S05 - 575-21-700 Tech Questions responses updated - GJ CO - 8-28-25.docx

DOCX document 243 KB Posted

Attached to
Y1DA--575-21-700 | Construction| EHRM Infrastructure Upgrades | Grand Junction, CO
Solicitation number
36C77625B0039
Issued by

About this file

This document is a Technical Questions and Solicitation Responses Tracking Sheet for VA Project 575-21-700, a construction project for Electronic Health Record Modernization (EHRM) Infrastructure Upgrades at the Grand Junction VA Medical Center in Colorado. The project involves comprehensive infrastructure improvements across multiple buildings (1, 5, 6, 7, 8, 9, 12, 20, 35, 36, 37, 39/44, 45), including electrical panel upgrades, power systems, building management system interfaces, HVAC reassessment, communication infrastructure upgrades, physical security enhancements, and fiber optic backbone improvements.

The tracking sheet contains 129 technical questions and responses from contractors, covering detailed aspects of the project such as cabling installation, conduit requirements, fire stopping, safety systems, utility work, and technical specifications. Key points include upgrading to CAT 6A cabling, installing new UPS systems, performing telecommunications room modifications, adding physical access control and video surveillance systems, and implementing new fiber optic infrastructure. The solicitation (36C77625B0039) is managed by the Department of Veterans Affairs Technology Acquisition Center Austin, with the bid due date extended to August 14, 2025. The contract is structured as a firm fixed-price procurement with specific technical requirements for infrastructure modernization.

View the file

Other files

File Type Posted
575-700.VA Archtitectural Grand Junction EHRM Addendum 2 - Changed Sheets Only.pdf PDF
For Information Only - B44_2013_TERRACON_41013_Parking_Garage.pdf PDF
575-700.VA Civil Grand Junction EHRM Addendum 2 - Fiber Optic Manhole Detail.pdf PDF
575-700.VA Telecom Grand Junction EHRM Addendum 2 - Changed Sheets Only.pdf PDF
For Information Only - B9_2019_Geotech_Report_HB_Boiler_Plant.pdf PDF
575-700.VA Mechanical Grand Junction EHRM Addendum 2 - Changed Sheets Only.pdf PDF
S06- Amendment 0009.pdf PDF
S06 - Amendment 0008.pdf PDF
S06- Amendment 0007.pdf PDF
32 05 23 Cement and Concrete for Exterior Improvements.pdf PDF
32 12 16 Asphalt Paving.pdf PDF
CIP concrete short form.pdf PDF
S06- Amendment 0006- Bid due date extended 08-28-25.pdf PDF
S06- Amendment 0005- Bid due date extended.pdf PDF
S06- Amendment 0005- Bid due date extended.pdf PDF
B12 Roof 20250730.pdf PDF
S06- Amendment 0004- Bid opening info and all tech questions responses.pdf PDF
4 Utility Plan.pdf PDF
B7 Roof 20250730.pdf PDF
S05 - 575-21-700 All Tech Questions Responses - CO.docx DOCX document
S06- Amendment 0003 - DB Wages updated - Bid extension - RFI answers.pdf PDF
S05 - 575-21-700 Tech Questions Responses- GJ CO 07-28-25.docx DOCX document
P07- Updated Wages Determination - Grand Junction CO 07-25-2025.pdf PDF
S04- Signed site visit sign in sheet - 57521700 CO.pdf PDF
S06- Amendment 0002- Signed site visit sheet.pdf PDF
ATT 12- Drawings - EHRM - Grand Junction - CO.pdf PDF
ATT 13- Specifications-Combined- EHRM - Grand Junction CO.pdf PDF
ATT 4- Grand Junction CO - SPECS 07-03-25- Addendum.pdf PDF
ATT 11 - Site Visit Instructions.pdf PDF
ATT 1- Grand Junction EHRM - Drawings 07-03-25 - Addendum.pdf PDF
S06 - Amendment 0001.pdf PDF
ATT 7 - Spec 01 31 00.01 Project Management and Coordination.pdf PDF
ATT 3- Estimated Construction Schedule- EHRM- Grand Junction CO.pdf PDF
ATT 10 - GEO Reports B20.pdf PDF
ATT 6 - Wages Determination - Grand Junction CO.pdf PDF
ATT 5- 100 CD Basis of Design -Combined- Grand Junction CO.pdf PDF
ATT 1- Grand Junction EHRM - Drawings 07-03-25.pdf PDF
ATT 8 - Limitations on Subcontracting.docx DOCX document
36C77625B0039.pdf PDF
ATT 11- Site Visit Instructions.pdf PDF
ATT 4- Grand Junction CO - SPECS 07-03-25.pdf PDF
ATT 2- Parking Guidelines Grand Junction VAMC.pdf PDF
ATT 9- Hazardous Materials Report.pdf PDF
Show all 43

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TECHNICAL QUESTIONS AND

SOLICITATION #:
36C77625B0039
RESPONSES TRACKING SHEET
PROJECT TITLE:
575-21-700 Construction EHRM Infrastructure Upgrades , Grand Junction VAMC , CO
#
OWNER
ANSWERED
CONTRACTOR QUESTION
VA RESPONSE
1
TECH

It is not clear if the cable locations are to be reused or are they to be new pathways in walls?

Contractor to include in their bid price the cost of 3% of additional data port rough-ins for existing conditions where either the device is determined to not have an existing conduit pathway, or the existing conduit pathway does not accommodate new cabling.

Because of Design Alert 16 cable quantities at most locations are reduced. A ¾" rough-in which is what most existing rough-ins will be can support up to 3 cables and most devices have 2. There should not be any new rough-ins, so there is nothing to quantify. Comment by Moffett, Michael T.: So the expectation is clear, I recommend we state offerors are to include in their bid price the cost of additional pathways. Otherwise it is quite likely we will see mod request to add new pathways when they should have been included in the initial bid price.

