Attachment 2 - Price Schedule.docx
DOCX document 16 KB Posted
- Solicitation number
- 36C25926Q0519
About this file
This is a Price Schedule document for fire system inspection and repair services at the Department of Veterans Affairs Western Colorado Health Care System (VA WCHCS) for the base year period of July 1, 2026 through June 30, 2027.
The contract includes three line items (CLINs) requiring labor and equipment. CLIN 0001 covers repair of kitchen hood deficiencies at three locations (NFS, Canteen, and CLC) with a quantity of 3 job orders. CLIN 0002 addresses labor and equipment to close annual deficiency findings including battery replacement and sensor strobe equipment upgrades across five locations (Parking Garage, Buildings 5, 6, 33, and 37) with a quantity of 5 job orders. CLIN 0003 requires labor and equipment to close quarterly sprinkler deficiency findings across thirteen buildings (1, 5, 6, 7, 8, 12, 13, 20, 22, 33, 34, 36, and 45) with a quantity of 13 job orders. Unit pricing is expressed in job orders (JB), with all unit prices and total amounts left blank for offerors to complete. The solicitation number is 36C25926Q0519, with offers due by 5:00 PM Mountain Time on June 22, 2026, and the contracting officer is identified as Heather Chase at heather.chase2@va.gov. This is a one-year-only requirement with no incumbent contractor.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PRICE SCHEDULE
POP: Base Year July 1, 2026 – June 30, 2027
| CLIN |
| DESCRIPTION OF SERVICES |
| QTY |
| U/I |
| UNIT PRICE |
| TOTAL AMOUNT |
| 0001 |
| Repair Kitchen Hood Deficiencies (NFS, Canteen, and CLC locations) in accordance with the Statement of Work. |
Contract Period: Base POP Begin: 07-01-2026 POP End: 06-30-2027
| 3 |
| JB |
| $_______ |
| $_____________ |
| 0002 |
| Labor and equipment to close Annual deficiency findings in accordance with the Statement of Work. Tasks include battery replacement and sensor strobe equipment. Affected locations include Parking Garage, Buildings 5, 6, 33, and 37. |
Contract Period: Base POP Begin: 07-01-2026 POP End: 06-30-2027
| 5 |
| JB |
| $_______ |
| $_____________ |
| 0003 |
| Labor and equipment to close Quarterly Sprinkler deficiency findings in accordance with the Statement of Work. Affected locations include Buildings 1, 5, 6, 7, 8, 12, 13, 20, 22, 33, 34, 36, and 45. |
Contract Period: Base POP Begin: 07-01-2026 POP End: 06-30-2027
| 13 |
| JB |
| $_______ |
| $_____________ |
| BASE YEAR TOTAL |
| $ |
File details come from the government source that posted it. Updated .