ATT 3- Estimated Construction Schedule- EHRM- Grand Junction CO.pdf

PDF 2 MB Posted

Attached to
Y1DA--575-21-700 | Construction| EHRM Infrastructure Upgrades | Grand Junction, CO
Solicitation number
36C77625B0039
Issued by

About this file

The document is an Estimated Construction Schedule for the VA Grand Junction EHRM (Electronic Health Record Modernization) Infrastructure Upgrades project at the Grand Junction VA Medical Center. The comprehensive schedule spans from May 1, 2025 to February 10, 2027, covering a total duration of 642 calendar days (465 working days), which is approximately 21 months. The project involves extensive infrastructure upgrades across multiple buildings (Buildings 1, 5, 6, 7, 8, 9, 12, 20, 35, 36, 37, 44, and 45), focusing on telecommunications rooms, fiber optic cabling, electrical systems, power infrastructure, and building renovations.

The schedule is structured in multiple phases, including preconstruction, site work, exterior improvements, and building-specific renovations. Key milestones include mobilization starting May 1, 2025, construction of redundant site fiber loops, telecommunications room upgrades, installation of new cabling, power panel replacements, and mechanical/electrical equipment installations. The project accounts for weather contingencies, long-lead equipment procurement, and includes provisions for Infection Control Risk Assessment (ICRA) walls. Critical path activities are driven by transformer procurement and installation, with system start-ups, commissioning, and final inspections scheduled throughout 2026, culminating in project closeout on February 10, 2027.

View the file

Other files

File Type Posted
S05 - 575-21-700 Tech Questions responses updated - GJ CO - 8-28-25.docx DOCX document
575-700.VA Archtitectural Grand Junction EHRM Addendum 2 - Changed Sheets Only.pdf PDF
For Information Only - B44_2013_TERRACON_41013_Parking_Garage.pdf PDF
575-700.VA Civil Grand Junction EHRM Addendum 2 - Fiber Optic Manhole Detail.pdf PDF
575-700.VA Telecom Grand Junction EHRM Addendum 2 - Changed Sheets Only.pdf PDF
For Information Only - B9_2019_Geotech_Report_HB_Boiler_Plant.pdf PDF
575-700.VA Mechanical Grand Junction EHRM Addendum 2 - Changed Sheets Only.pdf PDF
S06- Amendment 0009.pdf PDF
S06 - Amendment 0008.pdf PDF
S06- Amendment 0007.pdf PDF
32 05 23 Cement and Concrete for Exterior Improvements.pdf PDF
32 12 16 Asphalt Paving.pdf PDF
CIP concrete short form.pdf PDF
S06- Amendment 0006- Bid due date extended 08-28-25.pdf PDF
S06- Amendment 0005- Bid due date extended.pdf PDF
S06- Amendment 0005- Bid due date extended.pdf PDF
B12 Roof 20250730.pdf PDF
S06- Amendment 0004- Bid opening info and all tech questions responses.pdf PDF
4 Utility Plan.pdf PDF
B7 Roof 20250730.pdf PDF
S05 - 575-21-700 All Tech Questions Responses - CO.docx DOCX document
S06- Amendment 0003 - DB Wages updated - Bid extension - RFI answers.pdf PDF
S05 - 575-21-700 Tech Questions Responses- GJ CO 07-28-25.docx DOCX document
P07- Updated Wages Determination - Grand Junction CO 07-25-2025.pdf PDF
S04- Signed site visit sign in sheet - 57521700 CO.pdf PDF
S06- Amendment 0002- Signed site visit sheet.pdf PDF
ATT 12- Drawings - EHRM - Grand Junction - CO.pdf PDF
ATT 13- Specifications-Combined- EHRM - Grand Junction CO.pdf PDF
ATT 4- Grand Junction CO - SPECS 07-03-25- Addendum.pdf PDF
ATT 11 - Site Visit Instructions.pdf PDF
ATT 1- Grand Junction EHRM - Drawings 07-03-25 - Addendum.pdf PDF
S06 - Amendment 0001.pdf PDF
ATT 7 - Spec 01 31 00.01 Project Management and Coordination.pdf PDF
ATT 10 - GEO Reports B20.pdf PDF
ATT 6 - Wages Determination - Grand Junction CO.pdf PDF
ATT 5- 100 CD Basis of Design -Combined- Grand Junction CO.pdf PDF
ATT 1- Grand Junction EHRM - Drawings 07-03-25.pdf PDF
ATT 8 - Limitations on Subcontracting.docx DOCX document
36C77625B0039.pdf PDF
ATT 11- Site Visit Instructions.pdf PDF
ATT 4- Grand Junction CO - SPECS 07-03-25.pdf PDF
ATT 2- Parking Guidelines Grand Junction VAMC.pdf PDF
ATT 9- Hazardous Materials Report.pdf PDF
Show all 43

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VA Grand Junction EHRM Grand Junction VA Medical Center

Estimated Construction Schedule

VA Contract #36C77622C0145 SES Project #22295.000

12/17/2024

Grand Junction VAMC - EHRM

Construction Baseline- 100CD

Schedule Narrative

Job No. 211372.000

17 December 2024

Veterans Health Administration Grand Junction

VAMC - EHRM

Grand Junction, CO

Grand Junction VAMC EHRM Infrastructure Upgrades

Baseline Schedule Analysis- 100 CD 17 December 2024

FOR OFFICIAL USE ONLY (FOUO) – PROCUREMENT SENSITIVE Page 1 of 4

I. SCHEDULE

GENERAL PROJECT INFORMATION and ASSUMPTIONS

▪ Project sequence has been defined, per 100% Construction documents, as:

o Construct a new redundant site fiber loop from the new server room to all outbuildings.

Maintain the existing fiber duct bank and feeds from the existing server room as currently constructed until the end of the project.

o Construct new telecommunications rooms and expand existing to remain telecommunications rooms. Route new and redundant fiber to new telecommunications rooms. In existing to remain telecommunications rooms, route the redundant fiber backbone from the new main computer room. Maintain the existing rooms and fiber backbone cabling until the area being served by each respective telecommunications room has been refed. Provide new A/B power panels, HVAC, and grounding in new and existing to remain rooms. Power all telecommunications room loads from the new panels.

o For new or expanded telecommunications rooms, provide new cables from the existing outlets to the new rooms. Remove existing Category 5e or lower cabling after new cables have been pulled into the outlets to maintain operational capability of the spaces to the greatest extent possible.

o After new cabling has been installed, remove existing backbone cabling in telecommunications rooms being abandoned. In existing to remain telecommunications rooms, replace the existing fiber optic backbone cabling with new cabling matching the requirements in the guidelines.

o Replace the existing interbuilding backbone cabling with new fiber optic cabling meeting the requirements stated in the guidelines.

▪ There are two project specific calendars in the schedule. Activities have been assigned the 5-days with federal holidays or the 7 days with no holidays.

▪ 12 days of weather contingency included per NOAA data for Grand Junction, CO. Weather has only been included for site work which is limited and thus the weather contingency is not in the critical path.

▪ Mechanical and Electrical equipment has been determined to be long lead items for procurement, per current industry conditions. The schedule is being driven by the Transformer process from submittal to delivery.

▪ Work on building 20 can also be affected by the lead times of MEP Equipment.

▪ Temporary or Infection Control Risk Assessment (ICRA) walls are needed to separate operational areas and included in the schedule.

▪ There is no financial benefit to spending additional funds on compressing the duration of the schedule or creating concurrency due to the long lead times for Electrical Equipment.

▪ Commissioning on buildings will drive the Final Inspections, and these will drive the Punch list and the

Final Completion.

▪ The start of the schedule (Data Date) has been defined arbitrarily as spring of 2025.

FOR OFFICIAL USE ONLY (FOUO) – PROCUREMENT SENSITIVE Page 2 of 4

PROJECT LOCATION

The proposed project is located at the Grand Junction VA Medical Center, located at Grand Junction, CO.

SCHEDULE

We assume the project will be demolition and protection of areas only. Construction Duration Includes all Site, Renovation Work, Final Inspections, and 1 month of Commissioning.

We anticipate the following duration ranges:

▪ Construction NTP = 01MAY2025

▪ Construction Duration = 642 calendar days = 465 working days ≈ 21 months

▪ Mid-Point of Construction = FEB2026

▪ Construction Finish = 10FEB2027

CHANGES FROM 65% TO 100%

The following are the changes made to the schedule per drawings and estimate:

▪ Building 1 – New UPS rooms were reduced to 1 room; repurposing of TR rooms was reduced by 8 rooms to a total of 14 rooms. Rooms were missing in the previous schedule and durations had to be increased to account for those.

▪ Building 6 – The new TR room was eliminated

▪ Building 22 – eliminated from the schedule

▪ Building 34 (Data Center) – There is no construction work on this building, but activities were added for IT/Telecom/Security wiring terminations

▪ Building 35 – The new TR room was eliminated

▪ Building 36 – The new TR room was eliminated

▪ Building 44 – The new TR room was eliminated

▪ Building 45 – The new TR room was eliminated

FOR OFFICIAL USE ONLY (FOUO) – PROCUREMENT SENSITIVE Page 3 of 4

LONGEST PATH

The baseline critical path has 0 days of float and it’s driven by Mobilization and the ATS, UPS, and Transformer submittal process including procurement which then leads to the installation of the ATS, UPS, and Transformer on BLDG 01 and interior and MEP work on the existing TR room of Bldg 01.