I would have expected the AE firm to have estimated the total number of potential new pathways based on the current capacity of the existing pathways and anticipated need for more capacity for larger CAT 6 cable. This is what we paid the AE for.

A ½" conduit can support 2 cables and would be the worst case conduit size. A new rough-in would only be needed if something unforseen came up, or the contractor wanted to provide as part of their means and methods. There is not anything for SES to quantify.)

Per Drawing TN000 – Phasing General Notes E. Existing cable removal: after new cabling has been installed and activated, remove existing backbone cabling and existing area outlet cabling from telecommunications rooms being abandoned. Remove unused cabling in previously abandoned telecommunications rooms.

YES
Please identify the system for Division 28 - Electronic Safety and Security > Physical Access Control System in document “Att 4 Specifications Grand Junction Data Center.”

Devices for the system in question are indicated on the Telecom TN400 series sheets . The specifics for each system are identified within the specifications. Comment by Moffett, Michael T.: I recommend we specifically state which drawings. All to often I have seen a response this and it turns out we never verified which plans and in the end the info wasn’t there. Furthermore, the more specific we are in our answers, the less ambiguity we will have if a dispute arises

Also, any information contractor’s need from the so-called spec book needs to be in the drawings or the specifications. The spec book is for informatioon only and not binding. The spec book is for our internal use, not the contractors. We paid the AE to provide complete specs and drawings. Comment by Moffett, Michael T.: Just as the drawings, I highly recommend specifically where in the specs this is located.

The BOD report should not have been included in the solicitation. That is a document for us, not the contractors. All pertinent info contractors need should be in the specs and drawings.

It should be removed from the attachment list.

I don’t understand why there is a separate spec attachment for project management. Why isn’t included in attachment 13?

Why is the construction schedule included in the attachments? After reading the narrative is clear this was for internal purposes. We should not be dictating the contractor’s schedule other than giving them the total number of days after NTP.

The so-called spec book and schedule needs to be labeled and called out as “For Information Only” and inform the offerors the schedule and spec book is not binding and the drawings and specifications control. Comment by John Sanborn: A/E did not intend these additionla documents be sent for solicitation and they were not provided with the 100%. These are being removed via Ammnedment.

Design Team requires more clarity regarding information being requested if beyond what is shown within the drawings and specifications.

YES
Please identify the system for Division 28 - Electronic Safety and Security > Intrusion Detection System in document “Att 4 Specifications Grand Junction Data Center.”

System shall meet specifications identified in spec Section 28 16 00 –Part 2 – Sections 2.1 to 2.12 for system requirements. Comment by Moffett, Michael T.: Same recommendation as before.

Devices for the system in question are indicated on the Telecom plans. The specifics for each system are identified within the specifications..

Design Team requires more clarity regarding information being requested if beyond what is shown within the drawings and specification.

YES
Please identify the system for Division 28 - Electronic Safety and Security > Video Surveillance in document “Att 4 Specifications Grand Junction Data Center.”

System shall meet specifications identified in spec Section 28 23 00 –Part 2 – Sections 2.1 to 2.11 for system requirements

Devices for the system in question are indicated on the Telecom plans. The specifics for each system are identified within the specifications. Comment by Moffett, Michael T.: Same recommendation as before.

Video cameras are a combination of systems throughout the property. No maintenance.

YES
Please identify the system for Division 28 - Electronic Safety and Security > Fire Detection and Alarm in document “Att 4 Specifications Grand Junction Data Center.”
System shall meet specifications
identified in spec Section 28 32 00 –Part 2 – Sections 2.1 to 2.4 for system requirements.Comment by Moffett, Michael T.: Same recommendation as before.

Devices for the system in question are indicated on the Electrical plans. The specifics for each system are identified within the specifications.

6
MECH
Can we get the spec section for the Mini Split Systems shown on the schedule on M600?
SECTION 23 81 23 COMPUTER-ROOM AIR-CONDITIONERS

Comment by Moffett, Michael T.: See previous comments about the lack of specifics in our answers.

7
CIVIL
Yes
We see the new duct bank going through existing sidewalks, curb and gutter, roadways and parking lots but did not find any division 32 specs to go with the work. Can the VA provide them?
Contractor to match existing asphalt and concrete sections. All division 32 work is patchback only.Comment by Moffett, Michael T.: How can they match it if they don’t have the specs stating what they are to match? What is the concrete and asphalt formula they are to match? What is the compaction and base and subbase material they are to match?

Div 32 specs included in amendment

8
CIVIL
Yes
We see details for the new duct banks themselves but nothing showing where they are to enter the buildings, what kind of foundations or walls will need to be penetrated or excavate under. Can the engineer provide the required details showing how each of these building are to receive the new duct banks?

Civil scope ends 5' outside of each building.

Each building has a concrete foundation wall that will require core drilling. Mechanical/Electrical/and Telecom specs provide clarity on steel sleeves where passing through a foundation or existing CMU/masonry wall.

9
CIVIL
Yes
There are a lot of notes that state contractor to verify actual depth of crossing utilities, we can do that but wouldn’t be able to do it before the bid, so we have to bid off existing drawings. How would we be reimbursed should the drawings be incorrect and a major conflict exists?

Utilities have been located based on new civil surveys and existing drawings.

We do anticipate that the construction teams have their own Utility Locator on their team to assist with locates. Small field adjustments will be required along the route to account for existing conditions. Areas of dense utilities have by hydro-excavated on other EHRMs Contractor should include a small contingency in their excavation fees to cover unknowns that could not be determined during the design phase. GPRS of the entire alignment would have been impractical.

