This document is a Technical Questions and Responses Tracking Sheet for Solicitation #36C77625B0039, a VA construction project for EHRM Infrastructure Upgrades at the Grand Junction VAMC in Colorado. The project involves comprehensive infrastructure improvements across multiple buildings, including electrical panel upgrades, power systems, UPS installations, building management system interfaces, HVAC assessments, communication infrastructure upgrades, physical security enhancements, and fiber optic backbone expansion.
The tracking sheet contains 150 detailed technical questions and responses from potential contractors, covering critical aspects such as cable pathways, electronic safety systems, utility work, site logistics, scheduling, licensing, and technical specifications. Key project details include a firm fixed-price contract, a bid due date of August 14, 2025, and work spanning buildings 1, 5, 6, 7, 8, 9, 12, 20, 35, 36, 37, 39/44, and 45. The project requires extensive infrastructure modifications, including data outlet upgrades to Cat 6A, physical security system integrations, and campus-wide network infrastructure improvements, with the VA Western Colorado Health Care System managing the overall implementation.
View the file
Other files
Show all 43
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TECHNICAL QUESTIONS AND
| SOLICITATION #: |
| 36C77625B0039 |
| RESPONSES TRACKING SHEET |
| PROJECT TITLE: |
| 575-21-700 Construction EHRM Infrastructure Upgrades , Grand Junction VAMC , CO |
| # |
| RECEIVED |
| ANSWERED |
| CONTRACTOR QUESTION |
| VA RESPONSE |
It is not clear if the cable locations are to be reused or are they to be new pathways in walls?
Please identify the system for Division 28 - Electronic Safety and Security > Physical Access Control System in document “Att 4 Specifications Grand Junction Data Center.”
System shall meet specifications out in the SPEC book.
Please identify the system for Division 28 - Electronic Safety and Security > Intrusion Detection System in document “Att 4 Specifications Grand Junction Data Center.”
System shall meet specifications out in the SPEC book.
Please identify the system for Division 28 - Electronic Safety and Security > Video Surveillance in document “Att 4 Specifications Grand Junction Data Center.”
System shall meet specifications out in the SPEC book.
Please identify the system for Division 28 - Electronic Safety and Security > Fire Detection and Alarm in document “Att 4 Specifications Grand Junction Data Center.”
System shall meet specifications out in the SPEC book.
| Can we get the spec section for the Mini Split Systems shown on the schedule on M600? |
| See spec Section 23 81 23 |
We see the new duct bank going through existing sidewalks, curb and gutter, roadways and parking lots but did not find any division 32 specs to go with the work. Can the VA provide them?
We see details for the new duct banks themselves but nothing showing where they are to enter the buildings, what kind of foundations or walls will need to be penetrated or excavate under. Can the engineer provide the required details showing how each of these building are to receive the new duct banks?
There are a lot of notes that state contractor to verify actual depth of crossing utilities, we can do that but wouldn’t be able to do it before the bid, so we have to bid off existing drawings. How would we be reimbursed should the drawings be incorrect and a major conflict exists?
Can we get the spec sections for DIV 03 Concrete?
| Is it the intent to remove all cabling shown on the TD Pages TD- 101 through TD-106D only? And what if there are abandoned cables from previous projects etc found - will they also have to be removed, and if so, how do we get reimbursed for that? |
| Yes, remove all cabling shown on plans. Additional cabling removed by modification request. |
On the UPS's and PDU's is it the intent to have 1 new UPS w/ PDU's per rack? Or can the VA give us a total of how many and what size UPS and associated equipment? Some Rack Elevations show the UPS's and others do not.
Yes each rack will require a UPS and PDU. See plans for #.
We looked through all the documents provided and found the Geotech report but seems to be for building 20 construction in 2008. No underground pathways are even proposed for that portion of the campus. Can we get a Geotech report for the areas we are excavating?
Will ICRA carts be required to use for hallways and corridors when working above the ceilings? If so for which buildings and which floors in those buildings?
See SPEC 01 35 26 1.12.
| How large are the new 3/4" backboards being installed in all TR's supposed to be in total? It just says bottom 8'-0" Min AFF - but how wide? |
| See sheet TN000 Backboard notes. |
| The Plan Notes #7, #8 and #9 on the A pages are all asking the GC to "verify before bidding" - That is impossible to do so how will that be reimbursed? |
| This should have been done at the Pre-bid site walk. |
A109 - Note #11 - What type of flooring is to be removed?
