This document outlines commissioning requirements for the renovation of the cooling tower system in Building 42 at the National Institute of Standards and Technology under solicitation number 1333ND21RNB190002. The contractor shall provide design and construction services to upgrade the capacity of the building's cooling towers. Key systems to be commissioned include chillers, pumps, cooling towers, filters, a plate heat exchanger, and related controls. The commissioning authority will direct the process and verify that equipment is installed and performing properly according to specifications. Responsibilities of the contractor, equipment suppliers, and commissioning authority are defined. Testing requirements and procedures are established for pre-functional checks, startup, training, and correcting any deficiencies.
View the file
Other files
Show all 45
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NIST BOULDER B42 - Cooling Tower Capacity Upgrade
CHILLER PLANT COMMISSIONING REQUIREMENTS – AMENDMENT 0003
PART 1 - GENERAL
1.1 COMMISSIONING
A. Commissioning is a systematic process of confirming that all building systems perform interactively according to the NIST’s Program Requirements and the Basis of Design and continuing through construction, acceptance and the warranty period with actual verification of performance.
B. This project will have selected HVAC systems commissioned. The commissioning process will be directed by a Commissioning Authority whose services will be provided by the design build contractor.
C. The Commissioning Authority shall report to the project CO, COR and the design build contractor.
D. Commissioning during design is intended to achieve the following specific objectives:
1. Verify NIST’s Program Requirements and Basis of Design are clearly documented, and they meet NIST’s goals and objectives.
2. Provide Design Review during design efforts.
3. Verify commissioning for the construction phase is adequately reflected in the bid documents.
E. Commissioning during the construction phase of this project is intended to achieve the following specific objectives:
1. Provide direction for the commissioning process during construction, particularly providing resolution to issues and providing details not developed during design (ex.
scheduling, participation of various parties, lines of reporting and approvals, coordination, etc.)
2. Verify that applicable equipment and systems are installed properly and receive adequate operational checkout by installing contractors.
3. Verify and document proper performance of equipment and systems.
4. Verify that O&M documentation left on site is complete.
5. Verify that NIST’s operating personnel are adequately trained.
F. The CxA works with the contractor according to established protocols to schedule the commissioning activities. The CxA will provide sufficient notice to the contractor and Owner for scheduling commissioning activities. Meanwhile, the CxA will integrate these activities into the master construction schedule. All parties will address scheduling problems and make necessary notifications in a timely manner in order to expedite the commissioning process.
G. The following narrative provides a brief overview of the commissioning tasks during construction and the general order in which they occur.
1. Commissioning during construction begins with a Commissioning Kick-Off Meeting –
Construction Team conducted by the CxA where the commissioning process is reviewed with the commissioning team members.
2. Additional meetings will be required throughout construction, scheduled by the CxA with necessary parties attending, to plan, scope, coordinate, schedule future activities and resolve problems.
3. Equipment documentation is submitted to the CxA through the submittal process, including detailed start-up procedures.
4. In general, the checkout and performance verification proceeds from simple to complex;
from component level to equipment to systems and intersystem levels with Prefunctional checklists being completed before functional testing begins.
5. The contractors, under their own direction, document and perform startup and initial checkout. The CxA documents that startup was completed according to the approved plans, when contracted. This may include the CxA witnessing start-up of selected equipment, if contracted.
6. The CxA verifies installation integrity thru the use of checklists.
7. The CxA develops specific equipment and system functional performance test procedures. The contractors review the procedures.
8. The procedures are executed by the contractors, under the direction of, and documented by the CxA.
9. Items of non-compliance in material, installation or setup are corrected at the contractor's expense and the system retested.
10. The CxA reviews the O&M documentation for completeness.
11. Commissioning is completed before Substantial Completion, whenever possible.
12. The CxA reviews and pre-approves the training plan provided by the contractors.
13. The contractors coordinate and provide training via qualified instructors.
14. Training occurs.
15. NIST verifies that training has occurred and provides a written statement that training has occurred.
16. Deferred testing is conducted, as specified or required
1.2 DEFINITIONS
A. Acceptance: A formal action, to declare that some aspect of the project meets defined require-ments, thus permitting subsequent activities to proceed.
B. Acceptance Phase: Phase of commissioning after start-up and initial checkout when functional performance tests, O&M documentation review and training occurs.
C. Approval: Acceptance that a piece of equipment or system has been properly installed and is functioning in the tested modes according to the contract documents.
D. Basis of Design (BOD): A document that records concepts, calculations, decisions and product selections used to meet NIST’s Project Requirements and to satisfy applicable regulatory re-quirements, standards and guidelines. The document includes both narrative descriptions and lists of individual items that support the design process. Also known as the Design Criteria.
E. Checklists: Verification checklists that are developed and used during all phases of the com-missioning process to verify that NIST’s Project Requirements are being achieved. This in-cludes checklists for general verification, plus testing, training, and other specific requirements.
F. Commissioning Authority (CxA): An entity identified by NIST who plans, schedules and coordi-nates the commissioning team to implement the Commissioning Process.
