Attach 4 PROJECT DESIGN AND CONSTRUCTION SUBMITTAL PROCEDURES_Rev 1_28AUG20.pdf
PDF 130 KB Posted
- Solicitation number
- 1333ND21RNB190002
About this file
This document provides submittal procedures for a federal construction project. The contractor shall provide cooling tower upgrades for the National Institute of Standards and Technology Building 42 Central Utility Plant in accordance with solicitation 1333ND21RNB190002. The contractor must submit design review materials at 60%, 90%, and 100% completion for government review. Final construction drawings and calculations are due in DWG format. Submittals include product data, shop drawings, samples, design data, and test reports. The contractor shall review all submittals for compliance prior to submitting to the government contracting officer's representative for action or approval. Incomplete submittals will be returned without review.
View the file
Other files
Show all 45
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NIST BOULDER B42 - Cooling Tower Capacity Upgrade
1333ND21RNB190002 1
PROJECT DESIGN AND CONSTRUCTION SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.1 DEFINITIONS
A. Action Submittals: Written and graphic information and physical samples that require project COR responsive action. Action submittals are those submittals indicated in individual Specification Sections as "action submittals."
B. Informational Submittals: Written and graphic information and physical samples that do not require project COR responsive action. Submittals may be rejected for not complying with requirements. Informational submittals are those submittals indicated in individual Specification Sections as "informational submittals."
1.2 SUBMISSIONS FOR DESIGN REVIEW MATERIALS
A. The DB contractor shall submit a design review submission schedule at project NTP. Each submission shall account for a 1-week NIST review and meeting.
B. The DB contractor shall submit design submission for 60, 90 and 100% completion, for review.
C. Final 100% construction dwgs shall be submitted in DWG format.
D. Final calculations shall be submitted for review.
E. Design Review Material for each submission shall be provided on CD-ROM.
1.3 CONSTRUCTION SUBMITTAL SCHEDULE
A. Submittal Schedule: Submit, as an action submittal, a list of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, ordering, manufacturing, fabrication, and delivery when establishing dates. Include additional time required for making corrections or revisions to submittals noted by project COR and additional time for handling and reviewing submittals required by those corrections.
1. Coordinate submittal schedule with list of subcontracts, the schedule of values, and Contractor's construction schedule.
2. Initial Submittal: Submit concurrently with startup construction schedule. Include submittals required during the first 60 days of construction. List those submittals required to maintain orderly progress of the Work and those required early because of long lead time for manufacture or fabrication.
3. Final Submittal: Submit concurrently with the first complete submittal of Contractor's construction schedule.
1333ND21RNB190002 2
a. Submit revised submittal schedule to reflect changes in current status and timing for submittals.
4. Format: Arrange the following information in a tabular format:
a. Scheduled date for first submittal.
b. Specification Section number and title.
c. Submittal Category: Action; informational.
d. Name of subcontractor.
e. Description of the Work covered.
1.4 INSPECTION REPORTS
A. Factory-Authorized Service Representative's Reports: Prepare written information documenting manufacturer's factory-authorized service representative's tests and inspections specified in other Sections. Include the following:
1. Name, address, telephone number, and email address of factory-authorized service representative making report.
2. Statement that equipment complies with requirements.
3. Results of operational and other tests and a statement of whether observed performance complies with requirements.
4. Statement whether conditions, products, and installation will affect warranty.
5. Other required items indicated in individual Specification Sections.
B. Manufacturer's Technical Representative's Field Reports: Prepare written information documenting manufacturer's technical representative's tests and inspections specified in other Sections. Include the following:
1. Name, address, telephone number, and email address of technical representative making report.
2. Statement on condition of substrates and their acceptability for installation of product.
3. Statement that products at Project site comply with requirements.
4. Summary of installation procedures being followed, whether they comply with requirements and, if not, what corrective action was taken.
5. Results of operational and other tests and a statement of whether observed performance complies with requirements.
6. Statement whether conditions, products, and installation will affect warranty.
7. Other required items indicated in individual Specification Sections.
1.5 SUBMITTAL FORMATS
A. Submittal Information: Include the following information in each submittal:
1. Project name.
2. Date.
3. Name of Contractor.
4. Name of firm or entity that prepared submittal.
5. Names of subcontractor, manufacturer, and supplier.
1333ND21RNB190002 3
6. Unique submittal number, including revision identifier. Include Specification Section number with sequential alphanumeric identifier; and alphanumeric suffix for resubmittals.
7. Category and type of submittal.
8. Submittal purpose and description.
9. Number and title of Specification Section, with paragraph number and generic name for each of multiple items.
10. Drawing number and detail references, as appropriate.
11. Indication of full or partial submittal.
12. Location(s) where product is to be installed, as appropriate.
13. Other necessary identification.
14. Remarks.
15. Signature of transmitter.
B. Deviations and Additional Information: On each submittal, clearly indicate deviations from requirements in the Contract Documents, including minor variations and limitations; include relevant additional information and revisions, other than those requested by the project COR on previous submittals. Indicate by highlighting on each submittal or noting on attached separate sheet.
