||||||
| ACAD 312255 | (Complete this portion for Architect / Engineer (A/E) | ||||||||||||
| Project Title: | REHABILITATE SCHOODIC WATER AND WASTEWATER SYSTEMS | construction service task order negotiation.) | |||||||||||
| SUBMITTAL | REQUIREMENTS | ARCHITECT / ENGINEER REVIEW TIME | |||||||||||
| (Indicate with X) | (Indicate in whole or partial hours.) | ||||||||||||
| INFORMATIONAL | ACTION | ||||||||||||
| SPECIFICATION SECTION | PARAGRAPH NUMBER | DESCRIPTION | CERTIFICATIONS OR LABORATORY TESTS | REPORTS OR CALCULATIONS | |||||||||
| OR PLAN | MANUFACTURER DATA | ||||||||||||
| AND INSTRUCTIONS | COPY | SAMPLES | SHOP DRAWINGS | MANUFACTURER DATA | |||||||||
| AND INSTRUCTIONS | AS-BUILT DRAWIGNS | ARCHITECT | CIVIL ENGINEER | PROCESS ENGINEER | STRUCTURAL ENGINEER | MECHANICAL ENGINEER | ELECTRICAL ENGINEER | INSTRUMENTATION ENGINEER | PROJECT MANAGER COORDINATION | LANDSCAPE ARCHITECT | |||
| 01 11 00 | Summary of Work |
01 26 01 Contract Modification Procedures
01 27 00 Definition of Contract Line Items
| 01 31 00 | Project Management and Coordination | ||
| 1.4.A-B | Coordination Drawings | X | |
| 1.4.C | Coordintation Digital Data Files | X | |
| 1.4.D | Division 1 Documents | X | |
| 1.6.C | List of employees needing access to NPS Sharepoint Site | X | |
| 1.8.C | Environmental Training Program | X |
| 01 32 16 | Construction Schedule | ||||
| 1.3.B | Schedule of Values | X | 2 | 2 | |
| 1.3.C | Construction Baseline Schedule | X | 2 | 2 | |
| 1.3.D | Critical Path Method (CPM) Reports | X | 2 | 2 | |
| 1.3.E | Construction Schedule Updates | X | 2 | 2 | |
| 1.3.F | Construction Schedule Revisions and Time Impact Analysus | X | 2 | 2 |
| 01 32 33 | Photographic Documentation | ||
| 1.2.A | Construction Images | X | |
| 1.2.B | Closeout Images | X |
01 33 23 Submittal Procedures
| 01 35 13.22 | Archeological Protection | |||
| 1.3.A | Daily Work Schedule | X | 1 |
| 01 35 23 | Safety Requirements | |||
| 1.3.A | Accident Prevention Plan | X | 1 |
| 01 40 00 | Quality Requirements | |||
| 1.4.A | Quality Control Plan | X | 1 | |
| 1.4.B | Qualification Data | X | 2 | |
| 1.4.C | Contractor Quality Control Daily Reports | X | 2 | |
| 1.4.D | Test Reports | X | 8 | |
| 1.4.E | Accessibility Inspection Report | X | 1 | |
| 1.4.F | Off-Site Inspection Reports | X | 1 | |
| 1.4.H | Permits, Licenses, and Certificates | X | 1 |
01 42 00 Reference Standards
01 42 13 Abbreviations and Acronyms
01 50 00 Temporary Facilities and Controls
| 01 57 19.11 | Indoor Air Quality Management | |||
| 1.4.A | Indoor Air Quality (IAQ) Management Plan | X | 1 | |
| 1.4.B | Product Data | |||
| 1.4.C | Inspection and Test Reports |
01 57 19.12 Noise and Acoustics Management
| 01 57 23 | Temporary Storm Water Pollution Prevention | |||
| 1.3.A.1 | Storm Water Pollution Prevention Plan (SWPPP) | X | 8 | |
| 1.3.A.2 | Under-An-Acre Pollution Prevention Plan (UPPP) | X | ||
| 1.3.B | Inspection Schedule - Pollution Prevention | X | ||