Vinyl Tile Flooring
A109 - Note #12 - please provide a detail of the decorative glass panels to be salvaged and replaced.
| Yes |
| Will the sign-in sheet from site visit be available in addendum? |
Signed Sign in sheet was posted on SAM.gov on July 16.
Please clarify if a superintendent can be a dual hat to cover the requirements of SSHO?
See SPEC 01 36 26 1.7 C.
If no to the question above, will the SSHO need to be full-time for this project?
See SPEC 01 35 26 1.9 See SPEC 01 36 26 1.7 D.
Please clarify if a superintendent can be a dual hat to cover the requirements of QA/QC?
Yes.
If no to the question above, will the QA/QC need to be full time for this project?
See question 22.
Can a superintendent be a triple hat to cover the requirements of SSHO and QA/QC?
Yes
| Please confirm if tax should be included in our proposal? |
| Everything should be included in the contractors proposal. We don’t provide tax waivers to contractors |
Please confirm if the current prevailing wages will be consistent for the life of the project with no escalation?
After award is made, if there is a change in the Wages determination, awardee needs to keep the same pricing until completion of the construction
Attachment #5 introduces a slew of brand name equipment, will “equal” or alternatives be allowed? If not, please provide the brand name or equal justification for these items.
All equipment shall match the specifications provided in the bid documents.
Please explain the cost estimating and budget approach, page 30 of Attachment #5. Once award the expectation is this procurement is a firm fixed price.
This contract is a firm fixed price.
Please consider updating the wage determination: General Decision Number: CO20250025 07/18/2025
Latest David Bacon Wages determination updated on July 25 was posted on SAM.gov as an amendment.
Please describe the difference between Attachment #13 100% CD Specification and Attachment #5 100% CD Basis of Design. Is one more important than the other? If there is a discrepancy between the two? Which one do we follow?
Please follow the latest files/docs uploaded on Sam.gov. If a document listed is not available for download that means we have removed the file.
Please clarify, do we use Attachment 4 or Attachment 13 for the 100% Design specification, they look the same. Amendment #1 Box 14 is not clear what you are swapping out.
Please follow the latest files/docs uploaded on Sam.gov. If a document listed is not available for download that means we have removed the file.
Who is responsible for contracting the commissioning agent?
The VA Western Colorado Health Care System.
Is the use of temporary plastic wall panels (such as STARC panels) acceptable to meet ICRA requirements?
The VA cannot provide means and methods. Temporary plastic wall panels shall meet SPEC 01 35 26.
Will shutdowns be required to be done during off hours or weekends?
See SPEC 01 00 00 1.6 K
Will TR rooms, mechanical rooms, etc. be cleared of all stored items prior to the contractor entering those areas?
TR rooms will not have any items stored in them.
Mechanical rooms will be cleared upon request.
Will a full-time fire watch be required during activities such as cutting, brazing and welding? How long after such activities are completed?
See SPEC 01 35 26 1.14.K
Who is the vendor or contractor currently servicing and maintaining the Building Automation System or Temperature Controls System?
VA staff is servicing equipment.
With regards to underground utility work how much open trenching be allowed at a time?
See SPEC 01 35 26 1.18.
After backfilling, topsoil and seed have been applied who is responsible for watering? If the contractor is responsible will water be provided by the facility?
See SPEC 01 00 00 1.19.
On all underground utility work please confirm if excavated material is acceptable for re-use as backfill?
Please confirm if the contractor is responsible for any rock removal that is encountered. If so, what is the assumed elevations and quantity of rock material?
Please confirm if a unit price can be established for rock removal as opposed to carrying in bid?
Please confirm if there is a separate staging area onsite for fill material to be stockpiled for re-use?
Please advise if the site contains any contaminated soil that needs to be removed.
Please confirm if we will be allowed to keep a locked storage container or conex box within the grounds.
See SPEC 01 00 00 1.6.
Will a guard / escort be required at all work areas including but not limited to buildings, outside areas?
See SPEC 01 00 00 1.5.B.
Advise what is the existing data cabling manufacturer, wire thickness details, etc?
To allow sufficient time to review responses and prepare our bid we kindly request that you please extend the bid date.
Bid due date was extended to August 14, 2025.