10
CIVIL
Yes
Can we get the spec sections for DIV 03 Concrete?

Calibre/JTB: Specs 03 30 53 will be provided via amendment Comment by Moffett, Michael T.: Are they included in the solicitation? If not, it doesn’t matter if they were already provided to the VA. VA needs to determine if we actually have them and if so, then the answer should be the specs will be provided via amendment #?????. If the VA determines we do not have the, then the AE needs to provide them, again if necessary.

YES
Is it the intent to remove all cabling shown on the TD Pages TD- 101 through TD-106D only? And what if there are abandoned cables from previous projects etc found - will they also have to be removed, and if so, how do we get reimbursed for that?
New cabling shall be cat 6a.

Per Drawing TN000 – Phasing General Notes E. Existing cable removal: after new cabling has been installed and activated, remove existing backbone cabling and existing area outlet cabling from telecommunications rooms being abandoned. Remove unused cabling in previously abandoned telecommunications rooms.

Existing unused cabling is to be removed and included in the bid price.

12
ELEC
YES
On the UPS's and PDU's is it the intent to have 1 new UPS w/ PDU's per rack? Or can the VA give us a total of how many and what size UPS and associated equipment? Some Rack Elevations show the UPS's and others do not.

As shown on the drawings, Building 1 will have 2 central UPS’s, so the racks in Building 1 will not contain rack mounted UPS’s.

As shown on the drawings, The racks in all the other buildings will have rack mounted UPS’s. Comment by Moffett, Michael T.: Why isn’t this shown on the plans? Comment by John Sanborn: This is shown on the drawings, additional clarification added to the response.

YES
We looked through all the documents provided and found the Geotech report but seems to be for building 20 construction in 2008. No underground pathways are even proposed for that portion of the campus. Can we get a Geotech report for the areas we are excavating?
The project no longer includes excavation for new building construction. The geotech report provided is from a design option for an external TR at building 20 and that option has been abandonedComment by Moffett, Michael T.: So is this geotech report even applicable to this project? If not, then it should be either removed or marked as “for information only.”

VA – please label any Geotech reports provided as FIO

YES
Will ICRA carts be required to use for hallways and corridors when working above the ceilings? If so for which buildings and which floors in those buildings?

See SPEC 01 35 26 1.12.

15
TECH
How large are the new 3/4" backboards being installed in all TR's supposed to be in total? It just says bottom 8'-0" Min AFF - but how wide?
Refer to the drawings TN000 communications symbol legend, Provide 3/4" thick x 4' wide x 8' high A/C grade fire-retardant treated plywood backboard. Refer to floorplans for widths. Cut additional plywood to fit approximate width indicated on floorplans.Comment by Moffett, Michael T.: This should be shown on the plans or specs.Comment by John Sanborn: Specific reference to plans added to response.
16
ARCH
The Plan Notes #7, #8 and #9 on the A pages are all asking the GC to "verify before bidding" - That is impossible to do so how will that be reimbursed?
We now understand that contractors may not be able to verify these conditions before submitting bids, so that CYA portion of the note will be removed.

Plan notes 7,8 & 9 refers to work that needs to be completed to ensure all walls extend to the deck above with gypsum board on both sides to create a contained TR room. The existing walls may or may not already extend to the deck above. During our site investigation, we checked each condition to see if those walls need studs, gypsum board or some combination. The keynotes 7,8 & 9 tell which combination is needed for each wall. We added the note "contractors to verify before bidding" as a way for the contractor to verify mechanical ducts, conduit lines and other such infrastructure that may impede extending the walls to deck. . Comment by Moffett, Michael T.: This type of response is not acceptable in my opinion. We paid for a complete design. Putting this on the contractor because the AE apparently chose to not do a complete design is not what we paid for. On top of that, to state they are to verify before bidding is ridiculous. What does wors case scope even mean? How can a contractor reasonably estimate that? All the AE is going is setting us up for a problem during construction. I have seen this way too often and it is always a problem.

17
ARCH

A109 - Note #11 - What type of flooring is to be removed?

The two existing flooring types are carpet and hard surface flooring assumed to be LVT.

18
ARCH

A109 - Note #12 - please provide a detail of the decorative glass panels to be salvaged and replaced.

The “existing” decorative panels are held up using “existing” metal wall standoffs.

The standoffs are standard fasteners for mounting panels to a wall.

The drawings provide size, location and quantity details. , but we will provide a basic detail for mounting these. The contractor, when sourcing the additional wall standoffs, should attempt to match the “existing” wall standoff as best as they can. Our note "Contractors should verify before bidding" will be revised to "New wall standoffs should match existing wall standoffs". See attached wall stand-off/attachment detail.

. Comment by Moffett, Michael T.: If it should be easy to field verify during the pre-bid meeting then it should have been very easy to call it out in the plans or specs. The pre-bid meeting is not the place to learn this info. It needs to be made available to everyone, not just those in attendance. Once again, we paid for a complete design. This info should have been added to the plans or specs. I would expect the detail will be added in the forthcoming conformed copy of the plans and specs.

YES
Will the sign-in sheet from site visit be available in addendum?

Signed Sign in sheet was posted on SAM.gov

YES
Please clarify if a superintendent can be a dual hat to cover the requirements of SSHO?
Yes.
See SPEC 01 36 26 1.7 C.Comment by Moffett, Michael T.: We need to give a direct and specific answer, even if it is repeating the specs, then refer the offerors to the spec.

C. These Competent Persons can have collateral duties as the subcontractor’s superintendent and/or work crew lead persons as well as fill more than one specialized CP role (i.e. Asbestos, Electrical, Cranes, & Derricks, Demolition, Fall Protection, Fire Safety/Life Safety, Ladder, Rigging, Scaffolds, and Trenches/Excavations).