| 1.3.C | Inspection Schedule - Storm Water Pollution Prevention | X | ||
| 1.3.D | Erosion Control Products | X |
01 57 26 Dust Control
| 01 58 13 | Safety Signage | |||
| 1.2.A | Product Data | X | 2 | |
| 1.2.B | Manufacturer's Catalogs and Data Sheets | X | ||
| 1.2.C | Manufacturer's Standard Color Chips | X | ||
| 1.2.D | Sign Schedule w/ Locations and Graphics | X |
| 01 67 00 | Product Requirements | ||
| 1.3.A.1 | Affirmative Procurement Reporting Form | X | |
| 1.3.A.2 | Environmental Data | X | |
| 1.3.A.3 | Material Safety Data Sheets | X | |
| 1.3.A.4 | Chain of Custody Documentation | X |
| 01 73 29 | Cutting and Patching | |||
| 1.2.A | Cutting and Patching Plan | X | 2 |
| 01 73 40 | Execution | |||
| 1.2.A | Certificates | X | 1 | |
| 1.2.B | Landfill Receipts | X | 1 | |
| 1.2.C | Certified Surveys | X | 1 | |
| 1.2.D | Quantity Surveys | X | 1 |
| 01 74 19 | Construction Waste Management and Disposal | ||||
| 1.4.A | Waste Management Plan | X | 4 | ||
| 1.4.B | Progress Documentation | X | |||
| 1.4.C | Waste Reduction Calculations | X | |||
| 1.4.D | Records of Donations | X | |||
| 1.4.E | Records of Sales | X | |||
| 1.4.F | Recycling and Processing Facility Records | X | |||
| 1.4.G | Landfill and Incinerator Disposal Records | X | |||
| 1.4.H | Qualification Data | X | |||
| 1.4.I | Progress Payment Requirements | X | |||
| 1.4.J | Closeout Submittals | X |
| 01 77 00 | Closeout Procedures | X | 16 | 16 | 4 | 4 | 16 | 16 | 8 | |||||
| 1.2.C | Project Record Drawings | X | ||||||||||||
| 1.3 | Equipment, piping and valve tags | X | X | |||||||||||
| 1.4.A.1 | Specific Warranties, Guarantees, Worksmanship Bonds, Final | |||||||||||||
| Certifications, and Similar Documents | X | |||||||||||||
| 14.A.2 | NPS required forms for occupancy, fire sprinkler/alarm acceptance, and other similar forms or certificates | X | ||||||||||||
| 1.4.A.4 | Environmental Record Documents | X | ||||||||||||
| 1.4.A.5 | Posted Operating Instructions | X | ||||||||||||
| 1.4.A.6 | Keys and Keying Schedule | X | ||||||||||||
| 1.4.A.9 | Pre-functional Checklists and Functional Performance Testing | |||||||||||||
| Reports | X | |||||||||||||
| 1.4.A.10 | Test and Balance Report | X |
| 01 78 23 | Operation and Maintenance Data | |||||||
| 1.2.A | Operations and Maintenance Manuals | X | 24 | 4 | 16 | 24 | 8 |
| 01 79 00 | Demonstration and Training | |||||||
| 1.3.A | Instruction Program | X | 1 | 4 | 4 | 4 | 2 | |
| 1.3.B | Demonstration and Training Video | X | 1 | 4 | 4 | 4 | 2 |
| 01 80 00 | Equipment Startup and Testing | ||||||||
| 1.1.G | System-Specific Startup, Testing, and Training Plans | X | 8 | 32 | 8 | 24 | 24 | 24 | |
| 3.1.J | Equipment Start-Up Certification Forms | X | 2 | 2 | 1 | 2 | 2 | 2 |
| 02 41 00 | Demolition | ||||
| 1.4.A | Demolition Schedule | X | 1 | ||
| 1.4.B | Records | X |
| 02 83 33.13 | Lead Paint Disturbing and Encapsulation Activites | |||||||
