Attach 7 Project Record Documents.pdf

PDF 125 KB Posted

Attached to
NIST Building 42 Central Utility Plant - Cooling Tower Upgrade
Solicitation number
1333ND21RNB190002
Issued by

About this file

This document outlines requirements for maintaining project record documents for a federal contract to upgrade the cooling towers at the National Institute of Standards and Technology Building 42 in Boulder, Colorado. The contractor must keep one set of marked-up drawings and shop drawings incorporating revisions, and must accurately record information about dimensional changes, equipment locations, concealed utilities, and other details varying from original contract drawings. The contractor must also maintain product data submittals noting any variations from submittals, and must organize digital records of drawings and product data in separate electronic files for submission to the Contracting Officer's Representative. Proper storage and access requirements for maintained record documents are also specified.

View the file

Other files

File Type Posted
Attach 30 CUP Elec One-Lines Amend 003.pdf PDF
Attach 29 CUP Control Modifications Amend 003.pdf PDF
1333ND21RNB190002 0003.pdf PDF
Attach 31 Variable Frequency Drive Requirements Amend 0003.pdf PDF
Attach 3 Project Summary-Amend 0003.pdf PDF
Attach 27 chilled water enhancements- amend 003.pdf PDF
Attach 1 SOW Amend 3 1.15.21_ (002).pdf PDF
Attach 9 Chiller Plant Commissioning Requirements amend 0003.pdf PDF
Attach 8 Demonstration and Training-Amend 0003.pdf PDF
Attach 11 Cooling Tower Requirements Amend 0003.pdf PDF
Attach 28 COOLING TOWER FOUNDATION AND SUMP LAYOUT Amend 003.pdf PDF
Attach 10 Direct Digital Control (DDC) System for HVAC-amend 0003.pdf PDF
Attach 25 NIST CUP PHASE 2 CONSTRUCTION DRAWING PDFS.zip ZIP file
Attach 24 NIST CUP PHASE 1 CONSTRUCTION DRAWING PDFs.zip ZIP file
1333ND21RNB190002 0002.pdf PDF
Attach 26 NIST CUP PHASE 3 CONSTRUCTION DRAWING PDFS.zip ZIP file
Attach 1 SOW 11DEC2020 FINAL.docx DOCX document
1333ND21RNB190002 0001.pdf PDF
Attach 4 PROJECT DESIGN AND CONSTRUCTION SUBMITTAL PROCEDURES_Rev 1_28AUG20.pdf PDF
Attach 5 Quality Requirements R5-2020-10-2.pdf PDF
Attach 20 existing cooling tower support evaluation.pdf PDF
Attach 18 SITE UTILITY DISTRIBUTION SYSTEM ENHANCED CHILLER CAPACITY.pdf PDF
Attach 9 chiller plant commisioning.pdf PDF
Attach 14 SITE UTILITY DISTRIBUTION SYSTEM NIST PHASE 2.pdf PDF
Attach 3 Project Summary REV2-2020-09-10.pdf PDF
Attach 13 PRELIMINARY COOLING TOWER LAYOUT.pdf PDF
Attach 1 SOW 22OCT2020.pdf PDF
Attach A Cons and Design Exp Proj-Data-Sheet.pdf PDF
Attach 23 PUMP PACKAGE FACTORY TEST.pdf PDF
Attach 8 Demonstration and Training.pdf PDF
Attach B_NIST AMD Boulder PPQ Form.pdf PDF
Attach 17 PHASE 2 CHILLER SUBMITTAL.pdf PDF
Attach 2 General Instructions for Conducting Work at NIST Boulder 19NOV19 Rev C.pdf PDF
Attach 12 Identification for Electrical Systems.pdf PDF
Attach 19 SITE UTILITY DISTRIBUTION SYSTEM ENHANCED CHILLER CAPACITY-ELECTRICAL.pdf PDF
Attach 15 chilled water schematic .pdf PDF
Attach 11 cooling tower REV 2.pdf PDF
Attach 16 cond water schematic.pdf PDF
Attach 6 Operation and Maintenance Data.pdf PDF
Attach 22 PUMP PACKAGE WITH HX SUBMITTAL.pdf PDF
Attach 10 Direct Digital Control (DDC) System for HVAC.pdf PDF
1333ND21RNB190002.pdf PDF
Attach 21 PHASE 2 COOLING TOWER SUBMITTAL.pdf PDF
Attach C_ResumeFormKeyPersonnel.pdf PDF
Attach D_KeyPersonnelStatement.pdf PDF
Show all 45