G. Commissioning Plan: A document that outlines the organization, schedule, allocation of re-sources, and documentation requirements of the commissioning process.
H. Commissioning Process: A quality-focused process for enhancing the delivery of a project and includes verifying and documenting that the facility and its systems and assemblies are planned, designed, installed, tested, operated and maintained to meet NIST’s Project Require-ments.
I. Commissioning Process Progress Report: A written document that details activities completed as part of the commissioning process and significant findings from those activities that is con-tinuously updated during the course of a project.
J. Commissioning Report: A document recording the results of the commissioning process, includ-ing the record documents, performance of the commissioned systems and documents all si-gnoffs.
K. Commissioning Specifications: The contract document that details the objective, scope and implementation of the construction and acceptance phases of the commissioning process as developed in the Commissioning Plan.
L. Commissioning Team: A team comprised of the CxA, NIST, and Contractor. Individuals, each having the authority to act on behalf of the entity he or she represents, explicitly organized to implement the commissioning process through coordinated action.
M. Contract Documents: The documents binding on parties involved in the construction of this project (drawings, specifications, change orders, amendments, contracts, Cx Plan, etc.)
N. Contractor: the design build contractor, subcontractors, Consultants (engineers) and Subcon-sultants who comprise the design team.
O. Data Logging: The monitoring and recording of flow, current, status, pressure, etc. of equipment using ‘stand-alone’ data recorders separate from the control system or the trending capacities of control systems.
P. Deferred Performance Tests (DPTs): Performance tests that are performed, at the discretion of the CxA, after substantial completion, due to partial occupancy, equipment, seasonal require-ments, design, or other site conditions that disallow the test from being performed.
Q. Deficiency: A condition in the installation or function of a component, piece of equipment or sys-tem that is not in compliance with the Contract Documents (that is, does not perform properly or is not complying with NIST’s Project Requirements).
R. Equipment Manufacturer: The multiple companies that will manufacturer equipment and products for the commissioned systems and who will participate as required in the commissioning activi-ties.
S. Factory Testing: Testing of equipment on-site or at the factory, by factory personnel, with or with-out NIST’s representative present.
T. Functional Performance Test: The testing of the dynamic function and operation of equipment and systems using manual (direct observation) or monitoring methods. Functional testing is the dynamic testing of systems (rather than just components) under full operation. Systems are tested under various modes, such as during low cooling or heating loads, high loads, compo-nent failures, unoccupied, varying outside air temperatures, etc. The systems are run through all the control system’s sequence of operation and components are verified to be responding as the sequences state. The commissioning authority develops the functional test procedures in a sequential written form, coordinates, oversees and documents the actual testing, which is usu-ally performed by the installing contractor or vendor.
U. HVAC&R: Heating, Ventilating, Air Conditioning, and Refrigeration.
V. Issues Log: A formal and ongoing record of problems or concerns – and their resolution – that have been raised by members of the commissioning team during the course of the commission-ing process.
W. Manual Test: Using hand-held instruments, immediate control system readouts or direct observa-tion to verify performance (contrasted to analyzing monitored data taken over time to make the ‘observation’).
X. Monitoring: The recording of parameters (flow, current, status, pressure, etc.) of equipment op-eration using data loggers or the trending capabilities of control systems.
Y. Non-Compliance: See Deficiency.
Z. Non-Conformance: See Deficiency.
AA. Owner’s Project Requirements (OPR): A written document that details functional requirements of the Project and the expectations of how the Project will be used and operated. This includes project and design goals, measurable performance criteria, budgets, schedules, success crite-ria, and supporting information. (Also formerly known as the Design Intent Document.)
BB. Owner’s Representative or Project Manager (Owner): The contracting and managing authority for NIST who oversees the design and/or construction of the project.
CC. Over-written Value: Writing over a sensor value in the control system to see the response of a system.
DD. Phased Commissioning: Commissioning that is completed in phases (by floors, for example) due to the size of a project or other scheduling issues, in order to minimize the total construc-tion time.
EE. Re-Commissioning Management Manual: A single manual that contains information required for recommissioning the projects’ building systems.
FF. Sampling: Functionally testing only a fraction of the total number of identical or near identical pieces of equipment.
GG. Seasonal Performance Test: Performance tests that are deferred until the system(s) will expe-rience conditions closer to their design conditions based on weather conditions.
HH. Simulated Condition: Condition that is created for the purpose of testing the response of a sys-tem (eg. Raising/lowering the set-point of a thermostat to see the response in a VAV box).
II. Simulated Signal: Disconnecting a sensor and using a signal generator to simulate a sensor value for the purpose of testing a full range of conditions.
JJ. Startup: The initial starting or activating of dynamic equipment, including completing construc-tion checklists.
KK. Systems Manual: A systems focused composite document that includes the operation manual, maintenance manual, and additional information of use to NIST during the occupancy and op-erations phase.
LL. Systems, Subsystems, and Equipment: Where these terms are used together or separately, they shall mean “as-built” systems, subsystems, and equipment.
MM. Test Procedures: The step-by-step process which must be executed to fulfill the test require-ments. The test procedures are developed by the CxA.