281300 Physical Access Control System, 281600 Intrusion Detection System & 282300 Video Surveillance: We are adding to the existing PACS, IDS and Video Surveillance systems. Are there existing maintenance contractors for these systems? If so, can you please provide the contact information for the maintenance contractors? Will additional licenses be needed for cameras?
1. No.
2. N/A.
283100 – Fire Alarm & Detection: We are adding to the existing fire alarm system. Is there an existing maintenance contractor for the fire alarm system? If so, can you please provide the contact information for the maintenance contractor?
1. No.
2. N/A.
Is all work to be performed during regular business hours?
See SPEC 01 00 00 1.3.
Mechanical drawings show keynote 108 (‘Increase Exhaust Rate of Existing Air Terminal’)- Who is responsible for this (VA facility or Contractor)?
Mechanical- Are new in-line fans to be controlled and/or monitored by BAS?
Sheet CU100 Shows requirement for Fiber Optic Manholes- Please advise if there are details and sizes for these FO manholes.
The RFP did not identify a laydown yard for contractors. Please advise.
See SPEC 01 00 00 1.6.
Contractor laydown area shall be the south half of the traffic circle west of the docks.
There are two EHRM projects out for bid, what is the timeline for these 2 projects, which EHRM project needs to start first? Are these two projects going to be awarded and started at the same time?
Each project shall be its own contract. Each project has its own timeline. Keep questions related to this project.
The VA estimated schedule for site work/Duct bank and restoration seems short for the extent of work considering possible relocation of existing utilities and shutdown requests duration for existing utilities. Can this be adjusted to add for utility shutdown request period?
VA estimated schedule is a comparison tool for this project. Contractor shall follow SPEC 01 32 16.15.
Please advise if sitework for duct banks will be performed during winter (note that VA estimated schedule of May 2025 has already passed for sitework). If this is winter work, then the schedule needs to be adjusted further to cover for weather conditions.
VA shall not provide means and method to contractor.
1. Per VA estimated Construction Schedule included in the RFP, the duration for installation and completion of activity ‘Install Communications System’ seem to be short (ex; Bldg 1, Level 1) which shows duration of ‘Communications Install’ at 10 days only. If this pertains to the whole ground floor (Bldg 1, Level 1), this is definitely not enough considering installation of new conduits and cabling for all the rooms. Please confirm if this is for the TR rooms only and not for the whole floor (Ref. Sheet B01-TN101A). The duration of 10 days will not be enough for the whole floor. Please advise and adjust schedule to include installation of conduits, and comms wiring for each floor rooms. Note that this will increase construction duration in consideration of adding durations for installation of data/comms to each room per floor and buildings.
Contractor shall provide the final schedule. VA schedule is an estimate. A time modification will need to be submitted and approved.
Is this project tax-exempt, if so, will a certificate be provided?
See question 25.
ET series drawings for CCTV camera. Bid spec documents do not specified what system are currently in place for this project, please answer the following questions:
a) What is the manufacturer of the current video management system?
b) What version/existing is the current video management system operating?
c) Are we expected to support version upgrades as part of this contract?
d) Are there sufficient existing licenses to support the new cameras?
e) Are the cameras to be 2MP pan/tilt/zoom or fixed dome?
f) Is there a current vendor/installer of this system that we can contact? Please Provide Contact
ET series drawings for card reader/pin pad. Bid spec documents do not specified what system are currently in place for this project, please answer the following questions:
a) What is the manufacturer of the current access control system.
b) What version/existing software is the access control system operating.
c) Are we expected to support the version? updates as part of the contract?
d) Are the sufficient licenses to support the new doors?
e) Is there any existing integration between the access control and CCTV systems?
f) Is there a current vendor/installer of this system that we can contact? Please Provide Contact
Is there an allowance of 1 1/4” data rough-in that should be carried within the Div.26 pricing? Some previous requirements on other projects requested 5-10% additional 1 1/4” data rough-in to cover what may have missed during design.
Existing Fire Alarm System - Is there a current maintenance vendor/installer of this system that we can contact? Please Provide Contact
Alarm Specialist.
COR Tia Clemmer
Existing Nurse Call System - Is there a current maintenance vendor/installer of this system that we can contact? Please Provide Contact
Beacon Comm, DAYON VALDEZ, 303-750-6500
Is conduit required for grounding conductors running/installed ceiling & risers?
