This is a geotechnical memorandum prepared by GDM of Oregon, a Service-Disabled Veteran-Owned Small Business, dated February 29, 2024, documenting soil conditions at the Jonathan M. Wainwright VA Medical Center in Walla Walla, Washington for the Exterior Improvements Project. The site is characterized by loamy and silty soils with areas of clay and sandy loam, typical of the region's agricultural prominence. Soil composition includes three primary layers: a topsoil layer rich in organic material with limited structural bearing capacity; subsoil layers of loam, silt loam, and clay loam offering moderate to high bearing capacities but presenting shrink-swell challenges in clay-rich areas; and underlying strata of bedrock or gravel deposits providing good bearing capacity for deep foundations. Groundwater levels fluctuate seasonally based on local precipitation and proximity to rivers/streams, with potential impacts on excavation and foundation design due to soil saturation and hydrostatic pressure concerns.

The memorandum identifies three primary geotechnical challenges: soil stability issues from seasonal volume changes in high clay content areas, erosion and sediment control requirements during construction, and seismic considerations for compliance with local building codes. Preliminary recommendations specify that a detailed geotechnical investigation is not recommended; instead, ASCE-7 should be used to determine seismic parameters based on Site Class D requirements with 1500 PSF bearing capacity. Foundation designs should employ an underpinning system to level and restrain buildings, with helical piers as an alternative option. The memorandum emphasizes comprehensive erosion and sediment control measures and effective stormwater management, noting that most foundation damage results from inadequate gutters, downspouts, and water conveyance systems. The assessment was prepared by Adam Goddin, PE (WA PE #46,941).

View the file

Other files

File Type Posted
36C26026R0033 0009.pdf PDF
36C26026R0033 0008.docx DOCX document
Attachment 2 - SPECS VOL 1 Rev 1 Less T1 and T2.pdf PDF
Attachment 4 - 687-23-101_100__COMPLETE_DRAWING_SET_VA REDLI.pdf PDF
Attachment 10 - RFI Questions P0008.docx DOCX document
Attachment 13 - Asbestos Survey - Building 49 - Final Rev 1.pdf PDF
Attachment 20 - Asbestos Survey - Building 105 - Final Rev 1.pdf PDF
Attachment 12 - Asbestos Survey - Building 48 - Final Rev 1.pdf PDF
Attachment 21 - Asbestos Survey - Building 107 - Final Rev 1.pdf PDF
Attachment 11 - Asbestos Survey - Building 41 - Final Rev 1.pdf PDF
Attachment 19 - Asbestos Survey - Building 82 - Final Rev 1.pdf PDF
Attachment 29 - Mobilization-Project-Areas.pdf PDF
Attachment 17 - Asbestos Survey - Building 76 - Final Rev 1.pdf PDF
Attachment 23 - Asbestos Survey - Building T1 - Final Rev 1.pdf PDF
Attachment 22 - Asbestos Survey - Building 120 - Final Rev 1.pdf PDF
Attachment 26 - Exterior Building Lead Condition-Presence-Absence.pdf PDF
Attachment 16 - Asbestos Survey - Building 66 - Final Rev 1.pdf PDF
Attachment 10 - Asbestos Survey - Building 31 - Final Rev 1.pdf PDF
Attachment 15 - Asbestos Survey - Building 65 - Final Rev 1.pdf PDF
Attachment 25 - Asbestos Survey - Building T7 - Final Rev 1.pdf PDF
Attachment 27 - 08 71 00 DOOR HARDWARE.pdf PDF
Attachment 18 - Asbestos Survey - Building 81 - Final Rev 1.pdf PDF
Attachment 24 - Asbestos Survey - Building T2 - Final Rev 1.pdf PDF
36C26026R0033 0007.pdf PDF
Attachment 28 - RFI and Responses 687-23-101.xlsx XLSX spreadsheet
Attachment 14 - Asbestos Survey - Building 63 - Final Rev 1.pdf PDF
36C26026R0033 0006.docx DOCX document
Site Visit 2nd Sheet.pdf PDF
Site Visit Sign-In Sheet - February 9 2026.jpg JPG image
36C26026R0033 0005.docx DOCX document
36C26026R0033 0004.docx DOCX document
687-23-101- 36C26026R0033 - Contractor Questions and Answers.pdf PDF
36C26026R0033 0003.docx DOCX document
36C26026R0033 0002.docx DOCX document
36C26026R0033 0002 pdf version Rev. 01.pdf PDF
36C26026R0033 0002 pdf version Rev. 01.pdf PDF
36C26026R0033 pdf version.pdf PDF
36C26026R0033 0001.docx DOCX document
36C26026R0033.docx DOCX document
Attachment 5 - Divisional Price Breakout.xlsx XLSX spreadsheet
Attachment 1 - SOW CON Repair Exterior Features Rev 01.docx DOCX document
Attachment 9 - Wage Determination 1.23.2026.pdf PDF
Attachment 6 - Limitations on Subcontracting 687-23-101 Repair Exteriors.docx DOCX document
Attachment 2 - SPECS VOL 1 687-23-101 Exterior Repairs 01.26.2026.pdf PDF
Attachment 3 - SPECS VOL 2 687-23-101 Exterior Repairs 01.26.2026.pdf PDF
Attachment 4 - COMPLETE_DRAWING_SET_VA REDLINES.pdf PDF
Attachment 8 - Contractor Rules of Behavior 687-23-101 Repair Exterior Features.pdf PDF
Attachment 7 - PPQ NCO 20 687-23-101.docx DOCX document
Show all 48