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NIST BOULDER B42 - Cooling Tower Capacity Upgrade

1333ND21RNB190002 1

PROJECT RECORD DOCUMENTS

PART 1 - GENERAL

1.1 RECORD DRAWINGS

A. Record Prints: During construction maintain one set of marked-up paper copies of the Contract Drawings and Shop Drawings, incorporating new and revised drawings as modifications are issued.

1. Preparation: Mark record prints to show the actual installation where installation varies from that shown originally. Require individual or entity who obtained record data, whether individual or entity is Installer, subcontractor, or similar entity, to provide information for preparation of corresponding marked-up record prints.

a. Give particular attention to information on concealed elements that would be difficult to identify or measure and record later.

b. Accurately record information in an acceptable drawing technique.

c. Record data as soon as possible after obtaining it.

d. Record and check the markup before enclosing concealed installations.

e. Cross-reference record prints to corresponding photographic documentation.

2. Content: Types of items requiring marking include, but are not limited to, the following:

a. Dimensional changes to Drawings.

b. Revisions to details shown on Drawings.

c. Depths of foundations.

d. Locations and depths of underground utilities.

e. Revisions to routing of piping and conduits.

f. Revisions to electrical circuitry.

g. Actual equipment locations.

h. Duct size and routing.

i. Locations of concealed internal utilities.

j. Changes made following CO’s written orders.

k. Details not on the original Contract Drawings.

l. Field records for variable and concealed conditions.

m. Record information on the Work that is shown only schematically.

3. Mark the Contract Drawings and Shop Drawings completely and accurately. Use personnel proficient at recording graphic information in production of marked-up record prints.

4. Mark record sets with erasable, red-colored pencil. Use other colors to distinguish between changes for different categories of the Work at same location.

5. Mark important additional information that was either shown schematically or omitted from original Drawings.

6. Note Construction Change Directive numbers, alternate numbers, Change Order numbers, and similar identification, where applicable.

1333ND21RNB190002 2

B. Record Digital Data Files: Immediately before inspection for Certificate of Substantial Completion, review marked-up record prints with COR. When authorized, prepare a full set of corrected digital data files of the Contract Drawings, as follows:

1. Format: Same digital data software program, version, and operating system as the original Contract Drawings.

2. Format: DWG Version

3. Incorporate changes and additional information previously marked on record prints.

Delete, redraw, and add details and notations where applicable.

4. Refer instances of uncertainty to COR for resolution.

5. COR will furnish Contractor with digital data files of the Contract Drawings for use in recording information.

a. COR will provide data file layer information. Record markups in separate layers.

C. Format: Identify and date each record Drawing; include the designation "PROJECT RECORD DRAWING" in a prominent location.

1. Format: PDF electronic file, provide to COR on CD.

2. Record Digital Data Files: Organize digital data information into separate electronic files that correspond to each sheet of the Contract Drawings. Name each file with the sheet identification. Include identification in each digital data file.

3. Upload record DWG files to file transfer BOX account established by the COR.

4. Provide (1) CD each with the record DWG files to the COR.

5. Identification: As follows:

a. Project name.

b. Date.

c. Designation "PROJECT RECORD DRAWINGS."

d. Name of Contractor.

1.2 RECORD PRODUCT DATA

A. Recording: Maintain one copy of each submittal during the construction period for project record document purposes. Post changes and revisions to project record documents as they occur; do not wait until end of Project.

B. Preparation: Mark Product Data to indicate the actual product installation where installation varies substantially from that indicated in Product Data submittal.

1. Give particular attention to information on concealed products and installations that cannot be readily identified and recorded later.

2. Include significant changes in the product delivered to Project site and changes in manufacturer's written instructions for installation.

C. Format: Submit record Product Data as annotated PDF electronic file

1. Include record Product Data directory organized by Specification Section number and title, electronically linked to each item of record Product Data.