NN. Test Requirements: Requirements specifying what modes and functions, etc. shall be tested.
The test requirements are not the detailed test procedures. The test requirements are specified in the Contract Documents.
OO. Training Plan: A written document that details the expectations, schedule, budget and delivera-bles of commissioning process activities related to training of project operating and mainte-nance personnel, users, and occupants.
PP. Trending: Monitoring over a period of time.
QQ. Verification: The process by which specific documents, components, equipment, assemblies, systems, and interfaces among systems are confirmed to comply with the criteria described in NIST’s Project Requirements.
RR. Warranty Period: Warranty period for the entire project, including equipment components. War-ranty begins at Substantial Completion and extends typically for at least one year, unless specifi-cally noted otherwise in the Contract Documents.
1.3 SUBMITTALS
A. The CxA will review and approve submittals related to the commissioned equipment for con-formance to the Contract Documents as it relates to the commissioning process, to the func-tional performance of the equipment and adequacy for developing test procedures. This review is intended primarily to aid in the development of functional testing procedures and only sec-ondarily to verify compliance with equipment specifications. The CxA will notify the Contractor, NIST as requested, of items missing or areas that are not in conformance with Contract Docu-ments and which require resubmission.
B. The CxA will review the submittals once. The CxA will receive a copy of the final approved submittals.
1.4 QUALITY ASSURANCE
A. Test Equipment Calibration Requirements: Contractors will comply with test manufacturer’s calibration procedures and intervals. Recalibrate test instruments immediately after instru-ments have been repaired resulting from being dropped or damaged. Affix calibration tags to test instruments. Furnish calibration records to CxA upon request.
1.5 COORDINATION
A. Commissioning Kick-Off Meeting – Construction Team: Contractors will attend a meeting of the
Commissioning Team, chaired by the CxA, to review the scope of commissioning process activ-ities and the Commissioning Plan with discussions on milestones, activities, and assignments of responsibilities. The flow and type of documents and the amount of submittal data given to the CxA will be determined. Meeting minutes will then be distributed to all parties by the CxA.
B. Commissioning Meetings: Contractors will attend coordination meetings with the Commissioning
Team, chaired by the CxA, to review progress on the Commissioning Plan, construction deficien-cies, scheduling conflicts, and to discuss strategies and processes for upcoming commissioning process activities.
C. Miscellaneous Construction Meetings: The CxA attends selected planning and job-site meetings in order to remain informed on construction progress and to update parties involved in the com-missioning process.
D. Pre-testing Meetings: Contractors will attend pretest meetings with the Commissioning Team, chaired by the CxA, to review startup reports, pre-test inspection results, testing procedures, test-ing personnel and instrumentation requirements, and manufacturers’ authorized service repre-sentative services for each system, subsystem, equipment, and component to be tested.
E. Testing: Contractors will coordinate with testing personnel and agencies for timing and access for CxA to witness test.
F. Manufacturers’ Inspection and Startup Services: Contractors will coordinate services of manufac-turers’ inspection and startup services.
G. Testing, Adjusting and Balancing: Contractors will coordinate with plan and schedule for testing, adjusting and balancing for timing and access for CxA to witness process.
1.6 MINIMUM SYSTEMS TO BE COMMISSIONED
A. This includes the complete chilled water system, but is not limited to:
1. Chillers
2. Chilled water pumps
3. Condenser water pumps
4. Cooling towers
5. Condenser water filtration systems
6. Flat plate heat exchanger
7. Flat plate heat exchanger pumps
8. Controls and control sequences
PART 2 - PRODUCTS
2.1 TEST EQUIPMENT
A. All standard testing equipment required to perform startup, initial checkout and functional performance testing shall be provided by the Contractor for the equipment being tested B. Special equipment, tools and instruments (specific to a piece of equipment and only available from the vendor) required for testing shall be included in the base bid price to NIST and left on site, except for stand-alone data logging equipment that may be used by the CxA.
C. Proprietary test equipment and software required by any equipment manufacturer for program-ming and/or start-up, whether specified or not, shall be provided by the manufacturer of the equipment. Manufacturer shall provide the test equipment, demonstrate its use, and assist in the commissioning process as needed. Proprietary test equipment (and software) shall be-come the property of NIST upon completion of the commissioning process.
D. Data logging equipment and software required to test equipment will be provided by the CxA but shall not become the property of NIST.
E. All testing equipment shall be of sufficient quality and accuracy to test and/or measure system performance with the tolerances specified in the Specifications. If not otherwise noted, the fol-lowing minimum requirements apply: Temperature sensors and digital thermometers shall have a certified calibration within the past year to an accuracy of 0.5°F and a resolution of + or - 0.1°F. Pressure sensors shall have an accuracy of + or - 2.0% of the value range being meas-ured (not full range of meter) and have been calibrated within the last year.