C. PDF Submittals: Prepare submittals as PDF package, incorporating complete information into each PDF file. Name PDF file with submittal number.
D. Submittals for Web-Based Project Software: Prepare submittals as PDF files.
1.6 SUBMITTAL PROCEDURES
A. Prepare and submit submittals required by individual Specification Sections. Types of submittals are indicated in individual Specification Sections.
1. Web-Based Project Software: Prepare submittals in PDF form, and upload to web-based Project software website administered by the project COR.
B. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.
1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.
2. Submit all submittal items required for each Specification Section concurrently unless partial submittals for portions of the Work are indicated on approved submittal schedule.
3. Submit action submittals and informational submittals required by the same Specification Section as separate packages under separate transmittals.
4. Coordinate transmittal of submittals for related parts of the Work specified in different Sections so processing will not be delayed because of need to review submittals concurrently for coordination.
a. Project COR reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
C. Resubmittals: Make resubmittals in same form and number of copies as initial submittal.
1333ND21RNB190002 4
1. Note date and content of previous submittal.
2. Note date and content of revision in label or title block and clearly indicate extent of revision.
3. Resubmit submittals until they are marked with approval notation.
D. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.
1.7 SUBMITTAL REQUIREMENTS
A. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. If information must be specially prepared for submittal because standard published data are unsuitable for use, submit as Shop Drawings, not as Product Data.
2. Mark each copy of each submittal to show which products and options are applicable.
3. Include the following information, as applicable:
a. Manufacturer's catalog cuts.
b. Manufacturer's product specifications.
c. Standard color charts.
d. Statement of compliance with specified referenced standards.
e. Testing by recognized testing agency.
f. Application of testing agency labels and seals.
g. Notation of coordination requirements.
4. For equipment, include the following in addition to the above, as applicable:
a. Wiring diagrams that show factory-installed wiring.
b. Printed performance curves.
c. Operational range diagrams.
d. Clearances required to other construction, if not indicated on accompanying Shop
Drawings.
5. Submit Product Data before Shop Drawings, and before or concurrent with Samples.
B. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.
C. Qualification Data: Prepare written information that demonstrates capabilities and experience of firm or person. Include lists of completed projects with project names and addresses, contact information of architects and owners, and other information specified.
D. Design Data: Prepare and submit written and graphic information indicating compliance with indicated performance and design criteria in individual Specification Sections. Include list of assumptions and summary of loads. Include load diagrams if applicable. Provide name and version of software, if any, used for calculations. Number each page of submittal.
E. Certificates:
1333ND21RNB190002 5
1. Certificates and Certifications Submittals: Submit a statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity. Provide a notarized signature where indicated.
2. Installer Certificates: Submit written statements on manufacturer's letterhead certifying that Installer complies with requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project.
3. Manufacturer Certificates: Submit written statements on manufacturer's letterhead certifying that manufacturer complies with requirements in the Contract Documents.
Include evidence of manufacturing experience where required.
4. Material Certificates: Submit written statements on manufacturer's letterhead certifying that material complies with requirements in the Contract Documents.
5. Product Certificates: Submit written statements on manufacturer's letterhead certifying that product complies with requirements in the Contract Documents.
6. Welding Certificates: Prepare written certification that welding procedures and personnel comply with requirements in the Contract Documents. Submit record of Welding Procedure Specification and Procedure Qualification Record on AWS forms. Include names of firms and personnel certified.
F. Test and Research Reports:
1. Compatibility Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of compatibility tests performed before installation of product. Include written recommendations for primers and substrate preparation needed for adhesion.
2. Field Test Reports: Submit written reports indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements in the Contract Documents.
3. Material Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements in the Contract Documents.
4. Preconstruction Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of tests performed before installation of product, for compliance with performance requirements in the Contract Documents.
5. Product Test Reports: Submit written reports indicating that current product produced by manufacturer complies with requirements in the Contract Documents. Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency.
6. Research Reports: Submit written evidence, from a model code organization acceptable to authorities having jurisdiction, that product complies with building code in effect for Project. Include the following information:
a. Name of evaluation organization.
b. Date of evaluation.
c. Time period when report is in effect.
d. Product and manufacturers' names.
e. Description of product.
f. Test procedures and results.
g. Limitations of use.
1333ND21RNB190002 6
1.8 CONTRACTOR'S REVIEW
A. Action Submittals and Informational Submittals: Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents.
Note corrections and field dimensions. Mark with approval stamp before submitting to the project COR
B. Contractor's Approval: Indicate Contractor's approval for each submittal with a uniform approval stamp. Include name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.