Yes
Is there a requirement for x-ray scanning of concrete floor slabs prior to core drilling for floor-to-floor sleeves/conduits?
See SPEC 27 05 11 3.1.
Is there a location where site asphalt and concrete can be stored/separated? Can this material be removed from the site once per week?
No, waste will need to be removed daily..
Will soil testing be performed prior to construction, to determine if any soils are contaminated?
No
Is there a location where spoil dirt can be stored?
The grass area south of BLDG 34
Is there a specific location that will be used as a laydown yard during construction?
See question 55.
Will erosion control plans be provided?
No
Has there been any boring samples/test made for duct bank pathway/trench to determine subsurface condition?
No
WAO-There are no prints that indicate new locations. Is this a 1 for 1 replacement for existing cables?
Yes
Is there required a full survey of every room/above ceiling? If so, who dictates the outlet location and quantity of cables per location?
See addendum 1 drawings.
Can the government provide a quantity of CAT6 A cables that need to be installed by TR? Please provide a Drop Count Matrix that needs to be provided.
See addendum 1 drawings.
What is the drop counts of each coverage zone? If it is a 1 for 1 swap, how many existing drops are located in each coverage zone?
See addendum 1 drawings.
Is there a count and length for Cat6A patch cords?
No
Are we to provide one patch cable for each station and closet end?
Is there a count and length for Fiber Patch cords?
No
Are we to provide patch cables for each pair of strand at each end?
Is there any copper backbone (25-pair or larger) needed?
Is there required a full survey of every room/above ceiling for the for TN series note#2 (cable tray capacity)?
Is there an allowance for unforeseen cable tray that the A&E would like the EC to carry?
No
If innerduct is required, the specifications identify that it should be installed in cable trays or support systems, has this been accounted for in sizing of cable raceways as the innerduct will consume quite a bit of space.
Yes
Please confirm that the A/B backbone fiber to be installed in cable tray and not in a dedicated conduit raceway.
Confirmed
Existing conduit sizes are not shown in the documents for existing data outlets, please clarify what conduit size and fill should be assumed by the contractor for existing data outlets. If the conduit size is not sufficient to an existing outlet will the VA require a new conduit?
Assume ¾”, yes new conduit will be required if needed.
Please confirm the rough in required to the corridors from rooms with data outlets, is this conduit extending from the rooms into the corridors or just vertical conduit running up from the outlet? If running conduit into the fire rated sleeve, please provide a detail showing this connection.
Conduit will be required.
Are we to assume that areas with existing data devices will not require new fire rated wall sleeves? If new sleeves are required, please provide a count so that bidders will be aligned in scope of work.
Please confirm the new conduit will be in the wall and not surface mounted. In wall will have a significant cost impact with patching/painting.
New conduit in the walls.
Existing box sizes are not shown in the documents for data outlets. Please clarify how to proceed with figuring if existing boxes will be re-used or if new boxes will need to be provided.
Existing boxes can be used.
Please confirm that all firestopping must be either installed by an FM global approved contractor, or a UL qualified firestop contractor certified.
See SPEC 07 84 00 1.5.B.
Please confirm that the contractor is to include the services of a third party independent firestopping inspector in their bid.
See SPEC 07 84 00 1.5.C.
Please confirm that firestopping installers accredited by a firestopping product manufacturer will not be approved by the VA unless they meet the FM global or UL qualifications referenced in section 07 84 00
Contractor shall meet all specifications.
Are we to assume that areas with existing data devices will not require new boxes? If new boxes are required, please provide a count.
Existing boxes can be used, See the plans for a count.
TN000 Telecommunication General Notes “K” - Implies that all WAO are NEW. Please advise
Is there an allowance of Cat 6A cable that should be carried within the Div.27 pricing? Some previous requirements on other projects requested 5-10% additional Cat 6A cables,to cover what may have missed during design.
Contractor shall place bid by the current requirements.
1. TN000 Telecommunication General Notes “R,S & T” for horizontal sleeves into offices - Please give quantities & size for bidding.
Is there a proprietary Fire Alarm Contractor at the facility? If so, please provide the company name and point of contact.
Alarm Specialists There is no maintenance contractor for this system.
Is there a proprietary Controls Contractor at the facility? If so, please provide the company name and point of contact.