PART 3 - EXECUTION
3.1 GENERAL DOCUMENTATION REQUIREMENTS
A. Submittals: See Section 1.5 – SUBMITTALS for requirements.
B. Checklists
1. The CxA will prepare Pre-Functional Checklists for all commissioned components, equipment, and systems.
C. Red-lined Drawings: The Contractor will verify all equipment, systems, instrumentation, wiring and components are shown correctly on red-lined drawings. Preliminary red-lined drawings must be available to the Commissioning Team for use prior to start of the Functional Perfor-mance Testing. Changes, as a result of Functional Testing, must be incorporated into the final as-built drawings, which will be created from the red-lined drawings. The contracted party, as defined in the Contract Documents will create the as-built drawings.
D. Operation and Maintenance Data: Contractor will provide a copy of O&M literature within 45 days of each submittal acceptance for use during the commissioning process for all commis-sioned equipment and systems. The CxA will review the O&M literature once for conformance to project requirements. The CxA will receive a copy of the final approved O&M literature once corrections have been made by the Contractor.
E. Demonstration and Training: Contractor will provide demonstration and training as required by the specifications. A complete training plan and schedule must be submitted by the Con-tractor to the CxA four weeks (4) prior to any training. A training agenda for each training ses-sion must be submitted to the CxA one (1) week prior the training session.
3.2 DESIGN PROFESSIONAL’S RESPONSIBILITIES
A. Attend the Commissioning Kick-Off Meeting.
B. Perform as-built drawing preparation.
C. Provide the Basis of Design Document. The designers shall assist (along with the contractors) in clarifying the operation and control of commissioned equipment in areas where the specifica-tions, control drawings or equipment documentation is not sufficient for writing detailed testing procedures.
D. Participate in the resolution of system deficiencies identified during the commissioning, accord-ing to the contract documents.
E. Construction Record documents and specifications.
F. Ensure that the CxA’s submittals comments are incorporated into the Design Professional’s submittal comments prior to sending to contractor for distribution.
G. Facility operating procedures for normal, abnormal, and emergency modes of operation.
H. Participate in resolution of design non-conformance and design deficiencies identified during the warranty-period commissioning process.
3.3 CONTRACTOR'S RESPONSIBILITIES
A. Contractor shall assign representatives with expertise and authority to act on its behalf and shall schedule them to participate in and perform commissioning process activities including, but not limited to, the following brief overview:
1. Facilitate the coordination of commissioning and incorporate commissioning activities into the overall project.
2. Provide copies of all applicable submittals as required including all changes thereto.
3. Provide detailed startup procedures.
4. Evaluate performance deficiencies identified in test reports and, in collaboration with entity responsible for system and equipment installation, perform corrective actions.
5. Cooperate with the CxA for resolution of issues recorded in the Issues Log.
6. Attend commissioning team meetings held on a scheduled basis.
7. Furnish a copy of all construction documents, addenda, change orders and approved submittals and shop drawings related to commissioned equipment to the CxA. Furnish a copy of the O&M literature to the CxA forty five (45) days after final equipment submittals.
8. In each purchase order or subcontract written, include requirements for submittal data, O&M literature, commissioning tasks and training.
9. Integrate and coordinate commissioning process activities with construction schedule.
10. Review and accept construction checklists provided by the CxA.
11. Review and accept commissioning process test procedures provided by the CxA.
12. Complete commissioning process test procedures.
13. Submit training plan for approval, coordinate training and provide qualified instructors for training of Owner personnel.
14. Assist the CxA as necessary in the seasonal testing, deferred testing an deficiency resolution.
15. Ensure that subcontractors correct deficiencies and make necessary adjustments to submittals, O&M manuals and red-lined drawings for applicable issues identified in any seasonal testing.
3.4 EQUIPMENT SUPPLIERS RESPONSIBILITIES
A. Roles and Responsibilities
1. Provide all requested submittal data, including detailed start-up procedures and specific responsibilities of NIST, to keep warranties in force.
2. Assist in equipment testing per agreements with subcontractors.
3. Provide information requested by CxA regarding equipment sequence of operation and testing procedures.
3.5 COMMISSIONING AUTHORITY RESPONSIBILITIES
A. Roles and Responsibilities
1. The CxA is not responsible for the design concept, the design criteria, compliance with codes, design or general construction scheduling, cost estimating or construction man-agement.
2. The CxA may assist with problem solving and non-conformance items or deficiencies, but the CxA is not the Design Engineer / Engineer of Record, and the commissioning process does not preclude the design engineer / Engineer of Record of responsibilities for system evaluations, adequacy of systems to meet the OPR, capacities of systems, quality control checks, or any of the other elements and recommended final acceptance of systems to
NIST.
3. The primary role of the CxA is to coordinate and direct the commissioning activities in a logical, sequential and efficient manner using consistent protocols and forms, centralized documentation, clear and regular communications and consultants with all necessary parties, frequently updated timelines and schedules and technical expertise.
B. Commissioning Plan
1. The CxA shall develop a Commissioning Plan at the start of the project. The Commis-sioning Plan shall outline the organization, schedule, allocation of resources, and docu-mentation requirements of the Commissioning Process.
2. The Commissioning Plan shall be a “living document” in which information is added to or modified by the Commissioning Team during the course of the Project.
