Attach 9 chiller plant commisioning.pdf

PDF 110 KB Posted

Attached to
NIST Building 42 Central Utility Plant - Cooling Tower Upgrade
Solicitation number
1333ND21RNB190002
Issued by

About this file

This document outlines commissioning requirements for a federal contract to upgrade cooling towers at the National Institute of Standards and Technology Building 42 in Boulder, Colorado. The contractor will provide commissioning services directed by a Commissioning Authority, and will commission the complete chilled water system including chillers, pumps, cooling towers, filtration systems, heat exchangers, and controls. Commissioning must be complete and a Certificate of Commissioning Completion received before substantial completion. The contractor will integrate commissioning activities into the master schedule and coordinate the commissioning team comprised of the Commissioning Authority, COR, contractor, engineers, mechanical contractor, electrical contractor, TAB representative, and controls contractor.

View the file

Other files

File Type Posted
Attach 30 CUP Elec One-Lines Amend 003.pdf PDF
Attach 29 CUP Control Modifications Amend 003.pdf PDF
1333ND21RNB190002 0003.pdf PDF
Attach 31 Variable Frequency Drive Requirements Amend 0003.pdf PDF
Attach 3 Project Summary-Amend 0003.pdf PDF
Attach 27 chilled water enhancements- amend 003.pdf PDF
Attach 1 SOW Amend 3 1.15.21_ (002).pdf PDF
Attach 9 Chiller Plant Commissioning Requirements amend 0003.pdf PDF
Attach 8 Demonstration and Training-Amend 0003.pdf PDF
Attach 11 Cooling Tower Requirements Amend 0003.pdf PDF
Attach 28 COOLING TOWER FOUNDATION AND SUMP LAYOUT Amend 003.pdf PDF
Attach 10 Direct Digital Control (DDC) System for HVAC-amend 0003.pdf PDF
Attach 25 NIST CUP PHASE 2 CONSTRUCTION DRAWING PDFS.zip ZIP file
Attach 24 NIST CUP PHASE 1 CONSTRUCTION DRAWING PDFs.zip ZIP file
1333ND21RNB190002 0002.pdf PDF
Attach 26 NIST CUP PHASE 3 CONSTRUCTION DRAWING PDFS.zip ZIP file
Attach 1 SOW 11DEC2020 FINAL.docx DOCX document
1333ND21RNB190002 0001.pdf PDF
Attach 4 PROJECT DESIGN AND CONSTRUCTION SUBMITTAL PROCEDURES_Rev 1_28AUG20.pdf PDF
Attach 5 Quality Requirements R5-2020-10-2.pdf PDF
Attach 20 existing cooling tower support evaluation.pdf PDF
Attach 18 SITE UTILITY DISTRIBUTION SYSTEM ENHANCED CHILLER CAPACITY.pdf PDF
Attach 14 SITE UTILITY DISTRIBUTION SYSTEM NIST PHASE 2.pdf PDF
Attach 3 Project Summary REV2-2020-09-10.pdf PDF
Attach 13 PRELIMINARY COOLING TOWER LAYOUT.pdf PDF
Attach 1 SOW 22OCT2020.pdf PDF
Attach A Cons and Design Exp Proj-Data-Sheet.pdf PDF
Attach 23 PUMP PACKAGE FACTORY TEST.pdf PDF
Attach 8 Demonstration and Training.pdf PDF
Attach B_NIST AMD Boulder PPQ Form.pdf PDF
Attach 17 PHASE 2 CHILLER SUBMITTAL.pdf PDF
Attach 2 General Instructions for Conducting Work at NIST Boulder 19NOV19 Rev C.pdf PDF
Attach 12 Identification for Electrical Systems.pdf PDF
Attach 7 Project Record Documents.pdf PDF
Attach 19 SITE UTILITY DISTRIBUTION SYSTEM ENHANCED CHILLER CAPACITY-ELECTRICAL.pdf PDF
Attach 15 chilled water schematic .pdf PDF
Attach 11 cooling tower REV 2.pdf PDF
Attach 16 cond water schematic.pdf PDF
Attach 6 Operation and Maintenance Data.pdf PDF
Attach 22 PUMP PACKAGE WITH HX SUBMITTAL.pdf PDF
Attach 10 Direct Digital Control (DDC) System for HVAC.pdf PDF
1333ND21RNB190002.pdf PDF
Attach 21 PHASE 2 COOLING TOWER SUBMITTAL.pdf PDF
Attach C_ResumeFormKeyPersonnel.pdf PDF
Attach D_KeyPersonnelStatement.pdf PDF
Show all 45