YES
If no to the question above, will the SSHO need to be full-time for this project?
Yes.
See SPEC 01 36 26 1.7 D.Comment by Moffett, Michael T.: We should be answering yes or no then refer to the spec to support your answer. They may have already read the spec and it is not clear to them after reading it.

D. The SSHO or an equally-qualified Designated Representative/alternate will maintain a presence on the site during construction operations in accordance with FAR Clause 52.236-6: Superintendence by the Contractor. CPs will maintain presence during their construction activities in accordance with above mentioned clause.

22
VA

Please clarify if a superintendent can be a dual hat to cover the requirements of QA/QC?

No. Reference Spec 01 45 00 3.4 B. CQC System Manager: Identify as CQC System Manager an individual within the onsite work organization that is responsible for overall management of CQC and has the authority to act in all CQC matters for the Contractor. The CQC system Manager is required to be a graduate engineer, graduate architect, or a graduate of construction management, with a minimum of ten years construction experience on construction similar to the scope of this Contract. This CQC System manager is on the site at all times during construction and is employed by the General Contractor. The CQC System Manger is assigned as CQC System Manager but does not have duties as project superintendent in addition to quality control. Identify in the plan an alternate to serve in the event of the CDQC System Manager’s absence. The requirements for the alternate are the same as the CQC System Manager.

23
VA

If no to the question above, will the QA/QC need to be full time for this project?

Yes. Reference Spec 01 45 00 3.4 C. CQC System Manager: Identify as CQC System Manager an individual within the onsite work organization that is responsible for overall management of CQC and has the authority to act in all CQC matters for the Contractor. The CQC system Manager is required to be a graduate engineer, graduate architect, or a graduate of construction management, with a minimum of ten years construction experience on construction similar to the scope of this Contract. This CQC System manager is on the site at all times during construction and is employed by the General Contractor. The CQC System Manger is assigned as CQC System Manager but does not have duties as project superintendent in addition to quality control. Identify in the plan an alternate to serve in the event of the CDQC System Manager’s absence. The requirements for the alternate are the same as the CQC System Manager.

24
VA

Can a superintendent be a triple hat to cover the requirements of SSHO and QA/QC?

. Comment by Moffett, Michael T.: Once again, what does the spec say? That is the only acceptable answer.

No.

Reference Spec 01 45 00 3.4 CQC System Manager: Identify as CQC System Manager an individual within the onsite work organization that is responsible for overall management of CQC and has the authority to act in all CQC matters for the Contractor. The CQC system Manager is required to be a graduate engineer, graduate architect, or a graduate of construction management, with a minimum of ten years construction experience on construction similar to the scope of this Contract. This CQC System manager is on the site at all times during construction and is employed by the General Contractor. The CQC System Manger is assigned as CQC System Manager but does not have duties as project superintendent in addition to quality control. Identify in the plan an alternate to serve in the event of the CDQC System Manager’s

YES
Please confirm if tax should be included in our proposal?
Everything should be included in the contractors proposal, we don’t provide tax waivers to contractorsComment by Moffett, Michael T.: Should refer to the tax clause for reference.
YES
Please confirm if the current prevailing wages will be consistent for the life of the project with no escalation?

The WD at the time of award will set the minimum wages for the life of the project. The contractor is free to pay more. Comment by Moffett, Michael T.: I think a more clear answer should something like: The WD at the time of award will set the minimum wages for the life of the project. The contractor is free to pay more.

YES
Attachment #5 introduces a slew of brand name equipment, will “equal” or alternatives be allowed? If not, please provide the brand name or equal justification for these items.

All equipment shall match the specifications provided in the bid documents. Attachment #5 was for internal use and is being removed from solicitation via amendment. Comment by Moffett, Michael T.: Do we provide salient characteristics for these brand name items? If so, then they are free to submit proposed equals so long as those times satisfy the salient characteristics.

If we don’t have salient characteristics, do we have J&A’s for those items?

YES
Please explain the cost estimating and budget approach, page 30 of Attachment #5. Once award the expectation is this procurement is a firm fixed price.

This contract is a firm fixed price. Attachment #5 was for internal use and is being removed from solicitation via amendment. Comment by Moffett, Michael T.: This did not answer the question. If we did not include the “spec book” we would not have received this question.

YES
Please consider updating the wage determination: General Decision Number: CO20250025 07/18/2025

Latest David Bacon Wages determination was posted on SAM.gov as an amendment on July 28

YES
Please describe the difference between Attachment #13 100% CD Specification and Attachment #5 100% CD Basis of Design. Is one more important than the other? If there is a discrepancy between the two? Which one do we follow?

Please follow the latest files/docs uploaded on Sam.gov. If a document listed is not available for download that means we have removed the file. Comment by Moffett, Michael T.: We should be specific as to what the latest files/docs are that they are to use. We really didn’t answer the question. Furthermore, if we are no longer making document available, remove any reference to it. We are creating needless ambiguity and confusion that will only bite us in contract admin.

Attachment #5 was for internal use and is being removed from solicitation via amendment.

YES
Please clarify, do we use Attachment 4 or Attachment 13 for the 100% Design specification, they look the same. Amendment #1 Box 14 is not clear what you are swapping out.

Please follow the latest files/docs uploaded on Sam.gov. If a document listed is not available for download that means we have removed the file. The addendum ATT4 is the latest upload. It contains clarification on conduit/sleeves. Comment by Moffett, Michael T.: We should be specific as to what the latest files/docs are that they are to use. We really didn’t answer the question.

YES
Who is responsible for contracting the commissioning agent?

The VA. Comment by Moffett, Michael T.: Are we doing this through the AE or a stand along contract? If a stand along contract, what have we done to get this person on board?