| 1.5 B | Work Schedule and Sequence | X | X | |||||
| 1.5 B | Lead Paint Disturbance Plan | X | X | |||||
| 1.5 B | Hazardous Waste Management Plan | X | X | |||||
| 1.5 B | Qualifications | X | X | |||||
| 1.5 B | Manufacturer's Literature and Data | X | X | |||||
| 1.5 B | Site-Specific Health and Safety Plan | X | X | |||||
| 3.6 A | Post Work Submittals - Test Reports | X | X | |||||
| 3.6 A | Certificate of Final Visual Inspections | X | X | |||||
| 3.6 A | Record Documents | X | X |
03 33 00 Product data: Supports for reinforcement X 1
03 33 00 Product data: Admixtures X 1
03 33 00 Product data: Curing compounds X 1
03 33 00 Reinforcement shop drawiings X 2
03 33 00 Formwork shop drawings X 4
03 33 00 Construction joint layout X 1
03 33 00 Laboratory test reports for concrete materials and mix design test X 1
03 33 00 Materials certificates X 1
03 33 00 Cold weather and hot weather concreting procedures X 2
03 33 00 Concrete design mix X 1
| 09 91 00 | Special Coatings | |||
| 1.3.B | List of Products | X | 3 |
09 99 05 Shop Coatings
13 34 23.13 Portable and Mobile Buildings 8 8
22 05 29 Prefabricated Pipe Hangers, Supports, and Bracing X
23 09 03 Control Instrumentation 2
23 09 93 Control Sequences 2
23 34 00 Fans X 2 1
23 82 14 Heating and Cooling Terminal X 2 1
26 00 00 General Electrical Requirements
26 05 19 Low-Voltage Electrical Power Conductors and Cables X 1
26 05 26 Grounding and Bonding for Electrical Systems X 1
26 05 29 Hangers and Supports for Electrical Systems X 1
26 05 33 Raceway and Boxes for Electrical Systems X 1
26 05 43 Underground Ducts and Raceways for Electrical Systems X 2
26 05 73 Power System Studies X 2
26 24 16.13 Lighting and Appliance Panelboards X 2
26 27 26 Wiring Devices X 4
26 28 16 Enclosed Switches and Circuit Breakers
26 29 13 Enclosed Controllers X 2
26 32 13 Engine Generators X 8
26 36 23 Automatic Transfer Switches 4
26 43 00 Surge Protective Devices X 2
26 50 00 Lighting X 2
| 31 00 00 | Earthwork | ||||
| 1.3.B | Test Results | X | X | 4 | |
| 1.3.C | Borrow Material Test Results | X | X | 4 | |
| 1.3.D | Moisture Density Curves | X | X | 4 |
| 31 23 19 | Dewatering | |||||||
| 1.4.B | Temporary Construction Dewatering System Plan | X | 8 | 4 | ||||
| 1.4.C | Qualifications of the Temporary Construction Dewatering | |||||||
| System Design Engineer | X | |||||||
| 1.4.C | Qualifications of the Contractor or specialty subcontractor installing and operating the system | X | ||||||
| 1.4.C.1 | Signed and Sealed Design Calculations | X | ||||||
| 1.4.C.2 | Signed and Sealed Dimensioned Layout Drawings | X | ||||||
| 1.4.C.3 | Detailed Written Description of Dewatering Methods | X | ||||||
| 1.4.C.4 | Pumping Rates | X | ||||||
| 1.4.C.5 | Capacity and Number of standby Pumping Equipment | X | ||||||
| 1.4.C.6 | Capacity and Number of Standby Power Equipment | X | ||||||
| 1.4.C.7 | Treatment Tankage and Discharge Locations | X | ||||||