The secondary path is driven by Mobilization, then exterior work on the duct banks. The construction of Bldg 44 starts right after, with the interior work of the new TR Room. Once Bldg 44 is complete work will start in Bldg 45 and due to crew flow, after Bldg 45 is complete the work continues with the construction of interior partitions of buildings 05, 37, 06, 35, 16, 09, 08, 12, 07. Both paths end with Startup, Commissioning, and final inspections of Bldg 44, 45, 22, and 01. After the final inspection of Bldg 01 is completed, there will be additional time for a

NOTE: For this narrative, the Critical and Near Critical Path is shown collapsed. For a full view of the critical path please find the attached reports.

Activity ID Activity Name Original Duration

Start Finish

VA_Grand Junction- EHRM_100CD_01MAY2025VA_Grand Junction- EHRM_100CD_01MAY2025 465 1-May-25 10-Feb-27

Executive SummaryExecutive Summary 465 1-May-25 10-Feb-27

Construction MilestonesConstruction Milestones 465 1-May-25 10-Feb-27

C-ADMIN-1030 Construction NTP 0 1-May-25*

B44-1060 BLDG 44 - New TR Complete incl Commissioning 0 31-Dec-25

B45-1060 BLDG 45 - New TR Complete incl Commissioning 0 10-Apr-26

B01-1060 BLDG 01 - New TR Complete incl Commissioning 0 10-Sep-26

B01-1070 BLDG 01 - Repurposed Rm Complete 0 13-Jan-27

C-MILE-1010 Construction Final Project/Contract Closeout 0 10-Feb-27

ConstructionConstruction 465 1-May-25 10-Feb-27

Exterior and Site WorkExterior and Site Work 50 1-May-25 9-Jul-25

MOB-1010 Mobilization 10 1-May-25 14-May-25

Site DuctbankSite Ductbank 40 15-May-25 9-Jul-25

Electrical WorkElectrical Work 40 15-May-25 9-Jul-25

SITE-1020 Ductbank Excavation & Construction 40 15-May-25 9-Jul-25

BuildingsBuildings 395 10-Jul-25 13-Jan-27

Building 20 -ExistingBuilding 20 -Existing 42 10-Jul-25 5-Sep-25

B44-1080 Building 20 Contruction Start 0 10-Jul-25

B44-1090 Building 20- New TR Construction Finish 0 5-Sep-25

Interior WorkInterior Work 22 10-Jul-25 8-Aug-25

B20-INT1000 ICRA - New TR- 20 2 10-Jul-25 11-Jul-25

B20-INT1010 Frame Interior Partitions - Bldg 20 5 14-Jul-25 18-Jul-25

B20-INT1020 Install Interior Partitions - Bldg 20 5 21-Jul-25 25-Jul-25

B20-INT1030 Patch/Repair Existing Walls - Bldg 20 10 28-Jul-25 8-Aug-25

MEPMEP 20 11-Aug-25 5-Sep-25

B20E-MEP-1000 Install Distribution Systems - Bldg 20 5 11-Aug-25 15-Aug-25

B20E-MEP-1020 Install Electrical Distribution & Service - Bldg 20 4 18-Aug-25 21-Aug-25

B20E-MEP-1010 Install Fire Alarm & Detection Systems - Bldg 20 1 22-Aug-25 22-Aug-25

B20E-MEP-1040 Install Branch Wiring & Lighting Fixtures - Bldg 20 5 25-Aug-25 29-Aug-25

B20E-MEP-1060 Install Communications - Bldg 20 5 1-Sep-25 5-Sep-25

Building 44Building 44 85 8-Sep-25 2-Jan-26

B44-1000 Building 44 Contruction Start 0 8-Sep-25

B44-1010 Building 44- New TR Construction Finish 0 22-Dec-25

New TR Room- Building 44New TR Room- Building 44 76 8-Sep-25 22-Dec-25

Interior WorkInterior Work 20 8-Sep-25 3-Oct-25

B44-INT-1000 ICRA - New TR- 44 2 8-Sep-25 9-Sep-25

B44-INT-1030 Frame Interior Partitions - Bldg 44 5 10-Sep-25 16-Sep-25

B44-INT-1040 Install Interior Partitions - Bldg 44 5 17-Sep-25 23-Sep-25

B44-INT-1050 Patch/Repair Existing Walls - Bldg 44 8 24-Sep-25 3-Oct-25

MEPMEP 56 6-Oct-25 22-Dec-25

B44-MEP-1010 Install Distribution Systems - Bldg 44 8 6-Oct-25 15-Oct-25

B44-MEP-1020 Install Terminal & Package Units - Bldg 44 3 16-Oct-25 20-Oct-25

B44-MEP-1030 Install HVAC Trimout - Bldg 44 3 21-Oct-25 23-Oct-25

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3

2025 2026 2027

10-Feb-27, VA_Grand Junction- EHRM_100CD_01MAY2025

10-Feb-27, Executive Summary

10-Feb-27, Construction Milestones

Construction NTP, 1-May-25*

BLDG 44 - New TR Complete incl Commissioning, BLDG 45 - New TR Complete incl Commissioning, BLDG 01 - New TR Complete incl Commissioning, BLDG 01 - Repurposed Rm Complete, Construction Final Project/Contract Closeout, 10-Feb-27, Construction

9-Jul-25, Exterior and Site Work

Mobilization

9-Jul-25, Site Ductbank

9-Jul-25, Electrical Work

Ductbank Excavation & Construction

13-Jan-27, Buildings

5-Sep-25, Building 20 -Existing

Building 20 Contruction Start, 10-Jul-25

Building 20- New TR Construction Finish, 8-Aug-25, Interior Work

ICRA - New TR- 20

Frame Interior Partitions - Bldg 20

Install Interior Partitions - Bldg 20

Patch/Repair Existing Walls - Bldg 20

5-Sep-25, MEP

Install Distribution Systems - Bldg 20

Install Electrical Distribution & Service - Bldg 20

Install Fire Alarm & Detection Systems - Bldg 20

Install Branch Wiring & Lighting Fixtures - Bldg 20

Install Communications - Bldg 20

2-Jan-26, Building 44

Building 44 Contruction Start, 8-Sep-25

Building 44- New TR Construction Finish, 22-Dec-25, New TR Room- Building 44

3-Oct-25, Interior Work

ICRA - New TR- 44

Frame Interior Partitions - Bldg 44

Install Interior Partitions - Bldg 44

Patch/Repair Existing Walls - Bldg 44

22-Dec-25, MEP

Install Distribution Systems - Bldg 44

Install Terminal & Package Units - Bldg 44

Install HVAC Trimout - Bldg 44

VA_Grand Junction- EHRM_100CD_01MAY2025

Data Date: 1-May-25

*Critical Path

TASK filters: Critical, Longest Path.

Report Run Date: 17-Dec-24

Actual Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Milestone summary

Start Finish

B44-MEP-1040 Install Fire Sprinkler System - Bldg 44 3 4-Nov-25 6-Nov-25

B44-MEP-1050 Install Fire Alarm & Detection Systems - Bldg 44 3 18-Nov-25 20-Nov-25

B44-MEP-1060 Install Electrical Distribution & Service - Bldg 44 10 18-Nov-25 1-Dec-25

B44-MEP-1070 Install Branch Wiring & Lighting Fixtures - Bldg 44 10 21-Nov-25 4-Dec-25

B44-MEP-1100 Install Communications Systems - Bldg 44 10 5-Dec-25 18-Dec-25

B44-MEP-1110 Install Controls - Bldg 44 2 19-Dec-25 22-Dec-25

Repurpose Existing TR Room- Building 44Repurpose Existing TR Room- Building 44 2 1-Jan-26 2-Jan-26

Interior WorkInterior Work 2 1-Jan-26 2-Jan-26

B44-INT-1130 ICRA - Bldg 44 2 1-Jan-26 2-Jan-26

Building 45Building 45 72 5-Jan-26 14-Apr-26

B45-1000 Building 45 Contruction Start 0 5-Jan-26

B45-1010 Building 45- New TR Construction Finish 0 1-Apr-26

New TR Room- Building 45New TR Room- Building 45 63 5-Jan-26 1-Apr-26

Interior WorkInterior Work 17 5-Jan-26 27-Jan-26

B45-INT-1000 ICRA - New TR- 45 2 5-Jan-26 6-Jan-26

B45-INT-1030 Frame Interior Partitions - Bldg 45 5 7-Jan-26 13-Jan-26

B45-INT-1040 Install Interior Partitions - Bldg 45 5 14-Jan-26 20-Jan-26

B45-INT-1050 Patch/Repair Existing Walls - Bldg 45 5 21-Jan-26 27-Jan-26

MEPMEP 46 28-Jan-26 1-Apr-26

B45-MEP-1000 Install Mechanical/Plumbing Rough-in - Bldg 45 5 28-Jan-26 3-Feb-26

B45-MEP-1010 Install Distribution Systems - Bldg 45 5 28-Jan-26 3-Feb-26

B45-MEP-1020 Install Terminal & Package Units - Bldg 45 3 4-Feb-26 6-Feb-26

B45-MEP-1030 Install HVAC Trimout - Bldg 45 3 9-Feb-26 11-Feb-26

B45-MEP-1040 Install Fire Sprinkler System - Bldg 45 3 23-Feb-26 25-Feb-26

B45-MEP-1050 Install Fire Alarm & Detection Systems - Bldg 45 3 9-Mar-26 11-Mar-26