YES
Is the use of temporary plastic wall panels (such as STARC panels) acceptable to meet ICRA requirements?

The VA cannot provide means and methods. Temporary plastic wall panels shall meet SPEC 01 35 26.

YES
Will shutdowns be required to be done during off hours or weekends?

See SPEC 01 00 00 1.6 K Comment by Moffett, Michael T.: We should provide a direct answer in addition to referring to the spec.

1.6 K. Utilities Services: Maintain existing utility services for Medical Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR. Prior approval of utility outages. Any outage will require Station Facilities Management to coordinate with multiple other services, develop mitigation plans, and get approvals for the final concept. The Station needs at least 30 business-days-notice of a potential outage of any size. Formal submission must be made 15 days in advance, after coordination with the COR. Major outages (more than 4 hours) require 60 days-notice, to allow rescheduling patient appointments if required. Major outages must be shown on the initial construction schedule, or be added to the schedule as soon as the requirement is known.

YES
Will TR rooms, mechanical rooms, etc. be cleared of all stored items prior to the contractor entering those areas?

TR rooms will not have any items stored in them. Comment by Moffett, Michael T.: How much advance notice does the contractor need to give the VA?

Mechanical rooms will be cleared upon request.

Contractor shall provide 30 day’s notice to the VA prior to working within a space.

YES
Will a full-time fire watch be required during activities such as cutting, brazing and welding? How long after such activities are completed?

See SPEC 01 35 26 1.14.K Comment by Moffett, Michael T.: We should provide a direct answer in addition to referring to the spec.

K. Existing Fire Protection: Do not impair automatic sprinklers, smoke and heat detection, and fire alarm systems, except for portions immediately under construction, and temporarily for connections. Provide fire watch for impairments more than 4 hours in a 24-hour period. Request interruptions in accordance with Article, OPERATIONS AND STORAGE AREAS, and coordinate with COR and VA Safety Manager. All existing or temporary fire protection systems (fire alarms, sprinklers) located in construction areas shall be tested as coordinated with the medical center. Parameters for the testing and results of any tests performed shall be recorded by the medical center and copies provided to the Resident Engineer.

YES
Who is the vendor or contractor currently servicing and maintaining the Building Automation System or Temperature Controls System?

VA staff is servicing equipment.

YES
With regards to underground utility work how much open trenching be allowed at a time?

See SPEC 01 35 26 1.18. Comment by Moffett, Michael T.: We should provide a direct answer in addition to referring to the spec.

B. All excavations and trenches 24 inches in depth or greater shall require a written trenching and excavation permit (NOTE – some States and other local jurisdictions require separate state/jurisdiction-issued excavation permits). The permit shall have two sections, one section will be completed prior to digging or drilling and the other will be completed prior to personnel entering the excavations greater than 5 feet in depth. Each section of the permit shall be provided to the Facility Safety Officer and/or other Government Designated Authority prior to proceeding with digging or drilling and prior to proceeding with entering the excavation. After completion of the work and prior to opening a new section of an excavation, the permit shall be closed out and provided to the Facility Safety Officer

YES
After backfilling, topsoil and seed have been applied who is responsible for watering? If the contractor is responsible will water be provided by the facility?

See SPEC 01 00 00 1.19. Comment by Moffett, Michael T.: We should provide a direct answer in addition to referring to the spec.

F. Water (for Construction and Testing): Furnish temporary water service.

1. Obtain water by connecting to the Medical Center water distribution system. Provide reduced pressure backflow preventer at each connection as per code. Water is available at no cost to the Contractor.

40
CIVIL
Yes
On all underground utility work please confirm if excavated material is acceptable for re-use as backfill?

Clean soils can be used as backfill.

41
CIVIL
Yes
Please confirm if the contractor is responsible for any rock removal that is encountered. If so, what is the assumed elevations and quantity of rock material?

Contractor should not assume rock removal is required based on design depth. If rock encountered, contractor notify the CO and COR of the unforeseen conditions.

42
CIVIL
Yes
Please confirm if a unit price can be established for rock removal as opposed to carrying in bid?

See 41.

43
VA

Please confirm if there is a separate staging area onsite for fill material to be stockpiled for re-use?

Fill material will stored along the trench. Comment by Moffett, Michael T.: Typically? What is going to be allowed on this project. It doesn’t matter what is “typically” done. The contractor needs to know where it can be stored so they know much time they need to estimate for moving the soil back and forth.

44
VA

Please advise if the site contains any contaminated soil that needs to be removed.

No. If discovered, notify COR immediately of the differing site condition.

YES
Please confirm if we will be allowed to keep a locked storage container or conex box within the grounds.

See SPEC 01 00 00 1.6. Comment by Moffett, Michael T.: We should provide a direct answer in addition to referring to the spec.

1.6 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)

A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

YES
Will a guard / escort be required at all work areas including but not limited to buildings, outside areas?

See SPEC 01 00 00 1.5.B. Comment by Moffett, Michael T.: We should provide a direct answer in addition to referring to the spec.

4. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.

5. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.

Advise what is the existing data cabling manufacturer, wire thickness details, etc?

Existing cables will vary in manufacturer, wire thickness details, etc.

48
VA

To allow sufficient time to review responses and prepare our bid we kindly request that you please extend the bid date.

Bid due date was extended to August 14,2025

YES
281300 Physical Access Control System, 281600 Intrusion Detection System & 282300 Video Surveillance: We are adding to the existing PACS, IDS and Video Surveillance systems. Are there existing maintenance contractors for these systems? If so, can you please provide the contact information for the maintenance contractors? Will additional licenses be needed for cameras?

1. No.

2. N/A.

YES
283100 – Fire Alarm & Detection: We are adding to the existing fire alarm system. Is there an existing maintenance contractor for the fire alarm system? If so, can you please provide the contact information for the maintenance contractor?