3. At the end of the Project, the CxA shall provide NIST with the Final Commissioning Plan for NIST’s use.
C. Document Review
1. Review NIST’s Project Requirements and Basis of Design developed by the design pro-fessionals.
2. Perform a focused review of the drawings and specification during the Design Develop-ment and near the end of the Construction Document Phase, if contracted.
3. Develop full commissioning specifications for all systems and equipment to be commis-sioned. The commissioning specifications will be subject to approval of the design team and included in the final construction specifications.
4. Review submittals applicable to systems being commissioned for compliance for com-missioning needs, concurrent with the NIST’s review.
D. Cx Team Meetings
1. Commissioning during construction will begin with a ‘Commissioning Kick-Off Meeting – for Construction Team’ conducted by the CxA where the commissioning process is re-viewed with all of the commissioning team members.
2. Additional meetings will be required throughout construction and will be scheduled by the CxA on a weekly basis with necessary parties of the commissioning team attending, in order to plan, scope, coordinate, and schedule future activities and resolve problems.
E. Coordination and Scheduling
1. Coordinate and direct commissioning activities in a logical, sequential and efficient man-ner using consistent protocols and forms, centralized documentation, clear and regular communications, and consultations with all necessary parties.
2. Coordinate commissioning work with the contractor to ensure that commissioning activi-ties are being scheduled into the master project schedule.
F. Commissioning Progress
1. Perform site visits, as necessary, to observe component and system installations.
2. Attend selected planning and jobsite meetings to obtain information on construction pro-gress.
3. Review construction meeting minutes for revisions/substitutions relating to the commis-sioning process.
G. Pipe Testing, Flushing and Cleaning
1. Review and approve the pipe testing, flushing and cleaning plan submitted by the Con-tractor.
2. Witness all or part of the pipe testing, flushing and cleaning and be sufficiently confident that proper procedures are being followed.
3. Document via the online Commissioning Issues Log any deficiencies in the procedures or results.
H. Pre-Functional Checks
1. Verify proper installation of components, equipment, systems and assemblies. Sampling procedures may NOT be employed on systems and equipment.
I. Equipment and System Startup and Verification
1. Review and approve component, equipment, system and assembly startup plan devel-oped and submitted by the Contractor.
2. Approve system startup by reviewing startup reports, if contracted; and by selected site observation.
3. Review the Testing, Adjusting and Balancing execution plan for the project, which shall be submitted by the TAB subcontractor.
4. Verify and document the accuracy of the air and water systems balancing by spot testing the air and water reported field values with TAB subcontractors and by reviewing com-pleted reports.
J. Functional Performance Testing
1. With assistance from the Contractor, write Functional Performance Testing procedures for all components, equipment or systems to be commissioned.
2. With the assistance of the Contractors, coordinate Functional Performance Testing. Wit-ness and approve Functional Performance Testing performed by the Contractors.
3. With the assistance of the Contractors, coordinate retesting as necessary until satisfacto-ry performance is achieved.
4. Witness seasonal or deferred Functional Performance Testing as necessary.
K. Issue/Deficiency Logs
1. The CxA shall prepare a formal, ongoing, online record of deficiencies, problems and concerns – and their resolution – raised by members of the Commissioning Team during the Commissioning Process.
2. Issues will be recorded on an online Commissioning Issues Log for the Contractors to re-solve to the satisfaction of NIST. Issues will be added by the CxA. Team members are required to post their own responses to issues pertaining to their work. Team members are required to respond to issues added to the list within five (5) working days of being added by the CxA.
3. Issues will be revisited one (1) time to verify that the proper corrections have been made.
NIST reserves the right to deduct from the Contractors’ contract costs associated with additional revisits required for outstanding issues.
4. When issues are resolved, they will be closed on the Issues Log by the CxA.
L. Operation and Maintenance Data
1. The CxA shall review of the documentation submitted by the Contractor as required by the Specifications for completeness and accuracy. This commissioning review supple-ments, but does not replace, the Architect/Engineer’s review.
2. Review equipment warranties to ensure that NIST’s responsibilities are clearly defined.
M. Training
1. The Contractors will provide all documentation and qualified training personnel for train-ing.
2. The CxA will verify through the Contractor’s plan and schedule, training agendas, and se-lect observations that proper training procedures were followed on all commissioned sys-tems.
3. See appropriate section below pertaining to training.
N. Post Occupancy Review
1. The CxA will return to the site within the 12-month warranty period to address the follow-ing: review current building operations with facility staff and address outstanding issues related to NIST’s Project Requirements; Interview facility staff and identify problems or concerns with operating the building; Identify problems covered under warranty or under the original construction contract.
2. The CxA will make suggestions for improvements in the content of the O&M Manuals.
Any required changes shall be made by the contractor responsible for that section.
3. The CxA shall assist facility staff in developing reports, documents and requests for ser-vices to remedy outstanding problems.
O. Commissioning Final Report
1. The CxA shall provide a final report following the completion of all Functional Perfor-mance Testing. The report is to outline compliance and non-compliance to the construc-tion documents, as well as identify concerns relative to future performance
2.
