S05 - 575-21-700 All Tech Questions Responses - CO.docx
DOCX document 212 KB Posted
- Solicitation number
- 36C77625B0039
About this file
This document is a Technical Questions and Solicitation Responses Tracking Sheet for VA Contract 36C77625B0039, a complex infrastructure upgrade project at the Grand Junction VA Medical Center. The project involves comprehensive modifications to multiple buildings (1, 5, 6, 7, 8, 9, 12, 20, 35, 36, 37, 39/44, 45), focusing on infrastructure improvements including electrical systems, communication infrastructure, physical security upgrades, fiber optic cabling, and building management system interfaces.
Key details include a firm fixed-price contract with a bid due date of August 14, 2025, covering electrical panel upgrades, power systems, UPS installation, HVAC assessments, space reconfiguration, and communication infrastructure upgrades to Cat 6A cabling. The project requires new data outlets, patch panels, physical security enhancements, and a diversified Wide Area Network path to the data center. Contractors must navigate complex requirements including utility relocations, potential winter site work, and adherence to specific VA specifications across multiple buildings and systems.
View the file
Other files
Show all 43
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TECHNICAL QUESTIONS AND
| SOLICITATION #: |
| 36C77625B0039 |
| RESPONSES TRACKING SHEET |
| PROJECT TITLE: |
| 575-21-700 Construction EHRM Infrastructure Upgrades , Grand Junction VAMC , CO |
| # |
| OWNER |
| ANSWERED |
| CONTRACTOR QUESTION |
| VA RESPONSE |
| 1 |
| TECH |
It is not clear if the cable locations are to be reused or are they to be new pathways in walls?
Horizontal rough ins (conduit and box) within walls shall be reused. Pathways above ceilings shall be reused as much as possible. Construction team can provide new pathways as needed to support their means and methods.
| YES |
| Please identify the system for Division 28 - Electronic Safety and Security > Physical Access Control System in document “Att 4 Specifications Grand Junction Data Center.” |
Devices for the system in question are indicated on the plans. The specifics for each system are identified within the spec book. Design Team requires more clarity regarding information being requested if beyond what is shown within the drawings and specification.
| YES |
| Please identify the system for Division 28 - Electronic Safety and Security > Intrusion Detection System in document “Att 4 Specifications Grand Junction Data Center.” |
System shall meet specifications out in the SPEC book. Devices for the system in question are indicated on the plans. The specifics for each system are identified within the spec book. Design Team requires more clarity regarding information being requested if beyond what is shown within the drawings and specification.
| YES |
| Please identify the system for Division 28 - Electronic Safety and Security > Video Surveillance in document “Att 4 Specifications Grand Junction Data Center.” |
System shall meet specifications out in the SPEC book. Devices for the system in question are indicated on the plans. The specifics for each system are identified within the spec book. Design Team requires more clarity regarding information being requested if beyond what is shown within the drawings and specification.
| YES |
| Please identify the system for Division 28 - Electronic Safety and Security > Fire Detection and Alarm in document “Att 4 Specifications Grand Junction Data Center.” |
System shall meet specifications out in the SPEC book. Devices for the system in question are indicated on the plans. The specifics for each system are identified within the spec book. Design Team requires more clarity regarding information being requested if beyond what is shown within the drawings and specification.
| 6 |
| MECH |
| Can we get the spec section for the Mini Split Systems shown on the schedule on M600? |
| 238123 |
| 7 |
| CIVIL |
| Yes |
| We see the new duct bank going through existing sidewalks, curb and gutter, roadways and parking lots but did not find any division 32 specs to go with the work. Can the VA provide them? |
| Contractor to match existing asphalt and concrete sections. All division 32 work is patchback only. |
| 8 |
| CIVIL |
| Yes |
| We see details for the new duct banks themselves but nothing showing where they are to enter the buildings, what kind of foundations or walls will need to be penetrated or excavate under. Can the engineer provide the required details showing how each of these building are to receive the new duct banks? |
Civil scope will end at 5' outside of each building. It should be anticipated that each building will have concrete foundation walls that will require core drilling. Mechanical/Electrical/and Telecom specs provide clarity on steel sleeves where passing through a foundation or existing CMU/masonry wall.