B45-MEP-1060 Install Electrical Distribution & Service - Bldg 45 5 9-Mar-26 13-Mar-26

B45-MEP-1070 Install Branch Wiring & Lighting Fixtures - Bldg 45 8 12-Mar-26 23-Mar-26

B45-MEP-1090 Install Security Systems - Bldg 45 5 24-Mar-26 30-Mar-26

B45-MEP-1100 Install Communications Systems - Bldg 45 5 24-Mar-26 30-Mar-26

B45-MEP-1110 Install Controls - Bldg 45 2 31-Mar-26 1-Apr-26

Repurpose Existing TR Room- Building 45Repurpose Existing TR Room- Building 45 2 13-Apr-26 14-Apr-26

Interior WorkInterior Work 2 13-Apr-26 14-Apr-26

B45-INT-1130 ICRA - Bldg 45 2 13-Apr-26 14-Apr-26

Building 05Building 05 2 15-Apr-26 16-Apr-26

B05-1000 Building 05 Contruction Start 0 15-Apr-26

New TR Room- Building 05 (2nd Fl)New TR Room- Building 05 (2nd Fl) 2 15-Apr-26 16-Apr-26

Interior WorkInterior Work 2 15-Apr-26 16-Apr-26

B05-INT-1000 ICRA - New TR- 05 2 15-Apr-26 16-Apr-26

Building 37Building 37 2 17-Apr-26 20-Apr-26

B37-1000 Building 37 Contruction Start 0 17-Apr-26

New TR Room- Building 37New TR Room- Building 37 2 17-Apr-26 20-Apr-26

Interior WorkInterior Work 2 17-Apr-26 20-Apr-26

B37-INT-1000 ICRA - New TR- 37 2 17-Apr-26 20-Apr-26

Building 06Building 06 0 21-Apr-26 21-Apr-26

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3

2025 2026 2027

Install Fire Sprinkler System - Bldg 44

Install Fire Alarm & Detection Systems - Bldg 44

Install Electrical Distribution & Service - Bldg 44

Install Branch Wiring & Lighting Fixtures - Bldg 44

Install Communications Systems - Bldg 44

Install Controls - Bldg 44

2-Jan-26, Repurpose Existing TR Room- Building 44

2-Jan-26, Interior Work

ICRA - Bldg 44

14-Apr-26, Building 45

Building 45 Contruction Start, 5-Jan-26

Building 45- New TR Construction Finish, 1-Apr-26, New TR Room- Building 45

27-Jan-26, Interior Work

ICRA - New TR- 45

Frame Interior Partitions - Bldg 45

Install Interior Partitions - Bldg 45

Patch/Repair Existing Walls - Bldg 45

1-Apr-26, MEP

Install Mechanical/Plumbing Rough-in - Bldg 45

Install Distribution Systems - Bldg 45

Install Terminal & Package Units - Bldg 45

Install HVAC Trimout - Bldg 45

Install Fire Sprinkler System - Bldg 45

Install Fire Alarm & Detection Systems - Bldg 45

Install Electrical Distribution & Service - Bldg 45

Install Branch Wiring & Lighting Fixtures - Bldg 45

Install Security Systems - Bldg 45

Install Communications Systems - Bldg 45

Install Controls - Bldg 45

14-Apr-26, Repurpose Existing TR Room- Building 45

14-Apr-26, Interior Work

ICRA - Bldg 45

16-Apr-26, Building 05

Building 05 Contruction Start, 15-Apr-26

16-Apr-26, New TR Room- Building 05 (2nd Fl)

16-Apr-26, Interior Work

ICRA - New TR- 05

20-Apr-26, Building 37

Building 37 Contruction Start, 17-Apr-26

20-Apr-26, New TR Room- Building 37

20-Apr-26, Interior Work

ICRA - New TR- 37

21-Apr-26, Building 06

VA_Grand Junction- EHRM_100CD_01MAY2025

Data Date: 1-May-25

*Critical Path

TASK filters: Critical, Longest Path.

Report Run Date: 17-Dec-24

Actual Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Start Finish

B06-1000 Building 06 Contruction Start 0 21-Apr-26

Building 35Building 35 0 21-Apr-26 21-Apr-26

B35-1000 Building 35 Contruction Start 0 21-Apr-26

Building 36Building 36 0 21-Apr-26 21-Apr-26

B16-1000 Building 16 Contruction Start 0 21-Apr-26

Building 09Building 09 2 21-Apr-26 22-Apr-26

B09-1000 Building 09 Contruction Start 0 21-Apr-26

New TR Room- Building 09New TR Room- Building 09 2 21-Apr-26 22-Apr-26

Interior WorkInterior Work 2 21-Apr-26 22-Apr-26

B09-INT-1000 ICRA - New TR- 09 2 21-Apr-26 22-Apr-26

Building 08Building 08 2 23-Apr-26 24-Apr-26

B08-1000 Building 08 Contruction Start 0 23-Apr-26

New TR Room- Building 08New TR Room- Building 08 2 23-Apr-26 24-Apr-26

Interior WorkInterior Work 2 23-Apr-26 24-Apr-26

B08-INT-1000 ICRA - New TR- 08 2 23-Apr-26 24-Apr-26

Building 12Building 12 2 27-Apr-26 28-Apr-26

B12-1000 Building 12 Contruction Start 0 27-Apr-26

New TR Room- Building 12New TR Room- Building 12 2 27-Apr-26 28-Apr-26

Interior WorkInterior Work 2 27-Apr-26 28-Apr-26

B12-INT-1000 ICRA - New TR- 12 2 27-Apr-26 28-Apr-26

Building 07Building 07 2 29-Apr-26 30-Apr-26

B07-1000 Building 07 Contruction Start 0 29-Apr-26

New TR Room- Building 07New TR Room- Building 07 2 29-Apr-26 30-Apr-26

Interior WorkInterior Work 2 29-Apr-26 30-Apr-26

B07-INT-1000 ICRA - New TR- 07 2 29-Apr-26 30-Apr-26

Building 01Building 01 184 1-May-26 13-Jan-27

B01-1000 Building 01 Contruction Start 0 1-May-26

B01-1010 Building 01- New TR Construction Finish 0 1-Sep-26

New TR Rooms- Building 01 Level 1New TR Rooms- Building 01 Level 1 2 1-May-26 4-May-26

Interior WorkInterior Work 2 1-May-26 4-May-26

B01-INT-1000 ICRA - New TR- 01 L1 2 1-May-26 4-May-26

New TR Rooms- Building 01 Level 2New TR Rooms- Building 01 Level 2 82 5-May-26 26-Aug-26

Interior WorkInterior Work 29 5-May-26 12-Jun-26

B01-INT-1220 ICRA - New TR- 01 L2 2 5-May-26 6-May-26

B01-INT-1230 Frame Interior Partitions - Bldg 01 L2 5 7-May-26 13-May-26

B01-INT-1240 Install Interior Partitions - Bldg 01 L2 5 14-May-26 20-May-26

B01-INT-1200 Patch/Repair Existing Walls - Bldg 01 L2 8 21-May-26 1-Jun-26

B01-INT-1190 Paint - Bldg 01 L2 3 2-Jun-26 4-Jun-26

B01-INT-1210 Install Fire Treated Plywood - Bldg 01 L2 3 5-Jun-26 9-Jun-26

B01-INT-1180 Install Flooring - Bldg 01 L2 3 10-Jun-26 12-Jun-26

MEPMEP 53 15-Jun-26 26-Aug-26

B01-MEP-1250 Install Mechanical/Plumbing Rough-in - Bldg 01 L2 5 15-Jun-26 19-Jun-26

B01-MEP-1270 Install Terminal & Package Units - Bldg 01 L2 3 22-Jun-26 24-Jun-26

B01-MEP-1290 Install HVAC Trimout - Bldg 01 L2 3 25-Jun-26 29-Jun-26

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3

2025 2026 2027

Building 06 Contruction Start, 21-Apr-26

21-Apr-26, Building 35

Building 35 Contruction Start, 21-Apr-26

21-Apr-26, Building 36

Building 16 Contruction Start, 21-Apr-26

22-Apr-26, Building 09

Building 09 Contruction Start, 21-Apr-26

22-Apr-26, New TR Room- Building 09

22-Apr-26, Interior Work

ICRA - New TR- 09

24-Apr-26, Building 08

Building 08 Contruction Start, 23-Apr-26

24-Apr-26, New TR Room- Building 08

24-Apr-26, Interior Work

ICRA - New TR- 08

28-Apr-26, Building 12

Building 12 Contruction Start, 27-Apr-26

28-Apr-26, New TR Room- Building 12

28-Apr-26, Interior Work

ICRA - New TR- 12

30-Apr-26, Building 07

Building 07 Contruction Start, 29-Apr-26

30-Apr-26, New TR Room- Building 07

30-Apr-26, Interior Work

ICRA - New TR- 07

13-Jan-27, Building 01

Building 01 Contruction Start, 1-May-26

Building 01- New TR Construction Finish, 4-May-26, New TR Rooms- Building 01 Level 1

4-May-26, Interior Work

ICRA - New TR- 01 L1

26-Aug-26, New TR Rooms- Building 01 Level 2

12-Jun-26, Interior Work

ICRA - New TR- 01 L2

Frame Interior Partitions - Bldg 01 L2

Install Interior Partitions - Bldg 01 L2

Patch/Repair Existing Walls - Bldg 01 L2

Paint - Bldg 01 L2

Install Fire Treated Plywood - Bldg 01 L2

Install Flooring - Bldg 01 L2

26-Aug-26, MEP

Install Mechanical/Plumbing Rough-in - Bldg 01 L2

Install Terminal & Package Units - Bldg 01 L2

Install HVAC Trimout - Bldg 01 L2

VA_Grand Junction- EHRM_100CD_01MAY2025

Data Date: 1-May-25

*Critical Path

TASK filters: Critical, Longest Path.