3.6 GENERAL TESTING REQUIREMENTS
A. Prefunctional checklists are important to ensure that the equipment and systems are installed and operational. They ensure that functional performance testing (in-depth system checkout) may proceed without unnecessary delays. Each piece of equipment receives full Prefunctional checkout. The Prefunctional testing for a given system must be successfully completed prior to formal functional performance testing of equipment or subsystems of the given system. The Commissioning Authority shall complete the Pre-Functional checks in the field, with assistance from the installing Contractors (where necessary).
B. The installing contractors, under the direction of the CxA, shall perform Functional Performance
Testing of systems and sub-system performance after Pre-Functional checks have been com-pleted and all outstanding issues resolved.
C. The installing contractor will perform tests specified in Division 1 commissioning process activity
Sections and other sections specifying testing procedures according to approved testing proce-dures.
1. Verify and test performance using actual conditions whenever possible.
2. Simulate conditions by imposing an artificial load when it is not practical to test under ac-tual conditions. Set and document simulated conditions and methods of simulation. After test, return settings to normal operating conditions.
3. Alter set points when simulating conditions is not practical.
D. The CxA shall witness and document the results of all functional performance tests using the specific procedural forms developed for that purpose. Prior to testing, these forms are provided to the Contractors for review and comment.
E. deficiencies/non-conformance
1. The CxA will record the results of the functional test on the test form. All deficiencies or non-conformance items shall be noted and reported to NIST and Contractors on a stand-ardized form.
2. Corrections of minor deficiencies identified may be made during the tests at the discretion of the CxA.
3. Every effort will be made to expedite the testing process and minimize unnecessary de-lays, while not compromising the integrity of the procedures.
4. As tests progress and a deficiency is identified, the CxA discusses the issue with the ex-ecuting contractor.
5. When there is no dispute on the deficiency and the contractor accepts responsibility to correct it, the CxA documents the deficiency and the contractor’s response and intentions or corrections. The CxA and contractor then proceed to another test or sequence. Once the contractor corrects the deficiency, the test is rescheduled and repeated in the antici-pation of correct operation or function. If a deficiency is identified, the cost of retesting will be as per section 3.7.
6. When there is a dispute about a deficiency, regarding whether it is a deficiency or who is responsible, the CxA documents the deficiency and the contractor’s response. The defi-ciency is then forwarded to parties assumed to be responsible for the deficiency. Resolu-tions are made at the lowest management level possible. Other parties are brought into the discussion as needed. Final interpretive authority is with shall be NIST. Final ac-ceptance authority is with NIST and CxA. The CxA will then document the resolution process. Once the interpretation and resolution have been decided, the appropriate party corrects the deficiency. The CxA then reschedules the test as stated in the section above. Costs of retesting are as stated below in the applicable section.
F. Failure due to Manufacturer Defect
1. If 10% or three, whichever is greater, of identical pieces (size alone does not constitute a difference) of equipment fail to perform to the Contract Documents (mechanically or sub-stantively) due to manufacturing defect, not allowing it to meet its submitted performance spec, all identical units may be considered unacceptable by the CM/GC, CxA or Owner.
In such case, the Contractor shall provide NIST with the following.
2. Within one week of notification from the contractor or Owner, the Contractor or manufac-turer’s representative shall examine all other identical units making a record of the find-ings. The findings shall be provided to the contractor or Owner within two weeks of the original notice.
3. Within two weeks of the original notification, the Contractor or manufacturer shall provide a signed and dated, written explanation of the problem, cause of failures, etc. and all pro-posed solutions which shall include full equipment submittals. The proposed solutions shall not significantly exceed the specification requirements of the original installation.
4. The contractor, CxA or Owner will determine whether a replacement of all identical units or a repair is acceptable.
5. Two examples of the proposed solution will be installed by the Contractor and the Con-tractor will be allowed to test the installations for up to one week, upon which the CxA or owner will decide whether to accept the solution.
6. Upon acceptance, the Contractor and/or manufacturer shall replace or repair all identical items, at their expense and extend the warranty accordingly, if the original equipment warranty had begun. The replacement/repair work shall proceed with reasonable speed beginning within one week from when parts can be obtained.
G. Approval
1. The CxA notes each satisfactorily demonstrated function on the test form. Formal ap-proval of the functional test is made later after review by the CxA. The CxA recommends acceptance of each test to NIST using a standard form.
H. Deferred Testing
1. Unforeseen Deferred Testing – If any check or test cannot be completed due to the build-ing structure, required occupancy condition or other deficiency, execution of checklists and functional testing may be delayed upon approval of NIST. These tests will be con-ducted in the same manner as the seasonal tests, as soon as possible. Services of nec-essary parties will be negotiated.
2. Seasonal Testing - During the warranty period, seasonal testing (tests delayed until weather conditions are closer to the system’s design) shall be completed as part of this contract. The CxA shall coordinate this activity. Tests will be executed, documented and deficiencies corrected by the appropriate contractors, with facilities staff and the CxA wit-nessing. Any final adjustments to the O&M manuals and record documents due to sea-sonal testing will be made by the contractor.