1333ND21RNB190002 3

1.3 MAINTENANCE OF RECORD DOCUMENTS

A. Maintenance of Record Documents: Store record documents in the field office apart from the Contract Documents used for construction. Do not use project record documents for construction purposes. Maintain record documents in good order and in a clean, dry, legible condition, protected from deterioration and loss. Provide access to project record documents for COR reference during normal working hours.

END OF SECTION

PART 1 - GENERAL
1.1 RECORD DRAWINGS
A. Record Prints: During construction maintain one set of marked-up paper copies of the Contract Drawings and Shop Drawings, incorporating new and revised drawings as modifications are issued.
1. Preparation: Mark record prints to show the actual installation where installation varies from that shown originally. Require individual or entity who obtained record data, whether individual or entity is Installer, subcontractor, or similar entity...
a. Give particular attention to information on concealed elements that would be difficult to identify or measure and record later.
b. Accurately record information in an acceptable drawing technique.
c. Record data as soon as possible after obtaining it.
d. Record and check the markup before enclosing concealed installations.
e. Cross-reference record prints to corresponding photographic documentation.
2. Content: Types of items requiring marking include, but are not limited to, the following:
a. Dimensional changes to Drawings.
b. Revisions to details shown on Drawings.
c. Depths of foundations.
d. Locations and depths of underground utilities.
e. Revisions to routing of piping and conduits.
f. Revisions to electrical circuitry.
g. Actual equipment locations.
h. Duct size and routing.
i. Locations of concealed internal utilities.
j. Changes made following CO’s written orders.
k. Details not on the original Contract Drawings.
l. Field records for variable and concealed conditions.
m. Record information on the Work that is shown only schematically.
3. Mark the Contract Drawings and Shop Drawings completely and accurately. Use personnel proficient at recording graphic information in production of marked-up record prints.
4. Mark record sets with erasable, red-colored pencil. Use other colors to distinguish between changes for different categories of the Work at same location.
5. Mark important additional information that was either shown schematically or omitted from original Drawings.
6. Note Construction Change Directive numbers, alternate numbers, Change Order numbers, and similar identification, where applicable.
B. Record Digital Data Files: Immediately before inspection for Certificate of Substantial Completion, review marked-up record prints with COR. When authorized, prepare a full set of corrected digital data files of the Contract Drawings, as follows:
1. Format: Same digital data software program, version, and operating system as the original Contract Drawings.
2. Format: DWG Version
3. Incorporate changes and additional information previously marked on record prints. Delete, redraw, and add details and notations where applicable.
4. Refer instances of uncertainty to COR for resolution.
5. COR will furnish Contractor with digital data files of the Contract Drawings for use in recording information.
a. COR will provide data file layer information. Record markups in separate layers.
C. Format: Identify and date each record Drawing; include the designation "PROJECT RECORD DRAWING" in a prominent location.
1. Format: PDF electronic file, provide to COR on CD.
2. Record Digital Data Files: Organize digital data information into separate electronic files that correspond to each sheet of the Contract Drawings. Name each file with the sheet identification. Include identification in each digital data file.
3. Upload record DWG files to file transfer BOX account established by the COR.
4. Provide (1) CD each with the record DWG files to the COR.
5. Identification: As follows:
a. Project name.
b. Date.
c. Designation "PROJECT RECORD DRAWINGS."
d. Name of Contractor.
1.2 RECORD PRODUCT DATA
A. Recording: Maintain one copy of each submittal during the construction period for project record document purposes. Post changes and revisions to project record documents as they occur; do not wait until end of Project.
B. Preparation: Mark Product Data to indicate the actual product installation where installation varies substantially from that indicated in Product Data submittal.
1. Give particular attention to information on concealed products and installations that cannot be readily identified and recorded later.
2. Include significant changes in the product delivered to Project site and changes in manufacturer's written instructions for installation.
C. Format: Submit record Product Data as annotated PDF electronic file
1. Include record Product Data directory organized by Specification Section number and title, electronically linked to each item of record Product Data.
1.3 MAINTENANCE OF RECORD DOCUMENTS
A. Maintenance of Record Documents: Store record documents in the field office apart from the Contract Documents used for construction. Do not use project record documents for construction purposes. Maintain record documents in good order and in a cle...

File details come from the government source that posted it. Updated .