Report Run Date: 17-Dec-24

Actual Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Start Finish

B01-MEP-1310 Install Fire Sprinkler System - Bldg 01 L2 3 9-Jul-26 13-Jul-26

B01-MEP-1300 Install Fire Alarm & Detection Systems - Bldg 01 L2 3 23-Jul-26 27-Jul-26

B01-MEP-1320 Install Electrical Distribution & Service - Bldg 01 L2 8 23-Jul-26 3-Aug-26

B01-MEP-1330 Install Branch Wiring & Lighting Fixtures - Bldg 01 L2 6-Nov-25 28-Jul-26 10-Aug-26

B01-MEP-1340 Install Communications Systems - Bldg 01 L2 10 11-Aug-26 24-Aug-26

B01-MEP-1280 Install Controls - Bldg 01 L2 2 25-Aug-26 26-Aug-26

New TR Rooms- Building 01 Level 3New TR Rooms- Building 01 Level 3 2 27-Aug-26 28-Aug-26

MEPMEP 2 27-Aug-26 28-Aug-26

B01-MEP-1400 Install Controls - Bldg 01 L3 2 27-Aug-26 28-Aug-26

New TR Rooms- Building 01 Level 4, 5, & 6New TR Rooms- Building 01 Level 4, 5, & 6 2 31-Aug-26 1-Sep-26

MEPMEP 2 31-Aug-26 1-Sep-26

B01-MEP-1520 Install Controls - Bldg 01 L4, 5, & 6 2 31-Aug-26 1-Sep-26

Repurpose Existing TR Rooms- Building 01Repurpose Existing TR Rooms- Building 01 89 11-Sep-26 13-Jan-27

Interior WorkInterior Work 36 11-Sep-26 30-Oct-26

B01-INT-1130 ICRA - Bldg 01 L1 8 11-Sep-26 22-Sep-26

B01-INT-1150 Interior Demolition - Bldg 01 L1 10 23-Sep-26 6-Oct-26

B01-INT-1170 Install Interior Partitions - Bldg 01 L1 15 7-Oct-26 27-Oct-26

B01-INT-1110 Patch/Repair Existing Walls - Bldg 01 L1 18 7-Oct-26 30-Oct-26

MEPMEP 53 2-Nov-26 13-Jan-27

B01-MEP-1130 Install Mechanical/Plumbing Rough-in - Bldg 01 L1 20 2-Nov-26 27-Nov-26

B01-MEP-1140 Install Distribution Systems - Bldg 01 L1 20 2-Nov-26 27-Nov-26

B01-MEP-1150 Install Terminal & Package Units - Bldg 01 L1 20 4-Nov-26 1-Dec-26

B01-MEP-1170 Install HVAC Trimout - Bldg 01 L1 12 17-Nov-26 2-Dec-26

B01-MEP-1190 Install Fire Sprinkler System - Bldg 01 L1 20 19-Nov-26 16-Dec-26

B01-MEP-1180 Install Fire Alarm & Detection Systems - Bldg 01 L1 12 23-Nov-26 8-Dec-26

B01-MEP-1200 Install Electrical Distribution & Service - Bldg 01 L1 14 23-Nov-26 10-Dec-26

B01-MEP-1210 Install Branch Wiring & Lighting Fixtures - Bldg 01 L1 14 23-Nov-26 10-Dec-26

B01-MEP-1220 Install Communications Systems - Bldg 01 L1 14 11-Dec-26 30-Dec-26

B01-MEP-1160 Install Controls - Bldg 01 L1 10 31-Dec-26 13-Jan-27

Systems Start UpSystems Start Up 184 23-Dec-25 4-Sep-26

B44-1020 BLDG 44 Systems Start-Up 3 23-Dec-25 25-Dec-25

B45-1020 BLDG 45 Systems Start-Up 3 2-Apr-26 6-Apr-26

B01-1020 BLDG 01 Systems Start-Up 3 2-Sep-26 4-Sep-26

CommissioningCommissioning 183 26-Dec-25 8-Sep-26

B44-1040 BLDG 44 - New TR Commissioning 2 26-Dec-25 29-Dec-25

B45-1040 BLDG 45 - New TR Commissioning 2 7-Apr-26 8-Apr-26

B01-1040 BLDG 01 - New TR Commissioning 2 7-Sep-26 8-Sep-26

Final InspectionsFinal Inspections 183 30-Dec-25 10-Sep-26

B44-1050 BLDG 44 - New TR Final Inspections 2 30-Dec-25 31-Dec-25

B45-1050 BLDG 45 - New TR Final Inspections 2 9-Apr-26 10-Apr-26

B01-1050 BLDG 01 - New TR Final Inspections 2 9-Sep-26 10-Sep-26

CloseoutCloseout 20 14-Jan-27 10-Feb-27

CLOS-1010 Final Project Punch 10 14-Jan-27 27-Jan-27

CLOS-1000 Final Project/Contract Closeout 10 28-Jan-27 10-Feb-27

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3

2025 2026 2027

Install Fire Sprinkler System - Bldg 01 L2

Install Fire Alarm & Detection Systems - Bldg 01 L2

Install Electrical Distribution & Service - Bldg 01 L2

Install Branch Wiring & Lighting Fixtures - Bldg 01 L2

Install Communications Systems - Bldg 01 L2

Install Controls - Bldg 01 L2

28-Aug-26, New TR Rooms- Building 01 Level 3

28-Aug-26, MEP

Install Controls - Bldg 01 L3

1-Sep-26, New TR Rooms- Building 01 Level 4, 5, & 6

1-Sep-26, MEP

Install Controls - Bldg 01 L4, 5, & 6

13-Jan-27, Repurpose Existing TR Rooms- Building 01

30-Oct-26, Interior Work

ICRA - Bldg 01 L1

Interior Demolition - Bldg 01 L1

Install Interior Partitions - Bldg 01 L1

Patch/Repair Existing Walls - Bldg 01 L1

13-Jan-27, MEP

Install Mechanical/Plumbing Rough-in - Bldg 01 L1

Install Distribution Systems - Bldg 01 L1

Install Terminal & Package Units - Bldg 01 L1

Install HVAC Trimout - Bldg 01 L1

Install Fire Sprinkler System - Bldg 01 L1

Install Fire Alarm & Detection Systems - Bldg 01 L1

Install Electrical Distribution & Service - Bldg 01 L1

Install Branch Wiring & Lighting Fixtures - Bldg 01 L1

Install Communications Systems - Bldg 01 L1

Install Controls - Bldg 01 L1

4-Sep-26, Systems Start Up

BLDG 44 Systems Start-Up

BLDG 45 Systems Start-Up

BLDG 01 Systems Start-Up

8-Sep-26, Commissioning

BLDG 44 - New TR Commissioning

BLDG 45 - New TR Commissioning

BLDG 01 - New TR Commissioning

10-Sep-26, Final Inspections

BLDG 44 - New TR Final Inspections

BLDG 45 - New TR Final Inspections

BLDG 01 - New TR Final Inspections

10-Feb-27, Closeout

Final Project Punch

Final Project/Contract Closeout

VA_Grand Junction- EHRM_100CD_01MAY2025

Data Date: 1-May-25

*Critical Path

TASK filters: Critical, Longest Path.