| 1.4.C.8 | Technical Data on the Well Screens, Filter Materials, and Gradations | X | ||||||
| 1.4.C.9 | Structure Monitoring Plan | X | ||||||
| 1.4.C.10 | Pre-Construction and Post-Construction Survey | X | ||||||
| 1.4.C.11 | Effluent Monitoring Provisions and Laboratory Testing Methods | X | ||||||
| 1.4.C.12 | System Removal Requirements | X | ||||||
| 1.4.E | Water Monitoring Results | X | X |
| 31 23 23.33 | Excavatable Flowable Fill | |||
| 1.2.A | Mix Design | X | 1 |
| 31 25 00 | Erosion and Sedimentation Controls | |||
| 1.2.A | Work Plan & Schedule of Work | X | 2 |
| 31 37 00 | Riprap | ||||
| 1.2.B | Test Results | X | X | 1 |
| 31 50 00 | Excavation Support and Protection | ||||
| 1.4.B | Qualifications of temporary excavation support system design engineer | X | 4 | 2 | |
| 1.4.C | Certificate of Design and Complete Scaled and Dimensioned Layout Drawings | X | 1 | ||
| 1.4.D | Excavation Support System Monitoring Plan | X | 2 | 1 |
| 32 12 16 | Asphalt Paving | |||
| 1.3.A | Job MiX Formula | X | 1 | |
| 1.3.B | Delivery Slips | X | 4 |
| 32 16 13.33 | Asphalt Curbing | X | 1 | ||
| 1.3.A | Certificates | X |
| 32 16 13.43 | Granite Curbing | ||||
| 1.2.A | Shop Drawings | X | 1 | ||
| 1.2.B | Dimensional Information, Layout Diagrams, and Sources of Materials | X | 2 | ||
| 1.2.C | Mortar Mix Design | X | 0.25 | ||
| 1.2.D | Masonry Contractor's Qualifications | X |
| 32 16 23 | Concrete Sidewalks | X | 2 | ||
| 1.3.B | Certificate of Compliance | X |
| 32 17 23 | Pavement Markings | |||
| 1.2.B | Product Data | X | 1 |
| 32 31 13 | Chain Link Fence and Gates | X | 4 | 2 | |
| 1.7.A | Manufacturer Satisfactory Guarantee | X |
| 32 92 20 | Seeding | |||
| 1.2.A | Seed Certification | X | 1 | |
| 1.2.B | Top Soil Test Results | X | 1 | |
| 1.2.C | Lime & Fertilizer Invoices | X | 1 |
| 33 00 00 | Pipe and Pipe Fittings - General | ||||
| 3.3.B.3.d | Bacteriological Test Results | X | X | 1 |
33 01 12 Inspection and Testing of Water Utilities
33 01 30.01 Final Sewer Testing
33 01 30.02 Sewer Line Joint Testing
| 33 01 30.16 | Television Inspection of Sewers | |||||
| 1.3.B | NASSCO PACP Certifications | X | X | 1 | ||
| 3.1.D.4 | Video and Photographs | X | 24 | 4 |
| 33 01 30.51 | Sewer Flow Control | |||
| 1.2.A.1 | Proposed Schedule, Sequence of Construction, Duration of Activities, and Description of Sewer Control Methods | X | 4 | |
| 1.2.A.2 | Temporary Pumping Equipment Technical Data | X | 2 | |
| 1.2.A.3 | Sewer Flow Control Supplemental Information | X | 2 |
33 01 30.53 Sewer Line Cleaning
| 33 01 30.72 | Sewer Pipe Lining | ||||
| 2.3.A | Design Calculations | X | 2 | ||
| 2.3.B | Materials and Installation Procedures | X | 1 | ||
| 2.3.C | Pre-Installation CCTV Inspection and Post- Lining CCTV Inspection | X | 24 | ||
| 2.3.D | Outreach Plan | X | 1 | ||
| 2.3.E | Qualifications, Training, and Experience of Installers | X | X | 1 | |
| 2.3.F | Equipment List | X | 1 | ||
| 2.3.G | Plan for providing and disposing of water if curing the liner by water | X | 2 | ||