| 9 |
| CIVIL |
| Yes |
| There are a lot of notes that state contractor to verify actual depth of crossing utilities, we can do that but wouldn’t be able to do it before the bid, so we have to bid off existing drawings. How would we be reimbursed should the drawings be incorrect and a major conflict exists? |
We do anticipate that the construction team have their own Utility Locator on their team to assist with locates. Small field adjustments will be required along the route to account for existing conditions. Areas of dense utilities have by hydro-excavated on other EHRMs.
| 10 |
| CIVIL |
| Yes |
| Can we get the spec sections for DIV 03 Concrete? |
Calibre/JTB: Specification 03 30 53 was provided with bid documents
| YES |
| Is it the intent to remove all cabling shown on the TD Pages TD- 101 through TD-106D only? And what if there are abandoned cables from previous projects etc found - will they also have to be removed, and if so, how do we get reimbursed for that? |
| New cabling shall be cat 6a. Existing unused cabling located above ceiling would be an unforeseen condition and would need to be brought to the VAs attention at the time of observation to determine direction. |
| 12 |
| ELEC |
| YES |
| On the UPS's and PDU's is it the intent to have 1 new UPS w/ PDU's per rack? Or can the VA give us a total of how many and what size UPS and associated equipment? Some Rack Elevations show the UPS's and others do not. |
Building 1 will have 2 central UPS’s, so the racks in Building 1 will not contain rack mounted UPS’s. The racks in all the other buildings will have rack mounted UPS’s.
| YES |
| We looked through all the documents provided and found the Geotech report but seems to be for building 20 construction in 2008. No underground pathways are even proposed for that portion of the campus. Can we get a Geotech report for the areas we are excavating? |
| The project no longer includes excavation for new building construction. The geotech report provided is from a design option for an external TR at building 20 and that option has been abandoned |
| YES |
| Will ICRA carts be required to use for hallways and corridors when working above the ceilings? If so for which buildings and which floors in those buildings? |
See SPEC 01 35 26 1.12.
| 15 |
| TECH |
| How large are the new 3/4" backboards being installed in all TR's supposed to be in total? It just says bottom 8'-0" Min AFF - but how wide? |
| Provide 3/4" thick x 4' wide x 8' high A/C grade fire-retardant treated plywood backboard. Refer to floorplans for widths. Cut additional plywood to fit approximate width indicated on floorplans. |
| 16 |
| ARCH |
| The Plan Notes #7, #8 and #9 on the A pages are all asking the GC to "verify before bidding" - That is impossible to do so how will that be reimbursed? |
| Bidders to include worst case scope for these notes. |
| 17 |
| ARCH |
A109 - Note #11 - What type of flooring is to be removed?
The two existing flooring types are carpet and hard surface flooring assumed to be LVT.
| 18 |
| ARCH |
A109 - Note #12 - please provide a detail of the decorative glass panels to be salvaged and replaced.
Elevation, size & quantity are provided on detail 3/B01-A110.
These are existing panels with metal wall standoffs and should be easily field verified during a pre-bid meeting.
| YES |
| Will the sign-in sheet from site visit be available in addendum? |
Signed Sign in sheet was posted on SAM.gov
| YES |
| Please clarify if a superintendent can be a dual hat to cover the requirements of SSHO? |
See SPEC 01 36 26 1.7 C.
| YES |
| If no to the question above, will the SSHO need to be full-time for this project? |
See SPEC 01 35 26 1.9 See SPEC 01 36 26 1.7 D.
| 22 |
| VA |
Please clarify if a superintendent can be a dual hat to cover the requirements of QA/QC?
If the superintendent will be performing both roles, submitting party will need to identify how this will be achieved and be successful in both roles.
| 23 |
| VA |
If no to the question above, will the QA/QC need to be full time for this project?