Report Run Date: 17-Dec-24

Actual Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Start Finish

VA_Grand Junction- EHRM_100CD_01MAY2025VA_Grand Junction- EHRM_100CD_01MAY2025 465 1-May-25 10-Feb-27

Executive SummaryExecutive Summary 465 1-May-25 10-Feb-27

Construction MilestonesConstruction Milestones 465 1-May-25 10-Feb-27

C-ADMIN-1030 Construction NTP 0 1-May-25*

C-ADMIN-1020 Weather Contingency for Ductbank Scope 12 1-Aug-25 12-Aug-25

C-MILE-1110 Ductbank and Fiber Complete/ Ready to Tie to New TRs 0 12-Aug-25

C-MILE-1130 BLDG 20 - New TR Complete incl Commissioning 0 16-Sep-25

B44-1060 BLDG 44 - New TR Complete incl Commissioning 0 31-Dec-25

B44-1070 BLDG 44 - Repurposed Rm Complete 0 17-Feb-26

B45-1060 BLDG 45 - New TR Complete incl Commissioning 0 10-Apr-26

B06-1060 BLDG 06 - New TR Complete incl Commissioning 0 4-May-26

B35-1060 BLDG 35 - New TR Complete incl Commissioning 0 4-May-26

B16-1060 BLDG 16 - New TR Complete incl Commissioning 0 4-May-26

B22-1060 BLDG 22 - New TR Complete incl Commissioning 0 14-May-26

B45-1070 BLDG 45 - Repurposed Rm Complete 0 9-Jun-26

B06-1070 BLDG 06 - Repurposed Rm Complete 0 2-Jul-26

B35-1070 BLDG 35 - Repurposed Rm Complete 0 2-Jul-26

B16-1070 BLDG 16 - Repurposed Rm Complete 0 2-Jul-26

B05-1060 BLDG 05 - New TR Complete incl Commissioning 0 11-Aug-26

B37-1060 BLDG 37 - New TR Complete incl Commissioning 0 13-Aug-26

B09-1060 BLDG 09 - New TR Complete incl Commissioning 0 17-Aug-26

B12-1060 BLDG 12 - New TR Complete incl Commissioning 0 21-Aug-26

B07-1060 BLDG 07 - New TR Complete incl Commissioning 0 25-Aug-26

B08-1060 BLDG 08 - New TR Complete incl Commissioning 0 26-Aug-26

B01-1060 BLDG 01 - New TR Complete incl Commissioning 0 10-Sep-26

B05-1070 BLDG 05 - Repurposed Rm Complete 0 9-Oct-26

B37-1070 BLDG 37 - Repurposed Rm Complete 0 13-Oct-26

B09-1070 BLDG 09 - Repurposed Rm Complete 0 14-Oct-26

B12-1070 BLDG 12 - Repurposed Rm Complete 0 20-Oct-26

B07-1070 BLDG 07 - Repurposed Rm Complete 0 22-Oct-26

B08-1070 BLDG 08 - Repurposed Rm Complete 0 28-Oct-26

B01-1070 BLDG 01 - Repurposed Rm Complete 0 13-Jan-27

C-MILE-1010 Construction Final Project/Contract Closeout 0 10-Feb-27

PreconstructionPreconstruction 70 1-May-25 6-Aug-25

Submittals & ProcurementSubmittals & Procurement 70 1-May-25 6-Aug-25

SubmittalsSubmittals 20 1-May-25 28-May-25

SUBM-1000 Prepare & Submit Long Lead Items Submittal 20 1-May-25 28-May-25

Review and ApproveReview and Approve 20 29-May-25 25-Jun-25

SUBM-1020 AE/VA Review and Approve Long Lead Items Submittal 20 29-May-25 25-Jun-25

Fab/ DeliverFab/ Deliver 30 26-Jun-25 6-Aug-25

PRCH-1010 Fabricate & Deliver MEP Long Lead Items 30 26-Jun-25 6-Aug-25

ConstructionConstruction 465 1-May-25 10-Feb-27

SUBM-1030 Prepare & Submit ATS, UPS, Transformer Submittal 25 6-May-25 9-Jun-25

Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan F Mar Apr May Jun JulAug 2025 2026 2027

10-Feb-27, VA_Grand Junction- EHRM_100CD_01MAY2025

10-Feb-27, Executive Summary

10-Feb-27, Construction Milestones

Construction NTP, 1-May-25*

Weather Contingency for Ductbank Scope

Ductbank and Fiber Complete/ Ready to Tie to New TRs, BLDG 20 - New TR Complete incl Commissioning, BLDG 44 - New TR Complete incl Commissioning, BLDG 44 - Repurposed Rm Complete, BLDG 45 - New TR Complete incl Commissioning, BLDG 06 - New TR Complete incl Commissioning, BLDG 35 - New TR Complete incl Commissioning, BLDG 16 - New TR Complete incl Commissioning, BLDG 22 - New TR Complete incl Commissioning, BLDG 45 - Repurposed Rm Complete, BLDG 06 - Repurposed Rm Complete, BLDG 35 - Repurposed Rm Complete, BLDG 16 - Repurposed Rm Complete, BLDG 05 - New TR Complete incl Commissioning, BLDG 37 - New TR Complete incl Commissioning, BLDG 09 - New TR Complete incl Commissioning, BLDG 12 - New TR Complete incl Commissioning, BLDG 07 - New TR Complete incl Commissioning, BLDG 08 - New TR Complete incl Commissioning, BLDG 01 - New TR Complete incl Commissioning, BLDG 05 - Repurposed Rm Complete, BLDG 37 - Repurposed Rm Complete, BLDG 09 - Repurposed Rm Complete, BLDG 12 - Repurposed Rm Complete, BLDG 07 - Repurposed Rm Complete, BLDG 08 - Repurposed Rm Complete, BLDG 01 - Repurposed Rm Complete, Construction Final Project/Contract Closeout, 6-Aug-25, Preconstruction

6-Aug-25, Submittals & Procurement

28-May-25, Submittals

Prepare & Submit Long Lead Items Submittal

25-Jun-25, Review and Approve

AE/VA Review and Approve Long Lead Items Submittal

6-Aug-25, Fab/ Deliver

Fabricate & Deliver MEP Long Lead Items

10-Feb-27, Construction

Prepare & Submit ATS, UPS, Transformer Submittal

VA_Grand Junction- EHRM_100CD_01MAY2025

Data Date: 1-May-25

*All Activities by WBS

TASK filter: All Activities

Report Run Date: 17-Dec-24

Actual Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Start Finish

SUBM-1040 AE/VA Review and Approve ATS, UPS, Transformer Submittal 15 10-Jun-25 30-Jun-25

PRCH-1020 Fabricate & Deliver MEP ATS, UPS, Transformer 210 1-Jul-25 20-Apr-26

Exterior and Site WorkExterior and Site Work 90 1-May-25 3-Sep-25

MOB-1010 Mobilization 10 1-May-25 14-May-25

Site DuctbankSite Ductbank 64 15-May-25 12-Aug-25

Electrical WorkElectrical Work 64 15-May-25 12-Aug-25

SITE-1020 Ductbank Excavation & Construction 40 15-May-25 9-Jul-25

SITE-1050 Ductbank-Pulling Site Fiber Loop Cables 15 10-Jul-25 30-Jul-25

SITE-1000 Backfill @ Ductbanks 15 11-Jul-25 31-Jul-25

SITE-1060 Site Communications and Security Scope 20 16-Jul-25 12-Aug-25

SiteworkSitework 40 10-Jul-25 3-Sep-25

SITE-1010 Pedestrian Paving 15 10-Jul-25 30-Jul-25

SITE-1030 Parking Lot 15 31-Jul-25 20-Aug-25

SITE-1040 Landscaping Repairs 10 21-Aug-25 3-Sep-25

BuildingsBuildings 395 10-Jul-25 13-Jan-27

Building 20 -ExistingBuilding 20 -Existing 42 10-Jul-25 5-Sep-25

B44-1080 Building 20 Contruction Start 0 10-Jul-25

B44-1090 Building 20- New TR Construction Finish 0 5-Sep-25

Interior WorkInterior Work 31 10-Jul-25 21-Aug-25

B20-INT1000 ICRA - New TR- 20 2 10-Jul-25 11-Jul-25

B20-INT1010 Frame Interior Partitions - Bldg 20 5 14-Jul-25 18-Jul-25

B20-INT1020 Install Interior Partitions - Bldg 20 5 21-Jul-25 25-Jul-25

B20-INT1030 Patch/Repair Existing Walls - Bldg 20 10 28-Jul-25 8-Aug-25

B20-INT1040 Paint - Bldg 20 3 11-Aug-25 13-Aug-25

B20-INT1050 Install Fire Treated Plywood - Bldg 20 3 14-Aug-25 18-Aug-25

B20-INT1060 Install Flooring - Bldg 20 3 19-Aug-25 21-Aug-25

MEPMEP 20 11-Aug-25 5-Sep-25

B20E-MEP-1000 Install Distribution Systems - Bldg 20 5 11-Aug-25 15-Aug-25

B20E-MEP-1020 Install Electrical Distribution & Service - Bldg 20 4 18-Aug-25 21-Aug-25

B20E-MEP-1010 Install Fire Alarm & Detection Systems - Bldg 20 1 22-Aug-25 22-Aug-25

B20E-MEP-1030 Install Ceiling Finishes - Bldg 20 5 25-Aug-25 29-Aug-25

B20E-MEP-1040 Install Branch Wiring & Lighting Fixtures - Bldg 20 5 25-Aug-25 29-Aug-25

B20E-MEP-1060 Install Communications - Bldg 20 5 1-Sep-25 5-Sep-25

B20E-MEP-1050 Install Security Systems - Bldg 20 5 1-Sep-25 5-Sep-25

Building 44Building 44 117 8-Sep-25 17-Feb-26

B44-1000 Building 44 Contruction Start 0 8-Sep-25

B44-1010 Building 44- New TR Construction Finish 0 22-Dec-25

New TR Room- Building 44New TR Room- Building 44 76 8-Sep-25 22-Dec-25

Interior WorkInterior Work 29 8-Sep-25 16-Oct-25

B44-INT-1000 ICRA - New TR- 44 2 8-Sep-25 9-Sep-25

B44-INT-1030 Frame Interior Partitions - Bldg 44 5 10-Sep-25 16-Sep-25

B44-INT-1040 Install Interior Partitions - Bldg 44 5 17-Sep-25 23-Sep-25

B44-INT-1050 Patch/Repair Existing Walls - Bldg 44 8 24-Sep-25 3-Oct-25

B44-INT-1060 Paint - Bldg 44 3 6-Oct-25 8-Oct-25

Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan F Mar Apr May Jun JulAug 2025 2026 2027