3.7 OPERATION AND MAINTENANCE MANUALS
A. CxA Review and Approval - Prior to substantial completion, the CxA shall review the O&M manuals, documentation and record documents for systems that were commissioned to verify compliance with the Specifications. The CxA will communicate deficiencies in the manuals to the contractor and NIST. Upon a successful review of the corrections, the CxA recommends approval and acceptance of these sections of the O&M manuals to the contractor and NIST.
The CxA also reviews each equipment warranty and verifies that all requirements to keep the warranty valid are clearly stated. This work does not supersede NIST’s review of the O&M manuals
3.8 TRAINING OF OWNER PERSONNEL
A. The contractors shall be responsible for training coordination, scheduling and ultimately for ensur-ing that training is completed.
B. The CxA shall oversee the training of Owner’s personnel for commissioned equipment and sys-tems.
1. The CxA shall interview the Owner’s staff to determine the special needs and areas where training will be most valuable. NIST and CxA shall decide how rigorous the train-ing should be for each piece of commissioned equipment. The CxA shall communicate the results to the contractor.
2. The contractor will submit one comprehensive training plan to the CxA and NIST.
3. The plan will be reviewed by the CxA and NIST. Comments pertaining to its deficien-cies will be forwarded to the contractor. The training plan will be rewritten until ap-proved by the CxA and NIST The final approved training plan will cover the following elements:
a. Equipment (included in training)
b. Intended audience
c. Location of training
d. Objectives
e. Subjects covered (description, duration of discussion, special methods, etc.)
f. Duration of training on each subject
g. Qualified instructor for each subject
i. Instructor qualifications j.
3.9 REPORTING
A. The CxA will provide regular reports to NIST, on a pre-determined frequency in accordance with the project schedule. The CxA will regularly communicate with all members of the commissioning team, keeping them apprised of commissioning progress and scheduling changes through, mem-os, progress reports, etc.
B. The CxA will keep all documentation and log all commissioning-related issues that require current or future attention including deficiencies. An agreed-upon form will track the status of documen-tation and testing for each piece of equipment and system.
3.10 COMMISSIONING DOCUMENTATION
A. The CxA oversees and maintains the development of commissioning documentation. The com-missioning documentation shall be kept in three ring binders and organized by system and sub-system when practical. All pages shall be numbered, and a table of contents page(s) shall be provided. The commissioning documentation shall include, but not be limited to, the following:
1. Plan for delivery and review of submittals, systems manuals, and other documents and reports.
2. Identification of installed systems, assemblies, equipment, and components including design changes that occurred during the construction phase.
3. Process and schedule for completing construction checklists and manufacturer's pre-start and startup checklists for systems, assemblies, equipment, and components to be verified and tested.
4. Certificate of completion certifying that installation, prestart checks, and startup proce-dures have been completed.
5. Certificate of readiness certifying that systems, subsystems, equipment, and associat-ed controls are ready for testing.
6. Test and inspection reports and certificates.
7. Corrective action documents.
8. Verification of testing, adjusting, and balancing reports.
9. Approved final test and balance report for the building being commissioned.
10. All accepted shop drawings of systems equipment. Shop drawings shall be full size sheets folded as required to fit in binders.
11. All pre-functional performance test checklists, signed by personnel performing and/or witnessing test, organized by system and sub-system.
12. All verification and functional performance test checklists/results, signed by personnel performing and/or witnessing test, organized by system and sub-system. This infor-mation may be used for calibrating the original energy simulation model. The revised model will be used to create the baseline for energy use in the building.