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NIST BOULDER B42 - Cooling Tower Capacity Upgrade

1333ND21RNB190002 1

CHILLER PLANT COMMISSIONING REQUIREMENTS

PART 1 - GENERAL

1.1 COMMISSIONING

A. This project will have selected HVAC systems commissioned. The commissioning process will be directed by a Commissioning Authority whose services will be provided by the design build contractor.

B. The Commissioning Authority shall report to the project CO, COR and the design build contractor.

1.2 ADMINISTRATIVE / SUPERVISORY PERSONNEL

A. Commissioning Authority: the design build contractor shall provide the services of a qualified Commissioning Authority.

B. Test and Balance Contractor (TAB) Qualifications. The design build contractor will provide the services of a qualified test and balance contractor, approved by the Owner.

C. Controls Contractor and Lead Technician Qualifications. The Control contractor and the lead technician shall be approved by the Owner.

1.3 SUBMITTAL AND DATA REQUIREMENTS FOR COMMISSIONING

A. The Commissioning Authority shall receive a copy of the submittals for equipment to be commissioned.

B. The Commissioning Authority will review Contractor submittals applicable to systems being commissioned for compliance with commissioning needs.

C. NIST shall provide available information and submittals for existing equipment to be commissioned.

D. Contractor shall provide balancing report of existing chiller plant, before any modifications

1.4 PREREQUISITES TO SUBSTANTIAL COMPLETION

A. The commissioning must be complete, and Certificate of Commissioning Completion received, prior to Substantial Completion, unless approved by the CO and COR.

1333ND21RNB190002 2

B. Commissioning Completion is the point at which all commissioning requirements, except planned control system training performed after occupancy and any required seasonal or approved deferred testing, have been satisfactorily completed and recommended for acceptance by the Commissioning Agent. Achieving Commissioning Completion is the responsibility of the design build contractor.

This includes for all systems, but is not limited to:

1. Completed and signed start-up and pre-functional checklist documentation

2. Requested trend log data

3. Submission of final approved TAB report

4. Completion of all functional testing

5. Required training of Owner personnel completed and approved

6. Submission of the approved O&M manuals

7. All identified deficiencies in new work completed by design build contractor, have been corrected or are approved by the CO and COR to be excepted from this milestone

1.5 MINIMUM SYSTEMS TO BE COMMISSIONED

A. This includes the complete chilled water system, but is not limited to:

1. Chillers

2. Chilled water pumps

3. Condenser water pumps

4. Cooling towers

5. Condenser water filtration systems

6. Flat plate heat exchanger

7. Flat plate heat exchanger pumps

8. Controls and control sequences

PART 2 - PRODUCTS

2.1 GENERAL COMMISSIONING REQUIREMENTS

A. COORDINATION

1. Commissioning Team. The members of the commissioning team shall consist of the

Commissioning Authority (CA), the COR, the Design Build Contractor, design engineers, the Mechanical Contractor (MC), the Electrical Contractor (EC), the TAB representative, the Controls Contractor (CC).

B. Management. The CA is hired by the Design Build Contractor. The CA directs and coordinates the commissioning activities and the reports to the COR and the Design Build Contractor. All members work together to fulfill their contracted responsibilities and meet the objectives of the Contract Documents.