AE/VA Review and Approve ATS, UPS, Transformer Submittal

Fabricate & Deliver MEP ATS, UPS, Transformer

3-Sep-25, Exterior and Site Work

Mobilization

12-Aug-25, Site Ductbank

12-Aug-25, Electrical Work

Ductbank Excavation & Construction

Ductbank-Pulling Site Fiber Loop Cables

Backfill @ Ductbanks

Site Communications and Security Scope

3-Sep-25, Sitework

Pedestrian Paving

Parking Lot

Landscaping Repairs

13-Jan-27, Buildings

5-Sep-25, Building 20 -Existing

Building 20 Contruction Start, 10-Jul-25

Building 20- New TR Construction Finish, 21-Aug-25, Interior Work

ICRA - New TR- 20

Frame Interior Partitions - Bldg 20

Install Interior Partitions - Bldg 20

Patch/Repair Existing Walls - Bldg 20

Paint - Bldg 20

Install Fire Treated Plywood - Bldg 20

Install Flooring - Bldg 20

5-Sep-25, MEP

Install Distribution Systems - Bldg 20

Install Electrical Distribution & Service - Bldg 20

Install Fire Alarm & Detection Systems - Bldg 20

Install Ceiling Finishes - Bldg 20

Install Branch Wiring & Lighting Fixtures - Bldg 20

Install Communications - Bldg 20

Install Security Systems - Bldg 20

17-Feb-26, Building 44

Building 44 Contruction Start, 8-Sep-25

Building 44- New TR Construction Finish, 22-Dec-25, New TR Room- Building 44

16-Oct-25, Interior Work

ICRA - New TR- 44

Frame Interior Partitions - Bldg 44

Install Interior Partitions - Bldg 44

Patch/Repair Existing Walls - Bldg 44

Paint - Bldg 44

VA_Grand Junction- EHRM_100CD_01MAY2025

Data Date: 1-May-25

*All Activities by WBS

TASK filter: All Activities

Report Run Date: 17-Dec-24

Actual Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Start Finish

B44-INT-1070 Install Fire Treated Plywood - Bldg 44 3 9-Oct-25 13-Oct-25

B44-INT-1080 Install Flooring - Bldg 44 3 14-Oct-25 16-Oct-25

MEPMEP 56 6-Oct-25 22-Dec-25

B44-MEP-1000 Install Mechanical/Plumbing Rough-in - Bldg 44 5 6-Oct-25 10-Oct-25

B44-MEP-1010 Install Distribution Systems - Bldg 44 8 6-Oct-25 15-Oct-25

B44-MEP-1020 Install Terminal & Package Units - Bldg 44 3 16-Oct-25 20-Oct-25

B44-MEP-1030 Install HVAC Trimout - Bldg 44 3 21-Oct-25 23-Oct-25

B44-MEP-1040 Install Fire Sprinkler System - Bldg 44 3 4-Nov-25 6-Nov-25

B44-MEP-1050 Install Fire Alarm & Detection Systems - Bldg 44 3 18-Nov-25 20-Nov-25

B44-MEP-1060 Install Electrical Distribution & Service - Bldg 44 10 18-Nov-25 1-Dec-25

B44-MEP-1070 Install Branch Wiring & Lighting Fixtures - Bldg 44 10 21-Nov-25 4-Dec-25

B44-MEP-1080 Install Ceiling Finishes - Bldg 44 5 28-Nov-25 4-Dec-25

B44-MEP-1100 Install Communications Systems - Bldg 44 10 5-Dec-25 18-Dec-25

B44-MEP-1090 Install Security Systems - Bldg 44 6 5-Dec-25 12-Dec-25

B44-MEP-1110 Install Controls - Bldg 44 2 19-Dec-25 22-Dec-25

Repurpose Existing TR Room- Building 44Repurpose Existing TR Room- Building 44 34 1-Jan-26 17-Feb-26

Interior WorkInterior Work 15 1-Jan-26 21-Jan-26

B44-INT-1130 ICRA - Bldg 44 2 1-Jan-26 2-Jan-26

B44-INT-1150 Interior Demolition - Bldg 44 3 5-Jan-26 7-Jan-26

B44-INT-1170 Install Interior Partitions - Bldg 44 3 8-Jan-26 12-Jan-26

B44-INT-1110 Patch/Repair Existing Walls - Bldg 44 2 13-Jan-26 14-Jan-26

B44-INT-1100 Paint - Bldg 44 2 15-Jan-26 16-Jan-26

B44-INT-1090 Install Flooring - Bldg 44 3 19-Jan-26 21-Jan-26

MEPMEP 24 15-Jan-26 17-Feb-26

B44-MEP-1130 Install Mechanical/Plumbing Rough-in - Bldg 44 3 15-Jan-26 19-Jan-26

B44-MEP-1140 Install Distribution Systems - Bldg 44 3 15-Jan-26 19-Jan-26

B44-MEP-1150 Install Terminal & Package Units - Bldg 44 2 20-Jan-26 21-Jan-26

B44-MEP-1170 Install HVAC Trimout - Bldg 44 2 22-Jan-26 23-Jan-26

B44-MEP-1190 Install Fire Sprinkler System - Bldg 44 2 5-Feb-26 6-Feb-26

B44-MEP-1180 Install Fire Alarm & Detection Systems - Bldg 44 2 6-Feb-26 9-Feb-26

B44-MEP-1200 Install Electrical Distribution & Service - Bldg 44 2 6-Feb-26 9-Feb-26

B44-MEP-1120 Install Ceiling Finishes - Bldg 44 2 10-Feb-26 11-Feb-26

B44-MEP-1210 Install Branch Wiring & Lighting Fixtures - Bldg 44 2 10-Feb-26 11-Feb-26

B44-MEP-1220 Install Communications Systems - Bldg 44 2 12-Feb-26 13-Feb-26

B44-MEP-1230 Install Security Systems - Bldg 44 2 12-Feb-26 13-Feb-26

B44-MEP-1160 Install Controls - Bldg 44 2 16-Feb-26 17-Feb-26

Building 45Building 45 112 5-Jan-26 9-Jun-26

B45-1000 Building 45 Contruction Start 0 5-Jan-26

B45-1010 Building 45- New TR Construction Finish 0 1-Apr-26

New TR Room- Building 45New TR Room- Building 45 63 5-Jan-26 1-Apr-26

Interior WorkInterior Work 26 5-Jan-26 9-Feb-26

B45-INT-1000 ICRA - New TR- 45 2 5-Jan-26 6-Jan-26

B45-INT-1030 Frame Interior Partitions - Bldg 45 5 7-Jan-26 13-Jan-26

B45-INT-1040 Install Interior Partitions - Bldg 45 5 14-Jan-26 20-Jan-26

Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan F Mar Apr May Jun JulAug 2025 2026 2027

Install Fire Treated Plywood - Bldg 44

Install Flooring - Bldg 44

22-Dec-25, MEP

Install Mechanical/Plumbing Rough-in - Bldg 44

Install Distribution Systems - Bldg 44

Install Terminal & Package Units - Bldg 44

Install HVAC Trimout - Bldg 44

Install Fire Sprinkler System - Bldg 44

Install Fire Alarm & Detection Systems - Bldg 44

Install Electrical Distribution & Service - Bldg 44

Install Branch Wiring & Lighting Fixtures - Bldg 44

Install Ceiling Finishes - Bldg 44

Install Communications Systems - Bldg 44

Install Security Systems - Bldg 44

Install Controls - Bldg 44

17-Feb-26, Repurpose Existing TR Room- Building 44

21-Jan-26, Interior Work

ICRA - Bldg 44

Interior Demolition - Bldg 44

Install Interior Partitions - Bldg 44

Patch/Repair Existing Walls - Bldg 44

Paint - Bldg 44

Install Flooring - Bldg 44

17-Feb-26, MEP

Install Mechanical/Plumbing Rough-in - Bldg 44

Install Distribution Systems - Bldg 44

Install Terminal & Package Units - Bldg 44

Install HVAC Trimout - Bldg 44

Install Fire Sprinkler System - Bldg 44

Install Fire Alarm & Detection Systems - Bldg 44

Install Electrical Distribution & Service - Bldg 44

Install Ceiling Finishes - Bldg 44

Install Branch Wiring & Lighting Fixtures - Bldg 44

Install Communications Systems - Bldg 44

Install Security Systems - Bldg 44

Install Controls - Bldg 44

9-Jun-26, Building 45

Building 45 Contruction Start, 5-Jan-26

Building 45- New TR Construction Finish, 1-Apr-26, New TR Room- Building 45

9-Feb-26, Interior Work

ICRA - New TR- 45

Frame Interior Partitions - Bldg 45

Install Interior Partitions - Bldg 45

VA_Grand Junction- EHRM_100CD_01MAY2025

Data Date: 1-May-25

*All Activities by WBS

TASK filter: All Activities

Report Run Date: 17-Dec-24

Actual Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Start Finish

B45-INT-1050 Patch/Repair Existing Walls - Bldg 45 5 21-Jan-26 27-Jan-26

B45-INT-1060 Paint - Bldg 45 3 28-Jan-26 30-Jan-26

B45-INT-1070 Install Fire Treated Plywood - Bldg 45 3 2-Feb-26 4-Feb-26

B45-INT-1080 Install Flooring - Bldg 45 3 5-Feb-26 9-Feb-26

MEPMEP 46 28-Jan-26 1-Apr-26

B45-MEP-1000 Install Mechanical/Plumbing Rough-in - Bldg 45 5 28-Jan-26 3-Feb-26

B45-MEP-1010 Install Distribution Systems - Bldg 45 5 28-Jan-26 3-Feb-26

B45-MEP-1020 Install Terminal & Package Units - Bldg 45 3 4-Feb-26 6-Feb-26

B45-MEP-1030 Install HVAC Trimout - Bldg 45 3 9-Feb-26 11-Feb-26

B45-MEP-1040 Install Fire Sprinkler System - Bldg 45 3 23-Feb-26 25-Feb-26

B45-MEP-1050 Install Fire Alarm & Detection Systems - Bldg 45 3 9-Mar-26 11-Mar-26