END OF SECTION
| PART 1 - GENERAL |
| 1.1 COMMISSIONING |
| A. Commissioning is a systematic process of confirming that all building systems perform interactively according to the NIST’s Program Requirements and the Basis of Design and continuing through construction, acceptance and the warranty period with ac... |
| B. This project will have selected HVAC systems commissioned. The commissioning process will be directed by a Commissioning Authority whose services will be provided by the design build contractor. |
| C. The Commissioning Authority shall report to the project CO, COR and the design build contractor. |
| D. Commissioning during design is intended to achieve the following specific objectives: |
| 1. Verify NIST’s Program Requirements and Basis of Design are clearly documented, and they meet NIST’s goals and objectives. |
| 2. Provide Design Review during design efforts. |
| 3. Verify commissioning for the construction phase is adequately reflected in the bid documents. |
| E. Commissioning during the construction phase of this project is intended to achieve the following specific objectives: |
| 1. Provide direction for the commissioning process during construction, particularly providing resolution to issues and providing details not developed during design (ex. scheduling, participation of various parties, lines of reporting and approvals, ... |
| 2. Verify that applicable equipment and systems are installed properly and receive adequate operational checkout by installing contractors. |
| 3. Verify and document proper performance of equipment and systems. |
| 4. Verify that O&M documentation left on site is complete. |
| 5. Verify that NIST’s operating personnel are adequately trained. |
| F. The CxA works with the contractor according to established protocols to schedule the commissioning activities. The CxA will provide sufficient notice to the contractor and Owner for scheduling commissioning activities. Meanwhile, the CxA will int... |
| G. The following narrative provides a brief overview of the commissioning tasks during construction and the general order in which they occur. |
| 1. Commissioning during construction begins with a Commissioning Kick-Off Meeting – Construction Team conducted by the CxA where the commissioning process is reviewed with the commissioning team members. |
| 2. Additional meetings will be required throughout construction, scheduled by the CxA with necessary parties attending, to plan, scope, coordinate, schedule future activities and resolve problems. |
| 3. Equipment documentation is submitted to the CxA through the submittal process, including detailed start-up procedures. |
| 4. In general, the checkout and performance verification proceeds from simple to complex; from component level to equipment to systems and intersystem levels with Prefunctional checklists being completed before functional testing begins. |
| 5. The contractors, under their own direction, document and perform startup and initial checkout. The CxA documents that startup was completed according to the approved plans, when contracted. This may include the CxA witnessing start-up of selected... |
| 6. The CxA verifies installation integrity thru the use of checklists. |
| 7. The CxA develops specific equipment and system functional performance test procedures. The contractors review the procedures. |
| 8. The procedures are executed by the contractors, under the direction of, and documented by the CxA. |
| 9. Items of non-compliance in material, installation or setup are corrected at the contractor's expense and the system retested. |
| 10. The CxA reviews the O&M documentation for completeness. |
| 11. Commissioning is completed before Substantial Completion, whenever possible. |
| 12. The CxA reviews and pre-approves the training plan provided by the contractors. |
| 13. The contractors coordinate and provide training via qualified instructors. |
| 14. Training occurs. |
| 15. NIST verifies that training has occurred and provides a written statement that training has occurred. |
| 16. Deferred testing is conducted, as specified or required |
| 1.2 DEFINITIONS |
| 1.3 SUBMITTALS |
| 1.4 QUALITY ASSURANCE |
| 1.5 COORDINATION |
| 1.6 MINIMUM SYSTEMS TO BE COMMISSIONED |
| A. This includes the complete chilled water system, but is not limited to: |
| 1. Chillers |
| 2. Chilled water pumps |
| 3. Condenser water pumps |
| 4. Cooling towers |
| 5. Condenser water filtration systems |
| 6. Flat plate heat exchanger |
| 7. Flat plate heat exchanger pumps |
| 8. Controls and control sequences |
| PART 2 - PRODUCTS |
| 2.1 TEST EQUIPMENT |
| PART 3 - EXECUTION |
| 3.1 GENERAL DOCUMENTATION REQUIREMENTS |
| 3.2 DESIGN PROFESSIONAL’S RESPONSIBILITIES |
| 3.3 CONTRACTOR'S RESPONSIBILITIES |
| A. Contractor shall assign representatives with expertise and authority to act on its behalf and shall schedule them to participate in and perform commissioning process activities including, but not limited to, the following brief overview: |
| 1. Facilitate the coordination of commissioning and incorporate commissioning activities into the overall project. |
| 2. Provide copies of all applicable submittals as required including all changes thereto. |
| 3. Provide detailed startup procedures. |
| 4. Evaluate performance deficiencies identified in test reports and, in collaboration with entity responsible for system and equipment installation, perform corrective actions. |
| 5. Cooperate with the CxA for resolution of issues recorded in the Issues Log. |
| 6. Attend commissioning team meetings held on a scheduled basis. |
| 7. Furnish a copy of all construction documents, addenda, change orders and approved submittals and shop drawings related to commissioned equipment to the CxA. Furnish a copy of the O&M literature to the CxA forty five (45) days after final equipment ... |
| 8. In each purchase order or subcontract written, include requirements for submittal data, O&M literature, commissioning tasks and training. |
| 9. Integrate and coordinate commissioning process activities with construction schedule. |
| 10. Review and accept construction checklists provided by the CxA. |
| 11. Review and accept commissioning process test procedures provided by the CxA. |
| 12. Complete commissioning process test procedures. |
| 13. Submit training plan for approval, coordinate training and provide qualified instructors for training of Owner personnel. |
| 14. Assist the CxA as necessary in the seasonal testing, deferred testing an deficiency resolution. |
| 15. Ensure that subcontractors correct deficiencies and make necessary adjustments to submittals, O&M manuals and red-lined drawings for applicable issues identified in any seasonal testing. |
| 3.4 EQUIPMENT SUPPLIERS RESPONSIBILITIES |
| 3.5 COMMISSIONING AUTHORITY RESPONSIBILITIES |
| 3.6 GENERAL TESTING REQUIREMENTS |
| 3.7 OPERATION AND MAINTENANCE MANUALS |
| A. CxA Review and Approval - Prior to substantial completion, the CxA shall review the O&M manuals, documentation and record documents for systems that were commissioned to verify compliance with the Specifications. The CxA will communicate deficienc... |
| 3.8 TRAINING OF OWNER PERSONNEL |
| 3.9 REPORTING |
| 3.10 COMMISSIONING DOCUMENTATION |