Ideally, QC is a full time team member throughout the project.
| 24 |
| VA |
Can a superintendent be a triple hat to cover the requirements of SSHO and QA/QC?
The project shall have a full time safety person. If a single person is performing two full time positions, provide summary for how this will be successful.
| YES |
| Please confirm if tax should be included in our proposal? |
| Everything should be included in the contractors proposal, we don’t provide tax waivers to contractors |
| YES |
| Please confirm if the current prevailing wages will be consistent for the life of the project with no escalation? |
After award is made, if there is a change in the Wages determination, awardee needs to keep the same pricing until completion of the construction
| YES |
| Attachment #5 introduces a slew of brand name equipment, will “equal” or alternatives be allowed? If not, please provide the brand name or equal justification for these items. |
All equipment shall match the specifications provided in the bid documents.
| YES |
| Please explain the cost estimating and budget approach, page 30 of Attachment #5. Once award the expectation is this procurement is a firm fixed price. |
This contract is a firm fixed price.
| YES |
| Please consider updating the wage determination: General Decision Number: CO20250025 07/18/2025 |
Latest David Bacon Wages determination was posted on SAM.gov as an amendment on July 28
| YES |
| Please describe the difference between Attachment #13 100% CD Specification and Attachment #5 100% CD Basis of Design. Is one more important than the other? If there is a discrepancy between the two? Which one do we follow? |
Please follow the latest files/docs uploaded on Sam.gov. If a document listed is not available for download that means we have removed the file.
| YES |
| Please clarify, do we use Attachment 4 or Attachment 13 for the 100% Design specification, they look the same. Amendment #1 Box 14 is not clear what you are swapping out. |
Please follow the latest files/docs uploaded on Sam.gov. If a document listed is not available for download that means we have removed the file.
| YES |
| Who is responsible for contracting the commissioning agent? |
The VA.
| YES |
| Is the use of temporary plastic wall panels (such as STARC panels) acceptable to meet ICRA requirements? |
The VA cannot provide means and methods. Temporary plastic wall panels shall meet SPEC 01 35 26.
| YES |
| Will shutdowns be required to be done during off hours or weekends? |
See SPEC 01 00 00 1.6 K
| YES |
| Will TR rooms, mechanical rooms, etc. be cleared of all stored items prior to the contractor entering those areas? |
TR rooms will not have any items stored in them.
Mechanical rooms will be cleared upon request.
| YES |
| Will a full-time fire watch be required during activities such as cutting, brazing and welding? How long after such activities are completed? |
See SPEC 01 35 26 1.14.K
| YES |
| Who is the vendor or contractor currently servicing and maintaining the Building Automation System or Temperature Controls System? |
VA staff is servicing equipment.
| YES |
| With regards to underground utility work how much open trenching be allowed at a time? |
See SPEC 01 35 26 1.18.
| YES |
| After backfilling, topsoil and seed have been applied who is responsible for watering? If the contractor is responsible will water be provided by the facility? |
See SPEC 01 00 00 1.19.
| 40 |
| CIVIL |
| Yes |
| On all underground utility work please confirm if excavated material is acceptable for re-use as backfill? |
Clean soils can be used as backfill.
| 41 |
| CIVIL |
| Yes |
| Please confirm if the contractor is responsible for any rock removal that is encountered. If so, what is the assumed elevations and quantity of rock material? |
Contractor should not assume rock removal is required based on design depth. If rock encountered, contractor to coordinate with VA.
| 42 |
| CIVIL |
| Yes |
| Please confirm if a unit price can be established for rock removal as opposed to carrying in bid? |
See 41.
| 43 |
| VA |
Please confirm if there is a separate staging area onsite for fill material to be stockpiled for re-use?
Typically fill material is stored along the trench.
| 44 |
| VA |
Please advise if the site contains any contaminated soil that needs to be removed.
VA
| YES |
| Please confirm if we will be allowed to keep a locked storage container or conex box within the grounds. |
See SPEC 01 00 00 1.6.
| YES |
| Will a guard / escort be required at all work areas including but not limited to buildings, outside areas? |
See SPEC 01 00 00 1.5.B.
