Attachment 30 - Milestone Schedule.pdf
PDF 322 KB Posted
- Attached to
- 36C77623B0043 - EHRM Infrastructure Upgrades - Hines, IL - Solicitation Federal contract opportunity
- Solicitation number
- 36C77623B0043
About this file
This document provides a milestone schedule for mechanical, electrical, plumbing, and fire protection engineering consulting services for the VA Hines EHRM Project located in Hines, Illinois. Key dates include a notice to proceed by July 26th, with 30%, 60%, 90-95%, and 100% design submittals due on September 24th, February 23rd, March 15th, and May 5th respectively. Review meetings will take place 10 to 30 days after each submittal. A final documents package is due May 31st. The schedule also includes planned design modifications and a change request.
View the file
Other files for this federal contract opportunity
Show all 50
36C77623B0043 - EHRM Infrastructure Upgrades - Hines, IL - Solicitation has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
APPENDIX 4
Milestone Schedule
Mechanical
Electrical
Plumbing
Fire Protection
Technology
Consulting Engineers www.specializedeng.com
May 31, 2023
RE: VA Hines EHRM Project Schedule
SES Project #: 21081 VA Project #: 578-21-701 Software Presented: Word/PDF
Remaining Milestone Schedule
• NTP – July 26th
• CPM Draft Schedule and Milestones – Aug 26th (30 days from NTP)
• CPM Final Working Schedule – September 10th (45 days from NTP)
• 30% Design Submittal – September 24th (60 days from NTP)
• Mod 1 – Add Buildings: 3 & 220, Remove Building 215 – September 24th
• 30% Review Meeting – October 4th (10 days)
• Notice to proceed into 60% – December 15th.
• 60% Design Submittal – February 23rd (34 days)
• 60% Review Meeting – March 24th and April 1st
• Issue 65% Complete Package – November 14th (18 days)
• 65% Review Meeting – November 30th (16 days)
• 65% Review Comments Returned – December 16th /17th
• 65% Acceptance Discussion – February 1st
• 90% 95% Design Submittal – March 15th (42 days) o Change Request B included (Descoping of MCR and Fusion Splice)
• 90% 95% Review Meeting – April 14th (30 days)
• 100% Design Submittal – May 5th (21 days) o Change Request for B228 Economizer
• 100% Review Meeting – May 15th (10 days) o Goals for review meeting:
▪ Review comments for DCIE and HEFP
▪ 4 hour window
• 100% Final Documents – May 31st (16 days)