1. No.

2. N/A.

YES
Is all work to be performed during regular business hours?

See SPEC 01 00 00 Comment by Moffett, Michael T.: We should provide a direct answer in addition to referring to the spec.

1.3.

Contractor Work Hours

1. Normal working hours for this contract will be from 7:00AM to 4:30PM (local time) Monday through Friday except for weekends and established Federal Holidays.

2. Performing on-site work outside normal working hours will require approval from the Contracting Officer and the COR. Requests shall be submitted via email at least 72 hours prior to the requested date and at no additional cost to the Government. Approvals are subject to the availability of on-site staff.

52
MECH
YES
Mechanical drawings show keynote 108 (‘Increase Exhaust Rate of Existing Air Terminal’)- Who is responsible for this (VA facility or Contractor)?

Keynote 108 - Contractor. Contractor shall provide all TAB and work shown on contract documents. Comment by Moffett, Michael T.: There should be a note in the drawings stating this or stated in the specs.

53
MECH
YES

Mechanical- Are new in-line fans to be controlled and/or monitored by BAS?

No BAS control required; fans are to run 24/7/365. See added fan control diagram on mechanical drawing M501 provided via amendment #2. Comment by Moffett, Michael T.: There should be a note in the drawings stating this or stated in the specs.

54
CIVIL

Sheet CU100 Shows requirement for Fiber Optic Manholes- Please advise if there are details and sizes for these FO manholes.

Fiber Optic Manhole Detail to be sent along with this Addendum #2 drawings Titled 575-700.VA Civil Grand Junction EHRM Addendum 2 - Fiber Optic Manhole Detail - Sheet CU101 Comment by Moffett, Michael T.: What is the detail/sheet number?

YES
The RFP did not identify a laydown yard for contractors. Please advise.

See SPEC 01 00 00 1.6.

Contractor laydown area shall be the south half of the traffic circle west of the docks.

YES
There are two EHRM projects out for bid, what is the timeline for these 2 projects, which EHRM project needs to start first? Are these two projects going to be awarded and started at the same time?

Each project shall be its own contract. Each project has its own timeline. Keep questions related to this project. Comment by Moffett, Michael T.: We really didn’t answer the question, particularly if they will start at the same time. They are probably wanting to know if there they will be working side-by-side another contractor.

YES
The VA estimated schedule for site work/Duct bank and restoration seems short for the extent of work considering possible relocation of existing utilities and shutdown requests duration for existing utilities. Can this be adjusted to add for utility shutdown request period?

VA estimated schedule is a comparison tool for this project. Contractor shall develop their own schedule and follow SPEC 01 32 16.15. Comment by Moffett, Michael T.: I don’t understand what this means. I think they are saying our POP isn’t long enough. It would be a good idea to reconsider the POP.

We should be telling the contractors the schedule is for information only and they are to develop their own schedule independent of the schedule in the solicitation. It should not be included in the contract when awarded.

Attachment #3 on Construction Schedule was for internal use and is being removed from solicitation via amendment.

YES
Please advise if sitework for duct banks will be performed during winter (note that VA estimated schedule of May 2025 has already passed for sitework). If this is winter work, then the schedule needs to be adjusted further to cover for weather conditions.

. Comment by Moffett, Michael T.: This isn’t a means and methods issue. It is a scheduling issue which we muddied the waters by including our own schedule, which we should not have. We should tell the offerors the schedule for information only and they are to develop their own independent schedule after award and weather related delays will be addressed in accordance with the Default Clause. Comment by John Sanborn: Clarification added Contractor shall develop their own schedule after award and weather related delays will be addressed in accordance with the Default Clause

Attachment #3 on Construction Schedule was for internal use and is being removed from solicitation via amendment.

YES
1. Per VA estimated Construction Schedule included in the RFP, the duration for installation and completion of activity ‘Install Communications System’ seem to be short (ex; Bldg 1, Level 1) which shows duration of ‘Communications Install’ at 10 days only. If this pertains to the whole ground floor (Bldg 1, Level 1), this is definitely not enough considering installation of new conduits and cabling for all the rooms. Please confirm if this is for the TR rooms only and not for the whole floor (Ref. Sheet B01-TN101A). The duration of 10 days will not be enough for the whole floor. Please advise and adjust schedule to include installation of conduits, and comms wiring for each floor rooms. Note that this will increase construction duration in consideration of adding durations for installation of data/comms to each room per floor and buildings.

. Comment by Moffett, Michael T.: See my previous comment about the schedule. We should tell them it is for information only and the awardee will develop their own independent schedule. Comment by John Sanborn: Clarification added Contractor shall develop their own schedule after award

Attachment #3 on Construction Schedule was for internal use and is being removed from solicitation via amendment.

YES
Is this project tax-exempt, if so, will a certificate be provided?

See question 25.

61
TECH

ET series drawings for CCTV camera. Bid spec documents do not specified what system are currently in place for this project, please answer the following questions:

a) What is the manufacturer of the current video management system?

b) What version/existing is the current video management system operating?

c) Are we expected to support version upgrades as part of this contract?

d) Are there sufficient existing licenses to support the new cameras?

e) Are the cameras to be 2MP pan/tilt/zoom or fixed dome?

f) Is there a current vendor/installer of this system that we can contact? Please Provide Contact

We have identified that most of the GJVA CCTV camera system is Honeywell but we also have Axis, and Milesight cameras in our CCTV system. The contractor will need to VIF which system they will be working with. Comment by Moffett, Michael T.: We should have identified what we have that they will be working with. That is what we paid the AE to do.

The cameras should be 8mp, fisheye and PTZ capable.

