ATTACH 15 - SEED PROJECT -SOW DBEH 11-1638 Demolish Heavy Equipment Shop B49800.pdf

PDF 1 MB Posted

Attached to
DBEH 25-1628_Demolition Indefinite Delivery Indefinite Quantity
Solicitation number
FA252126B0003
Issued by

About this file

This is a Statement of Work (SOW) for the demolition and site restoration of Heavy Equipment Shop B49800 at Cape Canaveral Space Force Station, Florida, with a project number of DBEH 11-1638 and completion date of June 30, 2026.

The Contractor shall safely demolish the obsolete, deteriorated facility and fully restore the site within 180 calendar days from Notice to Proceed. The work encompasses pre-demolition hazardous materials surveys (asbestos, lead-based paint, PCBs), utility disconnection and termination, complete hazardous materials abatement and disposal, systematic demolition and removal of the superstructure, concrete slabs, and foundations to 18 inches below final grade, segregation and proper disposal of all construction and demolition debris, backfilling with clean fill, final grading to ensure positive drainage, and paving the entire disturbed area with hot mix asphalt matching or exceeding the quality of surrounding parking areas. The Contractor must obtain an approved AF Form 103 (Work Clearance), coordinate permits including burn permits, conduct a wildlife survey two weeks prior to work, prepare and implement a Stormwater Pollution Prevention Plan, and manage hazardous waste through 45 CES/CEIE with monthly disposal records. Work is restricted to Monday-Friday, 0700-1600, excluding federal holidays, with utility outages requiring 14 days' advance coordination. The Contractor shall provide a Project Manager, Superintendent, Site Safety and Health Officer, and Quality Control Manager. Key deliverables include an Accident Prevention Plan, SWPPP, Hazardous Materials Inventory (AF Form 3952), final As-Built Record Drawings in AutoCAD Civil 3D format, waste disposal manifests, permit certifications, and a DD Form 1354. All salvageable materials become Contractor property to offset bid costs. The work is subject to government inspection with final acceptance granted upon completion, full site restoration, and approval of all deliverables.

View the file

Other files

File Type Posted
FA252126B0003 Abstract.pdf PDF
ATTACH 17 - SEED PROJECT - Pricing Sheet- 02 September 2026.xlsx XLSX spreadsheet
ATTACH_7___Question_and_Answer_Compiled- Amendment 02.pdf PDF
ATTACH 03 - DEMO IDIQ Pricing Sheet-02 September 2026.xlsx XLSX spreadsheet
Solicitation Amendment - FA252126B00030002- Conformed Copy.pdf PDF
Solicitation Amendment FA252126B00030002 SF 30.pdf PDF
Conformed Solicitation Amendment 1_ FA252126B0003 0001 SF 1442.pdf PDF
Solicitation Amendment 1 - FA252126B00030001- SF30.pdf PDF
ATTACH 24 - Demo IDIQ Site Visit- 17 August 2026.pdf PDF
ATTACH_7___Question_and_Answer_Compiled.pdf PDF
ATTACH 03 - DEMO IDIQ Pricing Sheet.xlsx XLSX spreadsheet
ATTACH 22 Facility Data.pdf PDF
ATTACH 15 - SEED PROJECT -SOW DBEH111638_Demolish Heavy Equipment Shop B49800_21AUG2026.pdf PDF
ATTACH 23 - Building Assessment Summary 49800.xlsx XLSX spreadsheet
Solicitation FA252126B0003 0001 SF 1442.pdf PDF
ATTACH 4 - Bid Schedule Summary- Amendment 01.pdf PDF
ATTACH 11 - DBA WD- Residential_Brevard-18 May 2026.pdf PDF
ATTACH 4 - Bid Schedule Summary.pdf PDF
ATTACH 8 - DBA WD- Building_Brevard-18 May 2026.pdf PDF
ATTACH 5 -DEMO IDIQ GPP Certification.pdf PDF
ATTACH 6 -DEMO IDIQ Haz Waste Generation Form.pdf PDF
ATTACH 10 - DBA WD- Highway_Brevard-18 May 2026.pdf PDF
ATTACH 7 - Question and Answer Template.xlsx XLSX spreadsheet
ATTACH 17 - SEED PROJECT - Pricing Sheet.xlsx XLSX spreadsheet
ATTACH 2 -DEMO IDIQ Specifications.pdf PDF
ATTACH 12 - SCA WD- Brevard- 13 May 2026.pdf PDF
ATTACH 3 - DEMO IDIQ Pricing Sheet.xlsx XLSX spreadsheet
ATTACH 21 - PIEE Solicitation- Posting Offer Guide.pdf PDF
ATTACH 19 - EDWOSB-SelfPerformanceCertificationWrksht.pdf PDF
ATTACH 9 - DBA WD- Heavy_Brevard-18 May 2026.pdf PDF
ATTACH 18 - SEED PROJECT - SHPO Response 49800 Demo_260624_184357.pdf PDF
ATTACH 20 - PIEE Solicitation- PIEE Vendor Registration.pdf PDF
Solicitation - FA252126B0003.pdf PDF
ATTACH 13 - Rules of Engagement for Site Visit- Seed Project.pdf PDF
ATTACH 16 - SEED PROJECT - Plans_DBEH111638.pdf PDF
ATTACH 1 -DEMO IDIQ Statement of Work_15JUL2026.pdf PDF
ATTACH 14 - Badge Request 45 SFS Form V14.pdf PDF
Show all 37