1.9 PROJECT CO AND COR REVIEW
A. Action Submittals: The project CO and COR will review each submittal, indicate corrections or revisions required.
B. Informational Submittals: The project CO and COR will review each submittal and will not return it or will return it if it does not comply with requirements.
C. Incomplete submittals are unacceptable, will be considered nonresponsive, and will be returned for resubmittal without review.
END OF SECTION
| PART 1 - GENERAL |
| 1.1 DEFINITIONS |
| A. Action Submittals: Written and graphic information and physical samples that require project COR responsive action. Action submittals are those submittals indicated in individual Specification Sections as "action submittals." |
| B. Informational Submittals: Written and graphic information and physical samples that do not require project COR responsive action. Submittals may be rejected for not complying with requirements. Informational submittals are those submittals indicate... |
| 1.2 SUBMISSIONS FOR DESIGN REVIEW MATERIALS |
| A. The DB contractor shall submit a design review submission schedule at project NTP. Each submission shall account for a 1-week NIST review and meeting. |
| B. The DB contractor shall submit design submission for 60, 90 and 100% completion, for review. |
| C. Final 100% construction dwgs shall be submitted in DWG format. |
| D. Final calculations shall be submitted for review. |
| E. Design Review Material for each submission shall be provided on CD-ROM. |
| 1.3 CONSTRUCTION SUBMITTAL SCHEDULE |
| A. Submittal Schedule: Submit, as an action submittal, a list of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, ordering, manufacturing, fabrication, and delivery when establis... |
| 1. Coordinate submittal schedule with list of subcontracts, the schedule of values, and Contractor's construction schedule. |
| 2. Initial Submittal: Submit concurrently with startup construction schedule. Include submittals required during the first 60 days of construction. List those submittals required to maintain orderly progress of the Work and those required early becaus... |
| 3. Final Submittal: Submit concurrently with the first complete submittal of Contractor's construction schedule. |
| a. Submit revised submittal schedule to reflect changes in current status and timing for submittals. |
| 4. Format: Arrange the following information in a tabular format: |
| a. Scheduled date for first submittal. |
| b. Specification Section number and title. |
| c. Submittal Category: Action; informational. |
| d. Name of subcontractor. |
| e. Description of the Work covered. |
| 1.4 INSPECTION REPORTS |
| A. Factory-Authorized Service Representative's Reports: Prepare written information documenting manufacturer's factory-authorized service representative's tests and inspections specified in other Sections. Include the following: |
| 1. Name, address, telephone number, and email address of factory-authorized service representative making report. |
| 2. Statement that equipment complies with requirements. |
| 3. Results of operational and other tests and a statement of whether observed performance complies with requirements. |
| 4. Statement whether conditions, products, and installation will affect warranty. |
| 5. Other required items indicated in individual Specification Sections. |
| B. Manufacturer's Technical Representative's Field Reports: Prepare written information documenting manufacturer's technical representative's tests and inspections specified in other Sections. Include the following: |
| 1. Name, address, telephone number, and email address of technical representative making report. |
| 2. Statement on condition of substrates and their acceptability for installation of product. |
| 3. Statement that products at Project site comply with requirements. |
| 4. Summary of installation procedures being followed, whether they comply with requirements and, if not, what corrective action was taken. |
| 5. Results of operational and other tests and a statement of whether observed performance complies with requirements. |
| 6. Statement whether conditions, products, and installation will affect warranty. |
| 7. Other required items indicated in individual Specification Sections. |
| 1.5 SUBMITTAL FORMATS |
| A. Submittal Information: Include the following information in each submittal: |
| 1. Project name. |
| 2. Date. |
| 3. Name of Contractor. |
| 4. Name of firm or entity that prepared submittal. |
| 5. Names of subcontractor, manufacturer, and supplier. |
| 6. Unique submittal number, including revision identifier. Include Specification Section number with sequential alphanumeric identifier; and alphanumeric suffix for resubmittals. |
| 7. Category and type of submittal. |
| 8. Submittal purpose and description. |
| 9. Number and title of Specification Section, with paragraph number and generic name for each of multiple items. |
| 10. Drawing number and detail references, as appropriate. |
| 11. Indication of full or partial submittal. |
| 12. Location(s) where product is to be installed, as appropriate. |
| 13. Other necessary identification. |
| 14. Remarks. |
| 15. Signature of transmitter. |
| B. Deviations and Additional Information: On each submittal, clearly indicate deviations from requirements in the Contract Documents, including minor variations and limitations; include relevant additional information and revisions, other than those r... |
| C. PDF Submittals: Prepare submittals as PDF package, incorporating complete information into each PDF file. Name PDF file with submittal number. |
| D. Submittals for Web-Based Project Software: Prepare submittals as PDF files. |
| 1.6 SUBMITTAL PROCEDURES |
| A. Prepare and submit submittals required by individual Specification Sections. Types of submittals are indicated in individual Specification Sections. |
| 1. Web-Based Project Software: Prepare submittals in PDF form, and upload to web-based Project software website administered by the project COR. |
| B. Coordination: Coordinate preparation and processing of submittals with performance of construction activities. |
| 1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity. |
| 2. Submit all submittal items required for each Specification Section concurrently unless partial submittals for portions of the Work are indicated on approved submittal schedule. |
| 3. Submit action submittals and informational submittals required by the same Specification Section as separate packages under separate transmittals. |
| 4. Coordinate transmittal of submittals for related parts of the Work specified in different Sections so processing will not be delayed because of need to review submittals concurrently for coordination. |
| a. Project COR reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received. |
| C. Resubmittals: Make resubmittals in same form and number of copies as initial submittal. |
| 1. Note date and content of previous submittal. |
| 2. Note date and content of revision in label or title block and clearly indicate extent of revision. |
| 3. Resubmit submittals until they are marked with approval notation. |
D. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmi...
