Attach 8 Demonstration and Training.pdf

PDF 101 KB Posted

Attached to
NIST Building 42 Central Utility Plant - Cooling Tower Upgrade
Solicitation number
1333ND21RNB190002
Issued by

About this file

This document outlines training requirements for the renovation of cooling towers at the National Institute of Standards and Technology Building 42 Central Utility Plant. The contractor must develop an instruction program consisting of training modules covering the basis of system design, documentation, emergencies, operations, adjustments, troubleshooting, maintenance, and repairs. For each module, the contractor is required to submit a learning objective and outline describing the specific skills and knowledge to be taught. The contractor must coordinate the instruction schedule with NIST and submit attendance records for each training. The opportunity was initially announced under solicitation number 1333ND20RNB190037 and is now identified as 1333ND21RNB190002. The contractor will provide all labor, materials, and equipment to design and renovate the cooling towers in accordance with the solicitation, statement of work, and attached documents.

View the file

Other files

File Type Posted
Attach 30 CUP Elec One-Lines Amend 003.pdf PDF
Attach 29 CUP Control Modifications Amend 003.pdf PDF
1333ND21RNB190002 0003.pdf PDF
Attach 31 Variable Frequency Drive Requirements Amend 0003.pdf PDF
Attach 3 Project Summary-Amend 0003.pdf PDF
Attach 27 chilled water enhancements- amend 003.pdf PDF
Attach 1 SOW Amend 3 1.15.21_ (002).pdf PDF
Attach 9 Chiller Plant Commissioning Requirements amend 0003.pdf PDF
Attach 8 Demonstration and Training-Amend 0003.pdf PDF
Attach 11 Cooling Tower Requirements Amend 0003.pdf PDF
Attach 28 COOLING TOWER FOUNDATION AND SUMP LAYOUT Amend 003.pdf PDF
Attach 10 Direct Digital Control (DDC) System for HVAC-amend 0003.pdf PDF
Attach 25 NIST CUP PHASE 2 CONSTRUCTION DRAWING PDFS.zip ZIP file
Attach 24 NIST CUP PHASE 1 CONSTRUCTION DRAWING PDFs.zip ZIP file
1333ND21RNB190002 0002.pdf PDF
Attach 26 NIST CUP PHASE 3 CONSTRUCTION DRAWING PDFS.zip ZIP file
Attach 1 SOW 11DEC2020 FINAL.docx DOCX document
1333ND21RNB190002 0001.pdf PDF
Attach 4 PROJECT DESIGN AND CONSTRUCTION SUBMITTAL PROCEDURES_Rev 1_28AUG20.pdf PDF
Attach 5 Quality Requirements R5-2020-10-2.pdf PDF
Attach 20 existing cooling tower support evaluation.pdf PDF
Attach 18 SITE UTILITY DISTRIBUTION SYSTEM ENHANCED CHILLER CAPACITY.pdf PDF
Attach 9 chiller plant commisioning.pdf PDF
Attach 14 SITE UTILITY DISTRIBUTION SYSTEM NIST PHASE 2.pdf PDF
Attach 3 Project Summary REV2-2020-09-10.pdf PDF
Attach 13 PRELIMINARY COOLING TOWER LAYOUT.pdf PDF
Attach 1 SOW 22OCT2020.pdf PDF
Attach A Cons and Design Exp Proj-Data-Sheet.pdf PDF
Attach 23 PUMP PACKAGE FACTORY TEST.pdf PDF
Attach B_NIST AMD Boulder PPQ Form.pdf PDF
Attach 17 PHASE 2 CHILLER SUBMITTAL.pdf PDF
Attach 2 General Instructions for Conducting Work at NIST Boulder 19NOV19 Rev C.pdf PDF
Attach 12 Identification for Electrical Systems.pdf PDF
Attach 7 Project Record Documents.pdf PDF
Attach 19 SITE UTILITY DISTRIBUTION SYSTEM ENHANCED CHILLER CAPACITY-ELECTRICAL.pdf PDF
Attach 15 chilled water schematic .pdf PDF
Attach 11 cooling tower REV 2.pdf PDF
Attach 16 cond water schematic.pdf PDF
Attach 6 Operation and Maintenance Data.pdf PDF
Attach 22 PUMP PACKAGE WITH HX SUBMITTAL.pdf PDF
Attach 10 Direct Digital Control (DDC) System for HVAC.pdf PDF
1333ND21RNB190002.pdf PDF
Attach 21 PHASE 2 COOLING TOWER SUBMITTAL.pdf PDF
Attach C_ResumeFormKeyPersonnel.pdf PDF
Attach D_KeyPersonnelStatement.pdf PDF
Show all 45