JCI Controls, There is no maintenance contractor for this system.
Is there a proprietary Cameras at the facility? If so, please provide the company name and point of contact.
B44-TN400 Please confirm the estimated drop count for TR 106 in Building 44.
See plans.
B44-TN400 Please add cabling notes to drawing.
For estimating purposes, the enlarged drawings give a count of existing cable count to be demolished and estimated work area outlets. Please confirm which drop count we should use for estimating the project.
| B45-TN400 The Cabling notes say there’s 0 existing cable count and estimated work area outlets total active of 105. Are we to price it as there being 0 or 105 at the end of the project |
| 105 |
TS001 does not look to have a ductbank running to Building 44. Please confirm the location of Building 44 and the duct bank route.
BLDG 44 is the Parking Structure (the site plan shows 39 which is incorrect) and it is fed from the west side. See plan TS001.
01 45 00 – Quality Control – Can the Superintendent be the QC Manager?
Yes
| 01 35 26 – 1.7 – Can the Superintendent be the SSHO? |
| See SPEC 01 35 26 1.7 |
Detail 5 on sheet TN601 – For estimating purposes how many of these new communications outlets should we figure?
Compare the Demo & New Construction plan sheets
CU100 Utility Plan – Can the VA provide a detail on the fiber optic manhole they would like to have installed?
B01-E500 – Sheet Notes 1 and 2 – Can the VA confirm that these UPS are new and not existing?
New
B01-M200 – This drawing seems to be incomplete; can the VA provide a better drawing showing that all this work is taking place in the basement?
For the condensing units mounted on the roofs can the VA provide pictures of all the locations so that we can better estimate the price for patching and repairing the roofing material?
There are no existing condensing units on the roof.
M500- There is no concrete pad detail for the condensing units can the VA please provide.
6” thick (3” above grade) with 6” x 6” welded wire reinforcement.
Please identify the system for Division 28- Electronic Safety and Security > Physical Access Control System in document “Att 4 Specifications Grand Junction Data Center.”
System shall meet specifications out in the SPEC book.
Please identify the system for Division 28 - Electronic Safety and Security > Intrusion Detection System in document “Att 4 Specifications Grand Junction Data Center.”
System shall meet specifications out in the SPEC book.
Please identify the system for Division 28 - Electronic Safety and Security > Video Surveillance in document “Att 4 Specifications Grand Junction Data Center.”
System shall meet specifications out in the SPEC book.
Please identify the system for Division 28 - Electronic Safety and Security > Fire Detection and Alarm in document “Att 4 Specifications Grand Junction Data Center.”
System shall meet specifications out in the SPEC book.
B01-M300 – B45-M300- Are the controls on existing units that are removed to be reused if possible?
SEE SPEC 28 31 00 1.2.E.
B01-M300- Keynote 108 – increasing the exhaust rate of existing air terminal, is this done at VFD’s/AHU or are we to adjust the damper during TAB?
Yes
Are the new in-line fans to be controlled and/or monitored by BAS?
Yes
M600- Is there a central controller that all the FCU’s will be reporting to? Can the VA provide a ladder diagram?
M600- Who is responsible for the humidity sensors and so they need to report to Metasys?
The contractor, yes.
M600- What is controlling the control valves on the FCU’s?
M600- Does there need to be any monitoring or alarming to the condensing units for each FCU?
As it relates to the Metasys system, is it the only work to monitor and alarm each FCU?
5/TN-106 calls out for us to provide a 1-1/4” conduit and 4” square by 2-1/8” deep box with single gang plastic ring.
a. Does the current/existing conduit and box meet this detail?
b. Is this detail for all drop locations? This detail is not identified at any of the new locations.
i. If a new hard pipe is required in all these locations this will increase the drywall patch/paint and ICRA cost for the project. Also increasing the duration contractors will be on site. We would need every room to be unoccupied during the duration of work. Does the VA want to treat the existing drops as unforeseen site conditions?
c. Is surface mounting of 1-1/4” conduit and box acceptable?
d. Confirm J-hooks are acceptable once the conduit is stubbed up above accessible ceilings.
e. Is flexible conduit acceptable as in-wall raceway(s) for security/electrical/data?
A. Some may not meet this detail.
B. Yes. i Yes there will be drywall repairs needed.
C. No D. Yes E. Yes image1.jpeg image2.jpeg image3.jpeg