B45-MEP-1060 Install Electrical Distribution & Service - Bldg 45 5 9-Mar-26 13-Mar-26

B45-MEP-1070 Install Branch Wiring & Lighting Fixtures - Bldg 45 8 12-Mar-26 23-Mar-26

B45-MEP-1080 Install Ceiling Finishes - Bldg 45 5 17-Mar-26 23-Mar-26

B45-MEP-1100 Install Communications Systems - Bldg 45 5 24-Mar-26 30-Mar-26

B45-MEP-1090 Install Security Systems - Bldg 45 5 24-Mar-26 30-Mar-26

B45-MEP-1110 Install Controls - Bldg 45 2 31-Mar-26 1-Apr-26

Repurpose Existing TR Room- Building 45Repurpose Existing TR Room- Building 45 42 13-Apr-26 9-Jun-26

Interior WorkInterior Work 16 13-Apr-26 4-May-26

B45-INT-1130 ICRA - Bldg 45 2 13-Apr-26 14-Apr-26

B45-INT-1150 Interior Demolition - Bldg 45 3 15-Apr-26 17-Apr-26

B45-INT-1170 Install Interior Partitions - Bldg 45 2 20-Apr-26 21-Apr-26

B45-INT-1110 Patch/Repair Existing Walls - Bldg 45 2 22-Apr-26 23-Apr-26

B45-INT-1100 Paint - Bldg 45 2 24-Apr-26 27-Apr-26

B45-INT-1120 Install Fire Treated Plywood - Bldg 45 2 28-Apr-26 29-Apr-26

B45-INT-1090 Install Flooring - Bldg 45 3 30-Apr-26 4-May-26

MEPMEP 33 24-Apr-26 9-Jun-26

B45-MEP-1130 Install Mechanical/Plumbing Rough-in - Bldg 45 3 24-Apr-26 28-Apr-26

B45-MEP-1140 Install Distribution Systems - Bldg 45 3 24-Apr-26 28-Apr-26

B45-MEP-1150 Install Terminal & Package Units - Bldg 45 2 29-Apr-26 30-Apr-26

B45-MEP-1170 Install HVAC Trimout - Bldg 45 2 1-May-26 4-May-26

B45-MEP-1190 Install Fire Sprinkler System - Bldg 45 2 15-May-26 18-May-26

B45-MEP-1180 Install Fire Alarm & Detection Systems - Bldg 45 2 29-May-26 1-Jun-26

B45-MEP-1200 Install Electrical Distribution & Service - Bldg 45 2 29-May-26 1-Jun-26

B45-MEP-1120 Install Ceiling Finishes - Bldg 45 2 2-Jun-26 3-Jun-26

B45-MEP-1210 Install Branch Wiring & Lighting Fixtures - Bldg 45 2 2-Jun-26 3-Jun-26

B45-MEP-1220 Install Communications Systems - Bldg 45 2 4-Jun-26 5-Jun-26

B45-MEP-1230 Install Security Systems - Bldg 45 2 4-Jun-26 5-Jun-26

B45-MEP-1160 Install Controls - Bldg 45 2 8-Jun-26 9-Jun-26

Building 05Building 05 128 15-Apr-26 9-Oct-26

B05-1000 Building 05 Contruction Start 0 15-Apr-26

B05-1010 Building 05- New TR Construction Finish 0 31-Jul-26

New TR Room- Building 05 (2nd Fl)New TR Room- Building 05 (2nd Fl) 78 15-Apr-26 31-Jul-26

Interior WorkInterior Work 29 15-Apr-26 25-May-26

Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan F Mar Apr May Jun JulAug 2025 2026 2027

Patch/Repair Existing Walls - Bldg 45

Paint - Bldg 45

Install Fire Treated Plywood - Bldg 45

Install Flooring - Bldg 45

1-Apr-26, MEP

Install Mechanical/Plumbing Rough-in - Bldg 45

Install Distribution Systems - Bldg 45

Install Terminal & Package Units - Bldg 45

Install HVAC Trimout - Bldg 45

Install Fire Sprinkler System - Bldg 45

Install Fire Alarm & Detection Systems - Bldg 45

Install Electrical Distribution & Service - Bldg 45

Install Branch Wiring & Lighting Fixtures - Bldg 45

Install Ceiling Finishes - Bldg 45

Install Communications Systems - Bldg 45

Install Security Systems - Bldg 45

Install Controls - Bldg 45

9-Jun-26, Repurpose Existing TR Room- Building 45

4-May-26, Interior Work

ICRA - Bldg 45

Interior Demolition - Bldg 45

Install Interior Partitions - Bldg 45

Patch/Repair Existing Walls - Bldg 45

Paint - Bldg 45

Install Fire Treated Plywood - Bldg 45

Install Flooring - Bldg 45

9-Jun-26, MEP

Install Mechanical/Plumbing Rough-in - Bldg 45

Install Distribution Systems - Bldg 45

Install Terminal & Package Units - Bldg 45

Install HVAC Trimout - Bldg 45

Install Fire Sprinkler System - Bldg 45

Install Fire Alarm & Detection Systems - Bldg 45

Install Electrical Distribution & Service - Bldg 45

Install Ceiling Finishes - Bldg 45

Install Branch Wiring & Lighting Fixtures - Bldg 45

Install Communications Systems - Bldg 45

Install Security Systems - Bldg 45

Install Controls - Bldg 45

9-Oct-26, Building 05

Building 05 Contruction Start, 15-Apr-26

Building 05- New TR Construction Finish, 31-Jul-26, New TR Room- Building 05 (2nd Fl)

25-May-26, Interior Work

VA_Grand Junction- EHRM_100CD_01MAY2025

Data Date: 1-May-25

*All Activities by WBS

TASK filter: All Activities

Report Run Date: 17-Dec-24

Actual Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Start Finish

B05-INT-1000 ICRA - New TR- 05 2 15-Apr-26 16-Apr-26

B05-INT-1030 Frame Interior Partitions - Bldg 05 2 20-Apr-26 21-Apr-26

B05-INT-1040 Install Interior Partitions - Bldg 05 5 22-Apr-26 28-Apr-26

B05-INT-1050 Patch/Repair Existing Walls - Bldg 05 10 29-Apr-26 12-May-26

B05-INT-1060 Paint - Bldg 05 3 13-May-26 15-May-26

B05-INT-1070 Install Fire Treated Plywood - Bldg 05 3 18-May-26 20-May-26

B05-INT-1080 Install Flooring - Bldg 05 3 21-May-26 25-May-26

MEPMEP 58 13-May-26 31-Jul-26

B05-MEP-1000 Install Mechanical/Plumbing Rough-in - Bldg 05 5 13-May-26 19-May-26

B05-MEP-1010 Install Distribution Systems - Bldg 05 10 13-May-26 26-May-26

B05-MEP-1020 Install Terminal & Package Units - Bldg 05 3 27-May-26 29-May-26

B05-MEP-1030 Install HVAC Trimout - Bldg 05 3 1-Jun-26 3-Jun-26

B05-MEP-1040 Install Fire Sprinkler System - Bldg 05 3 15-Jun-26 17-Jun-26

B05-MEP-1050 Install Fire Alarm & Detection Systems - Bldg 05 3 29-Jun-26 1-Jul-26

B05-MEP-1060 Install Electrical Distribution & Service - Bldg 05 10 29-Jun-26 10-Jul-26

B05-MEP-1070 Install Branch Wiring & Lighting Fixtures - Bldg 05 10 2-Jul-26 15-Jul-26

B05-MEP-1080 Install Ceiling Finishes - Bldg 05 5 9-Jul-26 15-Jul-26

B05-MEP-1100 Install Communications Systems - Bldg 05 10 16-Jul-26 29-Jul-26

B05-MEP-1090 Install Security Systems - Bldg 05 6 16-Jul-26 23-Jul-26

B05-MEP-1110 Install Controls - Bldg 05 2 30-Jul-26 31-Jul-26

Repurpose Existing TR Room- Building 05 (1st Fl)Repurpose Existing TR Room- Building 05 (1st Fl) 43 12-Aug-26 9-Oct-26