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NIST BOULDER B42 - Cooling Tower Capacity Upgrade

1333ND21RNB190002 1

DEMONSTRATION AND TRAINING

PART 1 - GENERAL

1.1 INFORMATIONAL SUBMITTALS

A. Instruction Program: Submit outline of instructional program for demonstration and training, including a list of training modules and a schedule of proposed dates, times, length of instruction time, and instructors' names for each training module. Include learning objective and outline for each training module.

B. Attendance Record: For each training module, submit list of participants and length of instruction time.

1.2 COORDINATION

A. Coordinate instruction schedule with project CO and COR operations. Adjust schedule as required to minimize disrupting Owner's operations and to ensure availability of Owner's personnel.

B. Coordinate instructors, including providing notification of dates, times, length of instruction time, and course content.

C. Coordinate content of training modules with content of approved emergency, operation, and maintenance manuals. Do not submit instruction program until operation and maintenance data have been reviewed and approved by Architect.

1333ND21RNB190002 2

1.3 INSTRUCTION PROGRAM

A. Program Structure: Develop an instruction program that includes individual training modules for each system and for equipment not part of a system, as required by individual Specification Sections.

B. Training Modules: Develop a learning objective and teaching outline for each module. Include a description of specific skills and knowledge that participant is expected to master. For each module, include instruction for the following as applicable to the system, equipment, or component:

1. Basis of System Design, Operational Requirements, and Criteria: Include the following:

a. System, subsystem, and equipment descriptions.

b. Performance and design criteria if Contractor is delegated design responsibility.

c. Operating standards.

d. Regulatory requirements.

e. Equipment function.

f. Operating characteristics.

g. Limiting conditions.

h. Performance curves.

2. Documentation: Review the following items in detail:

a. Emergency manuals.

b. Systems and equipment operation manuals.

c. Systems and equipment maintenance manuals.

d. Product maintenance manuals.

e. Project Record Documents.

f. Identification systems.

g. Warranties and bonds.

h. Maintenance service agreements and similar continuing commitments.

3. Emergencies: Include the following, as applicable:

a. Instructions on meaning of warnings, trouble indications, and error messages.

b. Instructions on stopping.

c. Shutdown instructions for each type of emergency.

d. Operating instructions for conditions outside of normal operating limits.

e. Sequences for electric or electronic systems.

f. Special operating instructions and procedures.

1333ND21RNB190002 3

4. Operations: Include the following, as applicable:

a. Startup procedures.

b. Equipment or system break-in procedures.

c. Routine and normal operating instructions.

d. Regulation and control procedures.

e. Control sequences.

f. Safety procedures.

g. Instructions on stopping.

h. Normal shutdown instructions.

i. Operating procedures for emergencies.

j. Operating procedures for system, subsystem, or equipment failure.

k. Seasonal and weekend operating instructions.

l. Required sequences for electric or electronic systems.

m. Special operating instructions and procedures.

5. Adjustments: Include the following:

a. Alignments.

b. Checking adjustments.

c. Noise and vibration adjustments.

d. Economy and efficiency adjustments.

6. Troubleshooting: Include the following:

a. Diagnostic instructions.

b. Test and inspection procedures.