| 1.7 SUBMITTAL REQUIREMENTS |
| A. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment. |
| 1. If information must be specially prepared for submittal because standard published data are unsuitable for use, submit as Shop Drawings, not as Product Data. |
| 2. Mark each copy of each submittal to show which products and options are applicable. |
| 3. Include the following information, as applicable: |
| a. Manufacturer's catalog cuts. |
| b. Manufacturer's product specifications. |
| c. Standard color charts. |
| d. Statement of compliance with specified referenced standards. |
| e. Testing by recognized testing agency. |
| f. Application of testing agency labels and seals. |
| g. Notation of coordination requirements. |
| 4. For equipment, include the following in addition to the above, as applicable: |
| a. Wiring diagrams that show factory-installed wiring. |
| b. Printed performance curves. |
| c. Operational range diagrams. |
| d. Clearances required to other construction, if not indicated on accompanying Shop Drawings. |
5. Submit Product Data before Shop Drawings, and before or concurrent with Samples.
| B. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data. |
| C. Qualification Data: Prepare written information that demonstrates capabilities and experience of firm or person. Include lists of completed projects with project names and addresses, contact information of architects and owners, and other informati... |
| D. Design Data: Prepare and submit written and graphic information indicating compliance with indicated performance and design criteria in individual Specification Sections. Include list of assumptions and summary of loads. Include load diagrams if ap... |
| E. Certificates: |
| 1. Certificates and Certifications Submittals: Submit a statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents... |
| 2. Installer Certificates: Submit written statements on manufacturer's letterhead certifying that Installer complies with requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project. |
| 3. Manufacturer Certificates: Submit written statements on manufacturer's letterhead certifying that manufacturer complies with requirements in the Contract Documents. Include evidence of manufacturing experience where required. |
| 4. Material Certificates: Submit written statements on manufacturer's letterhead certifying that material complies with requirements in the Contract Documents. |
| 5. Product Certificates: Submit written statements on manufacturer's letterhead certifying that product complies with requirements in the Contract Documents. |
| 6. Welding Certificates: Prepare written certification that welding procedures and personnel comply with requirements in the Contract Documents. Submit record of Welding Procedure Specification and Procedure Qualification Record on AWS forms. Include ... |
| F. Test and Research Reports: |
| 1. Compatibility Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of compatibility tests performed before installation of product. Include written recommendation... |
| 2. Field Test Reports: Submit written reports indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements in the Contract Docu... |
| 3. Material Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements in the Contract Documents. |
| 4. Preconstruction Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of tests performed before installation of product, for compliance with performance requiremen... |
| 5. Product Test Reports: Submit written reports indicating that current product produced by manufacturer complies with requirements in the Contract Documents. Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified t... |
| 6. Research Reports: Submit written evidence, from a model code organization acceptable to authorities having jurisdiction, that product complies with building code in effect for Project. Include the following information: |
| a. Name of evaluation organization. |
| b. Date of evaluation. |
| c. Time period when report is in effect. |
| d. Product and manufacturers' names. |
| e. Description of product. |
| f. Test procedures and results. |
| g. Limitations of use. |
| 1.8 CONTRACTOR'S REVIEW |
| A. Action Submittals and Informational Submittals: Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before ... |
| B. Contractor's Approval: Indicate Contractor's approval for each submittal with a uniform approval stamp. Include name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for co... |
| 1.9 PROJECT CO AND COR REVIEW |
| A. Action Submittals: The project CO and COR will review each submittal, indicate corrections or revisions required. |
| B. Informational Submittals: The project CO and COR will review each submittal and will not return it or will return it if it does not comply with requirements. |
| C. Incomplete submittals are unacceptable, will be considered nonresponsive, and will be returned for resubmittal without review. |