Advise what is the existing data cabling manufacturer, wire thickness details, etc?
Existing cables will vary in manufacturer, wire thickness details, etc.
| 48 |
| VA |
To allow sufficient time to review responses and prepare our bid we kindly request that you please extend the bid date.
Bid due date was extended to August 14,2025
| YES |
| 281300 Physical Access Control System, 281600 Intrusion Detection System & 282300 Video Surveillance: We are adding to the existing PACS, IDS and Video Surveillance systems. Are there existing maintenance contractors for these systems? If so, can you please provide the contact information for the maintenance contractors? Will additional licenses be needed for cameras? |
1. No.
2. N/A.
| YES |
| 283100 – Fire Alarm & Detection: We are adding to the existing fire alarm system. Is there an existing maintenance contractor for the fire alarm system? If so, can you please provide the contact information for the maintenance contractor? |
1. No.
2. N/A.
| YES |
| Is all work to be performed during regular business hours? |
See SPEC 01 00 00 1.3.
| 52 |
| MECH |
| YES |
| Mechanical drawings show keynote 108 (‘Increase Exhaust Rate of Existing Air Terminal’)- Who is responsible for this (VA facility or Contractor)? |
Contractor. Contractor shall provide all TAB and work shown on contract documents.
| 53 |
| MECH |
| YES |
Mechanical- Are new in-line fans to be controlled and/or monitored by BAS?
No BAS control required; fans are to run 24/7/365.
| 54 |
| CIVIL |
Sheet CU100 Shows requirement for Fiber Optic Manholes- Please advise if there are details and sizes for these FO manholes.
Fiber Optic Manhole Detail to be sent along with this document
| YES |
| The RFP did not identify a laydown yard for contractors. Please advise. |
See SPEC 01 00 00 1.6.
Contractor laydown area shall be the south half of the traffic circle west of the docks.
| YES |
| There are two EHRM projects out for bid, what is the timeline for these 2 projects, which EHRM project needs to start first? Are these two projects going to be awarded and started at the same time? |
Each project shall be its own contract. Each project has its own timeline. Keep questions related to this project.
| YES |
| The VA estimated schedule for site work/Duct bank and restoration seems short for the extent of work considering possible relocation of existing utilities and shutdown requests duration for existing utilities. Can this be adjusted to add for utility shutdown request period? |
VA estimated schedule is a comparison tool for this project. Contractor shall follow SPEC 01 32 16.15.
| YES |
| Please advise if sitework for duct banks will be performed during winter (note that VA estimated schedule of May 2025 has already passed for sitework). If this is winter work, then the schedule needs to be adjusted further to cover for weather conditions. |
VA shall not provide means and method to contractor.
| YES |
| 1. Per VA estimated Construction Schedule included in the RFP, the duration for installation and completion of activity ‘Install Communications System’ seem to be short (ex; Bldg 1, Level 1) which shows duration of ‘Communications Install’ at 10 days only. If this pertains to the whole ground floor (Bldg 1, Level 1), this is definitely not enough considering installation of new conduits and cabling for all the rooms. Please confirm if this is for the TR rooms only and not for the whole floor (Ref. Sheet B01-TN101A). The duration of 10 days will not be enough for the whole floor. Please advise and adjust schedule to include installation of conduits, and comms wiring for each floor rooms. Note that this will increase construction duration in consideration of adding durations for installation of data/comms to each room per floor and buildings. |
Contractor shall provide the final schedule. VA schedule is an estimate.
| YES |
| Is this project tax-exempt, if so, will a certificate be provided? |
See question 25.
| 61 |
| TECH |
ET series drawings for CCTV camera. Bid spec documents do not specified what system are currently in place for this project, please answer the following questions:
a) What is the manufacturer of the current video management system?
b) What version/existing is the current video management system operating?
c) Are we expected to support version upgrades as part of this contract?
d) Are there sufficient existing licenses to support the new cameras?
e) Are the cameras to be 2MP pan/tilt/zoom or fixed dome?
f) Is there a current vendor/installer of this system that we can contact? Please Provide Contact
Most of the GJVA CCTV camera system is Honeywell but we also have Axis, and Milesight cameras in our CCTV system. The contractor will need to VIF which system they will be working with.