1333ND21RNB190002 3

C. Scheduling. The CA will work with the Design Build Contractor to schedule the commissioning activities. The Design Build Contractor shall integrate all commissioning activities into the master schedule. This shall include schedule information for activities such as submittal review, installation inspections, O&M submittals, start-up, functional testing, TAB, and training. All parties will address scheduling problems and make necessary notifications in a timely manner in order to expedite the commissioning process.

2.2 COMMISSIONING PROCESS

A. Commissioning Plan. The commissioning plan shall provide guidance in the execution of the commissioning process.

B. Commissioning scoping meetings shall be conducted.

C. The Commissioning Plan shall identify how commissioning responsibilities are distributed, identifying which parties are responsible for producing the various commissioning procedures, reports, NIST notifications, and forms required.

D. The Commissioning Plan shall include the commissioning schedule.

E. The CA and the Design Build Contractor shall prepare an organizational chart showing lines of communication.

F. The CA and the Design Build Contractor shall prepare a tabular summary to identify which contractor personnel and subcontractors will participate in each test and identify instrumentation required for each test.

G. Commissioning Process. The following narrative provides a brief overview of the typical commissioning tasks during construction and the general order in which they occur.

1. Commissioning during construction begins with a scoping meeting conducted by the CA where the commissioning process is reviewed with the commissioning team members.

2. Additional meetings will be required throughout construction, scheduled by the CA with necessary parties attending, to plan, scope, coordinate, schedule future activities and resolve problems.

3. Equipment documentation is submitted to the CA during normal submittals, including detailed start-up procedures.

4. The CA works with the Subs in developing startup plans and startup documentation formats, including providing the Subs with prefunctional checklists to be incorporated in the start-up plans and completed during the startup process.

5. In general, the checkout and performance verification proceeds from simple to complex;

from component level to equipment to systems and intersystem levels with start-up and prefunctional checklists being completed before functional testing.

6. The Subs, under their own direction, execute and document the prefunctional checklists and perform startup and initial checkout. The CA documents that the checklists and startup were completed according to the approved plans. This may include the CA witnessing start-up of selected equipment.

7. The CA develops recommended equipment and system functional performance test (FT) procedures. The Design Build Contractor Subs review the procedures for personnel safety issues, equipment protection and warranty, physical installation restriction.

8. The procedures are executed by the Design Build Contractor.

1333ND21RNB190002 4

9. Items of non-compliance in material, installation or setup are corrected.

10. The CA reviews the O&M documentation for completeness.

11. Commissioning is completed before Substantial Completion.

12. The CA reviews, pre-approves and coordinates the training provided by the Design Build

Contractor and verifies that is was completed.