| 2.3.H | Odor Mitigation Plan | X | 1 | ||
| 2.3.I | Proposed or Potential Repair and/or Rehabilitation Methods | X | 4 | ||
| 2.3.J | Wet-Out Logs, Saturation Charts, and Curing Schedules | X | 4 | ||
| 2.3.K | Temperature Measurements and Samples for Testing | X | 4 |
| 33 01 30.81 | Manhole Rehabilitation | |||
| 1.5.A | Shop Drawings | X | 8 | |
| 1.5.B | Materials and Installation Procedures | X | 2 | |
| 1.5.C | Field-Testing Processes and Procedures | X | 2 | |
| 1.5.D | Five Verifiable References | X | 2 | |
| 1.5.E | Installation History | X | 1 |
| 33 05 05 | Watermains and Appurtenances | ||||
| 1.3.A | Shop Drawings and Product Data | X | 6 | 2 |
33 05 09.13 Couplings and Connectors for Buried Applications X 1
33 05 17 Sewer Force Main Copper Tubing Size HDPE X 4
33 05 19 Ductil Iron Pipe and Fittings Buried Application X 1
| 33 05 31.11 | Polyvinyl Chloride Gravity Sewer Pipe | ||||
| 1.3.A | Shop Drawings | X | 2 | ||
| 1.3.B | Certificate of Conformance | X | X | 1 |
| 33 05 33 | High Density Polyethylene Pipe and Fittings | |||||
| 1.3.A | Shop Drawings | X | 1 | |||
| 1.3.B | Certification of Conformance | X | X | 1 | ||
| 1.3.C | Experience Statement | X | 0 | |||
| 1.3.D | Joint Fusion Data | X | 1 | |||
| 1.3.E | Manufacturer Installation Instructions and Specifications | X | 1 |
| 33 05 46 | Asbestos-Containing Materials Abatement | |||||
| 1.2.A | Abatement Plan | X | X | 1 | ||
| 1.5.B.1 | Certification of Compliance | X | X | X | 0 | |
| 1.5.B.2 | Respiratory Protection Program | X | X | 0 | ||
| 1.5.B.3 | Project Schedule | X | X | 1 | ||
| 1.5.B.4 | Emergency Action Plan | X | X | 1 | ||
| 1.5.B.5 | Proposed Waste Disposal Site and Waste Transporter | X | X | 1 | ||
| 1.5.B.6 | Safety Data Sheets | X | X | 0 | ||
| 1.5.B.7 | Work Plan | X | X | 1 | ||
| 1.5.C | Results of Personnel Exposure Monitoring | X | ||||
| 1.5.D | Disposal Receipts | X | ||||
| 1.5.D.2 | Copies of On-Site Job Logs, Notifications, Permits, Accident Reports, Waivers of Lien | X | ||||
| 1.5.D.3 | Copies of Any Notices of Non-Compliance | X |
| 33 05 61 | Concrete Manholes | ||||||
| 1.3.A | Shop Drawings and Manufactuer's Literature | X | X | 8 | 4 | ||
| 1.3.B | Test Results | X | X |
33 05 97 Identification and Signage for Utilities X 1
| 33 11 36 | Submersible Well Pump | |||||
| 1.3.A | Shop Drawings, Manufacturers' Literature, Maintenance Data, Operating Instructions, and List of Spare Parts and Maintenance Materials | X | X | 8 | 2 | |
| 1.3.B.1 | Factory Certified Testing | X | 2 | |||
| 1.3.B.2 | Field Acceptance Testing | X | 2 | |||
| 1.3.C | Complete Dimensions of Pump and Motor Unit, Series and Types of Shafts, Type of Bowl Lining, and Drawings | X | 2 |
| 33 14 19 | Gate Valves | ||||||
| 1.3.A | Shop Drawings | X | X | 3 | 1 | ||
| 1.3.B | Manufacturer's Certificate of Conformance | X | X | ||||
| 1.3.C | Manufacturer's Installation Instructions and Specifications | X | X |