The cameras should be 8mp, fisheye and PTZ capable.
| 62 |
| VA |
ET series drawings for card reader/pin pad. Bid spec documents do not specified what system are currently in place for this project, please answer the following questions:
a) What is the manufacturer of the current access control system.
b) What version/existing software is the access control system operating.
c) Are we expected to support the version? updates as part of the contract?
d) Are the sufficient licenses to support the new doors?
e) Is there any existing integration between the access control and CCTV systems?
f) Is there a current vendor/installer of this system that we can contact? Please Provide Contact
For any other questions, contractors need to see spec sections 28 13 00 for Access Control and 28 23 00 for Video Surveillance.
| 63 |
| TECH |
Is there an allowance of 1 1/4” data rough-in that should be carried within the Div.26 pricing? Some previous requirements on other projects requested 5-10% additional 1 1/4” data rough-in to cover what may have missed during design.
Please use a 3% allowance.
| YES |
| Existing Fire Alarm System - Is there a current maintenance vendor/installer of this system that we can contact? Please Provide Contact |
Alarm Specialist.
COR Tia Clemmer
| YES |
| Existing Nurse Call System - Is there a current maintenance vendor/installer of this system that we can contact? Please Provide Contact |
A new system is currently being installed. That project is not completed at the moment.
| 66 |
| ELEC |
| YES |
| Is conduit required for grounding conductors running/installed ceiling & risers? |
No, it is not required.
| YES |
| Is there a requirement for x-ray scanning of concrete floor slabs prior to core drilling for floor-to-floor sleeves/conduits? |
See SPEC 27 05 11 3.1.
| YES |
| Is there a location where site asphalt and concrete can be stored/separated? Can this material be removed from the site once per week? |
See question 55.
| 69 |
| CIVIL |
| Yes |
| Will soil testing be performed prior to construction, to determine if any soils are contaminated? |
Soils testing will be the responsibility of the contractor if required by the VA.
| 70 |
| CIVIL |
| Yes |
| Is there a location where spoil dirt can be stored? |
Contractor to coordinate with VA on stockpile locations as project progresses.
| YES |
| Is there a specific location that will be used as a laydown yard during construction? |
See question 55.
| 72 |
| CIVIL |
| Yes |
| Will erosion control plans be provided? |
See stormwater management plan for inlet protection and construction limits. Contractor to provide erosion control measures during trenching activities.
| 73 |
| CIVIL |
| Yes |
| Has there been any boring samples/test made for duct bank pathway/trench to determine subsurface condition? |
No
| 74 |
| TECH |
WAO-There are no prints that indicate new locations. Is this a 1 for 1 replacement for existing cables?
No. This is not a 1 to 1 replacement. Work area outlets have been reduced per design alert 16. Refer to demolition sheets for existing cable counts and new work sheets for new cable counts.
| YES |
| Is there required a full survey of every room/above ceiling? If so, who dictates the outlet location and quantity of cables per location? |
See addendum 1 drawings. The contractor should expect to survey all locations to further confirm quantities.
| YES |
| Can the government provide a quantity of CAT6 A cables that need to be installed by TR? Please provide a Drop Count Matrix that needs to be provided. |
See addendum 1 drawings.
| YES |
| What is the drop counts of each coverage zone? If it is a 1 for 1 swap, how many existing drops are located in each coverage zone? |
See addendum 1 drawings.
| YES |
| Is there a count and length for Cat6A patch cords? |
See addendum 1 drawings.
| 79 |
| TECH |
Are we to provide one patch cable for each station and closet end?
Provide patch cables to match quantity of data drops at each WAO.
| 80 |
| TECH |
Is there a count and length for Fiber Patch cords?
No
| 81 |
| TECH |
Are we to provide patch cables for each pair of strand at each end?
