Attach 3 Project Summary-Amend 0003.pdf

PDF 114 KB Posted

Attached to
NIST Building 42 Central Utility Plant - Cooling Tower Upgrade
Solicitation number
1333ND21RNB190002
Issued by

About this file

This project summary outlines the scope of work for the Building 42 Central Utility Plant Cooling Tower Upgrade project at the National Institute of Standards and Technology in Boulder, Colorado. The contractor will provide engineering, design, and construction services to replace and upgrade the existing cooling towers and associated equipment. Specific tasks include removing and replacing the existing chillers and cooling towers, installing new remote sumps and bypass piping, connecting a new filtration system to the existing controls network, upgrading electrical and providing third party commissioning. The contractor must coordinate all work with the facility owner and verify existing building information. Work is to be performed between September and March to minimize disruptions to building occupants.

View the file

Other files

File Type Posted
Attach 30 CUP Elec One-Lines Amend 003.pdf PDF
Attach 29 CUP Control Modifications Amend 003.pdf PDF
1333ND21RNB190002 0003.pdf PDF
Attach 31 Variable Frequency Drive Requirements Amend 0003.pdf PDF
Attach 27 chilled water enhancements- amend 003.pdf PDF
Attach 1 SOW Amend 3 1.15.21_ (002).pdf PDF
Attach 9 Chiller Plant Commissioning Requirements amend 0003.pdf PDF
Attach 8 Demonstration and Training-Amend 0003.pdf PDF
Attach 11 Cooling Tower Requirements Amend 0003.pdf PDF
Attach 28 COOLING TOWER FOUNDATION AND SUMP LAYOUT Amend 003.pdf PDF
Attach 10 Direct Digital Control (DDC) System for HVAC-amend 0003.pdf PDF
Attach 25 NIST CUP PHASE 2 CONSTRUCTION DRAWING PDFS.zip ZIP file
Attach 24 NIST CUP PHASE 1 CONSTRUCTION DRAWING PDFs.zip ZIP file
1333ND21RNB190002 0002.pdf PDF
Attach 26 NIST CUP PHASE 3 CONSTRUCTION DRAWING PDFS.zip ZIP file
Attach 1 SOW 11DEC2020 FINAL.docx DOCX document
1333ND21RNB190002 0001.pdf PDF
Attach 4 PROJECT DESIGN AND CONSTRUCTION SUBMITTAL PROCEDURES_Rev 1_28AUG20.pdf PDF
Attach 5 Quality Requirements R5-2020-10-2.pdf PDF
Attach 20 existing cooling tower support evaluation.pdf PDF
Attach 18 SITE UTILITY DISTRIBUTION SYSTEM ENHANCED CHILLER CAPACITY.pdf PDF
Attach 9 chiller plant commisioning.pdf PDF
Attach 14 SITE UTILITY DISTRIBUTION SYSTEM NIST PHASE 2.pdf PDF
Attach 3 Project Summary REV2-2020-09-10.pdf PDF
Attach 13 PRELIMINARY COOLING TOWER LAYOUT.pdf PDF
Attach 1 SOW 22OCT2020.pdf PDF
Attach A Cons and Design Exp Proj-Data-Sheet.pdf PDF
Attach 23 PUMP PACKAGE FACTORY TEST.pdf PDF
Attach 8 Demonstration and Training.pdf PDF
Attach B_NIST AMD Boulder PPQ Form.pdf PDF
Attach 17 PHASE 2 CHILLER SUBMITTAL.pdf PDF
Attach 2 General Instructions for Conducting Work at NIST Boulder 19NOV19 Rev C.pdf PDF
Attach 12 Identification for Electrical Systems.pdf PDF
Attach 7 Project Record Documents.pdf PDF
Attach 19 SITE UTILITY DISTRIBUTION SYSTEM ENHANCED CHILLER CAPACITY-ELECTRICAL.pdf PDF
Attach 15 chilled water schematic .pdf PDF
Attach 11 cooling tower REV 2.pdf PDF
Attach 16 cond water schematic.pdf PDF
Attach 6 Operation and Maintenance Data.pdf PDF
Attach 22 PUMP PACKAGE WITH HX SUBMITTAL.pdf PDF
Attach 10 Direct Digital Control (DDC) System for HVAC.pdf PDF
1333ND21RNB190002.pdf PDF
Attach 21 PHASE 2 COOLING TOWER SUBMITTAL.pdf PDF
Attach C_ResumeFormKeyPersonnel.pdf PDF
Attach D_KeyPersonnelStatement.pdf PDF
Show all 45

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NIST BOULDER B42 - Cooling Tower Capacity Upgrade -

8/28/2020 1

PROJECT SUMMARY (Amend 0003)

PART 1 - GENERAL

1.1 PROJECT INFORMATION

A. Project Identification: Building 42 - Cooling Tower Capacity Upgrade

1. Project Location: NIST - Boulder, Colorado.

B. Owner: NIST – US Department of Commerce

1.2 PROJECT COMMUNICATION

A. All communications shall be directed to the project CO and COR.’

1.3 WORK INCLUDED IN THIS CONTRACT

A. The Work of Project is defined by the Contract Documents and consists of the following:

1. Engineering drawings, specifications and construction

2. Chiller cooling tower removal and replacement (Amend 0003)

3. Chiller cooling tower remote sumps (Amend 0003)

4. Chiller cooling tower bypass piping (Amend 0003)

5. Provide piping, cooling tower (new or existing), remote sump, pumps and controls for existing flat plate heat exchanger.