7. Maintenance: Include the following:

a. Inspection procedures.

b. Types of cleaning agents to be used and methods of cleaning.

c. List of cleaning agents and methods of cleaning detrimental to product.

d. Procedures for routine cleaning.

e. Procedures for preventive maintenance.

f. Procedures for routine maintenance.

g. Instruction on use of special tools.

8. Repairs: Include the following:

a. Diagnosis instructions.

b. Repair instructions.

c. Disassembly; component removal, repair, and replacement; and reassembly instructions.

d. Instructions for identifying parts and components.

e. Review of spare parts needed for operation and maintenance.

END OF SECTION

PART 1 - GENERAL
1.1 INFORMATIONAL SUBMITTALS
A. Instruction Program: Submit outline of instructional program for demonstration and training, including a list of training modules and a schedule of proposed dates, times, length of instruction time, and instructors' names for each training module. ...
B. Attendance Record: For each training module, submit list of participants and length of instruction time.
1.2 COORDINATION
A. Coordinate instruction schedule with project CO and COR operations. Adjust schedule as required to minimize disrupting Owner's operations and to ensure availability of Owner's personnel.
B. Coordinate instructors, including providing notification of dates, times, length of instruction time, and course content.
C. Coordinate content of training modules with content of approved emergency, operation, and maintenance manuals. Do not submit instruction program until operation and maintenance data have been reviewed and approved by Architect.
1.3 INSTRUCTION PROGRAM
A. Program Structure: Develop an instruction program that includes individual training modules for each system and for equipment not part of a system, as required by individual Specification Sections.
B. Training Modules: Develop a learning objective and teaching outline for each module. Include a description of specific skills and knowledge that participant is expected to master. For each module, include instruction for the following as applicable...
1. Basis of System Design, Operational Requirements, and Criteria: Include the following:
a. System, subsystem, and equipment descriptions.
b. Performance and design criteria if Contractor is delegated design responsibility.
c. Operating standards.
d. Regulatory requirements.
e. Equipment function.
f. Operating characteristics.
g. Limiting conditions.
h. Performance curves.
2. Documentation: Review the following items in detail:
a. Emergency manuals.
b. Systems and equipment operation manuals.
c. Systems and equipment maintenance manuals.
d. Product maintenance manuals.
e. Project Record Documents.
f. Identification systems.
g. Warranties and bonds.
h. Maintenance service agreements and similar continuing commitments.
3. Emergencies: Include the following, as applicable:
a. Instructions on meaning of warnings, trouble indications, and error messages.
b. Instructions on stopping.
c. Shutdown instructions for each type of emergency.
d. Operating instructions for conditions outside of normal operating limits.
e. Sequences for electric or electronic systems.
f. Special operating instructions and procedures.
4. Operations: Include the following, as applicable:
a. Startup procedures.
b. Equipment or system break-in procedures.
c. Routine and normal operating instructions.
d. Regulation and control procedures.
e. Control sequences.
f. Safety procedures.
g. Instructions on stopping.
h. Normal shutdown instructions.
i. Operating procedures for emergencies.
j. Operating procedures for system, subsystem, or equipment failure.
k. Seasonal and weekend operating instructions.
l. Required sequences for electric or electronic systems.
m. Special operating instructions and procedures.
5. Adjustments: Include the following:
a. Alignments.
b. Checking adjustments.
c. Noise and vibration adjustments.
d. Economy and efficiency adjustments.
6. Troubleshooting: Include the following:
a. Diagnostic instructions.
b. Test and inspection procedures.
7. Maintenance: Include the following:
a. Inspection procedures.
b. Types of cleaning agents to be used and methods of cleaning.
c. List of cleaning agents and methods of cleaning detrimental to product.
d. Procedures for routine cleaning.
e. Procedures for preventive maintenance.
f. Procedures for routine maintenance.
g. Instruction on use of special tools.
8. Repairs: Include the following:
a. Diagnosis instructions.
b. Repair instructions.
c. Disassembly; component removal, repair, and replacement; and reassembly instructions.
d. Instructions for identifying parts and components.
e. Review of spare parts needed for operation and maintenance.