This is a Price Schedule document for fire system inspection and repair services at VA Western Colorado Health Care System (WCHCS) under solicitation 36C25926Q0519. The contract covers a one-year period from July 15, 2026, through July 14, 2027, and includes three line items (CLINs) with blank pricing fields to be completed by offerors. CLIN 0001 requires repair of kitchen hood deficiencies at three locations (NFS, Canteen, and CLC) with a quantity of 3 job orders. CLIN 0002 involves labor and equipment to close annual deficiency findings including battery replacement and sensor strobe equipment at five locations (Parking Garage and Buildings 5, 6, 33, and 37) with a quantity of 5 job orders. CLIN 0003 covers labor and equipment to address quarterly sprinkler deficiency findings across thirteen buildings (1, 5, 6, 7, 8, 12, 13, 20, 22, 33, 34, 36, and 45) with a quantity of 13 job orders. All work must be performed in accordance with the Statement of Work and is intended to correct previously identified deficiencies and document repairs for Joint Commission audit purposes. Offers were due by June 29, 2026, at 12:00 PM MT to heather.chase2@va.gov. The price schedule contains no award date, set-asides, or contract vehicle designations.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PRICE SCHEDULE
POP: Base Year July 15, 2026 – July 14, 2027
| CLIN |
| DESCRIPTION OF SERVICES |
| QTY |
| U/I |
| UNIT PRICE |
| TOTAL AMOUNT |
| 0001 |
| Repair Kitchen Hood Deficiencies (NFS, Canteen, and CLC locations) in accordance with the Statement of Work. |
Contract Period: Base POP Begin: 07-15-2026 POP End: 07-14-2027
| 3 |
| JB |
| $_______ |
| $_____________ |
| 0002 |
| Labor and equipment to close Annual deficiency findings in accordance with the Statement of Work. Tasks include battery replacement and sensor strobe equipment. Affected locations include Parking Garage, Buildings 5, 6, 33, and 37. |
Contract Period: Base POP Begin: 07-15-2026 POP End: 07-14-2027
| 5 |
| JB |
| $_______ |
| $_____________ |
| 0003 |
| Labor and equipment to close Quarterly Sprinkler deficiency findings in accordance with the Statement of Work. Affected locations include Buildings 1, 5, 6, 7, 8, 12, 13, 20, 22, 33, 34, 36, and 45. |
Contract Period: Base POP Begin: 07-15-2026 POP End: 07-14-2027
| 13 |
| JB |
| $_______ |
| $_____________ |
| BASE YEAR TOTAL |
| $ |