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GDM of Oregon A Service‐Disabled Veteran‐Owned Small Business

GEOTECHNICAL MEMORANDUM

Date: 02/29/2024

From: Adam Goddin, PE; Engineer

Subject: Soil Conditions at Jonathan M. Wainwright VA Medical Center;

Walla Walla, WA

To: Eric Shreve, RA; Project Architect

This memorandum provides an overview of the known soil conditions at the site of the Jonathan M. Wainwright VA Medical Center; Walla Walla, WA It aims to outline general soil characteristics, potential geotechnical challenges, and preliminary considerations for future construction or development projects at this location. More specifically, the Exterior Improvements Project.

Site Description The area is characterized by its varied topography and the presence of local river/streams, which may influence local soil conditions and groundwater levels.

Soil Composition The soil in Walla Walla, Washington, generally consists of loamy and silty soils, with areas of clay and sandy loam. These soil types are indicative of the region's agricultural prominence and can vary significantly in terms of drainage properties and load-bearing capacities.

1. Topsoil Layer: The uppermost layer is typically rich in organic material, with a depth that varies across the site. This layer is important for vegetation but has limited structural bearing capacity.

2. Subsoil Layers: Below the topsoil, the subsoil layers consist primarily of loam, silt loam, and clay loam. These layers can offer moderate to high bearing capacities but may present challenges in terms of shrink-swell potential, especially in areas with significant clay content.

3. Underlying Strata: Bedrock or denser soil layers, such as gravel or sandy deposits, may be present at varying depths. These layers generally provide good bearing capacity and are critical for deep foundations.

Groundwater Conditions Groundwater levels in the area can fluctuate seasonally and are influenced by local precipitation patterns and proximity to local river/streams. The presence of groundwater near the surface can impact excavation works and foundation design due to potential issues with soil saturation and hydrostatic pressure.

Geotechnical Challenges

Soil Stability: Areas with high clay content may experience significant seasonal volume changes, leading to potential soil heave or settlement.

Erosion and Sediment Control: Due to the site's topography and soil types, erosion control measures will be critical during construction to prevent sediment runoff and protect water quality.

Seismic Considerations: While not in a primary seismic zone, seismic considerations may need to be addressed in the structural design to comply with local building codes.

Preliminary Recommendations

1. Geotechnical Investigation: A detailed geotechnical investigation, including soil borings and laboratory testing, is not recommended. Use ASCE-7 to determine seismic parameters based on Site Class D Requirements. Use 1500 PSF for bearing.

2. Foundation Design: Foundation designs should consider the variability in soil conditions, with special attention to areas with high clay content or shallow groundwater levels. Recommend using an underpinning system to level and restrain buildings. See attached engineering drawing. Helical piers may also be used.

3. Erosion and Water Management: Implement comprehensive erosion and sediment control measures, along with effective stormwater management practices, to protect soil stability and water quality during and after construction. Most of the damage caused to the foundations is by a lack of gutters, downspouts, and conveyance.

Conclusion The soil conditions at the Walla Walla, WA VA Medical Center present both challenges and opportunities for future development. A thorough understanding of these conditions will be crucial in ensuring the stability and longevity of any structures on this site.

Please feel free to contact me for further details or clarification regarding this preliminary assessment.