Interior WorkInterior Work 17 12-Aug-26 3-Sep-26

B05-INT-1130 ICRA - Bldg 05 3 12-Aug-26 14-Aug-26

B05-INT-1150 Interior Demolition - Bldg 05 3 17-Aug-26 19-Aug-26

B05-INT-1170 Install Interior Partitions - Bldg 05 2 20-Aug-26 21-Aug-26

B05-INT-1110 Patch/Repair Existing Walls - Bldg 05 2 24-Aug-26 25-Aug-26

B05-INT-1100 Paint - Bldg 05 2 26-Aug-26 27-Aug-26

B05-INT-1120 Install Fire Treated Plywood - Bldg 05 2 28-Aug-26 31-Aug-26

B05-INT-1090 Install Flooring - Bldg 05 3 1-Sep-26 3-Sep-26

MEPMEP 33 26-Aug-26 9-Oct-26

B05-MEP-1130 Install Mechanical/Plumbing Rough-in - Bldg 05 3 26-Aug-26 28-Aug-26

B05-MEP-1140 Install Distribution Systems - Bldg 05 3 26-Aug-26 28-Aug-26

B05-MEP-1150 Install Terminal & Package Units - Bldg 05 2 31-Aug-26 1-Sep-26

B05-MEP-1170 Install HVAC Trimout - Bldg 05 2 2-Sep-26 3-Sep-26

B05-MEP-1190 Install Fire Sprinkler System - Bldg 05 2 16-Sep-26 17-Sep-26

B05-MEP-1180 Install Fire Alarm & Detection Systems - Bldg 05 2 30-Sep-26 1-Oct-26

B05-MEP-1200 Install Electrical Distribution & Service - Bldg 05 2 30-Sep-26 1-Oct-26

B05-MEP-1120 Install Ceiling Finishes - Bldg 05 2 2-Oct-26 5-Oct-26

B05-MEP-1210 Install Branch Wiring & Lighting Fixtures - Bldg 05 2 2-Oct-26 5-Oct-26

B05-MEP-1220 Install Communications Systems - Bldg 05 2 6-Oct-26 7-Oct-26

B05-MEP-1230 Install Security Systems - Bldg 05 2 6-Oct-26 7-Oct-26

B05-MEP-1160 Install Controls - Bldg 05 2 8-Oct-26 9-Oct-26

Building 37Building 37 128 17-Apr-26 13-Oct-26

B37-1000 Building 37 Contruction Start 0 17-Apr-26

Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan F Mar Apr May Jun JulAug 2025 2026 2027

ICRA - New TR- 05

Frame Interior Partitions - Bldg 05

Install Interior Partitions - Bldg 05

Patch/Repair Existing Walls - Bldg 05

Paint - Bldg 05

Install Fire Treated Plywood - Bldg 05

Install Flooring - Bldg 05

31-Jul-26, MEP

Install Mechanical/Plumbing Rough-in - Bldg 05

Install Distribution Systems - Bldg 05

Install Terminal & Package Units - Bldg 05

Install HVAC Trimout - Bldg 05

Install Fire Sprinkler System - Bldg 05

Install Fire Alarm & Detection Systems - Bldg 05

Install Electrical Distribution & Service - Bldg 05

Install Branch Wiring & Lighting Fixtures - Bldg 05

Install Ceiling Finishes - Bldg 05

Install Communications Systems - Bldg 05

Install Security Systems - Bldg 05

Install Controls - Bldg 05

9-Oct-26, Repurpose Existing TR Room- Building 05 (1st Fl)

3-Sep-26, Interior Work

ICRA - Bldg 05

Interior Demolition - Bldg 05

Install Interior Partitions - Bldg 05

Patch/Repair Existing Walls - Bldg 05

Paint - Bldg 05

Install Fire Treated Plywood - Bldg 05

Install Flooring - Bldg 05

9-Oct-26, MEP

Install Mechanical/Plumbing Rough-in - Bldg 05

Install Distribution Systems - Bldg 05

Install Terminal & Package Units - Bldg 05

Install HVAC Trimout - Bldg 05

Install Fire Sprinkler System - Bldg 05

Install Fire Alarm & Detection Systems - Bldg 05

Install Electrical Distribution & Service - Bldg 05

Install Ceiling Finishes - Bldg 05

Install Branch Wiring & Lighting Fixtures - Bldg 05

Install Communications Systems - Bldg 05

Install Security Systems - Bldg 05

Install Controls - Bldg 05

13-Oct-26, Building 37

Building 37 Contruction Start, 17-Apr-26

VA_Grand Junction- EHRM_100CD_01MAY2025

Data Date: 1-May-25

*All Activities by WBS

TASK filter: All Activities

Report Run Date: 17-Dec-24

Actual Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Start Finish

B37-1010 Building 37- New TR Construction Finish 0 4-Aug-26

New TR Room- Building 37New TR Room- Building 37 78 17-Apr-26 4-Aug-26

Interior WorkInterior Work 29 17-Apr-26 27-May-26

B37-INT-1000 ICRA - New TR- 37 2 17-Apr-26 20-Apr-26

B37-INT-1030 Frame Interior Partitions - Bldg 37 2 22-Apr-26 23-Apr-26

B37-INT-1040 Install Interior Partitions - Bldg 37 5 24-Apr-26 30-Apr-26

B37-INT-1050 Patch/Repair Existing Walls - Bldg 37 10 1-May-26 14-May-26

B37-INT-1060 Paint - Bldg 37 3 15-May-26 19-May-26

B37-INT-1070 Install Fire Treated Plywood - Bldg 37 3 20-May-26 22-May-26

B37-INT-1080 Install Flooring - Bldg 37 3 25-May-26 27-May-26

MEPMEP 58 15-May-26 4-Aug-26

B37-MEP-1000 Install Mechanical/Plumbing Rough-in - Bldg 37 5 15-May-26 21-May-26

B37-MEP-1010 Install Distribution Systems - Bldg 37 10 15-May-26 28-May-26

B37-MEP-1020 Install Terminal & Package Units - Bldg 37 3 29-May-26 2-Jun-26

B37-MEP-1030 Install HVAC Trimout - Bldg 37 3 3-Jun-26 5-Jun-26

B37-MEP-1040 Install Fire Sprinkler System - Bldg 37 3 17-Jun-26 19-Jun-26

B37-MEP-1050 Install Fire Alarm & Detection Systems - Bldg 37 3 1-Jul-26 3-Jul-26

B37-MEP-1060 Install Electrical Distribution & Service - Bldg 37 10 1-Jul-26 14-Jul-26

B37-MEP-1070 Install Branch Wiring & Lighting Fixtures - Bldg 37 10 6-Jul-26 17-Jul-26

B37-MEP-1080 Install Ceiling Finishes - Bldg 37 5 13-Jul-26 17-Jul-26

B37-MEP-1100 Install Communications Systems - Bldg 37 10 20-Jul-26 31-Jul-26

B37-MEP-1090 Install Security Systems - Bldg 37 6 20-Jul-26 27-Jul-26

B37-MEP-1110 Install Controls - Bldg 37 2 3-Aug-26 4-Aug-26

Repurpose Existing TR Room- Building 37Repurpose Existing TR Room- Building 37 43 14-Aug-26 13-Oct-26

Interior WorkInterior Work 17 14-Aug-26 7-Sep-26

B37-INT-1130 ICRA - Bldg 37 3 14-Aug-26 18-Aug-26

B37-INT-1150 Interior Demolition - Bldg 37 3 19-Aug-26 21-Aug-26

B37-INT-1170 Install Interior Partitions - Bldg 37 2 24-Aug-26 25-Aug-26

B37-INT-1110 Patch/Repair Existing Walls - Bldg 37 2 26-Aug-26 27-Aug-26

B37-INT-1100 Paint - Bldg 37 2 28-Aug-26 31-Aug-26

B37-INT-1120 Install Fire Treated Plywood - Bldg 37 2 1-Sep-26 2-Sep-26

B37-INT-1090 Install Flooring - Bldg 37 3 3-Sep-26 7-Sep-26

MEPMEP 33 28-Aug-26 13-Oct-26

B37-MEP-1130 Install Mechanical/Plumbing Rough-in - Bldg 37 3 28-Aug-26 1-Sep-26

B37-MEP-1140 Install Distribution Systems - Bldg 37 3 28-Aug-26 1-Sep-26

B37-MEP-1150 Install Terminal & Package Units - Bldg 37 2 2-Sep-26 3-Sep-26

B37-MEP-1170 Install HVAC Trimout - Bldg 37 2 4-Sep-26 7-Sep-26

B37-MEP-1190 Install Fire Sprinkler System - Bldg 37 2 18-Sep-26 21-Sep-26

B37-MEP-1180 Install Fire Alarm & Detection Systems - Bldg 37 2 2-Oct-26 5-Oct-26

B37-MEP-1200 Install Electrical Distribution & Service - Bldg 37 2 2-Oct-26 5-Oct-26

B37-MEP-1120 Install Ceiling Finishes - Bldg 37 2 6-Oct-26 7-Oct-26

B37-MEP-1210 Install Branch Wiring & Lighting Fixtures - Bldg 37 2 6-Oct-26 7-Oct-26

B37-MEP-1220 Install Communications Systems - Bldg 37 2 8-Oct-26 9-Oct-26

B37-MEP-1230 Install Security Systems -…