62
VA

ET series drawings for card reader/pin pad. Bid spec documents do not specified what system are currently in place for this project, please answer the following questions:

a) What is the manufacturer of the current access control system.

b) What version/existing software is the access control system operating.

c) Are we expected to support the version? updates as part of the contract?

d) Are the sufficient licenses to support the new doors?

e) Is there any existing integration between the access control and CCTV systems?

f) Is there a current vendor/installer of this system that we can contact? Please Provide Contact

A. – F. ) Video cameras are a combination of systems thoughout the property.

B. No

For any other questions, contractors need to see spec sections 28 13 00 for Access Control and 28 23 00 for Video Surveillance. Comment by Moffett, Michael T.: We should be providing specific answers to each item in addition to referring to the spec.

63
TECH

Is there an allowance of 1 1/4” data rough-in that should be carried within the Div.26 pricing? Some previous requirements on other projects requested 5-10% additional 1 1/4” data rough-in to cover what may have missed during design.

5% at no extra cost to the government Comment by Moffett, Michael T.: There should be no contingencies. We will end up paying this 5% plus the cost of change when we mod the contact as if there wasn’t a 5% contingency. We paid the AE to provide a complete buildable design. This should have been included in the design.

YES
Existing Fire Alarm System - Is there a current maintenance vendor/installer of this system that we can contact? Please Provide Contact

Alarm Specialist.

COR Tia Clemmer

YES
Existing Nurse Call System - Is there a current maintenance vendor/installer of this system that we can contact? Please Provide Contact

Nurse call is being handled via a separate project and a new system is currently being installed. That project is not completed at the moment. Comment by Moffett, Michael T.: Do we know the manufacture of the call system? Do we have an idea of who the maintenance vendor will be? Has the construction contract been awarded? If so, we can easily find out who the installer will be.

66
ELEC
YES
Is conduit required for grounding conductors running/installed ceiling & risers?

No, if it was required then that would be on the drawings and specs.

YES
Is there a requirement for x-ray scanning of concrete floor slabs prior to core drilling for floor-to-floor sleeves/conduits?

See SPEC 27 05 11 3.1. Comment by Moffett, Michael T.: Should provide direct answer in addition to referring to spec.

B.

Investigate existing conditions in vicinity of required opening prior to coring, including an x-ray of floor if determined necessary by competent person or COR.

YES
Is there a location where site asphalt and concrete can be stored/separated? Can this material be removed from the site once per week?

See question 55.

69
CIVIL
Yes
Will soil testing be performed prior to construction, to determine if any soils are contaminated?

Yes . Comment by Moffett, Michael T.: If? How can the contractor price “if”? If we don’t tell them definitively yes, and during construction, they end up needing to do it, it will be a change. Why not just says yes now? I doubt the cost will be much and it will not impact the project like it could during construction.

70
CIVIL
Yes
Is there a location where spoil dirt can be stored?

Contractor to coordinate with VA on stockpile locations as project progresses.

YES
Is there a specific location that will be used as a laydown yard during construction?

See question 55.

72
CIVIL
Yes
Will erosion control plans be provided?
Spec 01 57 19 Section 1.4
Comment by Moffett, Michael T.: Refer to the specs where this is found.

See Erosion Control plan for inlet protection and construction limits. Contractor to provide erosion control measures during trenching activities.

73
CIVIL
Yes
Has there been any boring samples/test made for duct bank pathway/trench to determine subsurface condition?

No

74
TECH

WAO-There are no prints that indicate new locations. Is this a 1 for 1 replacement for existing cables?

No. This is not a 1 to 1 replacement Comment by Moffett, Michael T.: So we have info scattered around in places that do not pertain to the item. Electrical work should be in electrical plans, telecom should be in the telecom plans, demo should be demo.

Contractor’s don’t know what design alert 16 is. That info should be incorporated into the plans and specs. How much as the outlets been reduced and what are “new work sheets” for new cable counts?

Refer to telecom demolition sheets for existing cable counts and telecom new work sheets for new cable counts.

YES
Is there required a full survey of every room/above ceiling? If so, who dictates the outlet location and quantity of cables per location?

Existing WAO and quantities are shown on the Telecom demo plans, New WAO and quantities are shown on the New Telecom Plans.

See addendum 1 drawings. The contractor shall confirm quantities. Comment by Moffett, Michael T.: So the AE didn’t do a full room survey? If they had, the outlet location and quantities of cable per location would be known.

YES
Can the government provide a quantity of CAT6 A cables that need to be installed by TR? Please provide a Drop Count Matrix that needs to be provided.

See addendum 1 drawings.

YES
What is the drop counts of each coverage zone? If it is a 1 for 1 swap, how many existing drops are located in each coverage zone?

See addendum 1 drawings.

YES
Is there a count and length for Cat6A patch cords?

See addendum 1 drawings.

79
TECH

Are we to provide one patch cable for each station and closet end?

Provide patch cables to match quantity of data drops at each WAO.

80
TECH

Is there a count and length for Fiber Patch cords?

No Comment by Moffett, Michael T.: 75-80: These issues was a problem for another EHRM project I had. We really should have a matrix that has the counts for each room. If we don’t have counts, it will probably bite us after award. Comment by John Sanborn: Quantities added

81
TECH

Are we to provide patch cables for each pair of strand at each end?

Yes

82
TECH

Is there any copper backbone (25-pair or larger) needed?

No

83
SES T

Is there required a full survey of every room/above ceiling for the for TN series note#2 (cable tray capacity)?

No. If there is no existing cable tray then J-Hooks will be provided.

Generally tray is above corridors. Not every ceiling would need to be reviewed for cable tray capacity.

84
TECH

Is there an allowance for unforeseen cable tray that the A&E would like the EC to carry?