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Project Number: DBEH 11-1638

Project Title: Demolish Heavy Equipment Shop, B49800

Location: Cape Canaveral Space Force Station, Florida

Date: 30 JUNE 2026

1.0 Introduction and Purpose

This Statement of Work (SOW) defines the requirements for the safe demolition and complete site restoration of the subject facility located at Cape Canaveral Space Force Station (CCSFS).

The primary objective of this project is to eliminate safety hazards, reduce ongoing maintenance costs, and prepare the site for future use by removing the specified obsolete and deteriorated structure. This SOW encompasses all management, labor, materials, equipment, transportation, and supervision required to execute and complete the work described herein.

2.0 Background

The subject facility is no longer required to support any active mission and has no planned future use. Due to its age and exposure to the highly corrosive coastal environment (UFC 1-200-01, C5 Rating), the structure has significantly deteriorated, posing a safety risk. Demolition has been identified as the most effective course of action.

3.0 Scope of Work

The Contractor shall provide all services necessary to safely demolish the facility and restore the project site. The work shall primarily involve UFGS Divisions 01 (General Requirements), 02 (Existing Conditions), 31 (Earthwork), and 32 (Exterior Improvements).

3.1 Inclusions:

The work shall include, but is not limited to:

• Pre-demolition surveys for hazardous materials, including asbestos, lead-based paint (LBP), and Polychlorinated Biphenyls (PCBs).

• Coordination and acquisition of all required permits, including AF Form 103 (Work Clearance) and burn permits.

• Systematic disconnection, purging, and termination of all utilities (electrical, water, sewer, communications).

• Complete abatement and disposal of all identified hazardous materials.

• Systematic demolition and removal of the facility superstructure, concrete slabs, and foundations to a depth of 18 inches below final grade.

• Segregation, management, hauling, and proper disposal of all construction and demolition (C&D) debris, including hazardous waste, in accordance with all regulations.

• Paving of the project site, including backfilling of all voids with clean fill, final grading to ensure positive drainage, and paving the entire disturbed area with asphalt of a quality equal to or better than the surrounding parking area.

3.2 Exclusions:

This SOW specifically excludes: None.

4.0 Applicable Documents & Standards

The Contractor shall comply with the latest editions of all federal, state, and local laws, codes, and regulations. Work shall adhere to the following key documents, which form the minimum standard for this project:

• Unified Facilities Criteria (UFC) & Unified Facilities Guide Specifications (UFGS)

• Federal & State Regulations (including 29 CFR 1926, 40 CFR 260-280, and FDEP)

• Space Launch Delta 45 (SLD45) Installation Facilities Standards (IFS)

5.0 Specific Tasks & Requirements

5.1 Project Management:

• Personnel: Provide qualified personnel including an experienced Project Manager, Superintendent, Site Safety and Health Officer (SSHO), and Quality Control (QC) Manager.

• Scheduling: Submit and maintain a project schedule IAW UFGS 01 32 01.00 10.