Yes
| 82 |
| TECH |
Is there any copper backbone (25-pair or larger) needed?
No
| 83 |
| SES T |
Is there required a full survey of every room/above ceiling for the for TN series note#2 (cable tray capacity)?
Cable tray capacity will need to be confirmed. Generally tray is above corridors. Not every ceiling would need to be reviewed for cable tray capacity.
| 84 |
| TECH |
Is there an allowance for unforeseen cable tray that the A&E would like the EC to carry?
Not at this time.
| 85 |
| TECH |
If innerduct is required, the specifications identify that it should be installed in cable trays or support systems, has this been accounted for in sizing of cable raceways as the innerduct will consume quite a bit of space.
Innerduct is only permissible to be installed using metallic straps, hangers and fittings to support raceway from building structure per specification section 270533-2.1(H)(3).
| 86 |
| TECH |
Please confirm that the A/B backbone fiber to be installed in cable tray and not in a dedicated conduit raceway.
A/B backbone fiber to be installed in dedicated conduit.
| 87 |
| TECH |
Existing conduit sizes are not shown in the documents for existing data outlets, please clarify what conduit size and fill should be assumed by the contractor for existing data outlets. If the conduit size is not sufficient to an existing outlet will the VA require a new conduit?
Contractor should assume new cabling will fit within existing data drop rough-ins. Thin cat 6A cabling may be required. Conduit size likely varies across campus.
| 88 |
| TECH |
Please confirm the rough in required to the corridors from rooms with data outlets, is this conduit extending from the rooms into the corridors or just vertical conduit running up from the outlet? If running conduit into the fire rated sleeve, please provide a detail showing this connection.
Refer to detail 5 of sheet TN601. Conduit will not be run through fire rated sleeve.
| 89 |
| TECH |
Are we to assume that areas with existing data devices will not require new fire rated wall sleeves? If new sleeves are required, please provide a count so that bidders will be aligned in scope of work.
The construction team is required to select the cable routes. This doesn't allow the design team to quantify the sleeves. Sleeves are required and shall be included per the notes identified. Recommend each bidder identify the quantity of sleeves they have included with their bid so that bids can be reviewed accordingly.
| 90 |
| TECH |
Please confirm the new conduit will be in the wall and not surface mounted. In wall will have a significant cost impact with patching/painting.
New conduit will be in wall.
| 91 |
| TECH |
Existing box sizes are not shown in the documents for data outlets. Please clarify how to proceed with figuring if existing boxes will be re-used or if new boxes will need to be provided.
Locations with existing data devices will not require new boxes.
| YES |
| Please confirm that all firestopping must be either installed by an FM global approved contractor, or a UL qualified firestop contractor certified. |
See SPEC 07 84 00 1.5.B.
| YES |
| Please confirm that the contractor is to include the services of a third party independent firestopping inspector in their bid. |
See SPEC 07 84 00 1.5.C.
| YES |
| Please confirm that firestopping installers accredited by a firestopping product manufacturer will not be approved by the VA unless they meet the FM global or UL qualifications referenced in section 07 84 00 |
Contractor shall meet all specifications.
| 95 |
| TECH |
Are we to assume that areas with existing data devices will not require new boxes? If new boxes are required, please provide a count.
Areas with existing data devices will not require new boxes.
| 96 |
| TECH |
TN000 Telecommunication General Notes “K” - Implies that all WAO are NEW. Please advise
Data devices are existing unless specifically identified as new. Only in the case of an indicated new data device with rough-in assembly will the conduit indicated in this note be required.
| YES |
| Is there an allowance of Cat 6A cable that should be carried within the Div.27 pricing? Some previous requirements on other projects requested 5-10% additional Cat 6A cables,to cover what may have missed during design. |
Would recommend at least a 5% contingency. Discuss with COR
| 98 |
| TECH |
1. TN000 Telecommunication General Notes “R,S & T” for horizontal sleeves into offices - Please give quantities & size for bidding.