| 33 14 23 | Piping Insulation | |||||
| 1.3.A | Shop Drawings | X | X | 4 | 1 |
33 14 23.02 Valve Boxes X 1
| 33 15 01 | Rigid Board Insulation for Pipe in Trenches | |||
| 1.3.A | Shop Drawings, Product Data, and Manufacturer's Installation Instructions | X | 1 |
| 33 15 02 | Tracer Wire | |||
| 1.2.A | Manufacturer's Material Specifications | X | 1 |
40 05 06 Couplings, Adaptors, and Specials for Process Piping X 3
40 05 09 Wall Pipes, Floor Pipes, and Pipe Sleeves X 2
40 05 19 Ductile Iron Process Pipe X 2
40 05 24 Steel Process Pipe X 2
40 05 31.14 Polyvinyl Chloride PVC Pipe (Pressure) X 1
40 05 53 Valves and Specialties General
40 05 61 Gate Valves (INTERIOR) X 1
40 05 63 Process Systems Ball Valves Bronze Body X 0.5
40 05 65 Check Valves X 3
40 05 78 Air Release Valves X 2
| 40 61 00 | Instrumentation and Control General | |||
| 1.3.A.1 | Shop Drawings and Operation and Maintenane Manuals | X | 16 | |
| 1.3.A.5 | Samples of Programs and Graphics | X | 1 | |
| 1.3.B | Test and Checkout Reports | X | 4 |
| 40 62 00 | SCADA (HMI) System | ||||
| 1.2.A | Shop Drawings | X | X | 12 |
| 40 63 00 | Programmable Logic Controllers | |||
| 1.3.A | Shop Drawings | X | 4 | |
| 1.3.B | Ladder Logic | X | 2 | |
| 1.3.C.1 | PLC I/O Configurations | X | 4 | |
| 1.3.C.2 | PLC Communication Configurations | X | 4 | |
| 1.3.C.3 | PLC Cross Reference List | X | 4 | |
| 1.3.C.4 | PLC Tag Data Base and Memory Usage | X | 2 | |
| 1.3.C.5 | OIT Communication Configurations | X | 1 | |
| 1.3.C.6 | OIT Screen List | X | 1 | |
| 1.3.C.7 | OIT Screen Printouts | X | 1 |
| 40 66 00 | Communication Network | |||
| 1.3.A | Shop Drawings and Samples | X | 4 | |
| 1.3.B | Test and Checkout Reports | X | 2 | |
| 1.3.C | Directions | X | 2 | |
| 1.3.D | List of Local Service Departments | X | 0.5 | |
| 1.3.E | Record Drawings | X | 4 |
| 40 66 33 | Fiber Optic Cabling | ||||
| 1.4.A | Working Drawings, Shop Drawings, and Material Specifications | X | X | 2 | |
| 1.4.B | Fiber Diagrams | X | 2 |
| 40 66 43 | Wireless Network System | ||||
| 1.3.A | Shop Drawings | X | X | 2 | |
| 1.3.B | Operations and Maintenance Manuals | X | 4 | ||
| 1.3.C | Record Drawings | X | 8 |
| 40 67 00 | Control Panels | ||||
| 1.3.A | Shop Drawings | X | X | 2 | |
| 1.3.A.2 | Bill of Materials | X | 1 | ||
| 1.3.A.3 | Factory Acceptance Testing Report Results | X | 1 |
| 40 70 00 | Field Instruments | ||||
| 1.3.A | Shop Drawings and Samples | X | X | 4 |
| 41 22 13 | Portable Davit Crane and Cable Winch | ||||
| 1.3.A | Shop Drawings | X | X | 2 | |
| 1.3.B | Detailed Layout Drawings | X | 1 |
43 05 20 Pumps General
| 43 26 13 | Grinder Pump Station (WastewaterPSs) | ||||||
| 1.3.A | Shop Drawings, Manufactuer's Literature, Short-Term and Long-Term Storage Requirements, and Operations and Maintenance Manuals | X | X | 8 | 16 | 8 | |
| 1.3.B.2 | Precast Concrete Structure Design Calculations | X | 2 |
Total: 8 292.25 117.5 27 25 100 168.5 87 0