Coordinate utility outages a minimum of 14 days in advance.

• Submittals: Provide all submittals (e.g., Accident Prevention Plan, HAZMAT inventory on AF Form 3952) IAW UFGS 01 33 00.

5.2 Pre-Demolition & Site Preparation:

• Permitting: Secure an approved AF Form 103, Base Civil Engineering Work Clearance Request, before any ground disturbance.

• Environmental: Conduct a wildlife survey two weeks prior to site work. Prepare and implement a Stormwater Pollution Prevention Plan (SWPPP).

• Hazardous Materials: Conduct comprehensive testing for asbestos, LBP, and PCBs. Abate and handle all materials IAW the SLD45 Hazardous Waste Management Plan (HWMP).

5.3 Demolition & Debris Management:

• Demolition: Execute demolition activities safely, ensuring protection of adjacent facilities.

• Waste & Debris: Characterize and segregate all waste. Non-hazardous C&D debris shall be disposed of at a licensed and approved off-base facility. All hazardous waste will be managed by 45 CES/CEIE. Provide monthly records of the weight and volume of all disposed debris.

• Salvage Rights: All salvageable materials (e.g., metal) not specifically designated for government retention shall become the property of the Contractor upon demolition to allow for bid cost offsets.

5.4 Site Restoration:

• Grading: Backfill and compact all excavations. The final grade of the sub-base shall ensure positive drainage and prevent ponding.

• Paving: Pave the entire project area with hot mix asphalt (HMA) of a quality and thickness equal to or better than the existing, adjacent parking area. Ensure seamless integration with the surrounding pavement.

6.0 Deliverables

The Contractor shall submit all key pre-construction and closeout deliverables specified in the applicable UFGS sections, including:

• Pre-Construction: Accident Prevention Plan (APP), SWPPP, and Hazardous Materials Inventory (AF Form 3952).

• Closeout: Final "As-Built" Record Drawings (in AutoCAD Civil 3D format per SLD45 standards), waste disposal manifests, permit completion certifications, and a DD Form 1354.

7.0 Schedule / Period of Performance

• Period of Performance: 180 calendar days from Notice to Proceed (NTP).

• Hours of Operation: Work is restricted to Monday-Friday, 0700-1600, excluding federal holidays. Work outside these hours requires prior written approval from the Contracting Officer (CO).

8.0 Place of Performance

All work shall be performed at Heavy Equipment Shop, B49800, CCSFS, FL.

9.0 Acceptance Criteria & Inspection

All work is subject to inspection by the Government. Final acceptance will be granted when all work is complete, the site is fully restored, and all deliverables have been submitted and approved. A final inspection will be conducted to generate and resolve a "punch list."

10.0 Project Management & Reporting

• Primary POC: The Contractor shall designate a Project Manager to serve as the single point of contact.

• Progress Meetings: The Contractor shall attend weekly project meetings to discuss schedule, progress, and safety.

11.0 Appendix A

APPENDIX A:

Map & Pictures (For reference only. Contractor to confirm all conditions prior to work).

1. B49800 Location Map

2. B49800 Exterior

3. B49800 Exterior

4. B49800 Exterior

5. B49800 Interior

6. B49800 Interior

7. B49800 Interior

8. B49800 Interior

3.1 Inclusions:
3.2 Exclusions:
Unified Facilities Criteria (UFC) & Unified Facilities Guide Specifications (UFGS)
Federal & State Regulations (including 29 CFR 1926, 40 CFR 260-280, and FDEP)
Space Launch Delta 45 (SLD45) Installation Facilities Standards (IFS)
5.0 Specific Tasks & Requirements
5.1 Project Management:
5.2 Pre-Demolition & Site Preparation:
5.3 Demolition & Debris Management:
5.4 Site Restoration:
9.0 Acceptance Criteria & Inspection
All work is subject to inspection by the Government. Final acceptance will be granted when all work is complete, the site is fully restored, and all deliverables have been submitted and approved. A final inspection will be conducted to generate and re...
10.0 Project Management & Reporting
Primary POC: The Contractor shall designate a Project Manager to serve as the single point of contact.
Progress Meetings: The Contractor shall attend weekly project meetings to discuss schedule, progress, and safety.