About this file

This is a Statement of Work for construction services addressing repairs to exterior features at the Jonathon M. Wainwright Memorial Medical Center in Walla Walla, Washington. The project encompasses 25 buildings that exceed 50 years old with systems beyond their useful lives. Work requirements include repair of exterior features across various labor divisions, mechanical and electrical work necessary for exterior repairs, architectural services as required, and structural and foundation modifications to support new exterior repairs. The contractor must deliver inspection and testing documents, manuals, and warranty documentation per specifications, with a performance period of 365 days.

The contracting officer's representative will monitor all work and testing to ensure items are in clean condition and proper working order. Final system acceptance requires a systems demonstration per specifications. The contractor is responsible for organizing weekly update meetings with the government team, including the superintendent, site safety and health officer, COR, and relevant personnel, with meeting agendas covering project progress, upcoming work, hazard analysis, requests for information, and risk management. Meeting minutes must be provided to the COR following each session. Work hours will be coordinated with the COR, and all work will be performed at the VA Medical Center located at 77 Wainwright Drive, Walla Walla, WA 99362-3975. The solicitation number is 36C26026R0033, issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 20.

View the file

Other files for this federal contract opportunity

Other files attached to 687-23-101 CON Repair Exterior Features, newest first.
File Type Posted
36C26026R0033 0009.pdf PDF
36C26026R0033 0008.docx DOCX document
Attachment 10 - RFI Questions P0008.docx DOCX document
Attachment 4 - 687-23-101_100__COMPLETE_DRAWING_SET_VA REDLI.pdf PDF
Attachment 2 - SPECS VOL 1 Rev 1 Less T1 and T2.pdf PDF
Attachment 12 - Asbestos Survey - Building 48 - Final Rev 1.pdf PDF
Attachment 15 - Asbestos Survey - Building 65 - Final Rev 1.pdf PDF
Attachment 22 - Asbestos Survey - Building 120 - Final Rev 1.pdf PDF
Attachment 23 - Asbestos Survey - Building T1 - Final Rev 1.pdf PDF
Attachment 26 - Exterior Building Lead Condition-Presence-Absence.pdf PDF
Attachment 14 - Asbestos Survey - Building 63 - Final Rev 1.pdf PDF
Attachment 18 - Asbestos Survey - Building 81 - Final Rev 1.pdf PDF
Attachment 24 - Asbestos Survey - Building T2 - Final Rev 1.pdf PDF
Attachment 28 - RFI and Responses 687-23-101.xlsx XLSX spreadsheet
36C26026R0033 0007.pdf PDF
Attachment 10 - Asbestos Survey - Building 31 - Final Rev 1.pdf PDF
Attachment 11 - Asbestos Survey - Building 41 - Final Rev 1.pdf PDF
Attachment 13 - Asbestos Survey - Building 49 - Final Rev 1.pdf PDF
Attachment 16 - Asbestos Survey - Building 66 - Final Rev 1.pdf PDF
Attachment 19 - Asbestos Survey - Building 82 - Final Rev 1.pdf PDF
Attachment 20 - Asbestos Survey - Building 105 - Final Rev 1.pdf PDF
Attachment 21 - Asbestos Survey - Building 107 - Final Rev 1.pdf PDF
Attachment 25 - Asbestos Survey - Building T7 - Final Rev 1.pdf PDF
Attachment 27 - 08 71 00 DOOR HARDWARE.pdf PDF
Attachment 17 - Asbestos Survey - Building 76 - Final Rev 1.pdf PDF
Attachment 29 - Mobilization-Project-Areas.pdf PDF
36C26026R0033 0006.docx DOCX document
Site Visit 2nd Sheet.pdf PDF
36C26026R0033 0005.docx DOCX document
Site Visit Sign-In Sheet - February 9 2026.jpg JPG image
36C26026R0033 0004.docx DOCX document
687-23-101_Repair_Exterior_Features_Geotech Memorandum.pdf PDF
687-23-101- 36C26026R0033 - Contractor Questions and Answers.pdf PDF
36C26026R0033 0003.docx DOCX document
36C26026R0033 0002.docx DOCX document
36C26026R0033 0002 pdf version Rev. 01.pdf PDF
36C26026R0033 0002 pdf version Rev. 01.pdf PDF
36C26026R0033 pdf version.pdf PDF
36C26026R0033 0001.docx DOCX document
Attachment 4 - COMPLETE_DRAWING_SET_VA REDLINES.pdf PDF
Attachment 3 - SPECS VOL 2 687-23-101 Exterior Repairs 01.26.2026.pdf PDF
Attachment 2 - SPECS VOL 1 687-23-101 Exterior Repairs 01.26.2026.pdf PDF
36C26026R0033.docx DOCX document
Attachment 8 - Contractor Rules of Behavior 687-23-101 Repair Exterior Features.pdf PDF
Attachment 7 - PPQ NCO 20 687-23-101.docx DOCX document
Attachment 5 - Divisional Price Breakout.xlsx XLSX spreadsheet
Attachment 9 - Wage Determination 1.23.2026.pdf PDF
Attachment 6 - Limitations on Subcontracting 687-23-101 Repair Exteriors.docx DOCX document
Show all 48

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

687-23-101 Repair Exterior Features

STATEMENT OF WORK FOR CONSTRUCTION SERVICES

Jonathon M. Wainwright Memorial Medical Center Walla Walla, Washington May 21, 2025

1. General Many of the buildings at the Walla Walla VA exceed 50 years old and many systems are beyond their useful lives. This project repairs exterior features including roofs, siding, foundations, windows and other appurtenances.

2. Scope The scope of work for this project includes 25 buildings. The specifications and drawings demonstrate all the work requirements which include: Comment by Moreland, Marvin J. (Walla Walla): How many buildings? SSP has different number Comment by Howe, Susan L. (NCO20): 25 IS THE CORRECT NUMBER.

a. Repair of exterior features with various divisions of labor.

b. Mechanical and electrical work required to repair exterior features.

c. Architectural work as required to repair exterior features.

d. Structural and foundation modifications as required to support new exterior repairs.

3. Deliverables Inspection, testing documents, manuals, and warranty documents per Specifications.

4. Period of Performance The contractor has 365 days to perform all the work described.

5. Performance Monitoring The COR assigned to the Engineering Service will evaluate all work and testing performed. Items must be in a clean state and in a proper and acceptable working condition.

6. Inspection and Acceptance Criteria As part of final system acceptance, a systems demonstration is required per Specifications.

7. Project Meetings The contractor will be responsible for organizing weekly update meeting with the COR. At a minimum this meeting will include contractor’s superintendent, SSHO, government COR, and any other personnel relevant to that week’s agenda. The minimum weekly agenda will be a review of project progress, review of next week’s work, discussion of next week’s activity hazard analysis, review any RFIs, discuss any new risk or current risks not closed out, other topics as determined necessary by contractor or the VA. The quality control will have a separate meeting to discuss current activities and last week’s report with VA COR and contracting team.

Note: After any project meeting the contractor will provide a report with meeting minutes to the COR.

8. Work Hours Work hours will be coordinated with COR per Specification.

9. Place of Performance Walla Walla VA Medical Center - Jonathon M. Wainwright Memorial Medical Center located at 77 Wainwright Drive, Walla Walla, WA 99362-3975.