6. Cooling tower foundations

7. Chiller condenser water filtration system (Amend 0003)

8. Connection to existing JCI control system with new control sequences, as coordinated with existing ESCO contractor.

9. Cutting and patching of building walls, concrete and aprons (Amend 0003)

10. Chilled water plant balancing

11. Electrical upgrades with connections to new equipment

12. Third party commissioning of chilled water plant.

13. Provide piping and pumps to accommodate future chiller condenser water flow rates.

(Amend 0003)

14. Flat plate heat exchanger condenser water filtration system (Amend 0003)

8/28/2020 2

1.4 ACCESS TO SITE

A. Refer to attached document: “General Instructions for Conducting Work at NIST Boulder”

B. Contractor shall coordinate badging requirements with COR.

C. General: Contractor shall have limited use of Project site for construction operations.

1. Driveways, Walkways and Entrances: Keep driveways and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times.

Do not use these areas for parking or for storage of materials.

a. Schedule deliveries to minimize use of driveways and entrances by construction operations.

b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

D. Condition of Existing Building: Maintain portions of existing building affected by construction operations in a weathertight condition throughout construction period. Repair damage caused by construction operations.

E. Condition of Existing Grounds: Maintain portions of existing grounds, landscaping, and hardscaping affected by construction operations throughout construction period. Repair damage caused by construction operations.

1.5 COORDINATION WITH OCCUPANTS

A. Partial Owner Occupancy: Owner will occupy the premises during entire construction period, with the exception of areas under construction. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with Owner's operations. Maintain existing exits unless otherwise indicated.

1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Owner and authorities having jurisdiction.

2. On occupancy, Owner will assume responsibility for maintenance and custodial service for occupied portions of Work.

1.6 EQUIPMENT SHUTDOWNS

A. Cooling tower shutdown, removal and installation shall be phased and coordinated with the

COR.

B. Shutdowns require a minimum 2-week notification to COR.

C. Cooling tower shutdown and removal period shall be between September 1 and March 31.

8/28/2020 3

1.7 WORK RESTRICTIONS

A. Comply with the attached “Boulder General Contract Requirements Rev C”.

B. Work Restrictions, General: Comply with restrictions on construction operations.

1. Comply with limitations on use of public streets and with other requirements of authorities having jurisdiction.

C. On-Site Work Hours: Limit work in the existing building to normal business working hours Monday through Friday, unless otherwise coordinated with project COR.

1. Weekend Hours: to be reviewed with project COR

2. Early Morning Hours: to be reviewed with project COR

3. Hours for Utility Shutdowns: to be reviewed with project COR

D. Existing Utility Interruptions: Do not interrupt utilities serving facilities unless previously coordinated with project COR:

E. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and vibration, odors, or other disruption to Owner occupancy with project COR.

1. Maintain list of approved screened personnel with Owner's representative.

1.8 IT SECRUITY REQUIREMENTS

A. Contractor personnel requiring access to NIST IT systems must be screened at an appropriate level in accordance with the Department of Commerce IT Security Program Policy. The screening should be appropriate to the highest risk level of the IT systems and information accessed, using, as a minimum, National Agency Check with Inquiries (NACI).

B. Contractor personnel must complete NIST IT security awareness training or provide certificate of completion of an IT security training prior to accessing NIST information and/or technological resources.

C. Each contractor personnel must read and sign the NIST IT Access and Use (Rules of Behavior) prior to being granted access to any NIST IT accounts.

D. The contractor shall properly protect all information used, gathered, or developed as a result of work under the contract.

E. NIST documentation is considered proprietary and will not be shared. All documentation created by and used by the contractor for the project will be provided back to NIST at the end of the contract.

F. In the event that performance of any work under the contract causes the contractor/subcontractor to gain access to proprietary and/or confidential information, the contractor shall comply with non-disclosure requirements (e.g., non-disclosure agreement).

8/28/2020 4

G. The contractor shall perform a backup of the system and database prior to any maintenance, upgrades, patching or installations performed on the system. Backups will be maintained on the NIST government systems and will not be removed from the NIST site

1.9 ENGINEERING AND BUILDING CODES

A. All engineering shall be performed by licensed professional engineers.

1.10 EXISTING BUILDING INFORMATION

A. The contractor shall verify accuracy and correctness of all existing building information provided by NIST.

1.11 SPECIFICATION AND DRAWING CONVENTIONS

A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.

These conventions are as follows:

1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

2. Specification requirements are to be performed by Contractor unless specifically stated otherwise.

PART 1 - GENERAL
1.1 PROJECT INFORMATION
A. Project Identification: Building 42 - Cooling Tower Capacity Upgrade
1. Project Location: NIST - Boulder, Colorado.