13. Deferred testing is conducted, as specified or required.

14. Certificate of Commissioning Completion

END OF SECTION

PART 1 - GENERAL
1.1 COMMISSIONING
A. This project will have selected HVAC systems commissioned. The commissioning process will be directed by a Commissioning Authority whose services will be provided by the design build contractor.
B. The Commissioning Authority shall report to the project CO, COR and the design build contractor.
1.2 ADMINISTRATIVE / SUPERVISORY PERSONNEL
A. Commissioning Authority: the design build contractor shall provide the services of a qualified Commissioning Authority.
B. Test and Balance Contractor (TAB) Qualifications. The design build contractor will provide the services of a qualified test and balance contractor, approved by the Owner.
C. Controls Contractor and Lead Technician Qualifications. The Control contractor and the lead technician shall be approved by the Owner.
1.3 SUBMITTAL AND DATA REQUIREMENTS FOR COMMISSIONING
A. The Commissioning Authority shall receive a copy of the submittals for equipment to be commissioned.
B. The Commissioning Authority will review Contractor submittals applicable to systems being commissioned for compliance with commissioning needs.
C. NIST shall provide available information and submittals for existing equipment to be commissioned.
D. Contractor shall provide balancing report of existing chiller plant, before any modifications
1.4 PREREQUISITES TO SUBSTANTIAL COMPLETION
A. The commissioning must be complete, and Certificate of Commissioning Completion received, prior to Substantial Completion, unless approved by the CO and COR.
B. Commissioning Completion is the point at which all commissioning requirements, except planned control system training performed after occupancy and any required seasonal or approved deferred testing, have been satisfactorily completed and recommen...
This includes for all systems, but is not limited to:
1. Completed and signed start-up and pre-functional checklist documentation
2. Requested trend log data
3. Submission of final approved TAB report
4. Completion of all functional testing
5. Required training of Owner personnel completed and approved
6. Submission of the approved O&M manuals
7. All identified deficiencies in new work completed by design build contractor, have been corrected or are approved by the CO and COR to be excepted from this milestone
1.5 MINIMUM SYSTEMS TO BE COMMISSIONED
A. This includes the complete chilled water system, but is not limited to:
1. Chillers
2. Chilled water pumps
3. Condenser water pumps
4. Cooling towers
5. Condenser water filtration systems
6. Flat plate heat exchanger
7. Flat plate heat exchanger pumps
8. Controls and control sequences
PART 2 - PRODUCTS
2.1 GENERAL COMMISSIONING REQUIREMENTS
A. COORDINATION
1. Commissioning Team. The members of the commissioning team shall consist of the Commissioning Authority (CA), the COR, the Design Build Contractor, design engineers, the Mechanical Contractor (MC), the Electrical Contractor (EC), the TAB representat...
B. Management. The CA is hired by the Design Build Contractor. The CA directs and coordinates the commissioning activities and the reports to the COR and the Design Build Contractor. All members work together to fulfill their contracted responsibiliti...
C. Scheduling. The CA will work with the Design Build Contractor to schedule the commissioning activities. The Design Build Contractor shall integrate all commissioning activities into the master schedule. This shall include schedule information for a...
2.2 COMMISSIONING PROCESS
A. Commissioning Plan. The commissioning plan shall provide guidance in the execution of the commissioning process.
B. Commissioning scoping meetings shall be conducted.
C. The Commissioning Plan shall identify how commissioning responsibilities are distributed, identifying which parties are responsible for producing the various commissioning procedures, reports, NIST notifications, and forms required.
D. The Commissioning Plan shall include the commissioning schedule.
E. The CA and the Design Build Contractor shall prepare an organizational chart showing lines of communication.
F. The CA and the Design Build Contractor shall prepare a tabular summary to identify which contractor personnel and subcontractors will participate in each test and identify instrumentation required for each test.
G. Commissioning Process. The following narrative provides a brief overview of the typical commissioning tasks during construction and the general order in which they occur.
1. Commissioning during construction begins with a scoping meeting conducted by the CA where the commissioning process is reviewed with the commissioning team members.
2. Additional meetings will be required throughout construction, scheduled by the CA with necessary parties attending, to plan, scope, coordinate, schedule future activities and resolve problems.
3. Equipment documentation is submitted to the CA during normal submittals, including detailed start-up procedures.
4. The CA works with the Subs in developing startup plans and startup documentation formats, including providing the Subs with prefunctional checklists to be incorporated in the start-up plans and completed during the startup process.
5. In general, the checkout and performance verification proceeds from simple to complex; from component level to equipment to systems and intersystem levels with start-up and prefunctional checklists being completed before functional testing.
6. The Subs, under their own direction, execute and document the prefunctional checklists and perform startup and initial checkout. The CA documents that the checklists and startup were completed according to the approved plans. This may include the C...
7. The CA develops recommended equipment and system functional performance test (FT) procedures. The Design Build Contractor Subs review the procedures for personnel safety issues, equipment protection and warranty, physical installation restriction.
8. The procedures are executed by the Design Build Contractor.
9. Items of non-compliance in material, installation or setup are corrected.
10. The CA reviews the O&M documentation for completeness.
11. Commissioning is completed before Substantial Completion.
12. The CA reviews, pre-approves and coordinates the training provided by the Design Build Contractor and verifies that is was completed.
13. Deferred testing is conducted, as specified or required.
14. Certificate of Commissioning Completion