Not at this time. Comment by Moffett, Michael T.: Do we say anything about how many trays are to replaced or added? We should have an idea of what we will need just by observation. If we don’t know, then the AE has dropped the ball. This will probably come back to bite us.

Contractor shall include J-Hooks in all locations. Once in the field, existing cable tray can be utilized where existing conditions allow.

85
TECH

If innerduct is required, the specifications identify that it should be installed in cable trays or support systems, has this been accounted for in sizing of cable raceways as the innerduct will consume quite a bit of space.

Innerduct is only permissible to be installed using metallic straps, hangers and fittings to support raceway from building structure per specification section 270533-2.1(H)(3).

86
TECH

Please confirm that the A/B backbone fiber to be installed in cable tray and not in a dedicated conduit raceway.

27 05 35

2.2 FIBER OPTIC CABLE RACEWAY.

A. Design. Raceway system shall be a modular system of channels, fittings, and brackets, able to be assembled with couplers. Fittings for cable spillout shall maintain a minimum 2” bend radius.

B. Materials. Raceway shall be constructed of rigid PVC and ABS plastics.

A/B backbone fiber to be installed in dedicated conduit. Comment by Moffett, Michael T.: We should be referring to the drawing or spec that states this.

87
TECH

Existing conduit sizes are not shown in the documents for existing data outlets, please clarify what conduit size and fill should be assumed by the contractor for existing data outlets. If the conduit size is not sufficient to an existing outlet will the VA require a new conduit?

Contractor should assume new cabling will fit within existing data drop rough-ins. Thin cat 6A cabling may be required. Conduit size likely varies across campus. Comment by Moffett, Michael T.: This is another one that probably will come back to bite us. We should be able to give specific answers to this. If not, then the AE dropped the ball. I thought we were using CAT 6E, not A. If they can use either, how will they know how much A they need if we don’t give them the info they requested?

88
TECH

Please confirm the rough in required to the corridors from rooms with data outlets, is this conduit extending from the rooms into the corridors or just vertical conduit running up from the outlet? If running conduit into the fire rated sleeve, please provide a detail showing this connection.

Refer to detail 5 of sheet TN601. Conduit will not be run through fire rated sleeve.

89
TECH

Are we to assume that areas with existing data devices will not require new fire rated wall sleeves? If new sleeves are required, please provide a count so that bidders will be aligned in scope of work.

The intent of the design is that main corridors will be used for routing. Sleeve locations are shown on the enlarged TR plans. There will be additional sleeves from rooms to corridors that is left as means and methods for the contractor.

The construction team is required to select the cable routes. This doesn't allow the design team to quantify the sleeves. Comment by Moffett, Michael T.: This was a problem on another EHRM project. We should know if a new sleeve is needed and how many.

Furthermore, this is being procured using Sealed Bid procedures. There is no reviewing of individual price elements. The award will be made on price and price related factors only. There are no trade offs or best value. It will be the bottom-line price. The AE should have, as part of their due diligence, determined viability of potential pathways and routes. If obstacles are discovered, they should be called out in the plans. We are not paying the contractor to design this project. That is what we paid the AE to do.

Sleeves are required and shall be included per the notes identified. Recommend each bidder identify the quantity of sleeves they have included with their bid so that bids can be reviewed accordingly.

90
TECH

Please confirm the new conduit will be in the wall and not surface mounted. In wall will have a significant cost impact with patching/painting.

New conduit will be in wall.

91
TECH

Existing box sizes are not shown in the documents for data outlets. Please clarify how to proceed with figuring if existing boxes will be re-used or if new boxes will need to be provided.

Locations with existing data devices will not require new boxes.

YES
Please confirm that all firestopping must be either installed by an FM global approved contractor, or a UL qualified firestop contractor certified.

See SPEC 07 84 00 1.5.B. Comment by Moffett, Michael T.: Need to give direct answer in addition to referencing the spec.

B. Installer Qualifications: A firm that has been approved by FM Global according to FM Global 4991 or been evaluated by UL and found to comply with UL’s “Qualified Firestop Contractor Program Requirements.” Submit qualification data.

YES
Please confirm that the contractor is to include the services of a third party independent firestopping inspector in their bid.

See SPEC 07 84 00 1.5.C. Comment by Moffett, Michael T.: See previous comment.

C. Inspector Qualifications: Contractor to engage a qualified inspector to perform inspections and final reports. The inspector to meet the criteria contained in ASTM E699 for agencies involved in quality assurance and to have a minimum of two years’ experience in construction field inspections of firestopping systems, products, and assemblies. The inspector to be completely independent of, and divested from, the Contractor, the installer, the manufacturer, and the supplier of material or item being inspected. Submit inspector qualifications.

YES
Please confirm that firestopping installers accredited by a firestopping product manufacturer will not be approved by the VA unless they meet the FM global or UL qualifications referenced in section 07 84 00
Confirmed
See SPEC 07 84 00 1.5.B.Comment by Moffett, Michael T.: Need to give direct answer in addition to referencing the spec.

B. Installer Qualifications: A firm that has been approved by FM Global according to FM Global 4991 or been evaluated by UL and found to comply with UL’s “Qualified Firestop Contractor Program Requirements.” Submit qualification data. . Comment by Moffett, Michael T.: Need to provide a direct and specific answer. We don’t even reference any particular spec.

95
TECH

Are we to assume that areas with existing data devices will not require new boxes? If new boxes are required, please provide a count.

Areas with existing data devices will not require new boxes.

96
TECH

TN000 Telecommunication General Notes “K” - Implies that all WAO are NEW. Please advise

No. Would only apply to locations that do not have an existing rough in. Drawings would specifically indicate those locations.

Note should read:

K. FOR ALL NEW DATA OUTLETS

Data devices are existing…