B. Owner: NIST – US Department of Commerce

1.2 PROJECT COMMUNICATION
A. All communications shall be directed to the project CO and COR.’
1.3 WORK INCLUDED IN THIS CONTRACT
A. The Work of Project is defined by the Contract Documents and consists of the following:
1. Engineering drawings, specifications and construction
2. Chiller cooling tower removal and replacement (Amend 0003)
3. Chiller cooling tower remote sumps (Amend 0003)
4. Chiller cooling tower bypass piping (Amend 0003)
5. Provide piping, cooling tower (new or existing), remote sump, pumps and controls for existing flat plate heat exchanger.
6. Cooling tower foundations
7. Chiller condenser water filtration system (Amend 0003)
8. Connection to existing JCI control system with new control sequences, as coordinated with existing ESCO contractor.
9. Cutting and patching of building walls, concrete and aprons (Amend 0003)
10. Chilled water plant balancing
11. Electrical upgrades with connections to new equipment
12. Third party commissioning of chilled water plant.
13. Provide piping and pumps to accommodate future chiller condenser water flow rates. (Amend 0003)
14. Flat plate heat exchanger condenser water filtration system (Amend 0003)
1.4 ACCESS TO SITE
A. Refer to attached document: “General Instructions for Conducting Work at NIST Boulder”
B. Contractor shall coordinate badging requirements with COR.
C. General: Contractor shall have limited use of Project site for construction operations.
1. Driveways, Walkways and Entrances: Keep driveways and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or for storage of materials.
a. Schedule deliveries to minimize use of driveways and entrances by construction operations.
b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
D. Condition of Existing Building: Maintain portions of existing building affected by construction operations in a weathertight condition throughout construction period. Repair damage caused by construction operations.
E. Condition of Existing Grounds: Maintain portions of existing grounds, landscaping, and hardscaping affected by construction operations throughout construction period. Repair damage caused by construction operations.
1.5 COORDINATION WITH OCCUPANTS
A. Partial Owner Occupancy: Owner will occupy the premises during entire construction period, with the exception of areas under construction. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform...
1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Owner and authorities having jurisdi...
2. On occupancy, Owner will assume responsibility for maintenance and custodial service for occupied portions of Work.
1.6 EQUIPMENT SHUTDOWNS
A. Cooling tower shutdown, removal and installation shall be phased and coordinated with the COR.
B. Shutdowns require a minimum 2-week notification to COR.
C. Cooling tower shutdown and removal period shall be between September 1 and March 31.
1.7 WORK RESTRICTIONS
A. Comply with the attached “Boulder General Contract Requirements Rev C”.
B. Work Restrictions, General: Comply with restrictions on construction operations.
1. Comply with limitations on use of public streets and with other requirements of authorities having jurisdiction.
C. On-Site Work Hours: Limit work in the existing building to normal business working hours Monday through Friday, unless otherwise coordinated with project COR.
1. Weekend Hours: to be reviewed with project COR
2. Early Morning Hours: to be reviewed with project COR
3. Hours for Utility Shutdowns: to be reviewed with project COR
D. Existing Utility Interruptions: Do not interrupt utilities serving facilities unless previously coordinated with project COR:
E. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and vibration, odors, or other disruption to Owner occupancy with project COR.
1. Maintain list of approved screened personnel with Owner's representative.
1.8 IT SECRUITY REQUIREMENTS
A. Contractor personnel requiring access to NIST IT systems must be screened at an appropriate level in accordance with the Department of Commerce IT Security Program Policy. The screening should be appropriate to the highest risk level of the IT syst...
B. Contractor personnel must complete NIST IT security awareness training or provide certificate of completion of an IT security training prior to accessing NIST information and/or technological resources.
C. Each contractor personnel must read and sign the NIST IT Access and Use (Rules of Behavior) prior to being granted access to any NIST IT accounts.
D. The contractor shall properly protect all information used, gathered, or developed as a result of work under the contract.
E. NIST documentation is considered proprietary and will not be shared. All documentation created by and used by the contractor for the project will be provided back to NIST at the end of the contract.
F. In the event that performance of any work under the contract causes the contractor/subcontractor to gain access to proprietary and/or confidential information, the contractor shall comply with non-disclosure requirements (e.g., non-disclosure agree...
G. The contractor shall perform a backup of the system and database prior to any maintenance, upgrades, patching or installations performed on the system. Backups will be maintained on the NIST government systems and will not be removed from the NIST...
1.9 ENGINEERING AND BUILDING CODES
A. All engineering shall be performed by licensed professional engineers.
1.10 EXISTING BUILDING INFORMATION
A. The contractor shall verify accuracy and correctness of all existing building information provided by NIST.
1.11 SPECIFICATION AND DRAWING CONVENTIONS
A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:
1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.
2. Specification requirements are to be performed by Contractor unless specifically stated otherwise.

File details come from the government source that posted it. Updated .