The construction team is required to select the cable routes. This doesn't allow the design team to quantify the sleeves. Sleeves are required and shall be included per the notes identified. Recommend each bidder identify the quantity of sleeves they have included with their bid so that bids can be reviewed accordingly.
| YES |
| Is there a proprietary Fire Alarm Contractor at the facility? If so, please provide the company name and point of contact. |
Alarm Specialists
| BLANK ROW |
| BLANK ROW |
| YES |
| Is there a proprietary Controls Contractor at the facility? If so, please provide the company name and point of contact. |
JCI
TECH
Is there a proprietary Cameras at the facility? If so, please provide the company name and point of contact.
Can VA information detail on existing CCTV system.
| 103 |
| TECH |
B44-TN400 Please confirm the estimated drop count for TR 106 in Building 44.
There are no WAO in the B44 Parking Garage. This is a TE with a maximum amount of 96 ports in the future. It is estimated that there are approximately 20 existing drops.
| 104 |
| TECH |
B44-TN400 Please add cabling notes to drawing.
Drawings will not be reissued for the bidding process. There are no existing WAO in the B44 Parking Garage.
| 105 |
| TECH |
For estimating purposes, the enlarged drawings give a count of existing cable count to be demolished and estimated work area outlets. Please confirm which drop count we should use for estimating the project.
Drop count shall be based on estimated work area outlets
| 106 |
| TECH |
| B45-TN400 The Cabling notes say there’s 0 existing cable count and estimated work area outlets total active of 105. Are we to price it as there being 0 or 105 at the end of the project |
| Refer to sheet B45-TD101. Bid for worse case scenario. |
| 107 |
| TECH |
TS001 does not look to have a ductbank running to Building 44. Please confirm the location of Building 44 and the duct bank route.
Building 44 is labeled as Building 39 on site plan TS001. On the duct bank loop diagram on sheet B01-TN500, it is labeled as Building 44.
| 108 |
| VA |
01 45 00 – Quality Control – Can the Superintendent be the QC Manager?
Refer to prior question responded to
| YES |
| 01 35 26 – 1.7 – Can the Superintendent be the SSHO? |
| See SPEC 01 35 26 1.7 |
| 110 |
| TECH |
Detail 5 on sheet TN601 – For estimating purposes how many of these new communications outlets should we figure?
Drop count shall be based on estimated work area outlets. Refer to new work sheets for new WAO. Please use a 3% allowance.
| 111 |
| CIVIL |
| CU100 Utility Plan – Can the VA provide a detail on the fiber optic manhole they would like to have installed? |
| Fiber Optic Manhole Detail to be sent along with this document |
| 112 |
| ELEC |
| YES |
| B01-E500 – Sheet Notes 1 and 2 – Can the VA confirm that these UPS are new and not existing? |
The UPS’s are new and should be provided as part of this project.
| 113 |
| MECHARCH |
| YES |
| B01-M200 – This drawing seems to be incomplete; can the VA provide a better drawing showing that all this work is taking place in the basement? |
Concur, work is to occur in the crawl space of the north addition wing.
Yes, a revised plan can be provided to show the existing building more clearly.
| 114 |
| MECH VA |
For the condensing units mounted on the roofs can the VA provide pictures of all the locations so that we can better estimate the price for patching and repairing the roofing material?
This applies to buildings 7 and 12. Pictures will be included with the response. Please see attachments: 4 Utility Plan, B7 Roof 20250730 , and B12 Roof 20250730
| 115 |
| MECHSTRUCT |
| YES |
| M500- There is no concrete pad detail for the condensing units can the VA please provide. |
Prefabricated CU pads are acceptable for new grade mounted CUs.
| YES |
| Please identify the system for Division 28- Electronic Safety and Security > Physical Access Control System in document “Att 4 Specifications Grand Junction Data Center.” |
System shall meet specifications out in the SPEC book.
| YES |
| Please identify the system for Division 28 - Electronic Safety and Security > Intrusion Detection System in document “Att 4 Specifications Grand Junction Data Center.” |
System shall meet specifications out in the SPEC book.
| YES |
| Please identify the system for Division 28 - Electronic Safety and Security > Video Surveillance in document “Att 4 Specifications Grand Junction Data Center.” |
System shall meet specifications out in the SPEC book.
| YES |
| Please identify the system for Division 28 - Electronic Safety and Security > Fire Detection and Alarm in document “Att 4 Specifications Grand Junction Data Center.” |
System shall meet specifications out in the SPEC book.
| YES |
| B01-M300 – B45-M300- Are the controls on existing units that are removed to be reused if possible? |
SEE SPEC 28 31 00 1.2.E.
| 121 |
| MECH |
| YES |
| B01-M300- Keynote 108 – increasing the exhaust rate of existing air terminal, is this done at VFD’s/AHU or are we to adjust the damper during TAB? |
TAB work shall be done in accordance with specification 230593. Follow procedures and standards specified.
| 122 |
| MECH |
| YES |
| Are the new in-line fans to be controlled and/or monitored by BAS? |
Duplicate question, refer to response to 53 above.
| 123 |
| MECHVA |
| No, VA input needed |
| M600- Is there a central controller that all the FCU’s will be reporting to? Can the VA provide a ladder diagram? |
Provide per specification 230923 and View 1 on M501. VA to provide info on existing controls as-builts if available.
| 124 |
| MECH |
| YES |
| M600- Who is responsible for the humidity sensors and so they need to report to Metasys? |
Refer to M501. Temperature controls contractor shall provide all temperature and humidity sensors shown on control diagram
| 125 |
| MECH |
| YES |
| M600- What is controlling the control valves on the FCU’s? |
Refer to M501. The FCU controller.
| 126 |
| MECH |
| YES |
| M600- Does there need to be any monitoring or alarming to the condensing units for each FCU? |
Refer to M501.
| 127 |
| MECH |
| YES |
| As it relates to the Metasys system, is it the only work to monitor and alarm each FCU? |
Refer to M501.
| 128 |
| TECH |
5/TN-601 calls out for us to provide a 1-1/4” conduit and 4” square by 2-1/8” deep box with single gang plastic ring.
a. Does the current/existing conduit and box meet this detail?
b. Is this detail for all drop locations? This detail is not identified at any of the new locations.
i. If a new hard pipe is required in all these locations this will increase the drywall patch/paint and ICRA cost for the project. Also increasing the duration contractors will be on site. We would need every room to be unoccupied during the duration of work. Does the VA want to treat the existing drops as unforeseen site conditions?
c. Is surface mounting of 1-1/4” conduit and box acceptable?
d. Confirm J-hooks are acceptable once the conduit is stubbed up above accessible ceilings.
e. Is flexible conduit acceptable as in-wall raceway(s) for security/electrical/data?
a. Existing rough-ins are likely not all 1 1/4" conduits but that should generally not affect the project. Bidders shall assume existing data device rough-ins can accommodate the new cabling indicated. Contingency shall be carried per solicitation question #63 to cover the minimal locations where an existing rough-in does not have capacity. Contingency use for data devices will be tracked during construction.
b. The detail provided would only be required for new data device rough-ins that are specifically indicated with reference to the detail. Where no reference is provided, the existing rough-in will be reused. The majority of data device rough-ins will be reused for this project.
c. From an appearance standpoint, surface mounting conduit and boxes is not desired. The actual number of new rough-ins across the project is minimal. The preference is to plan for cutting in devices and patching back during the bid phase. New devices on masonry walls shall utilize comparable plug mold assembly to allow for a more aesthetic surface appearance. Further review of each new location can be performed during construction to determine if means and methods can be altered.
d. J-hooks are acceptable once above the ceiling. The VA would like to reuse existing cable tray where it exists, but jhooks are an approved solution for this project.
e. Flexible conduit is an acceptable solution in the cases indicated as long as installations are compliant with NEC requirements. Note article 517 has special requirements for patient care areas.
Refer to specification section 260533 – Raceway and Boxes for Electrical Systems and specification section 270533 – Raceways and Boxes for Communcations Systems.
image1.jpeg image2.jpeg image3.jpeg